 Issue dateTitleTopic
ML20217K33019 October 1999Safety Evaluation Supporting Amend 195 to License DPR-61High Radiation Area
Offsite Dose Calculation Manual
Incorporated by reference
Process Control Program
Fuel cladding
Fire Protection Program
ML20206C87628 April 1999Safety Evaluation Supporting Amend 194 to License DPR-61Earthquake
Pressure Boundary Leakage
CY-99-047, Ro:On 981217,identified Unsuccessful Dewatering of Cnsi HIC, Model PL8-120R,containing Resins.Caused by Apparent Failure of Dewatering Tree.Other HICs Have Been Procured,Recertified & Returned to Plant for Use23 March 1999Ro:On 981217,identified Unsuccessful Dewatering of Cnsi HIC, Model PL8-120R,containing Resins.Caused by Apparent Failure of Dewatering Tree.Other HICs Have Been Procured,Recertified & Returned to Plant for Use
CY-99-027, Annual Rept for 10CFR50.59, for Jan-Dec 1998.With31 December 1998Annual Rept for 10CFR50.59, for Jan-Dec 1998.WithSafe Shutdown
Boric Acid
Offsite Dose Calculation Manual
Fire Barrier
Time to boil
Temporary Modification
Process Control Program
Exemption Request
Earthquake
Fuel cladding
Continuous fire watch
Fire Protection Program
Fire Watch
ML20206F19731 December 1998Annual Rept for 1998 for Cyap. with
ML20198G91022 December 1998Proposed Rev 2 of Cyap QAP for Haddam Neck Plant. Marked Up Rev 1 IncludedOffsite Dose Calculation Manual
Nondestructive Examination
Process Control Program
Fire Protection Program
ML20238F21328 August 1998SER Accepting Defueled Emergency Plan for Emergency Planning for Connecticut Yankee Atomic Power CoFuel cladding
CY-98-136, Ro:On 980727,flow Blockage Occurred & Caused Pressure in Sys to Increase,Resulting in Relief Valve Lifting & Pipe Vibration,Which Caused Leaks to Develop.Caused by Nearly Closed post-filter Inlet Valve.Repaired 2 Leaks in Line12 August 1998Ro:On 980727,flow Blockage Occurred & Caused Pressure in Sys to Increase,Resulting in Relief Valve Lifting & Pipe Vibration,Which Caused Leaks to Develop.Caused by Nearly Closed post-filter Inlet Valve.Repaired 2 Leaks in Line
ML20237B74622 July 19981998 Defueled Emergency Plan Exercise Scenario Manual, Conducted on 980722Fire Watch
ML20202D16230 June 1998Safety Evaluation Supporting Amend 193 to License DPR-61Safe Shutdown
Shutdown Margin
Ultimate heat sink
Anticipated operational occurrence
Probabilistic Risk Assessment
Fuel cladding
Fire Protection Program
CY-98-068, Follow-up to Verbal Notification on 980413 of Film on Discharge Canal.Investigation Continuing.Samples Collected for Petroleum Analyses & Biological Characterization at Intake Structure & Discharge Canal.Replaced Sorbent Booms15 April 1998Follow-up to Verbal Notification on 980413 of Film on Discharge Canal.Investigation Continuing.Samples Collected for Petroleum Analyses & Biological Characterization at Intake Structure & Discharge Canal.Replaced Sorbent Booms
CY-98-045, Ro:On 980212,0219,0225 & 0312,separate Sheens of Approx One Cup of oil-like Substance Was Observed at Discharge Canal. Cause Has Not Been Clearly Identified.Called in Vendor Spill to Install Sorbent Booms to Absorb Sheen.W/One Drawing13 April 1998Ro:On 980212,0219,0225 & 0312,separate Sheens of Approx One Cup of oil-like Substance Was Observed at Discharge Canal. Cause Has Not Been Clearly Identified.Called in Vendor Spill to Install Sorbent Booms to Absorb Sheen.W/One Drawing
ML20217A00031 March 1998Monthly Operating Rept for Mar 1998 for Haddam Neck Plant
ML20217F06131 March 1998Historical Review Team ReptOffsite Dose Calculation Manual
Anticipated operational occurrence
Annual Radiological Environmental Operating Report
Process Control Program
Systematic Assessment of Licensee Performance
Fuel cladding
Power change
ML20217K21027 March 1998Safety Evaluation Supporting Amend 192 to License DPR-61High Radiation Area
Offsite Dose Calculation Manual
Process Control Program
CY-98-046, Follow-up to 980311 Verbal Notification of Film on Discharge Canal.Cause Not Yet Determined.Film Is Contained & Will Be Absorbed by Containment & Sorbent Booms That Were in Place in Discharge Canal12 March 1998Follow-up to 980311 Verbal Notification of Film on Discharge Canal.Cause Not Yet Determined.Film Is Contained & Will Be Absorbed by Containment & Sorbent Booms That Were in Place in Discharge Canal
