MONTHYEARRC-22-0004, (Vcsns), Unit 1 - 2021 Annual Letter of Certification and Testing Results of the Public Alerting System2022-01-14014 January 2022 (Vcsns), Unit 1 - 2021 Annual Letter of Certification and Testing Results of the Public Alerting System RC-18-0157, (Vcsns), Units 1, 2 and 3 Independent Spent Fuel Storage Installation - Order Approving Indirect Transfer of Control of Operating License and Combined Licenses2018-12-28028 December 2018 (Vcsns), Units 1, 2 and 3 Independent Spent Fuel Storage Installation - Order Approving Indirect Transfer of Control of Operating License and Combined Licenses RC-18-0149, ISFSI - Order Approving Indirect Transfer of Control of Operating License and Combined Licenses2018-12-21021 December 2018 ISFSI - Order Approving Indirect Transfer of Control of Operating License and Combined Licenses RC-18-0136, (Vcsns), Unit 1 - Request to Remove the Expired One-Time Extension to Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation and to Remove the Index from Technical Specifications (LAR-18-04683)2018-12-12012 December 2018 (Vcsns), Unit 1 - Request to Remove the Expired One-Time Extension to Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation and to Remove the Index from Technical Specifications (LAR-18-04683) RC-18-0144, (Vcsns), Unit 1 - Core Operating Limits Report (COLR) for Cycle 252018-11-20020 November 2018 (Vcsns), Unit 1 - Core Operating Limits Report (COLR) for Cycle 25 RC-18-0126, (Vcsns), Unit 1 - Notification of an Intended Change a Commitment Date for Open Phase Condition (OPC) Made in RC-17-01692018-11-0909 November 2018 (Vcsns), Unit 1 - Notification of an Intended Change a Commitment Date for Open Phase Condition (OPC) Made in RC-17-0169 RC-18-0070, (Vcsns), Unit 1 - Relief Request RR-4-14, Use of a Performance Based Testing Frequency for Pressure Isolation Valves as an Alternative to the Requirements of the American Society of Mechanical Engineers Code for ...2018-10-0808 October 2018 (Vcsns), Unit 1 - Relief Request RR-4-14, Use of a Performance Based Testing Frequency for Pressure Isolation Valves as an Alternative to the Requirements of the American Society of Mechanical Engineers Code for ... RC-18-0067, (Vcsns), Unit 1 - License Amendment Request - LAR-16-00644 - Revise Reactor Coolant System Operational Leakage Technical Specification Surveillance Requirement 4.4.6.2.22018-10-0808 October 2018 (Vcsns), Unit 1 - License Amendment Request - LAR-16-00644 - Revise Reactor Coolant System Operational Leakage Technical Specification Surveillance Requirement 4.4.6.2.2 RC-18-0123, NRC Request for Information Baseline Radiation Safety Inspection2018-10-0404 October 2018 NRC Request for Information Baseline Radiation Safety Inspection RC-18-0117, (Vcsns), Unit 1 - Fukushima Near-Term Task Force Recommendation 3.1: Seismic Probabilistic Risk Assessment2018-09-28028 September 2018 (Vcsns), Unit 1 - Fukushima Near-Term Task Force Recommendation 3.1: Seismic Probabilistic Risk Assessment RC-18-0112, (Vcsns), Unit 1 - Request for License Amendment to Virgil C. Summer Nuclear Station Technical Specification 3.8.2, D.C. Sources - Operating, Surveillance Requirements 4.8.2.1.B.2 and 4.8.2.1.C.32018-09-27027 September 2018 (Vcsns), Unit 1 - Request for License Amendment to Virgil C. Summer Nuclear Station Technical Specification 3.8.2, D.C. Sources - Operating, Surveillance Requirements 4.8.2.1.B.2 and 4.8.2.1.C.3 RC-18-0119, (Vcsns), Unit 1 - Supplement to License Amendment Request LAR-18-03422, Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation2018-09-19019 September 2018 (Vcsns), Unit 1 - Supplement to License Amendment Request LAR-18-03422, Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation RC-18-0118, (Vcsns), Unit 1 - Relief Request RR-4-18, Request for a Temporary Non-Code Repair of a Service Water System Flange2018-09-14014 September 2018 (Vcsns), Unit 1 - Relief Request RR-4-18, Request for a Temporary Non-Code Repair of a Service Water System Flange RC-18-0116, (Vcsns), Unit 1 - Request for a One-Time Extension to the Surveillance Frequency 4.4.4.6 of the Core Exit Temperature Instrumentation - Response to Request for Additional Information2018-09-11011 September 2018 (Vcsns), Unit 1 - Request for a One-Time Extension to the Surveillance Frequency 4.4.4.6 of the Core Exit Temperature Instrumentation - Response to Request for Additional Information RC-18-0113, (Vcsns), Unit 1 - Supplement to