ML20054N043

From kanterella
Jump to navigation Jump to search
Trip Rept of Caseload Forecast Panel 820413-15 Meeting W/Util at Site Re Collection of Data for Assessing Projected Fuel Load Date
ML20054N043
Person / Time
Site: Comanche Peak  
Issue date: 07/07/1982
From: Burwell S
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
Shared Package
ML20054N038 List:
References
NUDOCS 8207150296
Download: ML20054N043 (10)


Text

![*

g'*

UNITED STATES a -

V.

o NUCLEAR REGULATORY COMMISSION n

{ *.-

.,f WASHINGTON, D. C. 20555

('..../

JUL 7 1982 Docket Nos.:

50-445 and 50-446 AP PLIC ANT: Texas Utilities Generating Company FACILITY:

Comanche Peak Steam Electric Station, Units 1 and 2

SUBJECT:

SUMMARY

OF CASELOAD FORECAST PANEL EETING AND FACILITY TOUR AT COMANCHE PEAK Summary On April 13,14 and 15,1982, the Caseload Forecast Panel (CFP) met with the applicant and toured the Comanche Peak Steam Electric Station, Units 1 and 2 for the purpose of collecting data for assessing the projected fuel loading dates for these. two nuclear units. The visit was organized into two parts; 1.

A meeting with the applicant to review design and engineering, procurement and construction progress. Progress on prerequisite testing and preoperational procedures and testing was also revi ewed.

(First day) 2.

A tour of the station f acilities to observe status of construction.

The CFP also held discussions, with the NRC Resident Construction Inspector and NRC Resident Operations Inspector.

(Second and third day)

In sunnury, the applicant's target dates for fuel loading Unit 1 is June 1983, and for Unit 2 is December 1984. The CFP believes that the fuel loading date for Unit 1 could be in December 1983. The CFP estimates that the fuel loading date for Unit 2 is approximately 16 months later.

The data upon which our projections are based is given in the followi.ng sections of this meeting summary.

^

Meeting and Facility Tour Details Tuesday, April 13, 1982 at NRC Region IV, Arlington, Texas On this date, the CFP met with the applicant at the NRC Region IV offices in Arlington, Texas. This meeting was open to public observers as noted on the Meeting Notice issued March 29, 1982. A list of attendees and observers at the meeting and tour is given in Enclosure 1.

820715o296 820709 PDR ADOCK 0500044S G

PDR

~

~

JUL 7 1982 Mr. Burwell opened the meating with introductions and a statement on the purpose of the treeting.

The staff noted that it is still NRC practice to schedule OL reviews indexed to the applicant's dates. Therefore, the CFP projected dates take on less significance than in the past.

The agenda for the meeting was enclosed with the Meeting Notice noted above.

The applicant's presentation on the status of engineering, procurement and construction was led by Mr. J. B. George. Mr. George advised that construction on Unit I was 86 percent complete and construction on Unit 2 was 46 percent complete.

Fuel loading dates for Unit 1 and Unit 2 are targeted for June 1983 and December 1984 respectively. Major milestone dates for construction are shown on Enclosure 2.

The applicant has scheduled the hydrostatic test of the reactor coolant system for late June 1982. The Unit 1 turbine is now on its turning gear.

Many of the process systems are undergoing flushing and cleaning.

Electrical systems are energized. Of 298 subsystems necessary to operate Unit 1, construc-tion has turned over 193 subsystems to the startup group.

The installation of pipe hangers and restraints on Unit 1 are nearing completion and delays associated with this effort are a thing of the past. Mr. George noted that construction on Unit 2 was progressing smoothly and rapidly because of.

lessons learned on constructing Unit l.'

Mr. George stated there were no antici-pated problem areas which will delay fuel loading past the applicant's projected dates on either Unit 1 or Unit 2.

The engineering for the basic Unit 1 design has been complete for some time.

Engineering is now limited to the new requirements imposed by NUREG-0737 and resolution of interferences. The applicant's objective is to execute all NUREG-G737 requirements prior to loading. fuel in Unit 1.

The principal engineering effort on Unit 2 is over; the basic design is over 90 percent complete. The larg2r engineering activities are the design review of site generated design changes and the design of piping supports and restraints.

1 Procurenunt on Units 1 'and 2 is nearly complete. The only problem areas relate to additions to the uninterruptable power supply, radiation monitors, and sump and flood level instrumentation. ThE' equipment for the Technical Support Center and Emergency Offsite Facility wil.l..be delivered by Summer 1982.

l There are presently 4800 people working on construction of the site. They work 5 days a week,10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> a day. Two shifts are operational, with about 700 people working the back shift. About 1000 of the construction people are working on Unit 2, this will increase with time as Unit 1 nears completion.