ML20216D65328 February 1998Monthly Operating Rept for Feb 1998 for Haddam Neck Plant
ML20217D73828 February 1998Revised MOR for Feb 1998 Haddam Neck Plant
CY-98-012, Monthly Operating Rept for Jan 1998 for Connecticut Yankee Haddam Neck Plant31 January 1998Monthly Operating Rept for Jan 1998 for Connecticut Yankee Haddam Neck Plant
ML20217P48631 December 19971997 Annual Financial Rept, for Cyap
CY-98-010, Annual Rept for 10CFR50.59,Jan-Dec,199731 December 1997Annual Rept for 10CFR50.59,Jan-Dec,1997Safe Shutdown
Boric Acid
Ultimate heat sink
Anchor Darling
Emergency Lighting
Fuel cladding
Fire Protection Program
ML20198N66831 December 1997Monthly Operating Rept for Dec 1997 for Haddam Neck Plant
ML20199L58924 December 1997Independent Analysis & Evaluation of AM-241 & Transuranics & Subsequent Dose to Two Male Workers at Connecticut Yankee Atomic Power Plant
ML20203K42730 November 1997Monthly Operating Rept for Nov 1997 for Haddam Neck Plant
ML20199B11431 October 1997Monthly Operating Rept for Oct 1997 for Haddam Neck Plant
ML20198M81014 October 1997SER Accepting Proposed Revs to Util Quality Assurance Program at Facility
ML20198J88130 September 1997Monthly Operating Rept for Sept 1997 for Haddam Neck Plant
ML20217Q31731 August 1997Addl Changes to Proposed Rev 1 to QA Program
ML20210P87231 August 1997Post Decommissioning Activities Rept, for Aug 1997Coatings
ML20210U93031 August 1997Monthly Operating Rept for Aug 1997 for Haddam Neck Plant
CY-97-082, Special Rept:On 970708,routine Surveillance Testing of Seismic Monitoring Sys Instrumentation Revealed,Data Was Not Being Reproduced by Portion of Playback Sys.Station Presently Pursuing Replacement of Seismic Monitoring Sys14 August 1997Special Rept:On 970708,routine Surveillance Testing of Seismic Monitoring Sys Instrumentation Revealed,Data Was Not Being Reproduced by Portion of Playback Sys.Station Presently Pursuing Replacement of Seismic Monitoring SysSafe Shutdown Earthquake
Operating Basis Earthquake
Earthquake
ML20210L05231 July 1997Monthly Operating Rept for July 1997 for HNP
ML20149E44530 June 1997Monthly Operating Rept for June 1997 for Haddam Neck Plant
ML20140H52431 May 1997Monthly Operating Rept for May 1997 for Haddam Neck Plant
ML20141A00431 May 1997Independent Assessment of Radiological Controls Program at Cyap Haddam Neck Plant Final Rept May 1997High Radiation Area
Locked High Radiation Area
Process Control Program
Scaffolding
ML20141K42022 May 1997Safety Evaluation Supporting Amend 191 to License DPR-61Offsite Dose Calculation Manual
ML20141D41430 April 1997Monthly Operating Rept for Apr 1997 for Connecticut Yankee Haddam Neck
ML20138G59025 April 1997Proposed Rev 1 to Cyap QA Program for Haddam Neck PlantBoric Acid
Nondestructive Examination
Fire Protection Program
ML20137H30331 March 1997Rev 2 to Nuclear Training Loit/Lout Audit ReviewsPower change
ML20137W80531 March 1997Monthly Operating Rept for Mar 1997 for Haddam Neck Plant
ML20137C62814 March 1997Redacted Version of Rev 1 to Nuclear Training Loit/Lout Audit Reviews
ML20137A08028 February 1997Monthly Operating Rept for Feb 1997 for Haddam Neck Plant
ML20135C51026 February 19971996 Refuel Outage ISI Summary Rept for CT Yankee Atomic Power CoBoric Acid
Nondestructive Examination
Liquid penetrant
Dissimilar Metal Weld
B16268, Special Rept:On 970205,declared Main Stack-Wide Range Noble Gas Monitor Inoperable.Caused by Inadequate Calibr Methods. Will Revise Calibr Procedure to Technique to Demonstrate Accuracy & Linearity Over Intended Range of Monitor19 February 1997Special Rept:On 970205,declared Main Stack-Wide Range Noble Gas Monitor Inoperable.Caused by Inadequate Calibr Methods. Will Revise Calibr Procedure to Technique to Demonstrate Accuracy & Linearity Over Intended Range of Monitor
ML20135E32213 February 1997Independent Review Team Rept 1996 MP -1 Lout NRC Exam FailuresCondition Adverse to Quality
Grace period
ML20134L2753 February 1997Draft Rev to GPRI-30, Spent Fuel Storage Facility Licensing Basis/Design Basis
ML20138K57231 January 1997Monthly Operating Rept for Jan 1997 for Haddam Neck Plant.W/
ML20134L27910 January 1997Rev 0 to QA Program Grpi
ML20134L2918 January 1997Rev 0 to UFSAR Rev Grpi
ML20133M61231 December 1996Monthly Operating Rept for Dec 1996 for Yankee Haddam Neck Plant