Issue date | Title | Topic | |
---|---|---|---|
ML20057E486 | 6 August 1993 | Trip Repts of NRC Observation of Thermo-Lag Fire Barrier Test Specimen Const by Util for Qualification of Thermo-Lag Fire Barriers Installed in Facility & NUMARC for Generic Qualification of Thermo-Lag Fire Barriers in Industry | Fire Barrier |
ML20236Q435 | 6 November 1987 | Trip Rept of 871007 Visit to Corporate Consulting & Development Co,Ltd,In Raleigh,Nc Re Static Tests of HVAC Ductwork | |
ML20235F985 | 1 July 1987 | Trip Rept of 870623 Visit to Culver City,Ca Re Testing of Conduit Clamps at Anco Engineers,Inc.List of Meeting Attendees Encl | |
ML20209J318 | 3 September 1986 | Trip Rept of Attendance at 860821 Meeting in Arlington,Tx Re Util Plans for Plant Issues.Summaries of Observations Listed | |
ML20210S437 | 21 May 1986 | Trip Rept of 860505-07 Site Visit to Attend Civil/Structural Issues Audit Meetings.Audit Attendee List & Agenda Encl | Safe Shutdown Earthquake Backfit |
ML20140H475 | 1 April 1986 | Trip Rept of 851120-22 Site Audit of S&W Implementation of Project Procedure CPPP-8 for Piping & Pipe Supports.No Items of Noncompliance or Deviations Noted | |
ML20205K811 | 6 March 1986 | Trip Rept of 860219 Site Visit to Examine Problems Re Improperly Installed Cable Splices Used for Bunker-Remo Electrical Penetration Connections to Field Wiring.List of Attendees Encl | |
IA-86-270, Trip Rept of 860219 Site Visit to Examine Problems Re Improperly Installed Cable Splices Used for Bunker-Remo Electrical Penetration Connections to Field Wiring.List of Attendees Encl | 6 March 1986 | Trip Rept of 860219 Site Visit to Examine Problems Re Improperly Installed Cable Splices Used for Bunker-Remo Electrical Penetration Connections to Field Wiring.List of Attendees Encl | |
ML20205J541 | 18 February 1986 | Trip Rept of 851021-24 Site Visit Re QA Program Procedures. Listed Personnel Contacted at Site.Results of Discussions Documented in 860115 Memo | |
ML20153E341 | 18 February 1986 | Trip Rept of 851021-24 Site Visit Re QA Program Procedures. Results of Discussions Factored Into 860115 Memo | |
ML20137U727 | 29 January 1986 | Trip Rept 2201 of 860121 Visit to Robert L Cloud & Assoc,In Berkeley,Ca Re Participation in Facility Cable Tray Verification Program.Company Will Audit Cable Tray Tests Performed by Ebasco,Impell Corp & Anco | |
ML20137U779 | 22 January 1986 | Trip Rept 2202 of 860122 Visit to Impell Corp in Walnut Creek,Ca Re Applicability of Slenderness Ratio Limit to Facility Cable Tray Hangers & Impell Design Criteria & Procedures.Viewgraphs Encl | Earthquake |
ML20210C077 | 17 January 1986 | Trip Rept 2200 of 860117 Site Visit Re HVAC Hanger Program Audit.Status of Licensee Steam Electric Station Seismic Qualification Rept of Seismic Category 1 Duct Work & Hangers Changed from Approved to Not Approved on 860121 | |
ML20210B978 | 16 January 1986 | Trip Rept of 851202-03 Visit to Tera Ofcs in Bethesda,Md to Audit Documentation Supporting Initial Level of Homogeneity for Design Activities Review Procedure DAP-21 That Will Be Implemented to Validate Homogeneity | |
ML20141C966 | 18 December 1985 | Trip Rept of 851009-10,15-17 & 28-31 Site Visits Re Methodology Used by Applicant/Contractor in Establishing Equipment Populations & Equipment/Work Processes Homogeneity | |
ML20197E245 | 18 December 1985 | Trip Rept of 851125 Visit to S&W Engineering Corp Re Audit of Nonseismic Piping Effects on Seismic Design Piping. Further Audit of Anchor Designs Required.List of Attendees & Related Info Encl | Earthquake |
