ML22357A10031 March 2023and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendments Standard Emergency Plan and Consolidated Emergency Operations FacilitySafe Shutdown
Health Physics Network
High winds
Minimum staff
Fire Protection Program
Siren
ML22181A00017 August 2022Issuance of Amendments Reactor Trip System Power Range Instrumentation ChannelsSurveillance Frequency Control Program
L-PI-22-003, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections7 June 2022Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube InspectionsNondestructive Examination
ML22061A2061 April 2022Issuance of Amendments TSTF-471, Rev. 1, TSTF-571-T, and Administrative Changes to Technical Specification Section 5.0Shutdown Margin
High Radiation Area
Offsite Dose Calculation Manual
Hydrostatic
Nondestructive Examination
Pressure and Temperature Limits Report
Surveillance Frequency Control Program
Safeguards Contingency Plan
Deep Dose Equivalent
Power Uprate
L-PI-21-029, Exigent License Amendment Request to Revise Technical Specification 3.7.8 to Allow a One-Time Extension of the Completion Time of Required Action B.17 October 2021Exigent License Amendment Request to Revise Technical Specification 3.7.8 to Allow a One-Time Extension of the Completion Time of Required Action B.1Safe Shutdown
Ultimate heat sink
Non-Destructive Examination
ML20346A02015 March 2021Issuance of Amendment Nos. 235 and 223, Adoption of Technical Specifications Task Force Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4bSafe Shutdown
High winds
High Radiation Area
Mission time
Fire Barrier
Internal Flooding
Probabilistic Risk Assessment
FLEX
Surveillance Frequency Control Program
Large early release frequency
Earthquake
Maintenance Rule Program
Offsite Circuit
Backfit
ML20356A0025 February 2021Issuance of Amendment Nos. 234 and 222, Revise Technical Specifications 3.2.1 and 5.6.5 Identified in Westinghouse Nuclear Safety Advisory Letters NSAL-09-05, Revision 1, and NSAL-15-1Surveillance Frequency Control Program
ML20210M0148 September 2020and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendment Nos. 204, 231, and 219 TSTF-529 Clarify Use and Application RulesTime of Discovery
L-PI-20-001, License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-129 January 2020License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-1Anticipated operational occurrence
Surveillance Frequency Control Program
Power change
L-PI-19-041, Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements23 December 2019Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position RequirementsShutdown Margin
Anticipated operational occurrence
Surveillance Frequency Control Program
B.5.b Mitigating Strategies
Fuel cladding
L-PI-19-040, License Amendment Request: Revise Technical Specification 5.5.14 to Permanently Extend Containment Leakage Rate Test Frequency7 October 2019License Amendment Request: Revise Technical Specification 5.5.14 to Permanently Extend Containment Leakage Rate Test FrequencyInternal Flooding
Probabilistic Risk Assessment
Coatings
Operating Basis Earthquake
Aging Management
Surveillance Frequency Control Program
Large early release frequency
Moisture barrier
Maintenance Rule Program
Fuel cladding
Grace period
ML19045A48016 April 2019Issuance of Amendment Nos. 226 and 214 Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5BHigh winds
Shutdown Margin
High Radiation Area
Internal Flooding
Hydrostatic
Probabilistic Risk Assessment
Surveillance Frequency Control Program
Large early release frequency
Backfit
Power change
ML19029A09429 January 2019Issuance of Amendment No. 213, One-Time Technical Specification Change to Extend Completion Time for EDGs D5 and D6 (Emergency Circumstances)Safe Shutdown
Probabilistic Risk Assessment
