PNO-I-99-046, on 991008,NMP,Unit 1 Declared Unusual Event,Due to Carbon Dioxide Discharge in Records Storage Room of Administration Bldg,Which Was Migrating Beyond Confines of Storage Room.Nrc Resident Inspector Staff Responded8 October 1999PNO-I-99-046:on 991008,NMP,Unit 1 Declared Unusual Event,Due to Carbon Dioxide Discharge in Records Storage Room of Administration Bldg,Which Was Migrating Beyond Confines of Storage Room.Nrc Resident Inspector Staff Responded
IR 05000220/199900614 September 1999Insp Repts 50-220/99-06 & 50-410/99-06 on 990620-0731.NCVs Noted.Major Areas Inspected:Licensee Operations,Engineering, Maint & Plant SupportReactor Vessel Water Level
Anchor Darling
ML20196K65329 June 1999Notice of Violation from NRC OI Investigation Conducted on 980701-1211.Violation Noted:For Approx Four Hours on 980616, with NMP1 at Full Power,Sro Assumed Assistant Shift Supervisor Position,Contrary to TS Requirements
IR 05000220/199900421 June 1999Insp Repts 50-220/99-04 & 50-410/99-04 on 990328-0508.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant SupportSafe Shutdown
High Radiation Area
Non-Destructive Examination
Slow transfer
Nondestructive Examination
Temporary Modification
Locked High Radiation Area
Condition Adverse to Quality
Residual transfer
Foreign Material Exclusion
Scram Discharge Volume
Frazil ice
Earthquake
Fire Protection Program
Fire Watch
PNO-I-99-023, on 990411,NMP Performed Insps That Identified Indications of Crack Growth Around Portion of One of Vertical Welds.Repair Mod for Shroud Vertical Welds Is Expected to Take Approx Five Days to Complete12 May 1999PNO-I-99-023:on 990411,NMP Performed Insps That Identified Indications of Crack Growth Around Portion of One of Vertical Welds.Repair Mod for Shroud Vertical Welds Is Expected to Take Approx Five Days to Complete
IR 05000220/199801523 December 1998Insp Repts 50-220/98-15 & 50-410/98-15 on 980927-1121.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant SupportFitness for Duty
High Radiation Area
ML20196E53519 November 1998Notice of Violation from Investigation on 980303-0930. Violation Noted:On 971224,individual Left Controls at NMP-2 Unattended for Six Minutes to Go Into Shift Supervisor Ofc, Area Not at Controls as Noted in NMPC UFSAR Figure 13.5-1
IR 05000220/199801426 October 1998Insp Repts 50-220/98-14 & 50-410/98-14 on 980816-0926.No Violations Noted.Major Areas Inspected:Reviews of Licensee Activities in Functional Areas of Operations,Engineering, Maint & Plant SupportSafe Shutdown
Offsite Dose Calculation Manual
Temporary Modification
Emergency Lighting
ML20248A80020 May 1998Notice of Violation from Insp on 980406-0409.Violation Noted:During Insp,Inspectors Determined That Licensee Failed to Properly Store,Control & Classify Safeguards Info
ML20217L92528 April 1998Insp Repts 50-220/98-08 & 50-410/98-08 on 980406-21. Violations Noted.Major Areas Inspected:Licensee Security Force Capability to Protect Facility Against Radiological Sabotage & Compliance W/Safeguards Program Commitments
ML20199B86022 January 1998Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:On 970925,package Containing Metal Samples Removed from Unit 1 Emergency Cooling Tube Sheet Was Sent to Listed Company,Not on List
ML20198R4395 November 1997Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $50,000.Violations Noted:Listed non-safety Related SSCs Were Not Included in 10CFR50.65 Monitoring ProgramEmergency Lighting
ML20137U85010 April 1997Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $200,000.Violation Noted:As of 961105,measures Were Not Established to Assure Condition Adverse to Quality Are Promptly Identified & CorrectedHydrostatic
Condition Adverse to Quality
