RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | 3 January 2024 | Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | VT-2 |
RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days | 15 December 2023 | Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days | High winds Mission time Tornado Missile B.5.b Surveillance Frequency Control Program Recently irradiated fuel Offsite Circuit |
RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days | 13 December 2023 | Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days | Safe Shutdown Arc flash FLEX Missed surveillance Surveillance Frequency Control Program Offsite Circuit |
RS-23-121, Sixth Ten-Year Interval Inservice Testing Program | 30 November 2023 | Sixth Ten-Year Interval Inservice Testing Program | Safe Shutdown Packing leak High Radiation Area Grab sample Stroke time Squib Incorporated by reference Locked High Radiation Area Surveillance Frequency Control Program Scram Discharge Volume Excess Flow Check Valve Cold shutdown justification Power-Operated Valves Power Operated Valves |
RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation | 17 November 2023 | Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation | Time of Discovery Fitness for Duty Contraband Condition Adverse to Quality Safeguards Contingency Plan Preemption Authority Exemption Request |
RS-23-119, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information | 10 November 2023 | Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information | Time of Discovery Fitness for Duty Contraband Exemption Request |
RS-23-120, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information | 10 November 2023 | Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information | Time of Discovery Fitness for Duty Contraband Exemption Request |
RS-23-107, Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | 8 November 2023 | Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | Non-Destructive Examination Nondestructive Examination VT-2 |
RS-23-113, Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 | 20 October 2023 | Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 | Safe Shutdown Aging Management License Renewal |
RS-23-102, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation | 16 October 2023 | Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation | Time of Discovery Contraband Condition Adverse to Quality Safeguards Contingency Plan Preemption Authority Exemption Request |
RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation | 13 October 2023 | Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation | Time of Discovery Contraband Condition Adverse to Quality Safeguards Contingency Plan Preemption Authority Exemption Request |
RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans | 12 October 2023 | Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans | |
RS-23-090, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station | 7 September 2023 | Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station | Accident Tolerant Fuel |
RS-23-089, Sixth Ten-Year Interval Inservice Testing Program | 5 September 2023 | Sixth Ten-Year Interval Inservice Testing Program | Safe Shutdown Packing leak High Radiation Area Stroke time Squib Incorporated by reference Locked High Radiation Area Missed surveillance Surveillance Frequency Control Program Scram Discharge Volume Cold shutdown justification Power-Operated Valves Power Operated Valves Grace period |
RS-23-071, Application to Adopt TSTF-564, Safety Limit MCPR | 30 August 2023 | Application to Adopt TSTF-564, Safety Limit MCPR | Reactor Vessel Water Level Safety Limit Minimum Critical Power Ratio Anticipated operational occurrence Annual Radiological Environmental Operating Report Process Control Program Fuel cladding |
RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs | 30 August 2023 | Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs | Shutdown Margin Surveillance Frequency Control Program |
RS-23-086, Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | 28 August 2023 | Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | |
RS-23-081, Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation | 21 August 2023 | Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation | Safe Shutdown Reactor Vessel Water Level Safe Shutdown Earthquake Internal Flooding Hydrostatic Earthquake Recently irradiated fuel |
RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor | 4 August 2023 | Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor | |
RS-23-085, Supplemental Information Related to Request for Partial Site Release | 3 August 2023 | Supplemental Information Related to Request for Partial Site Release | |
RS-23-084, Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis | 24 July 2023 | Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis | Safe Shutdown Finite Element Analysis Aging Management |
RS-23-078, Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times | 16 June 2023 | Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times | |
RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations | 16 June 2023 | Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations | |
RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b | 8 June 2023 | License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b | Safe Shutdown High winds Shutdown Margin Reactor Vessel Water Level High Radiation Area Ultimate heat sink Mission time Anticipated operational occurrence Tornado Missile Water Inventory Control Safe Shutdown Earthquake Internal Flooding Hydrostatic Probabilistic Risk Assessment Operating Basis Earthquake Zebra Mussel FLEX B.5.b Fukushima Dai-Ichi Surveillance Frequency Control Program Scram Discharge Volume Feedwater Controller Failure Large early release frequency Tornado Missile Risk Evaluator Earthquake Turbine Missile Biofouling Offsite Circuit Failure to Scram |
RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors | 8 June 2023 | Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors | Safe Shutdown High winds Ultimate heat sink Mission time Tornado Missile Safe Shutdown Earthquake Internal Flooding Probabilistic Risk Assessment Zebra Mussel FLEX Fukushima Dai-Ichi Large early release frequency Earthquake Turbine Missile Biofouling |
RS-23-073, Request for Partial Site Release | 7 June 2023 | Request for Partial Site Release | Offsite Dose Calculation Manual Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Process Control Program |
RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling | 25 May 2023 | Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling | Hydrostatic Surveillance Frequency Control Program |
RS-23-070, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel | 16 May 2023 | Supplement to License Amendment Request Regarding Transition to GNF3 Fuel | |
RS-22-067, 10 CFR 50.46 Annual Report | 4 May 2023 | 10 CFR 50.46 Annual Report | |
RS-23-068, Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell | 28 April 2023 | Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell | Nondestructive Examination |
RS-23-058, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges | 24 April 2023 | Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges | Non-Destructive Examination Weld Overlay Coatings Nondestructive Examination Liquid penetrant Dissimilar Metal Weld |
RS-23-057, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel | 17 April 2023 | Supplement to License Amendment Request Regarding Transition to GNF3 Fuel | |
RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations | 23 March 2023 | Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations | Decommissioning Funding Plan Authorized possession limits |
RS-23-041, Response to Request for Additional Information for Alternative Request RV-23H | 14 March 2023 | Response to Request for Additional Information for Alternative Request RV-23H | |
RS-23-048, Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements | 7 March 2023 | Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements | Half scram Anticipated operational occurrence Safe Shutdown Earthquake Temporary Modification Abnormal operational transient Earthquake |
RS-23-007, Application to Adopt TSTF-564, Safety Limit MCPR | 3 March 2023 | Application to Adopt TSTF-564, Safety Limit MCPR | Reactor Vessel Water Level Safety Limit Minimum Critical Power Ratio Anticipated operational occurrence Annual Radiological Environmental Operating Report Process Control Program Fuel cladding |
RS-23-039, Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air | 1 March 2023 | Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air | Safe Shutdown Anticipated operational occurrence Surveillance Frequency Control Program Nonconservative Technical Specifications Fuel cladding |
RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 | 28 February 2023 | Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 | Fitness for Duty |
RS-23-037, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station | 22 February 2023 | Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station | |
RS-23-032, Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location | 3 February 2023 | Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location | Stroke time Water Inventory Control Surveillance Frequency Control Program |
RS-23-034, Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program | 2 February 2023 | Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program | |
RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 | 31 January 2023 | Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 | Safe Shutdown Fitness for Duty Shutdown Margin Non-Destructive Examination Offsite Dose Calculation Manual Commercial Grade Dedication Safe Shutdown Earthquake Coatings Nondestructive Examination Temporary Modification Cyber Security Condition Adverse to Quality Aging Management Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Process Control Program Operability Determination License Renewal Maintenance Rule Program Fire Protection Program |
RS-23-033, Request for Exemption from 10 CFR 2.109(b) | 27 January 2023 | Request for Exemption from 10 CFR 2.109(b) | License Renewal Exemption Request Subsequent License Renewal Fuel cladding |
RS-23-004, Response to Request for Additional Information Regarding Transition to GNF3 Fuel License Amendment Request | 23 January 2023 | Response to Request for Additional Information Regarding Transition to GNF3 Fuel License Amendment Request | |
RS-23-005, Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves | 17 January 2023 | Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves | |
RS-23-002, Application to Adopt TSTF-332, ECCS Response Time Testing | 13 January 2023 | Application to Adopt TSTF-332, ECCS Response Time Testing | Surveillance Frequency Control Program Scram Discharge Volume Pressure Boundary Leakage |
RS-22-085, Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis | 12 January 2023 | Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis | Safe Shutdown Earthquake |
RS-23-006, Supplemental Information Regarding License Amendment Request Relocation of Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report | 10 January 2023 | Supplemental Information Regarding License Amendment Request Relocation of Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report | Hydrostatic Pressure and Temperature Limits Report |
RS-22-127, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair | 14 December 2022 | Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair | Non-Destructive Examination Nondestructive Examination Dissimilar Metal Weld |
RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI | 30 November 2022 | Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI | Incorporated by reference |