FLEX
ML17362A2025 March 2018Issuance of Amendment Concerning Revision to the Prairie Island Nuclear Generating Plant, Units 1 and 2 Emergency Plan (CAC Nos. MF9345 and MF9346; EPID L-2017-LLA-0175)Minimum staff
ML16133A40616 June 2016Issuance of Amendment Nos. 217 and 205, Adoption of Technical Specifications Task Force TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation (CAC Nos. MF6449 and MF6450)
ML15264A20930 November 2015Issuance of Amendment Nos. 216 and 204 Regarding Revisions to Technical Specification 3.3.3 and Renewed Facility Operating LicenseSafe Shutdown
Reactor Vessel Water Level
Cyber Security
Fire Protection Program
ML15229A17626 August 2015Issuance of Amendment Nos. 215 and 203 Regarding Revision to Licensing Basis Analysis for a Waste Gas Decay Tank Rupture
ML15209A51217 July 2015Technical Specifications - Updating Instructions -Effective Date: 7/24/2015Fuel cladding
ML15209A50917 July 2015Technical Specifications - Updating InstructionsFuel cladding
L-PI-15-030, Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process29 June 2015Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement ProcessStroke time
Time to boil
ML15086A04621 May 2015Issuance of Amendment Nos. 214 and 202 Regarding Revisions to Technical Specification 3.8.1, AC Sources - OperatingSafe Shutdown
ML15062A01320 May 2015Issuance of Amendments 213 and 201 to Revise TS 3.5.3, ECCS - Shutdown
L-PI-15-004, Supplement to License Amendment Request (LAR) to Revise Technical Specification (TS) 3.5.3, ECCS (Emergency Core Cooling System)- Shutdown26 February 2015Supplement to License Amendment Request (LAR) to Revise Technical Specification (TS) 3.5.3, ECCS (Emergency Core Cooling System)- ShutdownPressure and Temperature Limits Report
L-PI-14-034, License Amendment Request (LAR) to Revise Technical Specification (TS) 3.3.3, Event Monitoring (EM) Instrumentation, and Additional Conditions Related to Alternative Source Term License Amendment Implementation11 December 2014License Amendment Request (LAR) to Revise Technical Specification (TS) 3.3.3, Event Monitoring (EM) Instrumentation, and Additional Conditions Related to Alternative Source Term License Amendment ImplementationSafe Shutdown
Unanalyzed Condition
Reactor Vessel Water Level
Post Accident Monitoring
ML14058A20719 February 2014Technical Specifications (3801 TS Markup)
ML13214A0292 August 2013Correction Letter for License Amendment Nos. 207 (Unit 1) and 194 (Unit 2)
ML13113A4002 July 2013License Amendments TSTF-510Nondestructive Examination
Incorporated by reference
L-PI-13-030, License Amendment Request (LAR) to Add a Methodology to Technical Specification (TS) 5.6.5, Core Operating Limits Report (Colr).23 May 2013License Amendment Request (LAR) to Add a Methodology to Technical Specification (TS) 5.6.5, Core Operating Limits Report (Colr).Shutdown Margin
ML13093A3449 May 2013License Amendments for Fuel Oil System and TSTF-501Safe Shutdown
L-PI-12-028, License Amendment Request (LAR) to Revise Technical Specification (TS) 3.8.1, AC Sources - Operating Emergency Diesel Generator Voltage Limits15 May 2012License Amendment Request (LAR) to Revise Technical Specification (TS) 3.8.1, AC Sources - Operating Emergency Diesel Generator Voltage LimitsSafe Shutdown
Anticipated operational occurrence
L-PI-12-013, Response to Requests for Additional Information Associated with Adoption of the Alternative Source Term (AST) Methodology24 February 2012Response to Requests for Additional Information Associated with Adoption of the Alternative Source Term (AST) MethodologyEarthquake
ML1129011151 December 2011Issuance of Amendments Revision of Technical Specifications 5.2.1, Onsite and Offsite Organizations and TS 5.3, Plant Staff Qualifications.