License Amendment Request LAR-18-03422 Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation2018-08-31031 August 2018 (Vcsns), Unit 1 - Supplement to License Amendment Request LAR-18-03422 Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation RC-18-0091, License Amendment Request - LAR-16-01490 National Fire Protection Association Standard 805 Program Revisions2018-08-29029 August 2018 License Amendment Request - LAR-16-01490 National Fire Protection Association Standard 805 Program Revisions RC-18-0111, License Amendment Request LAR-18-03422 Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation2018-08-24024 August 2018 License Amendment Request LAR-18-03422 Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation RC-18-0100, (Vcsns), Unit 1 - Technical Specification Change Request for the Revision of the Surveillance Frequency of the Turbine Trip Functional Unit: Response to Request for Additional Information2018-08-22022 August 2018 (Vcsns), Unit 1 - Technical Specification Change Request for the Revision of the Surveillance Frequency of the Turbine Trip Functional Unit: Response to Request for Additional Information RC-18-0105, (Vcsns), Unit 1 - Relief Request RR-4-17, Request to Utilize Code Case N-513-3 'Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1' for a Service Water ..2018-08-14014 August 2018 (Vcsns), Unit 1 - Relief Request RR-4-17, Request to Utilize Code Case N-513-3 'Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1' for a Service Water .. RC-18-0102, Withdrawal of Request to Revise Technical Specifications to Correct an Administrative Error2018-08-10010 August 2018 Withdrawal of Request to Revise Technical Specifications to Correct an Administrative Error RC-18-0098, (Vcsns), Units 1, 2 and 3 - Modification of Requested Latest Completion Date in Application for Order Approving Indirect Transfer of Control of Operating License and Combined Licenses2018-07-30030 July 2018 (Vcsns), Units 1, 2 and 3 - Modification of Requested Latest Completion Date in Application for Order Approving Indirect Transfer of Control of Operating License and Combined Licenses RC-18-0085, (Vcsns), Unit 1 - Notification of an Intended Change to a Commitment Made in RC-17-01262018-07-23023 July 2018 (Vcsns), Unit 1 - Notification of an Intended Change to a Commitment Made in RC-17-0126 RC-18-0090, (Vcsns), Unit 1 - Relief Request RR-4-16, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Response to Request...2018-07-12012 July 2018 (Vcsns), Unit 1 - Relief Request RR-4-16, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Response to Request... RC-18-0089, (Vcsns), Unit 1 - Relief Request RR-4-16, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping2018-07-11011 July 2018 (Vcsns), Unit 1 - Relief Request RR-4-16, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping RC-18-0084, Virgil C Summer Nuclear Station (Vcsns), Unit 1 - Relief Request RR-4-15, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Laws in Moderate Energy Class 2 or 3 Piping Response to Requ2018-07-0303 July 2018 Virgil C Summer Nuclear Station (Vcsns), Unit 1 - Relief Request RR-4-15, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Laws in Moderate Energy Class 2 or 3 Piping Response to Reques RC-18-0082, Relief Request RR-4-15, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping2018-07-0303 July 2018 Relief Request RR-4-15, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping RC-18-0079, Vigil C. Summer Nuclear Station (Vcsns), Unit 1 - Request to Revise Technical Specifications to Correct an Administrative Error2018-06-29029 June 2018 Vigil C. Summer Nuclear Station (Vcsns), Unit 1 - Request to Revise Technical Specifications to Correct an Administrative Error RC-18-0074, Change of the Commitment Date of DRIB/105A&B Door Submittal2018-06-18018 June 2018 Change of the Commitment Date of DRIB/105A&B Door Submittal RC-18-0060, (VCSNS) - Request to Revise Technical Specifications to Correct Administrative Error2018-05-30030 May 2018 (VCSNS) - Request to Revise Technical Specifications to Correct Administrative Error RC-18-0064, (Vcsns), Unit 1 - Annual Commitment Change Summary Report2018-05-18018 May 2018 (Vcsns), Unit 1 - Annual Commitment Change Summary Report RC-18-0063, Submittal of 10 CFR 72.48 Biennial Report for the Independent Spent Fuel Storage Installation2018-05-0202 May 2018 Submittal of 10 CFR 72.48 Biennial Report for the Independent Spent