IR 05000220/199400124 January 1994Insp Repts 50-220/94-01 & 50-410/94-01 on 940103-07.No Violations Noted.Major Areas Inspected:Mgt Support, Protected Area Barriers,Detection Aids & Assessment Aids, & Protected Area & Isolation Zone Lighting
IR 05000220/199302222 December 1993Insp Repts 50-220/93-22 & 50-410/93-22 on 931004-20.No Violations Noted.Major Areas Inspected:Mov Program Commitments & Enhancments Identified During Team Inspection in June 1992 Were Reviewed for ProgressStroke time
Anchor Darling
Operability Determination
Weak link
Exclusive Use
IR 05000220/199300112 November 1993Insp Repts 50-220/93-01 & 50-410/93-01 on 930919-1030. Violations Noted.Major Areas Inspected:Major Components & Sys for Leakage,Alignment,Lubrication,Cooling Water SupplyReactor Vessel Water Level
Temporary Modification
IR 05000220/19930235 November 1993Insp Repts 50-220/93-23 & 50-410/93-22 on 931012-14.No Violations Noted.Major Areas Inspected:Mgt Support,Program Plans & Audits,Protected & Vital Area Physical Barriers, Detection & Assessment Aids
PNO-I-93-058, on 931027,licensee Discovered Two Broken 100 Milliliter Vials of Yellow Powder (Believed to Be Yellowcake) at Corporate Ofc in Syracuse,Ny.No Personnel Contaminated.State of Ny Notified28 October 1993PNO-I-93-058:on 931027,licensee Discovered Two Broken 100 Milliliter Vials of Yellow Powder (Believed to Be Yellowcake) at Corporate Ofc in Syracuse,Ny.No Personnel Contaminated.State of Ny Notified
IR 05000220/199302427 October 1993Insp Repts 50-220/93-24 & 50-410/93-23 on 931018-22.No Violations Noted.Major Areas Inspected:Exams of Procedures, Representative Records,Interviews W/Personnel & Observations by InspectorsHigh Radiation Area
IR 05000220/199301918 October 1993Insp Rept 50-220/93-19 on 930823-27.No Violations Noted. Major Areas Inspected:Electrical Distribution Sys
ML20057G32712 October 1993Notice of Violation from Insp on 930808-0918.Violation Noted:On 930803,inspector Discovered Individual That Required Escort in Protected Area W/O Escort for Approx 25 Minutes
IR 05000220/19930126 October 1993Insp Repts 50-220/93-12 & 50-410/93-12 on 930615-18 & 0712-14.No Violations Noted.Major Areas inspected:930615-18 Emergency Preparedness Program & 930713 annual,full- Participation Emergency Preparedness Exercise
IR 05000220/19930181 October 1993Insp Repts 50-220/93-18 & 50-410/93-18 on 930808-0918. Violation Noted.Major Areas Inspected:Plant Operations, Maint & Surveillance Activities,Engineering & Plant Support, W/Regard to Radiological & Chemistry Controls & Security
IR 05000220/199301321 September 1993Insp Repts 50-220/93-13 & 50-410/93-13 on 930802-06.No Violations Noted.Major Areas Inspected:Design Changes & Mods,Installation & Testing of Mods,Interface/Communication, QA & Technical Support,Wrs & LERs
IR 05000220/199301516 September 1993Insp Repts 50-220/93-15 & 50-410/93-15 on 930719-23.No Violations or Deviations Noted.Major Areas Inspected:Offsite Power Supply Sources for Plant & to Review Licensees Corrective Action on Previously Identified Insp FindingsSafe Shutdown
Operability Assessment
IR 05000220/19930164 August 1993Insp Repts 50-220/93-16 & 50-410/93-16 on 930426-30.No Violations Noted.Major Areas Inspected:Mgt Controls,Audits, Calibration of Effluent & Process Radiation Monitoring Sys, Air Cleaning Sys & Implementation of Previous ProgramsOffsite Dose Calculation Manual
ML20056C16423 March 1993Notice of Violation from Insp on 930124-0227.Violation Noted:I&C Technicians Performing N1-ISP-032-004 Failed to Correctly Perform Procedural Steps 7.2.1-7.2.5 Resulting in Automatic Reactor Scram Due to False High Neutron Flux
ML20056C16612 March 1993Insp Repts 50-220/93-01 & 50-410/93-01 on 930124-0227. Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maintenance,Surveillance,Security & Safety Assessment/Quality Verification ActivitiesHalf scram
Stroke time
Scram Discharge Volume
