Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
IR 05000312/1999003 | 31 August 1999 | Insp Rept 50-312/99-03 on 990802-06.No Violations Noted. Major Areas Inspected:Decommissioning & Dismantlement Activities,Including Organization,Mgt & Cost Controls | Temporary Modification Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report |
IR 05000312/1999002 | 19 March 1999 | Insp Rept 50-312/99-02 on 990309-11.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program, Including Access Authorization,Alarm Station & Communication & Testing & Maint | |
IR 05000312/1998003 | 7 August 1998 | Insp Rept 50-312/98-03 on 980706-09.No Violations Noted. Major Areas Inspected:Review of Licensee Programs Related to SFP Safety,Status of Decommissioning,Safety Review & self-assessments & Radiological Safety Programs | High Radiation Area Scaffolding |
ML20248K630 | 3 June 1998 | Notice of Violation from Insp on 980519-21.Violation Noted:Inspector Determined That Licensee Failed to Review & Consider All Info Obtained During Background Investigation | |
IR 05000312/1998002 | 3 June 1998 | Insp Rept 50-312/98-02 on 980519-21.Violations Noted. Major Areas Inspected:Announced Insp of Licensee Physical Security Program | |
ML20202C477 | 5 February 1998 | Notice of Violation from Insp on 980105-08.Violation Noted: on 971222,shipment of Scrap Metal,In Form of Auxiliary Boiler,Was Released from Rancho Seco Site W/O Having Been Surveyed | |
ML20202C498 | 5 February 1998 | Insp Rept 50-312/98-01 on 980105-08.Violations Noted.Major Areas Inspected:Organization,Mgt & Cost Controls,Maint & Surveillance,Cold Weather Preparation,Decommissioning Performance & Status Review & Health Physics | Liquid penetrant |
ML20198K545 | 21 October 1997 | Notice of Violation from Insp on 970922-25.Violation Noted:On 970806,thermocouple for Spent Fuel Pool Temp Indicator Was Found to Be out-of-tolerance During Annual Calibration | |
IR 05000312/1997004 | 21 October 1997 | Insp Rept 50-312/97-04 on 970922-25.Violations Noted. Major Areas Inspected:Organization,Mgt,Cost Control,Safety Reviews,Design Changes,Mods,Decommissioning Performance & Status Review | Offsite Dose Calculation Manual Condition Adverse to Quality Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report |
IR 05000312/1997003 | 17 June 1997 | Insp Rept 50-312/97-03 on 970603-05.No Violations Noted. Major Areas Inspected:Records & Repts,Testing & Maint, Protected Area Barrier & Detection Aids,Assessment Aids, Alarm Station & Communication & Security System | |
IR 05000312/1997002 | 25 April 1997 | Insp Rept 50-312/97-02 on 970331-0403.No Violations Noted. Major Areas Inspected:Incremental Decommissioning Activities in Turbine Bldg,Radiation Protection,Sfp Activities & Quality Assurance | |
IR 05000312/1997001 | 21 March 1997 | Insp Repts 50-312/97-01 & 72-0011/97-01 on 970224-27.No Violations Noted.Major Areas Inspected:Licensee Planned Work Associated W/Dismantlement of Turbine Bldg & Radiological Controls Being Implemented During Work Activities | Offsite Dose Calculation Manual Coatings Annual Radiological Environmental Operating Report Process Control Program Annual Radiological Effluent Release Report |
IR 05000312/1996003 | 27 September 1996 | Insp Repts 50-312/96-03 & 72-0011/96-01 on 960909-12.No Violations Noted.Major Areas Inspected:Sfp & Radiological Ts,Radiological Exposure Controls & Implementation of New 10CFR49 Shipping Regulations | High Radiation Area Locked High Radiation Area |
IR 05000312/1993006 | 2 September 1993 | Insp Rept 50-312/93-06 on 930819.No Violations or Deviations Noted.Major Areas Inspected:Licensee Employee Concerns Program | |
IR 05000312/1993004 | 11 August 1993 | Mgt Meeting Rept 50-312/93-04 on 930727.Major Areas Discussed:Status of Activities,Including Maint of Plant Equipment,Fire Protection Equipment & Plant Personnel Morale | |