Fuel Storage Installation RC-18-0056, (Vcsns), Unit 1 - Licensee Event Reports (2016-001-02, 2016-002-01, 2016-003-02) - Revision to Correct Typographical Errors2018-04-25025 April 2018 (Vcsns), Unit 1 - Licensee Event Reports (2016-001-02, 2016-002-01, 2016-003-02) - Revision to Correct Typographical Errors RC-18-0059, Annual Radioactive Effluent Release Report2018-04-25025 April 2018 Annual Radioactive Effluent Release Report RC-18-0046, License Amendment Request LAR-14-01541 Integrated Leak Rate Test Peak Calculated Containment Internal Pressure Change Request for Additional Information2018-04-19019 April 2018 License Amendment Request LAR-14-01541 Integrated Leak Rate Test Peak Calculated Containment Internal Pressure Change Request for Additional Information RC-18-0036, (Vcsns), Unit 1 - Relief Request RR-4-13, Use of a Risk-Informed Process as an Alternative for the Selection of Class 1 and Class 2 Piping Welds - Response to Request for Additional Information2018-04-0202 April 2018 (Vcsns), Unit 1 - Relief Request RR-4-13, Use of a Risk-Informed Process as an Alternative for the Selection of Class 1 and Class 2 Piping Welds - Response to Request for Additional Information RC-18-0041, Report of Status of Decommissioning Funding2018-03-28028 March 2018 Report of Status of Decommissioning Funding RC-17-0175, Correction to Amendment No. 170 Request to Revise Technical Specifications to Correct Administrative Error2018-01-31031 January 2018 Correction to Amendment No. 170 Request to Revise Technical Specifications to Correct Administrative Error RC-18-0006, Independent Spent Fuel Storage Installation Re Application for Order Approving Indirect Transfer of Control of Operating License and Combined Licenses2018-01-25025 January 2018 Independent Spent Fuel Storage Installation Re Application for Order Approving Indirect Transfer of Control of Operating License and Combined Licenses RC-17-0169, Notification of an Intended Change of a Commitment Date for Open Phase Condition Made in RC-14-00192017-12-11011 December 2017 Notification of an Intended Change of a Commitment Date for Open Phase Condition Made in RC-14-0019 RC-17-0182, (VCSNS) - Anchor Darling Double Disc Gate Valve Information and Status2017-12-11011 December 2017 (VCSNS) - Anchor Darling Double Disc Gate Valve Information and Status RC-17-0172, Notification of Personnel Changes2017-11-30030 November 2017 Notification of Personnel Changes RC-17-0161, Submittal of Change of the Commitment Date of DRIB/105A&B Door2017-11-28028 November 2017 Submittal of Change of the Commitment Date of DRIB/105A&B Door RC-17-0135, Annual Commitment Change Summary Report2017-11-0303 November 2017 Annual Commitment Change Summary Report RC-17-0123, Relief Request RR-4-13, Use of a Risk-Informed Process as an Alternative for the Selection of Class 1 and Class 2 Piping Welds2017-10-30030 October 2017 Relief Request RR-4-13, Use of a Risk-Informed Process as an Alternative for the Selection of Class 1 and Class 2 Piping Welds RC-17-0140, Transmittal of 10 CFR 50.59 Biennial Report2017-10-23023 October 2017 Transmittal of 10 CFR 50.59 Biennial Report RC-17-0107, (Vcsns), Unit 1 - Integrated Leak Rate Test Peak Calculated Containment Internal Pressure Change2017-10-0606 October 2017 (Vcsns), Unit 1 - Integrated Leak Rate Test Peak Calculated Containment Internal Pressure Change RC-17-0134, Response to Request for Supplemental Information, License Amendment Request - LAR-15-01424; Implementation of WCAP-15376-P-A, Revision 12017-09-27027 September 2017 Response to Request for Supplemental Information, License Amendment Request - LAR-15-01424; Implementation of WCAP-15376-P-A, Revision 1 RC-17-0126, Reply to a Notice of Violation, Per Inspection Report 05000395/20170022017-09-0606 September 2017 Reply to a Notice of Violation, Per Inspection Report 05000395/2017002 RC-17-0112, Special Report (Spr) 2017-007 Regarding Waste Gas Holdup System Explosive Gas Monitoring System Being Inoperable for Greater than Thirty Days2017-09-0101 September 2017 Special Report (Spr) 2017-007 Regarding Waste Gas Holdup System Explosive Gas Monitoring System Being Inoperable for Greater than Thirty Days RC-17-0069, (Vcsns), Unit 1 - Quality Assurance Approval Certificate No. 0479, Transmittal of the Quality Assurance Program Description2017-08-30030 August 2017 (Vcsns), Unit 1 - Quality Assurance Approval Certificate No. 0479, Transmittal of the Quality Assurance Program Description 2022-01-14