PNO-I-90-092, on 901010,condensate Spill Occurred in Bldg. Caused by Malfunctioning Valve in Lineup for Transfer of New Resin from Mixing Tank to Condensate Demineralizer Bed. Excess Water Pumped Out sub-basement11 October 1990PNO-I-90-092:on 901010,condensate Spill Occurred in Bldg. Caused by Malfunctioning Valve in Lineup for Transfer of New Resin from Mixing Tank to Condensate Demineralizer Bed. Excess Water Pumped Out sub-basement
PNO-I-90-061, on 900806,plant Operators Manually Scrammed Reactor Due to High Vibration on Main Turbine Bearing.Caused by Blank Flange Left in Oil Supply Line to Bearing.Resident Inspectors Following Licensee Actions7 August 1990PNO-I-90-061:on 900806,plant Operators Manually Scrammed Reactor Due to High Vibration on Main Turbine Bearing.Caused by Blank Flange Left in Oil Supply Line to Bearing.Resident Inspectors Following Licensee Actions
IR 05000220/19890991 August 1990Final SALP Repts 50-220/89-99 & 50-410/89-99 for Mar 1989 - Feb 1990
PNO-I-90-059, on 900730,plant Shut Down Due to Excessive RCS Leakage.Util Will Repair Plant Electromatic Relief Valves Found to Be Leaking During Startup.State of Ny Has Been Informed30 July 1990PNO-I-90-059:on 900730,plant Shut Down Due to Excessive RCS Leakage.Util Will Repair Plant Electromatic Relief Valves Found to Be Leaking During Startup.State of Ny Has Been Informed
PNO-I-90-057, on 900727,restart Authorized for Facility. Util Agreed to Perform Self Assessments of Performance & Inform NRC Restart Assessment Panel of Self Assessment Results27 July 1990PNO-I-90-057:on 900727,restart Authorized for Facility. Util Agreed to Perform Self Assessments of Performance & Inform NRC Restart Assessment Panel of Self Assessment Results
PNO-I-89-072A, on 890828,augmented Insp Team Exit Meeting Subsequent Press Conference Held at Plant Re Licensee Use of sub-basement for Storage of Solid & Liquid Radwaste.Two Violations Noted29 August 1989PNO-I-89-072A:on 890828,augmented Insp Team Exit Meeting Subsequent Press Conference Held at Plant Re Licensee Use of sub-basement for Storage of Solid & Liquid Radwaste.Two Violations Noted
ML20247D5992 May 1989Investigation Rept 89-02 Re Misconduct of Ofc of Investigations Deputy Director,Ra Fortuna.Finding of No Misconduct or Dereliction of Duty Recommended
IR 05000220/198803016 November 1988Insp Repts 50-220/88-30 & 50-410/88-29 on 880926-30.No Violations Noted.Major Areas Inspected:Security Plan & Procedures,Mgt Organization,Audits,Records & Repts,Testing & Maint,Barriers,Security Power Supply & Assessment Aids
IR 05000220/19860991 July 1988Amended SALP Repts 50-220/86-99 & 50-410/87-99 for Nov 1986 - Feb 1988 & Feb 1987 - Feb 1988,respectively. Licensee Has Shown Limited Success W/Initiatives to Improve Previously Identified WeaknessesGrab sample
New Project Manager
Missed surveillance
Systematic Assessment of Licensee Performance
Fire Watch
ML20155F41710 June 1988Notice of Violation from Insp on 880404-08.Violation Noted: Site Procedures CBI-SC 1,Rev 0 & NES-8042433,Rev 3 Did Not Establish Adequate Controls Over Nondestructive Testing Process for Making Precision Thickness Measurements
IR 05000220/198800919 May 1988Insp Repts 50-220/88-09 & 50-410/88-09 on 880307-11 & 0404- 08.Violations Noted.Major Areas Inspected:Inservice Insp Program Re First 10-yr Insp Interval & Augmented Exams Conducted by Licensee,Including Procedures
PNO-I-88-010, on 880120,reactor Scrammed from 42% Power Based on Low Reactor Vessel Water Level.Caused by Equipment Operator Error.Nrc Dispatched Augmented Insp Team to Site to Review Generic Safety Implications of Event21 January 1988PNO-I-88-010:on 880120,reactor Scrammed from 42% Power Based on Low Reactor Vessel Water Level.Caused by Equipment Operator Error.Nrc Dispatched Augmented Insp Team to Site to Review Generic Safety Implications of EventReactor Vessel Water Level
