ML20217K330 | 19 October 1999 | Safety Evaluation Supporting Amend 195 to License DPR-61 | High Radiation Area Offsite Dose Calculation Manual Incorporated by reference Process Control Program Fuel cladding Fire Protection Program |
ML20211G963 | 30 August 1999 | SER Accepting Licensee Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves | Stroke time |
ML20196J219 | 30 June 1999 | SER Concluding That Licensee USI A-46 Implementation Program,In General,Met Purpose & Intent of Criteria in GIP-2 & Staff Sser 2 for Resolution of USI A-46 | Safe Shutdown Safe Shutdown Earthquake Operating Basis Earthquake Earthquake |
ML20207G641 | 3 June 1999 | Safety Evaluation Supporting Amends 105,235 & 171 to Licenses DPR-21,DPR-65 & NPF-49,respectively | |
ML20206M463 | 11 May 1999 | Safety Evaluation Supporting Alternative Proposed by Licensee to Perform Ultrasonic Exam on Inner Surface of Nozzle to safe-end Weld | Incorporated by reference Dissimilar Metal Weld |
ML20206G622 | 4 May 1999 | SER Accepting Util Request to Apply leak-before-break Status to Pressurizer Surge Line Piping for Millstone Nuclear Power Station,Unit 2 | Safe Shutdown Safe Shutdown Earthquake Operating Basis Earthquake Finite Element Analysis Earthquake Pressure Boundary Leakage |
ML20206C876 | 28 April 1999 | Safety Evaluation Supporting Amend 194 to License DPR-61 | Earthquake Pressure Boundary Leakage |
ML20204H713 | 17 March 1999 | Safety Evaluation Concluding That NNECO Provided Adequate Justification for Deviations from RG 1.97,Rev 2, Recommendations,For Instrumentation Monitoring CST Level & Containment Area Radiation at Mnps Unit 2 | |
ML20204C944 | 10 March 1999 | Safety Evaluation Denying Licensee Request for License Amend to Revise Frequency of Certain SRs for Electrical Power Sys | |
ML20207L263 | 5 March 1999 | Safety Evaluation Supporting Amend 104 to License DPR-21 | |
ML20207L596 | 22 February 1999 | Safety Evaluation Concluding That Code Requirements,Which Require 100 Percent Volumetric Exam of RPV flange-to-shell, Impractical to Perform to Extent Required & That Alternative Provide Reasonable Assurance of Structural Integrity | Incorporated by reference |
ML20203D760 | 11 February 1999 | Safety Evaluation Supporting Millstone 1 Certified Fuel Handler Training & Retraining Program | |
ML20196B050 | 24 November 1998 | Safety Evaluation Re Licensee 960213 Submittal of 180-day Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Plant,Unit 2 | Power Operated Valves Backfit |
ML20155K198 | 9 November 1998 | Safety Evaluation Re Application of leak-before-break Status to Portions of Safety Injection & Shutdown Cooling Sys | Safe Shutdown Earthquake Earthquake Pressure Boundary Leakage |
ML20195B871 | 9 November 1998 | Safety Evaluation Approving Revised Evaluation of Primary Cold Leg Piping leak-before-break Analysis for Plant | Earthquake Pressure Boundary Leakage |
ML20155C378 | 30 October 1998 | SER Denying Amend to Allow Changes to Fsar.Nrc Found That NNECO Had Not Considered Diversity Provided by Switch in Control Room That Removes Power to 1 of 2 MOV in SDC Sys Flow Path in Evaluation of High Low Pressure Design | |
ML20155C844 | 29 October 1998 | Safety Evaluation Accepting Licensee Proposal to Withdraw ATWS Test Commitment | |
ML20238F213 | 28 August 1998 | SER Accepting Defueled Emergency Plan for Emergency Planning for Connecticut Yankee Atomic Power Co | Fuel cladding |
ML20238F278 | 27 August 1998 | SER Related to Proposed Rev 20 to Northeast Utilities Quality Assurance Program Topical Rept for Millstone Nuclear Power Station,Units 1,2 & 3 | |
ML20237D500 | 20 August 1998 | SER Approving Code Case N-389-1, Alternative Rules for Repairs,Replacements,Or Mods,Section Xi,Div 1 | |
ML20236U705 | 22 July 1998 | Safety Evaluation Granting All Requests for Relief W/Exception of Requests RR-89-17 (Authorized for Class 1 Sys Only) & RR-89-21.Requests RR-13 & RR-14 Will Be Addressed in Separate Evaluation | Incorporated by reference |
ML20236K697 | 1 July 1998 | SER Accepting Third 10-year Interval Inservice Insp Program Plan,Rev 2 & Associated Request for Relief & Proposed Alternatives for Plant,Unit 2 | |
ML20236K353 | 1 July 1998 | Safety Evaluation Supporting Amend 218 to License DPR-65 | Boric Acid Hydrostatic |