[Table view] Category:Report
MONTHYEARML23325A2022024-01-16016 January 2024 CFR Part 52 Construction Lessons-Learned Report ML23024A1542023-01-23023 January 2023 Proposed Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Potential Subsequent License Renewal Activity ML22286A1392022-10-13013 October 2022 Special Report 2022-005, Inoperable Radiation Monitoring Instrumentation Channel ML22279A9892022-09-23023 September 2022 Restoration Project - Final Status Survey Release Record North Protected Area Yard Survey Unit 12201C - Revision 2 ML22069B1172022-03-10010 March 2022 Application for Alternative Request - Extension of Steam Generator Primary Inlet Nozzle Dissimilar Metal Weld Inspection Interval (Volumetric Examination) ML22049B0242022-02-18018 February 2022 2021 Q4 Summary Page IR 05000395/20210052021-08-24024 August 2021 Updated Inspection Plan for Virgil C.Summer Nuclear Station, Unit 1 (Report 05000395/2021005) ML21175A2472021-06-24024 June 2021 2020 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the....- ML20296A7082020-10-22022 October 2020 (VCSNS) Unit 1 - Alternative Requests RR-4-25 for Elimination of Reactor Pressure Vessel Threads in Flange Examination for the Remainder of the Fourth 10-Year ISI Interval ML20247J6162020-09-0303 September 2020 Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML20212L5762020-07-30030 July 2020 Annual Commitment Change Summary Report ML20203M1602020-07-20020 July 2020 VA Elec. & Power Co., Dominion Energy Nuclear Co. Inc., Dominion Energy Sc Inc., Millstone Power Station 2, N. Anna & Surry Power Stations 1 & 2, Virgil C. Summer Station 1, Updated Anchor Darling Double Disc Gate Valve Information & Status ML19204A1172019-07-17017 July 2019 Vigil C. Summer, Unit 1, Proposed Alternative Request RR-4-20 Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography ML19122A5172019-05-0202 May 2019 Annual Commitment Change Summary Report ML19056A4122019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Source Water Baseline Biological Characterization Data ML19056A4132019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Cooling Water System Data ML19056A4112019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Cooling Water Intake Structure Data ML19056A4142019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Entrainment Performance Studies ML19056A4102019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Source Water Physical Data RC-18-0117, (Vcsns), Unit 1 - Fukushima Near-Term Task Force Recommendation 3.1: Seismic Probabilistic Risk Assessment2018-09-28028 September 2018 (Vcsns), Unit 1 - Fukushima Near-Term Task Force Recommendation 3.1: Seismic Probabilistic Risk Assessment ML18179A4162018-06-28028 June 2018 ECCS Evaluation Model Revisions Report RC-18-0064, (Vcsns), Unit 1 - Annual Commitment Change Summary Report2018-05-18018 May 2018 (Vcsns), Unit 1 - Annual Commitment Change Summary Report ML17206A4592017-09-26026 September 2017 Staff Assessment of Response to Information Request Pursuant to 10 CFR 50.54(F) - Recommendation 9.3 of the Near-Term Task Force, Communications Assessment RC-17-0089, Focused Evaluation for External Flooding2017-06-30030 June 2017 Focused Evaluation for External Flooding RC-17-0057, Emergency Core Cooling System Evaluation Model Revisions Annual Report2017-05-15015 May 2017 Emergency Core Cooling System Evaluation Model Revisions Annual Report ML19056A4152017-02-28028 February 2017 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Appendix B, Entrainment Study, 2016 and Revised 2017 RC-16-0170, Mitigating Strategies Assessment (MSA) Report Submittal2016-12-22022 December 2016 Mitigating Strategies Assessment (MSA) Report Submittal RC-16-0143, (VCSNS) Unit 1 - Report of Full Compliance and Final Integrated Plan in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design...2016-10-31031 October 2016 (VCSNS) Unit 1 - Report of Full Compliance and Final Integrated Plan in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design... RC-16-0081, Submittal of 2015 Annual Commitment Change Summary Report2016-06-22022 June 2016 Submittal of 2015 Annual Commitment Change Summary Report RC-16-0086, Special Report 2016-003 Regarding Fire Barrier Not Restored to Operability Status within 7 Days of Inoperability2016-06-0909 June 2016 Special Report 2016-003 Regarding Fire Barrier Not Restored to Operability Status within 7 Days of Inoperability