ML20141K373 | 5 December 1985 | Trip Rept of 851126 Audit Discussions Per Slenderness Ratio Limitations for Hanger Type Supports.Ebasco Svcs,Inc Considering Adoption of Revised Procedure.Slenderness Ratios Should Be Used Only Where Uncertainties Exist | |
ML20141K376 | 2 December 1985 | Trip Rept of 851011 Audit W/Util,Tera & Comanche Peak Response Team.List of Attendees Encl.Meeting Between Tera & BNL Consultants Will Be Held to Discuss Steam Generator Lateral Restraints | |
ML20141K394 | 2 December 1985 | Trip Rept of 851113-14 Visit to Corporate Consulting & Development Co,Ltd to Audit Ongoing Tests of Electrical Conduit Clamps | |
ML20141K403 | 2 December 1985 | Trip Rept of 851118-22 Audit of Cable Tray Hanger Walkdown. Supports Walked Down & Noted Discrepancies Listed | |
ML20141K484 | 22 November 1985 | Trip Rept of 851025 Audit at S&W Ofcs in New York,Ny Re Piping & Pipe Support Effort.List of Attendees Encl | |
ML20137G635 | 21 November 1985 | Draft Trip Rept 2178 of 851029-31 Site Visit Re Item Vii.C, Const Reinsp/Documentation Review Plan | |
ML20138P784 | 24 October 1985 | Trip Rept of 850827-29 Site Visit W/Util & Contractors Re Witnessing of Unit 1 Cable Tray Supports Walkdown in Progress & Collection of Info Concerning New Allegations | |
ML20141K199 | 22 October 1985 | Trip Rept of 851008 Visit to Gibbs & Hill Ofc in New York,Ny Re Audit of Adlpipe Computer Code Used in Piping Analysis. Allegation AP-26 Questioning Validity of Code Verification & QA Maint Unsubstantiated.Agenda Encl | |
ML20141K238 | 22 October 1985 | Trip Rept of 851014-18 Site Visit Re Status of Comanche Peak Response Team Verification & Corrective Action Activities by S&W,Ebasco & Tera,Qa/Qc Const Verification Effort & Action Plan Implementation | Design basis earthquake |
ML20141K211 | 11 October 1985 | Trip Rept of 851008 Visit to Gibbs & Hill Ofc Re Followup on Allegation A-26 That Adlpipe Computer Program Not Validated. Attendance List Encl | |
ML20141K437 | 11 October 1985 | Trip Rept of 850923-26 Audit of S&W as-built Verification Walkdown.Contingent Upon Acceptable Resolution Re Piping Run Geometry & Clearances,S&W Walkdown Well Documented & Easily Verifiable | |
ML20141K467 | 11 October 1985 | Trip Rept of 850923-26 Site Visit W/Teledyne Engineering Svcs Re Audit of S&W as-built Verification Walkdown | |
ML20141K126 | 10 September 1985 | Trip Rept of 850829-30 Visit W/Util & Teledyne at S&W Ofcs in New York,Ny Re Status of S&W Effort Concerning Design Adequacy Program for Plant Piping & Pipe Supports.Lists of Attendees,Agenda & Util Action Plan Encl | |
ML20213F364 | 5 March 1985 | Trip Rept of 850208 Site Visit to Inspect Unused Holes in Cable Tray Support Flanges,To Locate Cantilevered Horizontal Plate Attached to Containment Liner Plate & to Inspect & Gather Info on Elastic Joint Filler | |
ML20141K430 | 7 February 1985 | Trip Rept of 850126 Site Visit Re Observation of Schmidt Hammer Tests,Seismic Air Space Between Structures & Insp of Portion of Exposed Ceiling in Control Room.List of Attendees & Comments Encl | |
ML20199G318 | 15 January 1985 | Trip Rept of 841114-16 Site Visit Re Meetings W/Qa/Qc Inspectors to Emphasize That All Safety Issues Must Be Resolved Before Units Can Be Licensed | |
ML20138M974 | 20 December 1983 | Trip Rept of 831129-30 Site Visit Statistical Analysis of Backfit Insp Program | Coatings Backfit |
ML20054N043 | 7 July 1982 | Trip Rept of Caseload Forecast Panel 820413-15 Meeting W/Util at Site Re Collection of Data for Assessing Projected Fuel Load Date | Hydrostatic |