IR 05000312/1992007 | 10 December 1992 | Insp Rept 50-312/92-07 on 921110-11.No Deviations or Violations Noted.Major Areas inspected:1992 Annual Emergency Preparedness Exercise & Associated Critiques & Inspector Identified Items | |
IR 05000312/1990014 | 14 November 1990 | Insp Rept 50-312/90-14 on 901003-04,09-11 & 1102.Violations Noted.Areas inspected:follow-up of Licensee Event Repts, Liquid Effluent,Solid Waste & Allegations | |
IR 05000312/1990011 | 31 July 1990 | Insp Rept 50-312/90-11 on 900527-0706.No Violations or Deviations Noted.Major Areas Inspected:Operational Safety Verification,Health Physics & Security Observations,Esf Sys Walkdown,Maint,Surveillance & Testing & QA | |
IR 05000312/1989016 | 21 September 1989 | Enforcement Conference Rept 50-312/89-16 on 890915. Violations Noted.Major Areas Discussed:Violations Noted in Insp Rept 50-312/89-16 & Indications That Findings Represent Decrease in Mgt Commitment to Emergency Preparedness | |
IR 05000312/1989012 | 21 September 1989 | Insp Rept 50-312/89-12 on 890801-04,21-25 & 30.No Violations Noted.Major Areas Inspected:Occupational Exposure,Including Alara,Radwaste Sys,Liquid & Liquid Wastes & Radwaste Mgt & Transportation | Offsite Dose Calculation Manual |
PNO-V-89-056, on 890911,SMUD Board Rejected Golden State Energy Proposal to Purchase Plant | 12 September 1989 | PNO-V-89-056:on 890911,SMUD Board Rejected Golden State Energy Proposal to Purchase Plant | |
IR 05000312/1989014 | 11 September 1989 | Insp Rept 50-312/89-14 on 890828-0901.Violations Noted Re Failure to Conduct Required Semiannual Health Physics Drill & Initial Training.Major Areas Inspected:Operational Status of Emergency Preparedness Program | |
PNO-V-89-053, on 890901,Golden State Energy Proposal to Purchase Rancho Seco Submitted to Util,Including MOU for Purchase of Plant,Power Sale Agreement & Interim Operation & Maint of Facility & Rate Structure.Vote Expected on 890907 | 5 September 1989 | PNO-V-89-053:on 890901,Golden State Energy Proposal to Purchase Rancho Seco Submitted to Util,Including MOU for Purchase of Plant,Power Sale Agreement & Interim Operation & Maint of Facility & Rate Structure.Vote Expected on 890907 | |
PNO-V-89-050, on 890823,util Announced That Board of Directors Would Meet on 890825 Re Proposed Golden State Energy Purchase of Plant.Key Issues Listed,Including MOU Addressing Power Sale Agreement | 23 August 1989 | PNO-V-89-050:on 890823,util Announced That Board of Directors Would Meet on 890825 Re Proposed Golden State Energy Purchase of Plant.Key Issues Listed,Including MOU Addressing Power Sale Agreement | |
IR 05000312/1989010 | 10 August 1989 | Insp Rept 50-312/89-10 on 890603-0721.No Violations Noted. Major Areas Inspected:Areas of Operational Safety Verification,Health Physics & Security Observations,Maint, Surveillance & Testing & QA & Followup Items | Shutdown Margin |
PNO-V-89-044, on 890720,util Board Voted by 4-1 Vote to Enter Exclusive Negotiations W/Quadrex Corp for Possible Sale of Plant.Key Milestone Dates Listed.Board Maintained That Several Key Issues Must Be Addressed Before Voting on Sale | 21 July 1989 | PNO-V-89-044:on 890720,util Board Voted by 4-1 Vote to Enter Exclusive Negotiations W/Quadrex Corp for Possible Sale of Plant.Key Milestone Dates Listed.Board Maintained That Several Key Issues Must Be Addressed Before Voting on Sale | |
IR 05000312/1989008 | 11 July 1989 | Insp Rept 50-312/89-08 on 890422-0602.No Violations or Deviations Noted.Two non-cited Violations Discussed.Major Areas Inspected:Operational Safety Verification,Health Physics & Security Observations & ESF Sys Walkdown | Moisture barrier |