RC-16-0008, Transmittal of Expedited Seismic Evaluation Process Report, Revision 12016-01-28028 January 2016 Transmittal of Expedited Seismic Evaluation Process Report, Revision 1 ML15296A3772015-11-0303 November 2015 Supplement to Staff Assessment of Response to 10 CFR 50.54(f) Information Request- Flood Causing Mechanism Reevaluation RC-15-0153, Submittal of 10 CFR 50.59 Biennial Report2015-10-0707 October 2015 Submittal of 10 CFR 50.59 Biennial Report ML15194A0552015-07-20020 July 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f), Seismic Hazard Reevaluations Relating to Recommendation 2.1 Fukushima Dai-Ichi RC-15-0020, Attachment 2 - Ihi Southwest Inner Diameter Examination Data, Part 2 of 22015-02-25025 February 2015 Attachment 2 - Ihi Southwest Inner Diameter Examination Data, Part 2 of 2 ML15061A0332015-02-25025 February 2015 Attachment 2 - Ihi Southwest Inner Diameter Examination Data, Part 2 of 2 ML14314A0332014-11-0505 November 2014 Submittal Special Report (Spr) 2014-006 ML14261A2762014-09-18018 September 2014 Draft September 23, 2014, Category 1 Public Meeting with V. C. Summer - Draft License Amendment Related to Approval of the Technical Support Center ML14141A4612014-06-0606 June 2014 Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-ichi Nuclear Power Plant Accident RC-14-0048, Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident2014-03-26026 March 2014 Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident ML14051A3632014-03-0505 March 2014 Closure Letter Concerning 2012 Annual Emergency Core Cooling System Evaluation Model Revisions Report (TAC No. Mf 2722) ML19056A4082014-02-28028 February 2014 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Thermal Mixing Zone Evaluation, Addendum: Additional Modeling Cases for Revised Reservoir Ambient and Discharge Temperatures ML14034A3392014-02-21021 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) ML14037A2282014-02-21021 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Virgil C. Summer Nuclear Station, Unit 1, TAC MF2338 ML14010A4152014-01-30030 January 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-ichi Nuclear Power Plant Accident ML13309B0532013-11-0404 November 2013 ECCS Evaluation Model Revisions 30-Day Report RC-13-0130, WCAP-17758-NP, Rev. 0, Technical Basis for Westinghouse Embedded Flaw Repair for V.C. Summer Unit 1 Reactor Vessel Head Penetration Nozzles and Attachment Welds.2013-08-31031 August 2013 WCAP-17758-NP, Rev. 0, Technical Basis for Westinghouse Embedded Flaw Repair for V.C. Summer Unit 1 Reactor Vessel Head Penetration Nozzles and Attachment Welds. RC-13-0038, Flooding Hazard Reevaluation Response to NRC Request for Information Pursuant to 10 CFR 50.54(F) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task.2013-03-12012 March 2013 Flooding Hazard Reevaluation Response to NRC Request for Information Pursuant to 10 CFR 50.54(F) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task. RC-13-0037, Permanent ILRT Interval Extension Risk Impact Assessment2013-03-0101 March 2013 Permanent ILRT Interval Extension Risk Impact Assessment ML13072A0832013-01-31031 January 2013 12-4116.IPEC.V002, Revision 1, Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation: EA-12-051 2024-01-16
[Table view] Category:Technical
MONTHYEARML23325A2022024-01-16016 January 2024 CFR Part 52 Construction Lessons-Learned Report ML23024A1542023-01-23023 January 2023 Proposed Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Potential Subsequent License Renewal Activity ML22279A9892022-09-23023 September 2022 Restoration Project - Final Status Survey Release Record North Protected Area Yard Survey Unit 12201C - Revision 2 ML22069B1172022-03-10010 March 2022 Application for Alternative Request - Extension of Steam Generator Primary Inlet Nozzle Dissimilar Metal Weld Inspection Interval (Volumetric Examination) ML21175A2472021-06-24024 June 2021 2020 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the....