Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
ML20217N586 | 22 October 1999 | Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 70-7002/99-09 Issued on 990827 | Condition Adverse to Quality |
ML20217H691 | 19 October 1999 | Ack Receipt of 990928 Application to Revise Technical Safety Requirements 2.2.3.15 & 2.7.3.14.Initial Administrative Review Finds Application Acceptable.Completion of Review Is Anticipated by 991215 | |
ML20217N759 | 18 October 1999 | Provides Monthly Update on Progress of Installation of Seismic Upgrade Mods to Bldgs C-331 & C-335 | |
ML20217N914 | 15 October 1999 | Forwards Rev 6 of NCS Cap,Providing Addl Details within Subtask 3.3,addl Ncsa/E Reviews & Establishes New Milestone to Conduct Addl Reviews IAW Procedure XP2=EG-NS1037, Review of Non-Priority 1 & 2 | |
ML20217M296 | 15 October 1999 | Provides Addl Changes to Updated SAR Certificate Amend Request,Including Changes Made IAW Item 5 of Plan of Action Schedule for Compliance Plan Issue 2 & Changes That Resulted from Reevaluation of Autoclave head-to-shell O-ring | |
ML20217M386 | 15 October 1999 | Provides Addl Changes to SAR Update Certificate Amend Request,Containing Changes That Resulted from re-evaluation of Autoclave head-to-shell O-ring Leakage Analysis Provided by DOE SAR Repts | |
ML20217G173 | 14 October 1999 | Requests Addl Info Re Applications Dtd 990924,requesting Amends to Cocs for Paducah & Portsmouth GDPs for Revised QA Programs.Encl Identifies Specific Info Needed.Info Should Be Provided within 30 Days | |
ML20217G467 | 14 October 1999 | Forwards Proprietary Insp Rept 70-7002/99-207 on 990920-23. No Violations Noted.Under Provisions of Section 2.790(d), Repts Containing Info Related to Licensee MC&A Program, Exempt from Public Disclosure | |
ML20217G181 | 14 October 1999 | Forwards Reissued Amend to Coc for Usec Paducah Gdp.Coc Corrects Coc Issued on 991006.Amend Number & Effective Date Were Inadvertently Incorporated as 3 & 991026,instead of 4 & 991105 | |
ML20217F680 | 12 October 1999 | Forwards Updated Paducah GDP Certificate Amend Requests at NRC for Approval | |
ML20217F548 | 8 October 1999 | Discusses Insp Rept 70-7002/99-12 on 990810-0920 at Ports- Mouth Gaseous Diffusion Plant.No Cited Violations of NRC Requirements Were Identified During Insp | |
ML20217B612 | 6 October 1999 | Forwards Copy of Security Incident Log for Month of Sept 1999 | |
ML20217B280 | 6 October 1999 | Forwards Insp Rept 70-7001/99-203 on 990921-23.No Violations Noted | |
ML20217B352 | 6 October 1999 | Forwards Amend 3 to Certificate of Compliance GDP-1 to Revise Six Technical Safety Requirements Sections.Sections Are 2.1.4.17,2.1.4.8,2.3.4.1,2.3.4.4,2.3.4.16 & 3.10.4.b. Compliance Evaluation Rept Also Encl | |
ML20217A478 | 4 October 1999 | Forwards Revised Event Rept 99-17,for Event Resulting from Determination That Sprinkler Sys Not Capable of Meeting Operability Requirements.Caused by Mineral Deposits.Provided Following Completion of Root Cause Evaluation | |
ML20212K894 | 4 October 1999 | Forwards Insp Rept 70-7001/99-10 on 990720-0907 & Forwards NOV Indicating That Some Personnel Were Incorrectly Granted Unescorted Access to Controlled Access Areas Without Having Necessary Specific Training | |
ML20216J893 | 1 October 1999 | Forwards Copy of Security Incident Log & Associated Info for Sept 1999 | |
ML20216J908 | 30 September 1999 | Forwards Revised Written Event Rept 99-10,rev 3,pertaining to Corroded Fire Sprinkler Heads Affecting Operability of high-pressure Fire Water (HPFW) Sprinkler Sys.No Commitment Contained in Rept | |
ML20217M370 | 29 September 1999 | Submits bi-monthly Update on Progress of Mods to Upgrade Audibility of Criticality Accident Alarm Sys (Caas).Schedule for CAAS Audibility Upgrades Attached | |
ML20216J789 | 27 September 1999 | Provides Required 30-day Event Rept 99-19 for Event That Resulted from Failure of Cascade Automatic Data Processing Data Processing Smoke Detection Sys at Portsmouth Gaseous Diffusion Plant.Encl 2 Is List of Commitments Made in Rept | |
ML20212H599 | 27 September 1999 | Responds to Violations Noted in Insp Rept 70-7002/99-09. Corrective Actions:Engineering Evaluated Site Rail Track Insp Process for Improvement | |
ML20212H380 | 24 September 1999 | Responds to 990723 RAI Re 1999 Annual Update to Certification Applications | |
