Trip Rept of 851008 Visit to Gibbs & Hill Ofc in New York,Ny Re Audit of Adlpipe Computer Code Used in Piping Analysis. Allegation AP-26 Questioning Validity of Code Verification & QA Maint Unsubstantiated.Agenda Encl
ML20141K199
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 10/22/1985
From: Hou S
NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM)
To: Shao L
NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM)
Shared Package
ML20141K202 List:
References
NUDOCS 8601220351
Download: ML20141K199 (2)


Text

, ,

M n ] j

' U864TED 51 Alts

, siesste %

f .\ NUCLE AR REGULATORY COMMisslON WASHipvGTOed. O C 30655

[

T- OCT e 2 25 fo MEMORANDlM FOR: Larry C. Shao, Leader Engineering Group Comanche Peak Project FROM:

Shou N. Hou, Mechanical / Piping Subgroup Leader Comanche Peak Project

SUBJECT:

TRIP REPORT - AUDIT OF G & H PIPING CODE On October 8,1985, the Staff and its consultant visited Gibbs & Hill (G&H) Office in New York for auditing the ADLPIPE computer code used by G&H in their piping analysis. This is a follow-up action for our evaluation of allegation AP-26, which questioned validity of code verification and QA maintenance. Audit agenda, summary of findings, and attendance list are attached.

The audit concludes that the alleged computer code was verified and QA maintained in accordance with acceptable procedure. Allegation AP-26 is not substantiated and there is no violation and adverse impact to the Comanche Peak Project. Our evaluation to AP-26 is complete.

7

3. W'

?

ou N. Hou Mechanical / Piping Subgroup Leader Comanche Peak Project

Enclosures:

1. Audit Agenda
2. Sumary of Audit Findings
3. Attendance List cc: V. Noonan J. P. Knight R. Ballard' S. Burwell R. Bosnak G. Bagchi C. Tramell D. Terao A. Vietti-Cook R. Masterson T. Westennan, RIV D. Landers, Teledyie jfh

, 8601220351 851022 PDR ADOCK 05000445 PDR

l AGENDA f istC AUDIT ON ADLPIPE PIPING ANALYSIS COMPUTER PROGRV.

I October 8,1985 Gibbs & Hill Office in New York

1. G & H Effort on ADLPIPE Code verification

- Benchmark problems and other computer ccdes used for comparison

- Compliance with Regulatory Guide 1.92

- G & H Procedure EDP-10

2. QA Maintenance of DIS /ADLPINE 4

- procedures used for updating, changing and identifying deficiencies

- personnel responsibilities for disseminating and evaluating pertinent infonnation

- Objective evidence that revisions have been reviewed and addressed according to procedures

- Mechanism to implement corrective actions.

3. Impact on Comanche Peak Project

- Deficiencies, if any, that require reanalpis.

Participants TUGC0 - John Marshall G5H - Bob Ballard, et al i i

NRC/ Comanche Feak Project - Shou Hou, Bob Masterson