- ML20296A7082020-10-22022 October 2020 (VCSNS) Unit 1 - Alternative Requests RR-4-25 for Elimination of Reactor Pressure Vessel Threads in Flange Examination for the Remainder of the Fourth 10-Year ISI Interval ML20203M1602020-07-20020 July 2020 VA Elec. & Power Co., Dominion Energy Nuclear Co. Inc., Dominion Energy Sc Inc., Millstone Power Station 2, N. Anna & Surry Power Stations 1 & 2, Virgil C. Summer Station 1, Updated Anchor Darling Double Disc Gate Valve Information & Status ML19204A1172019-07-17017 July 2019 Vigil C. Summer, Unit 1, Proposed Alternative Request RR-4-20 Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography ML19056A4142019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Entrainment Performance Studies ML19056A4132019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Cooling Water System Data ML19056A4122019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Source Water Baseline Biological Characterization Data ML19056A4102019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Source Water Physical Data ML19056A4112019-01-31031 January 2019 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Cooling Water Intake Structure Data RC-18-0117, (Vcsns), Unit 1 - Fukushima Near-Term Task Force Recommendation 3.1: Seismic Probabilistic Risk Assessment2018-09-28028 September 2018 (Vcsns), Unit 1 - Fukushima Near-Term Task Force Recommendation 3.1: Seismic Probabilistic Risk Assessment RC-17-0089, Focused Evaluation for External Flooding2017-06-30030 June 2017 Focused Evaluation for External Flooding ML19056A4152017-02-28028 February 2017 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Appendix B, Entrainment Study, 2016 and Revised 2017 RC-16-0143, (VCSNS) Unit 1 - Report of Full Compliance and Final Integrated Plan in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design...2016-10-31031 October 2016 (VCSNS) Unit 1 - Report of Full Compliance and Final Integrated Plan in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design... RC-14-0048, Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident2014-03-26026 March 2014 Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident ML19056A4082014-02-28028 February 2014 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Thermal Mixing Zone Evaluation, Addendum: Additional Modeling Cases for Revised Reservoir Ambient and Discharge Temperatures ML14034A3392014-02-21021 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) ML14037A2282014-02-21021 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Virgil C. Summer Nuclear Station, Unit 1, TAC MF2338 RC-13-0130, WCAP-17758-NP, Rev. 0, Technical Basis for Westinghouse Embedded Flaw Repair for V.C. Summer Unit 1 Reactor Vessel Head Penetration Nozzles and Attachment Welds.2013-08-31031 August 2013 WCAP-17758-NP, Rev. 0, Technical Basis for Westinghouse Embedded Flaw Repair for V.C. Summer Unit 1 Reactor Vessel Head Penetration Nozzles and Attachment Welds. RC-13-0038, Flooding Hazard Reevaluation Response to NRC Request for Information Pursuant to 10 CFR 50.54(F) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task.2013-03-12012 March 2013 Flooding Hazard Reevaluation Response to NRC Request for Information Pursuant to 10 CFR 50.54(F) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task. RC-13-0037, Permanent ILRT Interval Extension Risk Impact Assessment2013-03-0101 March 2013 Permanent ILRT Interval Extension Risk Impact Assessment ML13072A0832013-01-31031 January 2013 12-4116.IPEC.V002, Revision 1, Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation: EA-12-051 RC-12-0175, WCAP-17688-NP, Rev 0, V.C. Summer Unit 1 Seismic Walkdown Inspection Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic.2012-11-30030 November 2012 WCAP-17688-NP, Rev 0, V.C. Summer Unit 1 Seismic Walkdown Inspection Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. RC-12-0174, Final Flooding Walk Down Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendations 2.3 of the Near.2012-11-26026 November 2012 Final Flooding Walk Down Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendations 2.3 of the Near. RC-12-0189, Engineering Services Technical Report TR02060-0012012-11-20020 November 2012 Engineering Services Technical Report TR02060-001 RC-12-0173, Technical Basis for Westinghouse Embedded Flaw Repair for V. C. Summer Unit 1 Reactor Vessel Head Penetration Nozzles2012-11-14014 November 2012 Technical Basis for Westinghouse Embedded Flaw Repair for V. C. Summer Unit 1 Reactor Vessel Head Penetration Nozzles RC-12-0170, LTR-PAFM-12-137-NP, Rev. 1, Technical Basis for Westinghouse Embedded Flaw Repair for V. C. Summer, Unit 1, Reactor Vessel Head Penetration Nozzles.2012-11-0505 November 2012 LTR-PAFM-12-137-NP, Rev. 1, Technical Basis for Westinghouse Embedded Flaw Repair for V. C. Summer, Unit 1, Reactor Vessel Head Penetration Nozzles. RC-12-0110, LTR-PAFM-12-86-NP, Rev. 0, Flaw Tolerance