L-PI-11-037, License Amendment Request to Add Diesel Fuel Oil License Bases and Revise Technical Specifications 3.7.8 Re Cooling Water System & 3.8.3 Re Diesel Fuel Oil11 August 2011License Amendment Request to Add Diesel Fuel Oil License Bases and Revise Technical Specifications 3.7.8 Re Cooling Water System & 3.8.3 Re Diesel Fuel OilSafe Shutdown
Anticipated operational occurrence
Hydrostatic
Tornado Generated Missile
ML11172A02227 June 2011Technical Specifications, Unit 2, Renewed Facility Operating License for Prairie Island Nuclear Generating PlantEarthquake
ML11172A02027 June 2011Technical Specifications, Unit 1, Renewed Facility Operating License for Prairie Island Nuclear Generating PlantTime of Discovery
Shutdown Margin
Reactor Vessel Water Level
High Radiation Area
Grab sample
Offsite Dose Calculation Manual
Hydrostatic
Nondestructive Examination
Pressure and Temperature Limits Report
Earthquake
Deep Dose Equivalent
Pressure Boundary Leakage
Recently irradiated fuel
Fire Protection Program
Power change
Unidentified leakage
Power Uprate
L-PI-11-016, License Amendment Request (LAR) to Revise Surveillance Requirement (SR) Footnote in Technical Specification (TS) 3.8.1, AC Sources - Operating.3 February 2011License Amendment Request (LAR) to Revise Surveillance Requirement (SR) Footnote in Technical Specification (TS) 3.8.1, AC Sources - Operating.Offsite Circuit
L-PI-10-104, Supplement to Exigent License Amendment Request to Modify Technical Specifications Surveillance Requirement 3.8.1.1020 October 2010Supplement to Exigent License Amendment Request to Modify Technical Specifications Surveillance Requirement 3.8.1.10
ML10257154916 September 2010Correction to Amendment Nos. 195 and 184 Regarding Technical Specification Changes to Control Room Habitability Requirements
ML09257036715 September 2009Correction to Technical Specifications (TAC Nos. MD9142 and MD9143)
L-PI-08-080, License Amendment Request (LAR) to Revise Emergency Diesel Generator (EDG) Test Loads in Surveillance Requirement (SR) 3.8.1.3 and SR 3.8.1.94 November 2008License Amendment Request (LAR) to Revise Emergency Diesel Generator (EDG) Test Loads in Surveillance Requirement (SR) 3.8.1.3 and SR 3.8.1.9Mission time
ML08268159122 September 2008(PINGP-1 and 2), Technical Specifications ISFSI, Issuance of Amendments to Conform the Facility Operating Licenses to Reflect Transfer of Operating Authority (TAC L24245)
ML08268129122 September 2008Revised Operating Licenses & Technical Specifications, Issuance of Amendments to Conform the Facility Operating Licenses to Reflect Transfer of Operating Authority (TAC L24245, MD9622 and MD9623)Safe Shutdown
Safeguards Contingency Plan
Earthquake
Fire Protection Program
ML08205044518 July 2008Tech Spec Pages for Amendments 186 & 176 Adopting Provisions of Regulatory Guide (Rg) 1.52 Revision 3
ML08184023427 June 2008Prairie, Units 1 and 2, Tech Spec Pages for Amendments 185 and 175 Regarding Incorporation of TS Task Force Travelers TSTF-479, TSTF-485 and TSTF-497
ML0812705061 May 2008Submittal of Entire Re-Issue of ISFSI Technical Specifications
ML08014042528 January 2008Issuance of Amendments (TAC Nos. MD4209 & MD4210) - Tech Specs
ML07352040014 December 2007Technical Specifications in Support of Containment Sump Resolution
L-PI-07-086, License Amendment Request (LAR) to Revise Containment Spray Nozzle Surveillance Requirements (SR)19 November 2007License Amendment Request (LAR) to Revise Containment Spray Nozzle Surveillance Requirements (SR)Foreign Material Exclusion
ML07284035431 October 2007Tech Spec Page for Amendments 181 and 171, Revise TS 3.7.2 Main Steam Valves Closure Times by Relocating the Isolation Valve Closure Times to a Licensee-Controlled Document Identified as a Bases Reference
L-PI-07-061, License Amendment Request (LAR) to Increase the Unit 1 Emergency Diesel Generators' (EDG) Monthly Test Load16 August 2007License Amendment Request (LAR) to Increase the Unit 1 Emergency Diesel Generators' (EDG) Monthly Test Load