The present l

craf t work force consists of approximately 1,460 mechanical, 850 electrical, 60 instrumentation and control, and 880 civil workers. These will increase slightly until December 1982 and then decrease as Unit 2 nears completion.

l

a -

~

'JUL 7 1982- ~

_3_

The status of construction on.both Units 1 and 2 is summarized by the bulk conmadi ty comparison Table, Enclosure 3.

For Unit 1 structural concrete and piping and hangers are 93 percent or greater completed and wire and cables are greater than 75 percent complete except for security and lighting.

For Unit 2, structural concrete is 99 percent complete, large pipe is 60 percent complete, and small pipe, pipe hangers and electrical wire supports are roughly one-third complete. Little of the Unit 2 wire and cable has been installed at this time.

Mr. George summarized the status of construction of Unit 1 by describing an area analysis of scheduling status. Each building is reviewed for the work remaining to support a target fuel load date of June 15, 1983 for Unit 1.

All buildings are o.n schedule except the reactor building which shows a 32 day criticality (days to be recovered in order to meet the target date).

Since the previous CFP visit the applicant has made a decision to complete major construction activities in the Unit 2 control panel and cable spreading room areas prior to the fuel loading date for Unit 1.

Construction in this manner eliminates the need for a security barrier between these portions of the control building during completion of Unit 2.

This decision has added considerably to the wire and cable quantities which must be installed prior to Unit 1 fuel loading. Nevertheless, the work remaining in the control building is on schedule for a June 1983 fuel loading date.

The applicant's presentation on the status of the preoperational procedures, system turnover to the startup group and preoperational testing was led by Mr. Dick Camp. The status of preoperational procedures preparation is shown in the following table:

Preopsl Accept 2 Total Total test procedures required 135 41 176 Draft procedures not started 43 4

47 Draf t procedures in preparation 92 37 129 Draf t procedures being worked 34 6

40

, Test procedures in review 13 4

17 Test procedures approved 0

0 0

1)

Preoperational test procedures for safety related systems.

~

2)

Acceptance test procedures for non-safety systems.

The status of system testing was discussed. The construction group must turn-over 298 subsystems to the startup group for prerequisite and preoperational testing. The startup group has accepted 193 subsystems at this time. However, nearly all of subsystems have a list of items (punch list items) which must be resolved before the system is complete. The punch list for included subsystems

~

_4_s JbL

'? 1982 mst be essentially resolved before preoperational testing of a system can bega n.

Preoperational testing is expected to start in late June 1982.

The startup group is currently staffed at 45 startup engineers. The applicant expects this group to peak at about 68 startup engineers at the end of the year and remain constant through the third quarter of 1983.

The applicant reviewed the list of open potential deficiencies which were reported to the NRC in accordance with the requirements of 10 CFR 50.55(e).

The applicant does not expect any of these to impact the June 1983 fuel loading date.

Wednesday, April 14, 1982 at Comanche Peak Steam Electric Station, Glen Rose, Texas The CFP observed constnJction progress in the Unit 1 containment building, Unit i safeguard building, Unit 1 diesel generator rooms, and fuel building.

All large equipment items are installed. Most of the large and small piping is installed and complete. Many of the systems are running. Most of the pipe supports are installed. Most of the cabling is installed except that some of the cabling inside containment is not terminated.

The CFP met briefly with Mr. Dick Camp to review several documents that were not available at the April 13, 1982 meeting. The CFP inspecte,d the Master Systen Punchlist, a computer printout sheet, to gain insight into the number, nature, and scope of unresolved items remaining in the subsystems accepted by the startup group.

The CFP also inspected a documnt entitled Summary of CPSES Startup Program to gain insight into the organization and planning for the startup program.

The CFP interviewed the NRC Resident Construction Inspector, Mr. R. G. Taylor, and the NRC Resident Operations Inspector, Mr. D. L. Kelley during the April 14, 1982 facility vi sit. Mr. Taylor confirmed the general status of construction as presented by the applicant and observed by the CFP. Mr. Kelley confirmed the general status of preparation of operational procedures and conduct of testing operations by the startup group as presented by the applicant.

Thursday, April 15, 1982 at Comanche Peak Steam Electric Station, Glen Rose, l

Texas.

The CFP observed construction progress in the Unit 2 containment building and in the auxiliary building, particularly in the control room and cable spreading rooms.

Construction is proceeding rapidly on Unit 2.

The applicant has made l

i l

a.