Evaluation to Support Re-categorization of V. C. Summer Unit 1 Steam Generator Nozzle to Safe End Dissimilar Metal Weld Inspection Requirements.2012-06-27027 June 2012 LTR-PAFM-12-86-NP, Rev. 0, Flaw Tolerance Evaluation to Support Re-categorization of V. C. Summer Unit 1 Steam Generator Nozzle to Safe End Dissimilar Metal Weld Inspection Requirements. ML19056A4072012-01-0909 January 2012 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Thermal Mixing Zone Evaluation ML11321A1722011-11-15015 November 2011 License Amendment Request - LAR-06-00055, and to Adopt NFPA 805 Performance - Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) ML19056A4162009-09-30030 September 2009 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Monticello Reservoir Ichthyoplankton Studies, September 2008 Through August 2009 ML0821900132008-08-0707 August 2008 Monthly Operating Reports Second Quarter 2008 ML0604102762005-07-31031 July 2005 V.C. Summer High Burnup LTA Inspection Report. RC-05-0097, Core Operating Limits Report - Reference for Best Estimate Loss of Coolant Accident2005-06-30030 June 2005 Core Operating Limits Report - Reference for Best Estimate Loss of Coolant Accident ML0604002232004-12-31031 December 2004 1003361 - On-Line Monitoring of Instrument Channel Performance, Volume 1: Guidelines for Model Development and Implementation RC-06-0024, 1007930 - On-Line Monitoring of Instrument Channel Performance, Volume 3: Applications to Nuclear Power Plant Technical Specification Instrumentation2004-12-31031 December 2004 1007930 - On-Line Monitoring of Instrument Channel Performance, Volume 3: Applications to Nuclear Power Plant Technical Specification Instrumentation ML0300802992002-12-30030 December 2002 Special Report 2002-002 ML0227602642002-09-27027 September 2002 Evaluation of Reactor Pressure Vessel Nozzle to Hot-leg Piping Bimetallic Weld Joint Integrity for the V.C. Summer Nuclear Power Plant, Memorandum Dated 09/27/02 - Figure 20 ML0227704612002-09-27027 September 2002 Evaluation of Reactor Pressure Vessel Nozzle to Hot-leg Piping Bimetallic Weld Joint Integrity for the V.C. Summer Nuclear Power Plant, Figures 21 - 70 ML0230402682002-09-19019 September 2002 Part 4 of 4 - Westinghouse Technology Manual, Course Outline for R-104P and Course Manual 2024-01-16
[Table view] |
Text
Jeffrey B. Archie Vice President, Nuclear Operations 803.345.4214 A SCANA COMPANY June 30, 2005 RC-05-0097 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTN: Mr. R. E. Martin
Dear Sir / Madam:
Subject:
VIRGIL C. SUMMER NUCLEAR STATION DOCKET NO. 50/395 OPERATING LICENSE NO. NPF-12 LICENSE AMENDMENT REQUEST - LAR 04-3385 CORE OPERATING LIMITS REPORT - REFERENCE FOR BEST ESTIMATE LOSS OF COOLANT ACCIDENT (BELOCA)
Pursuant to 10 CFR 50.90, South Carolina Electric & Gas Company (SCE&G), acting for itself and as agent for South Carolina Public Service Authority, hereby requests an amendment to the Virgil C. Summer Nuclear Station (VCSNS) Technical Specifications (TS).
The proposed change will revise Administrative Control Section 6.9.1.11, Core Operating Limits Report. The revision will permit the Westinghouse best estimate methodology to be utilized in assuring our compliance to 10 CFR 50.46.
Information contained herein provides the No Significant Hazards Determination. Attachment I provides the TS page marked up with the proposed change. Attachment II provides the retyped TS page.
The VCSNS Plant Safety Review Committee and the Nuclear Safety Review Committee have reviewed and approved the proposed change. SCE&G has notified the State of South Carolina in accordance with 10CFR50.91 (b).
SCE&G requests approval of the proposed amendment within one year of submittal in accordance with the NRC goal for review of license amendment requests. Once approved, the amendment shall be implemented within 30 days.
There are no other TS changes in process that will affect or be affected by this change request.
FSAR Chapter 15 changes will be implemented as necessary after this change is approved.
There are no changes to any FPER sections.
If you have any questions or require additional information, please contact Mr. Ronald B. Clary at (803)-345-4757.
SCE&G I Virgil C.Summer NuclearStation
- P.0.Box 88 Jenkinsville, South Carolina 29065.T(803)345.5209 wwswscona.com 0 1
Document Control Desk LAR 04-3385 RC-05-0097 Page 2 of 2 I certify under penalty of perjury that the foregoing is true and correct.