ML20202D162 | 30 June 1998 | Safety Evaluation Supporting Amend 193 to License DPR-61 | Safe Shutdown Shutdown Margin Ultimate heat sink Anticipated operational occurrence Probabilistic Risk Assessment Fuel cladding Fire Protection Program |
ML20249C254 | 24 June 1998 | Safety Evaluation Accepting Proposed Rev 19 to NNECO QAP Topical Rept & Amended Through 980609.Informs That NNECO Exception to Provisions in Paragraph 10.3.5 of Constitutes Temporary & Acceptable Alternative | Foreign Material Exclusion |
ML20248J003 | 4 June 1998 | Safety Evaluation Accepting Millstone Nuclear Power Station Emergency Plan | |
ML20248M299 | 2 June 1998 | Safety Evaluation Approving Application Re Restructuring of Central Maine Power Co by Establishment of Holding Company | |
ML20248C413 | 26 May 1998 | SER of Individual Plant Exam of External Events Submittal on Millstone Nuclear Power Station,Unit 3 | Safe Shutdown High winds Safe Shutdown Earthquake Probabilistic Risk Assessment Earthquake Fire Protection Program Fatality |
ML20217M418 | 30 April 1998 | Suppl Safety Evaluation Accepting Licensee RCS Pressure & Heat Removal by Containment Heat Removal Sys post-accident Monitoring Instrumentation | |
ML20217K210 | 27 March 1998 | Safety Evaluation Supporting Amend 192 to License DPR-61 | High Radiation Area Offsite Dose Calculation Manual Process Control Program |
ML20216G792 | 13 March 1998 | Safety Evaluation Authorizing Proposed Alternative to Check Valve Obturator Movement Requirements of OM-10 for SIL Accumulator Outlet for Listed Check Valves | |
ML20203E852 | 17 February 1998 | SER Accepting Request for Relief from Requirements of 10CFR50.55a(f) for Performing Required Inservice Testing of Certain Class 2 Components IAW ASME Boiler & Pressure Vessel Code Section XI for Plant,Unit 3 | |
ML20203E934 | 17 February 1998 | SER Accepting Request for Relief from Requirements of 10CFR50.55a(g) for Performing Required Exams for Certain Class 1 Components IAW ASME Boiler & Pressure Vessel Code Section XI for Plant,Unit 3 | Incorporated by reference |
ML20203E244 | 9 February 1998 | Safety Evaluation Accepting Re Approval of Realistic,Median Centered Spectra Generated for Resolution of USI-A-46 | Earthquake |
ML20198R994 | 13 January 1998 | SER Accepting Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Millstone Nuclear Power Station,Unit 3 | Backfit |
ML20202H746 | 10 December 1997 | Safety Evaluation Accepting Licensee Position That Correction of AC-11 Single Failure Vulnerability Unncessary | Backfit |
ML20202J091 | 2 December 1997 | Safety Evaluation Accepting Proposed Exemption,Which Meets Special Circumstance Given in 10CFR50.12(a)(2)(ii) | Exemption Request |
ML20198S241 | 31 October 1997 | SE Accepting Licensee Request for Deviations from Recommendations in Reg Guide 1.97,Rev 2 for Temp & Flow Monitoring Instrumentation for Cooling Water to ESF Sys Components & Containment Isolation Valve Position | Scram Discharge Volume |
ML20212G599 | 27 October 1997 | Safety Evaluation Supporting Amend 103 to License DPR-21 | |
ML20217K880 | 27 October 1997 | Correction to Safety Evaluation Supporting Amend 103 to License DPR-21.Phrase or Rod Block Protection Has Been Deleted from Listed Sentence in Staff Associated SE | |
ML20212F138 | 22 October 1997 | Safety Evaluation Supporting Amend 102 to License DPR-21 | |
ML20198M810 | 14 October 1997 | SER Accepting Proposed Revs to Util Quality Assurance Program at Facility | |
ML20217M930 | 19 August 1997 | Safety Evaluation Accepting Continued Operation W/O High Startup Rate Trip by Nene for Millstone,Unit 2 | |
ML20149J266 | 23 July 1997 | Safety Evaluation Accepting Changes & Reanalyses in ECCS Evaluation Models & Application of Models for Plant,Unit 2 | |
ML20141L882 | 28 May 1997 | Safety Evaluation Supporting Amend 101 to License DPR-21 | |
ML20141K420 | 22 May 1997 | Safety Evaluation Supporting Amend 191 to License DPR-61 | Offsite Dose Calculation Manual |
ML20138A011 | 23 April 1997 | Safety Evaluation Accepting Licensee Proposal,Not to Perform Type C Leakage Rate Testing on 14 Subject CIVs | Hydrostatic |
ML20137V593 | 15 April 1997 | Safety Evaluation Supporting Amend 100 to License DPR-21 | |
ML20137U312 | 10 April 1997 | Safety Evaluation Supporting Amends 99,206 & 135 to Licenses DPR-21,DPR-65 & NPF-49,respectively | |
ML20134A033 | 23 January 1997 | Safety Evaluation Accepting Util Proposed Alternatives to ASME Code Requirements | Earthquake |