ML20212H125 | 24 September 1999 | Notifies NRC of Change in Regulatory Commitments Associated with Submittal Date for Update of Application SAR Chapter 3.Specifics of Commitment Changes of Listed | |
ML20212G940 | 23 September 1999 | Responds to 990806 Reply to NOV in Ltr with Insp Rept 70-7002/99-04.Revised Reply Reviewed & Responses to Violations 1.B & 1.C Do Not Fully Address Needs as Clarified in 990715 Telcon.Resubmit Response within 30 Days of Ltr | Condition Adverse to Quality |
ML20212G055 | 23 September 1999 | Provides Revised 30-day Event Rept 99-06 for Emergency Condition That Was Declared Alert at Portsmouth Gaseous Diffusion Plant | |
ML20212H372 | 22 September 1999 | Forwards NRC Form 790 Classification Record Documents for Paducah & Portsmouth GDPs That Were Generated During Month of Aug 1999.Without Encl | |
ML20212F098 | 22 September 1999 | Forwards Insp Rept 70-7001/99-12 on 990830-0902.Purpose of Insp Was to Determine If Security Requirements Adequately Implemented & Included Review of Approved Plant Security Plan.No Violations Identified | |
ML20217J121 | 20 September 1999 | Submits Listed Comments on NRC Proposed Rule, Reporting Requirements for Nuclear Power Reactors | |
ML20212D429 | 17 September 1999 | Forwards Required 30-day Written Event Rept Re Criticality Accident Alarm Sys Response Time in Bldg C-710.Encl 2 Contains Commitments Contained in Submittal | |
ML20212D423 | 16 September 1999 | Informs That Review of Event Rept Er 99-12 Revealed Listed Two Statements Inadvertently Omitted from Document | |
ML20212B661 | 15 September 1999 | Forwards Insp Rept 70-7001/99-202 on 990816-20.No Violations Noted | |
ML20212D236 | 15 September 1999 | Submits Monthly Update on Progress of Installation of Seismic Upgrade Mods to Bldgs C-331 & C-335 | |
ML20212A544 | 14 September 1999 | Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 70-7001/99-07 | Missed surveillance |
ML20212A553 | 14 September 1999 | Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 70-7001/99-08 | |
ML20216E691 | 13 September 1999 | Forwards 30-day Written Rept Er 99-18,re Actuation of Cascade ADP Smokehead in X-333 Bldg Low Assay Withdrawal Station.Caused by UF6 Release from Law A/B Compressor Shaft Seal Area.Planned C/As Will Be Provided in Revised Rept | |
ML20211Q995 | 10 September 1999 | Forwards 30-day Written Rept ER-99-12,re Loss of Power to Autoclave Position 1 North & 1 South Process Gas Leak Detection (Pgld) in Bldg C-333-A.Caused by Electrical Short Circuit.Submitted Work Request 501636 for PI SEX-4 | |
ML20211Q776 | 10 September 1999 | Forwards Insp Rept 70-7002/99-205 on 990816-20.No Violations Noted.Insp Consisted of Selective Exams of Computer Systems, Representative Records & Interviews with Personnel | |
ML20211P209 | 9 September 1999 | Provides Staff Written Clarification of NRC Reporting Expectations of When Double Contingency Losses Should Be Reported to NRC IAW Bulletin 91-001, Reporting Loss of Criticality Safety Controls, & Suppl | |
ML20216E489 | 9 September 1999 | Responds to Violations Noted in Insp Rept 70-7001/99-08. Corrective Actions:On 990602 Responsible Organization Manager Met with FP Engineer Performing Bldg Reappraisal & Made Clear Expectation for Prompt Reporting of Deficiencies | |
ML20211Q804 | 8 September 1999 | Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 70-7002/99-05 | |
ML20211Q717 | 8 September 1999 | Forwards Required 30-day Written Event Rept 99-14,rev 1,re 990628 Event Involving Actuation of Brake Sys on Liquid U Hexafluoride Handling Crane at Plant.Revised Rept Includes Corrective Actions.Commitments in Rept Also Encl | |
ML20211N895 | 7 September 1999 | Forwards Required 30 Day Event Rept 99-17,for Event That Resulted from Determination That 13 Sprinkler Sys Associated with High Pressure Fire Water Sys in Process Buildings Were Not Capable of Meeting Operability Requirements | |
ML20211P383 | 3 September 1999 | Forwards Coc GDP-1,amend 3 & Coc GDP-2,amend 4 for Paducah (Pgdp) & Portsmouth (Ports) Gdps,Respectively by Revising Pgdp & Ports QAPs in Vol 3 of Respective Certificate Applications | |
ML20211M640 | 3 September 1999 | Forwards Security Incident Log for Month of Aug 1999,per Requirements of 10CFR95.57(b) |