. JUL 7 1982 provisions for mounting pipe. hangers and restraints by embedding large numbers of studs in the walls throughout the Unit 2 containment. The installation of piping, piping hangers and cable trays appears well planned-and proceeding ef fici ently.

The control panel for Unit 1 is energized with many controls, instnaments and alarms functioning. The applicant has initiated a program to rework the control panel to reflect the results of its human factors review of the control room.

The applicant does not expect this to delay the June 1983 target fuel loading da te. The Unit 1 cable spreading room has a few empty cable trays, but most of the cables are in place.

The control consoles for Unit 2 are sitting in place, but there has been little or no wiring installed between the consoles and the Unit 2 cable spreading room.

The Unit 2 cable spreading room has the cabinets set in place and most of the cable trays are installed.

There are few if any cables installed in the Unit 2 cable spreading room.

Summary The CFP reviewed the status of constnJction on Units 1 and 2 and the status of the preoperational testing program for Unit 1.

The bulk of construction on Unit 1, and associated stnictures and systems needed to operate Unit 1,-

is approaching completion. The preoperational testing program for Unit 1 is expected to start in June 1982. Construction on Unit 2 appears to be proceeding efficiently.

Considering the status of construction and the preoperational testing program, the CFP believes the fuel loading date for Unit 1 could be in December 1983 provided no major delays develop during preoperational testing. The CFP estimates that the fuel loading date for Unit 2 is approximately 16 months later.

W.b S. B. Burwell, Project Manager Licensing Branch No.1 Division of Licensing s.._

Encl osures:

1.

Meeting & Facility Tour Attendance 2.

Construction Milestones 3.

Bulk Commodity Comparison i

cc w/encls.:

See next page l

l

Mr.'R. J. Gary Executive Vice President and General Manager Texas Utilities Generating Company 2001 Bryan Tower Dallas, Texas 75201 cc:

Nicholas S. Reynolds, Esq.

Mr. Robert G. Taylor Debevoise & Liberman Resident Inspector / Comanche Peak 1200 Seventeenth Street, N. W.

Nuc. lear Power Station Washington, D. C.

20036 c/o U. S. Nuclear Regulatory Commission j

Spencer C. Relyea, Esq.

P. O. Box 38 Worsham, Forsythe & Sampels Glen Rose, Texas 76043 2001 Bryan Tower

~

Dallas, Texas 75201 fir. John T. Collins U. S. NRC, Region IV Mr. Homer C. Schmidt 611 Ryan Plaza Drive Manager - Nuclear Services.

Suite 1000 Texas Utilities Services, Inc.

Arlington, Texas 76011 2001 Bryan Tower Dallas, Texas 75201 Mr. H..R.. Rock Gibbs and Hill, Inc.

393 Seventh Avenue New York, New York 10001 Mr. A. T. Parker Westinghouse Electric Corporation P. O. Box 355 Pittsburgh, Pennsylvania,15230 David J. Preister Assistant Attorney General Environmental Protection Division P. O. Box 12548', Capitol Station Austin, Texas 78711 Mrs. Juanita Ellis, President Citizens Association for Sound Energy

~1426 South Polk Dallas, Texas 75224 N

ee e

4 ENCLOSURE 1 1

14EETING AND FACILITY TOUR ATTENDANCE COMANCHE PEAK STEAM ELECTRIC STATION, UNITS 1 AND 2 Tuesday, April 12, 1982; NRC Region IV Offices

~

NRC Staff Applicants Observers-S. B. Burwell J. B. George J. Ellis, CASE W. H. Lovelace R. E. Camp M. Scott, Forth Worth B. J. Youngblood R. A. Jones Star-Telegram M. V. Rothschild J. S. Marshall D. Ferguson, Radio C. E. Wisner R. Werner Station-KRLD G. Hedrick D. Cassidy, WFAA-TV.

K. Sewell Wednesday, April 14, 1982; Comanche Peak Station

/

NRC Staff Applicants S. B. Burwell R. Murray W. H. Lovelace.

R. Werner B. J. Youngblood M. V. Rothschild Staff held discussions with R. E. Camp, R. Taylor and D. Kelley, Thursday, April 15, 1982; Comanche Peak Station NRC Staff Applicants S. B. Burwell

,R. Murray W. H. Lovelace R. Werner 3

B. J. Youngblood Staff held. discussion with R. Taylor.

l l.

ENCLOSURE 2 i

CONSTRUCTION MILESTONES MAJOR MILESTONES COMPLETE DATE 1.

Begin fill of Squaw Creek Reservoir Feb. 15, 1977 2.