PNO-I-88-009, on 880120,unusual Event Declared as Result of Worker Injured After Stepping Through Hole in Grating Between Reactor Vessel Flange & Refueling Cavity Floor.No Contamination Involved21 January 1988PNO-I-88-009:on 880120,unusual Event Declared as Result of Worker Injured After Stepping Through Hole in Grating Between Reactor Vessel Flange & Refueling Cavity Floor.No Contamination Involved
PNO-I-88-007, on 880115,present Unplanned Outage to Inspect & Repair Feedwater Sys Components & Supports Extended for Approx 3 Wks to Perform Insp of Bushings in Reactor Vessel Flange Which Hold 6-inch Diameter Reactor Vessel Head Studs19 January 1988PNO-I-88-007:on 880115,present Unplanned Outage to Inspect & Repair Feedwater Sys Components & Supports Extended for Approx 3 Wks to Perform Insp of Bushings in Reactor Vessel Flange Which Hold 6-inch Diameter Reactor Vessel Head Studs
PNO-I-87-120, on 871226,reactor Scram Occurred from Approx 25% Power Due to Turbine Trip on Low Condenser Vacuum Caused by Crack in Condenser Pipe Penetration.Pentration Seal Weld Repaired29 December 1987PNO-I-87-120:on 871226,reactor Scram Occurred from Approx 25% Power Due to Turbine Trip on Low Condenser Vacuum Caused by Crack in Condenser Pipe Penetration.Pentration Seal Weld Repaired
PNO-I-87-117, on 871219,reactor Manually Scrammed After Mechanical Vibrations from Turbine Bldg Felt in Control Room.Caused by Feedwater Control Valve Stem Separation from Disc.Outage Dependent on Availability of Repair Parts21 December 1987PNO-I-87-117:on 871219,reactor Manually Scrammed After Mechanical Vibrations from Turbine Bldg Felt in Control Room.Caused by Feedwater Control Valve Stem Separation from Disc.Outage Dependent on Availability of Repair Parts
PNO-I-87-114, on 871207,reactor Scrammed from Approx 96% Power Due to Low Reactor Vessel Water Level.Caused by Malfunction of Feedwater Control Valves 13A & 13B.Preventive & Corrective Maint Underway10 December 1987PNO-I-87-114:on 871207,reactor Scrammed from Approx 96% Power Due to Low Reactor Vessel Water Level.Caused by Malfunction of Feedwater Control Valves 13A & 13B.Preventive & Corrective Maint UnderwayReactor Vessel Water Level
IR 05000220/19870229 December 1987Insp Rept 50-220/87-22 on 871019-23.No Violations Noted. Major Areas Inspected:Design Change/Mods,Maint & Previously Identified ItemsTemporary Modification
Systematic Assessment of Licensee Performance
PNO-I-87-113, on 871128,condensate Storage Tank Ruptured Spilling Over 260,000 Gallons Nonradioactive Demineralized Water.Caused by Break in Seam Between Tank Sidewall & Floor. Vendor Onsite Inspecting Cause.Plant in Cold Shutdown2 December 1987PNO-I-87-113:on 871128,condensate Storage Tank Ruptured Spilling Over 260,000 Gallons Nonradioactive Demineralized Water.Caused by Break in Seam Between Tank Sidewall & Floor. Vendor Onsite Inspecting Cause.Plant in Cold Shutdown
PNO-I-87-096, on 871016,plant Scrammed on High Neutron Flux from 89% Power During Testing Causing Main Steam Pressure Oscillations Triggering APRM High Flux Scram.Crd Stub Tube Leakage Identified.Hydrostatic Tests Performed19 October 1987PNO-I-87-096:on 871016,plant Scrammed on High Neutron Flux from 89% Power During Testing Causing Main Steam Pressure Oscillations Triggering APRM High Flux Scram.Crd Stub Tube Leakage Identified.Hydrostatic Tests PerformedHydrostatic
IR 05000220/198701615 October 1987Exam Rept 50-220/87-16OL on 870804-06.Exam Results:All Three Senior Reactor Operator Candidates Passed Written & Operating Exams.Exam Key Encl
IR 05000410/19870181 October 1987Requalification & Replacement Exam Rept 50-410/87-18OL on 870707-07.Exam Results:Two of Four Senior Reactor Operator Candidates & Three of Four Reactor Operator Candidates Passed Exam.Exams Encl