Issue date | Title | Topic | |
---|---|---|---|
ML22307A060 | 3 November 2022 | EN 56200 - Fairbanks Morse Re Basic Component Which Fails to Comply or Contains a Defect | Overspeed |
ML20042E252 | 31 January 2020 | EN 54485 Target Rock Redacted Update to Part 21 Report on Defect of Modification of Valve Component and Main Disc Lift Misadjustment | |
ML20029D161 | 21 January 2020 | 10 CFR Part 21 Report, Notification of a Defect Modification of a Valve Component and Main Disc Lift Misadjustment | |
ML17081A453 | 20 March 2017 | Part 21 - Plastic Jar Dedication Sampling | |
ML17039A569 | 3 February 2017 | Final Part 21 Report on Defect, Potential for Test Induced Damage 0867F Series Main Steam Safety Relief Valves | |
ML17026A414 | 20 January 2017 | C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling | |
ML16278A471 | 22 September 2016 | Notification of 10 CFR Part 21 Condition, Masterpact Breaker Fail to Close | |
ML16281A270 | 22 September 2016 | Part 21 - Initial Notification of Masterpact Breaker Fail to Close | |
ML16209A048 | 13 July 2016 | Part 21 - Initial Notification of Masterpact Breaker Fail to Close | |
ML16196A065 | 9 July 2016 | Part 21 Report - Nonconformance on Struthers-Dunn Relay for Psge Nuclear LLC | Exclusive Use |
ML16162A679 | 8 June 2016 | Part 21 Report - Nonconformance on Struthers-Dunn Relay for PSEG Nuclear LLC | |
ML16139A832 | 13 May 2016 | Part 21 - Initial Notification of Masterpact Breaker Fail to Close | |
ML16139A833 | 13 May 2016 | Part 21 - Initial Notification of Masterpact Breaker Fail to Close | |
ML16098A445 | 22 March 2016 | Part 21 Notification - Sense and Transfer Module Resistive Short | |
ML15187A172 | 30 June 2015 | Interim Part 21 Report - Potential Test Induced Defect in 0867F Main Steam Safety Relief Valves | Flow Induced Vibration |
ML15134A018 | 7 May 2015 | Part 21 Report Regarding Struthers Dunn Relays with Contact Resistance Greater than One Ohm | |
ML15146A022 | 7 May 2015 | Qualtech Np - Potential 1O CFR Part 21 Notification on Struthers Dunn Relays | |
ML15134A017 | 1 May 2015 | Part 21 Report Regarding Potential Test Induced Defect in a 0867F Main Steam Safety Relief Valves | Flow Induced Vibration |
ML15103A244 | 6 April 2015 | Part 21 Report - Deviation of Hk Circuit Breaker Close Latch Spring | Commercial Grade Dedication |
ML15089A435 | 27 March 2015 | Part-21 Notification - Sense and Transfer Module Resistive Short | |
ML15077A422 | 17 March 2015 | Curtiss Wright Flow Control Co., Interim Part 21 Report - Potential Test Induced Defect in a 0867F Main Steam Safety Relief Valves | |
ML15022A650 | 20 January 2015 | Letter from Steven R. Eisenberg USNRC 10CFR Part 21 Notification | |
ML14274A052 | 22 September 2014 | Final Report 10CFR Part 21 Evaluation Regarding Misaligned Separators in LCR-25 Standby Batteries, Revision 1 - Original Letter Did Not Include the List of Affected Utilities | |
ML14210A010 | 23 July 2014 | Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve | Safe Shutdown Shutdown Margin Scram Discharge Volume Failure to Scram Affidavit |
ML14204A708 | 23 July 2014 | Enclosure 2, Description of Closure Evaluation, Non-Proprietary Information - Class I (Public) | Safe Shutdown Shutdown Margin Scram Discharge Volume Failure to Scram |
ML14204A707 | 23 July 2014 | Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV | Affidavit |
ML14169A030 | 15 June 2014 | Update to Interim Report - 10CFR 21 Evaluation Regarding Potential Deficiencies in Seismic Qualifications for PV-62 | |
ML14113A370 | 18 April 2014 | Part 21 - Thomas and Betts Printed Circuit Boards | Commercial Grade Dedication |
ML14303A526 | 28 March 2014 | Interim Part 21 Report - Misaligned Separators in LCR-25 Standby Batteries | |
ML13165A342 | 12 June 2013 | 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers | |
ML13044A075 | 8 February 2013 | Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology | Power Uprate |
ML13042A096 | 8 February 2013 | Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Error in Main Steam Line High Flow Calculational Methodology | Power Uprate |
ML12348A136 | 13 December 2012 | Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers | |
ML12352A123 | 13 December 2012 | 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers | |
ML12347A308 | 12 December 2012 | Part 21 60-Day Interim Report Notification: Error in Main Steam Line High Flow Calculational Methodology | |
ML12318A041 | 8 November 2012 | Part 21 Report - Commercial Grade Dedication Not Properly Applied to Butterfly Valves | Commercial Grade Dedication Condition Adverse to Quality |
ML12319A012 | 27 September 2012 | Error in Main Steam Line High Flow Calculational Methodology | |
ML12177A056 | 21 June 2012 | Part 21 - Reliability Degradation of Resistors in Trip Units and Readout Assemblies | |
ML12163A130 | 6 June 2012 | Part 21 Report - Failure of CRD Collet Retainer Tube/Outer Tube Weld | |
ML12158A447 | 6 June 2012 | Part 21 60-Day Interim Report Notification - Closufailure of CRD Collet Retainer Tube/Outer Tube Weld | |
ML12094A371 | 2 April 2012 | Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations | |
ML12097A316 | 2 March 2012 | Part 21 Report - Rosemont Pressure Tranmitters Out of Tolerance Condition | |
ML12066A118 | 2 March 2012 | Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations | |
ML12040A283 | 7 February 2012 | Notification of Potential Part 21 - Failure to Include Seismic Input in Reactor Control Blade Customer Guidance | Safe Shutdown Earthquake Operating Basis Earthquake Channel-control blade interference |
ML12038A028 | 2 February 2012 | Failure of CRD Collet Retainer Tube/Outer Tube Weld | |
ML12032A240 | 1 February 2012 | Notification of Potential Part 21 - 60-Day Interim Report Notification: Failure of CRD Collet Retainer Tube/Outer Tube Weld | |
ML11318A023 | 10 November 2011 | Notification of Part 21 Report Re Motor Power Leads Undersized | |
ML11228A084 | 12 August 2011 | Notification of Part 21 - Failure to Include Seismic Input in Reactor Control Blade Customer Guidance | Safe Shutdown Earthquake Operating Basis Earthquake Channel-control blade interference Scram Discharge Volume |
ML112240142 | 11 August 2011 | Part 21 60-Day Interim Report Notification: Failure to Include Seismic Input in Channel-Control Blade Interference Customer Guidance | Safe Shutdown Earthquake Channel-control blade interference Scram Discharge Volume |
ML110190072 | 18 January 2011 | Fm Notification Report Serial Number 10-05, Fairbanks Morse Engine, 1 Ocfr 21.21 (d)(3)(ii) Notification |