Set Reactor Vessel Unit #1 May 11, 1978 Unit #2 July 4, 1979 3.

Top-Out Containment Unit #1 Jan.19,1979 Unit #2 Oct. 17, 1980 4.

Complete Major Concrete Unit #1 July 1979 Unit #2 Oct. 1980 5.

Energize Transformers 138 KV Jan. 11, 1980 345 KV July 1, 1981 6.

Run First Major Mechanical System March 5, 1981 (Service Water) 7.

Completion of Secondary Flush,

April 4, 1982 p

h6faDJM N S W MAJOR MILESTONES TO G0 DATE 1.

Hydrostatic Test of Steam Generators May 1982 Lik: Jant 2.

Hydrostatic Test of Reactor Coolant System

-Scptcr.ber 1982 3.

Begin Hot Functional Tests December 1982 4.

. Integrated Leak Rate Test o_f. Containment December 1982 5.

Fuel Load Mid 1983

~

Sheet 1 of 2

4 UNIT Fr SU:lttARY ilAJ0R 111LESTONES:

Fuel Load December, 1984 -

SIT /lLRT September, 1984 June, 1984 Hot Functional March, 1984 RCS Cold Hydro February,1984 Steam Generator Hydro Diesel. Generator -

January,1984 Sequence December,1983 CVCS Flush November,1983 ECCS Flush Chemical Cleaning October,1983 September, 1983 RHR Flush STATUS:

DISCIPLINE

" COMPLETE Electrical 17.10%

Piping 39.28%

Instrumentation 25.82%

Civil /Structuta.1__

74.76%

tlechanical 27.17%

TOTAL 48.35" Piping is scheduled to complete the first quarter of 1983.

j Hangers are scheduled to complete the third quarter of 1983.

Electrical & Instrumentation are scheduled to complete the second quarter of 1984.

Sheet 2 of 2 i

4 DULK CGHODITY C0HPAR150N COHANCl!E PEAK UNITS 1 8 2 DATA 111RU mRCil 27, 1982 UNIT 1 UNIT 2 UNITS 1 4 2 EST!MTE ACTUAL

% COMP.

ESTlHATE ACTUAL

% COMP.

ESTlHATE ACRIAL

% CINP.

CONCRETE CY 273,408 268,022 98.0 107,296 106,687 99.4 3R0,704 374.709 98.4 PROCESS PIPE 2's 6 larger LF 138,907 130,784 94.2 101,279 61,393 60.6 240,186 192,177 80.0 2" 4 Smaller 1.F 178,562 174,082 97.5 79,766 28,028 35.1 258,328 202.110 78.2 YARD P!PE LF 36,262 36,259 100.0 6,096 6,065 99.5 42,358 42,324 99.9 PIPE IIANGERS 2's" 6 Larger EA 15.069 13,986 92.8 -

10,609 3,513 33.1 25,678 17,499 68.1 2" 6 Smaller EA 29,990

{ 28,388 94.7.

12.265 1,941 15.0 42,255 30,329 71.8 CARLE TRAY ~

fF 81,876 80,794 98.7 38,810 20.140 51.9 120,686 100,934 f 3. 6 CONDUIT 1.576,415' l.082.769 68.7 Total LF I,067,091 946,204 88.7 509,324 136,565 26.8 Exposed LF

$00,855 460,263 91.9 283,552 13,478 4.8 784,407 473,741 60.4 WIRE 4 CA!LLE-PULL Power LF 872,982 690,542 79.1 397,091 1,270,073 690,542 54.4 Control LF 2,869,101 2,708,905 94.4 1,332,415 20 4,201,516 2,708,925 64.5 385,000 42,936 11.2 Security LP 385,000 42,936 11.2 Instrumentation LF 922,915 728,543 78.9 605,564 1,598,479 728,543 45.6 Lighting LF 900,752 654,968 72.7 326,995 16.130 4.9 1,227,747 671,098 54.7 N!RE 6 CABLE-TERMINATE 33,675 14,737 43.8 Power EA 19,484 14,737 75.6 14,191 141,704 89,488 63.2 Control EA 95,330 89,488 93.9

'46,374 Security EA 14,000 4,239 30.3 14,000 4,239 30.3 Instrumentation EA 34,560 26,098 75.5 27,526 62,086 26.098 42.0 Lighting EA 39,921 18,983 47.6 18,529 58,450 18,983 32.5 INSTRlNENTS EA 2,525 1,933 76.6 1;858 238 12.8 4.383 2,171 49.5 m

Z O

FO t.n 55 m

~

e