IR 05000312/1989011 | 6 July 1989 | Insp Rept 50-312/89-11 on 890629-30.No Violations Noted. Major Areas Inspected:Licensee Radiochemical Analyses to Verify Accuracy of Measurements of Radionuclides in Release Tank Water & Sediment from Effluent Discharge Point | |
PNO-V-89-039, on 890620,util Announced That Licensee Open to Offers to Purchase Facility Until 890630.Of All Bidders,Only Quadrex Corp Proposes to Operate Facility as Nuclear Plant. Evaluation of Bids Expected to Be Completed by End of Jul | 3 July 1989 | PNO-V-89-039:on 890620,util Announced That Licensee Open to Offers to Purchase Facility Until 890630.Of All Bidders,Only Quadrex Corp Proposes to Operate Facility as Nuclear Plant. Evaluation of Bids Expected to Be Completed by End of Jul | |
PNO-V-89-036, on 890620,SMUD Voted 3-2 to Allow 10 Days for Qualified Private Bidders to Submit Proposals to Take Over Facility.Conditions Imposed on Bidders Listed.Existing Quadrex Proposal Withdrawn | 21 June 1989 | PNO-V-89-036:on 890620,SMUD Voted 3-2 to Allow 10 Days for Qualified Private Bidders to Submit Proposals to Take Over Facility.Conditions Imposed on Bidders Listed.Existing Quadrex Proposal Withdrawn | |
PNO-V-89-035, on 890619,licensee Announced That D Keuter Had Been Appointed New Site Manager & Jr Shetler as Deputy Site Manager.Licensee Recognizes That Organizational Changes Subj to NRC Approval | 20 June 1989 | PNO-V-89-035:on 890619,licensee Announced That D Keuter Had Been Appointed New Site Manager & Jr Shetler as Deputy Site Manager.Licensee Recognizes That Organizational Changes Subj to NRC Approval | |
PNO-V-89-034, on 890615,offer to Assume Financial & Technical Responsibility for Plant Announced.Plant Presently in Cold Shutdown W/Activities Continuing Towards off-loading Reactor Core in Oct 1989 | 16 June 1989 | PNO-V-89-034:on 890615,offer to Assume Financial & Technical Responsibility for Plant Announced.Plant Presently in Cold Shutdown W/Activities Continuing Towards off-loading Reactor Core in Oct 1989 | |
PNO-V-89-033C, on 890609,plant Reached Cold Shutdown in Preparation for Reinstalling Refueling Bridge Into Reactor Bldg.Bridge Removed for Refurbishment/Mod.Reduction in Force of Nonessential Contractor Personnel in Progress | 12 June 1989 | PNO-V-89-033C:on 890609,plant Reached Cold Shutdown in Preparation for Reinstalling Refueling Bridge Into Reactor Bldg.Bridge Removed for Refurbishment/Mod.Reduction in Force of Nonessential Contractor Personnel in Progress | |
PNO-V-89-033B, on 890608,licensee Continuing Cooldown of Plant.Ceo Nuclear,J Firlit,Announced Resignation.Work Force Reductions Initiated Which Will Initially Involve Approx 420 Nonessential Contractor Clerical & Crafts Personnel | 8 June 1989 | PNO-V-89-033B:on 890608,licensee Continuing Cooldown of Plant.Ceo Nuclear,J Firlit,Announced Resignation.Work Force Reductions Initiated Which Will Initially Involve Approx 420 Nonessential Contractor Clerical & Crafts Personnel | |
PNO-V-89-033A, on 890607,util Shut Down Plant & Entered Hot Shutdown Due to Voter Defeat of Measure K.Util Continuing to Implement Contingency Plan to Remove Plant from Svc. Reductions in Site Work Force Under Consideration | 7 June 1989 | PNO-V-89-033A:on 890607,util Shut Down Plant & Entered Hot Shutdown Due to Voter Defeat of Measure K.Util Continuing to Implement Contingency Plan to Remove Plant from Svc. Reductions in Site Work Force Under Consideration | |
PNO-V-89-033, on 890606,voters Defeated Measure K,Encouraging Util to Cease Operating Facility.Util Board Previously Announced That Plant Would Be Shutdown If Measure K Defeated.Safe Shutdown Plan Implemented | 7 June 1989 | PNO-V-89-033:on 890606,voters Defeated Measure K,Encouraging Util to Cease Operating Facility.Util Board Previously Announced That Plant Would Be Shutdown If Measure K Defeated.Safe Shutdown Plan Implemented | Safe Shutdown |
PNO-V-89-030, on 890518,airborne Process Monitors for Reactor Bldg Stack,Auxiliary Bldg Stack & Auxiliary Bldg Grade Level Vent Inoperable.Caused by Computer Controlled Svc Air Purge Valves in Open Position.Possibly Caused by Software Errors | 19 May 1989 | PNO-V-89-030:on 890518,airborne Process Monitors for Reactor Bldg Stack,Auxiliary Bldg Stack & Auxiliary Bldg Grade Level Vent Inoperable.Caused by Computer Controlled Svc Air Purge Valves in Open Position.Possibly Caused by Software Errors | Grab sample |
IR 05000312/1989007 | 28 April 1989 | Insp Rept 50-312/89-07 on 890417-21.No Violations Noted. Major Areas Inspected:Previously Identified Items & Status of Emergency Preparedness Program | |
IR 05000312/1989004 | 31 March 1989 | Insp Rept 50-312/89-04 on 890114-0303.Violations Noted.Major Areas Inspected:Operational Safety Verification,Health Physics & Security Observations,Esf Sys Walkdown,Maint,Qa Surveillance & Testing & Followup Items | Hydrostatic Finite Element Analysis |
ML20248J652 | 31 March 1989 | Notice of Violation from Insp on 890114-0303.Violations Noted:Engineering Change Notice Not Initiated for Rebuilt Governor for Auxiliary Feed Pump Installed on 890131 & Maint Work Request Not Reviewed Prior to Performance of Test | |
IR 05000312/1988039 | 28 March 1989 | SALP Rept 50-312/88-39 for July 1986 - Dec 1988 | Packing leak Grab sample Fire Barrier Stroke time Hydrostatic Temporary Modification Systematic Assessment of Licensee Performance Liquid penetrant Continuous fire watch Fire Protection Program Fire Watch |
ML20244A802 | 28 March 1989 | SALP Rept 50-312/88-39 for July 1986 - Dec 1988 | Fitness for Duty Packing leak Grab sample Fire Barrier Stroke time Hydrostatic Temporary Modification Systematic Assessment of Licensee Performance Liquid penetrant Continuous fire watch Fire Watch |
ML20244B114 | 27 March 1989 | Notice of Violation from Insp on 890123-0217.Violations Noted:Nonconformance Rept Not Written After Determination That Debris Caused Failure of Two Instrument Air Sys Check Valves During Performance of Test Procedure STP-774 | Temporary Modification |
ML20244B116 | 24 March 1989 | Insp Rept 50-312/89-01 on 890123-0217.Violations Noted.Major Areas Inspected:Maint Program & Implementation of Related Activities | |
IR 05000312/1988042 | 13 February 1989 | Insp Rept 50-312/88-42 on 881227-30 & 890125-27.No Violations Noted.Major Areas Inspected:Followup Items,Part 21 Repts,Lers & Licensee Program to Maintain Quality of Diesel Generator Fuel Oil | |
IR 05000312/1988041 | 13 February 1989 | Insp Rept 50-312/88-41 on 881214-890103.No Violations Noted. Major Areas Inspected:Onsite Followup of Event of 881212 & Associated Mgt Meetings on 881219 & 890103.Weaknesses Observed Re Decision to Operate Plant in Degraded State | |
IR 05000312/1988040 | 6 February 1989 | Insp Rept 50-312/88-40 on 881208-890113.No Violations or Deviations Noted.Major Areas Inspected:Operational Safety Verification,Health Physics & Security Observations,Esf Sys Walkdown,Maint,Qa & Surveillance & Testing | Fire Barrier Temporary Modification |
ML20235T221 | 6 February 1989 | Exam Rept 50-312/OL-88-02 on 881206-13.Exam Results:All Seven Senior Reactor Operator Candidates Passed Written & Oral Exams | |
ML20196B688 | 30 November 1988 | PNS-V-88-006:on 881126,licensee Received Telcon Alleging That Nonlicensed Equipment Operator Observed Using Illegal Drugs.Individual Submitted to Urinalysis Test & Showed Positive for Marijuana.Individual Terminated on 881130 | Fitness for Duty |
IR 05000312/1988035 | 21 November 1988 | Mgt Meeting Rept 50-312/88-35 on 881114.Major Areas Discussed:Licensee Operational Performance Since Restart in Mar 1988 & Progress Re Restart Commitments in Areas of Engineering,Procurement,Maint & Effluent Sys Areas |