(D - 36 , ,
Executed on lrl~ ffrey B r~
PAR/JBA/dr
Enclosures:
Evaluation of the proposed change Attachment(s): 3
- 1. Proposed Technical Specification Change - Mark-up
- 2. Proposed Technical Specification Change - Retyped
- 3. List of Regulatory Commitments c: N. 0. Lorick S. A. Byrne
,N. S.- Cams T. G. Eppink (w/o Attachments)
R. J. White W. D. Travers R. E. Martin NRC Resident Inspector Winston and Strawn P. Ledbetter T. P. O'Kelley RTS (LAR 04-3385)
File (813.20)
DMS (RC-05-0097)
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 1 of 13
Subject:
LICENSE AMENDMENT REQUEST - LAR 04-3385 ADMINISTRATIVE CONTROL SECTION 6.9.1.11
1.0 DESCRIPTION
South Carolina Electric & Gas Company (SCE&G) requests an amendment to revise the Virgil C. Summer Nuclear Station (VCSNS) Technical Specifications (TS) Administrative Controls. The proposed change to Section 6.9.1.11, Core Operating Limits Report, will permit utilization of the best estimate large break Loss of Coolant Accident (LOCA) methodology in assuring that the requirements of 10 CFR 50.46 remains satisfied.
2.0 PROPOSED CHANGE
Technical Specification 6.9.1.11 lists applicable references for the analytical methods used to determine core operating limits. This list of references includes the Westinghouse topical report (WCAP-10266-P-A, Rev. 2) that documents the currently approved large break LOCA analysis methodology. It is proposed that this reference would be replaced with the generically approved topical report for the Westinghouse best estimate large break LOCA analysis methodology (WCAP-12945-P-A) and reanalysis work plan (NSD-NRC-96-4746).
3;O->* BACKGROUND Westinghouse has obtained generic NRC approval of its topical report describing best-estimate large break LOCA methodology. NRC approval of the methodology is documented in the NRC safety evaluation report appended to the topical report (WCAP 12945-P-A, Volume 1 (Revision 2) and Volumes 2 through 5 (Revision 1), "Code Qualification Document for Best Estimate LOCA Analysis,' March 1998). A plant specific analysis for V. C. Summer Nuclear Station has been performed using the approved methodology.
V. C. Summer Nuclear Station was one of the plants for which portions of the analysis were performed prior to the final methodology revisions that were recommended by both the NRC and the ACRS. A work plan was submitted describing the reanalysis work that would be performed based on the NRC and ACRS comments for the final best estimate methodology approval. This work plan was performed for portions of the V. C. Summer Best Estimate LOCA Analysis. Specific details of the reanalysis work plan and the implications for V. C. Summer Nuclear Station is included in Table 1.
These changes are being made to incorporate the best-estimate methodology approach as part of the licensing basis for the V. C. Summer Nuclear Station large break LOCA analysis in accordance with 10CFR50.46, Regulatory Guide 1.157 "Best-Estimate Calculations of Emergency Core Cooling System Performance," and the Westinghouse
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 2 of 13 "Code Qualification Document for Best Estimate LOCA Analysis," WCAP-12945-P-A, Volumes 1-5. The values of major plant parameters assumed in the best-estimate LOCA analyses will be documented in the FSAR for V. C. Summer Nuclear Station.
These and other FSAR changes resulting from approval of this LAR will be made in accordance with 10 CFR 50.71 (e).
4.0 TECHNICAL ANALYSIS
A best estimate large break LOCA analysis has been performed for V. C. Summer Nuclear Station using the methodology contained in WCAP-12945-P-A. All plant specific parameters used in the analysis are bounded by the models and correlations contained in the generic methodology. Therefore, the V. C. Summer Nuclear Station analysis conforms to 10 CFR 50.46 and Section II of Appendix K, and meets the intent of Regulatory Guide 1.157. The conclusions of the analysis are that there is a high level of probability that:
- 1. The calculated maximum fuel element cladding temperature (peak cladding temperature) will not exceed 22000F.
- 2. The calculated total oxidation of the cladding (maximum cladding oxidation) will not exceed 0.17 times the total cladding thickness before oxidation.
- 3. The calculated total amount of hydrogen generated from the chemical reaction of A't.-* ithe-cladding with water.orssteam `maximum- hydrogen generation) wil!.not exceed,.
0.01 times the hypothetical amount that would be generated if all of the metal in the cladding cylinders surrounding the fuel, excluding the cladding surrounding the plenum volume, were to react.
- 4. The calculated changes in core geometry are such that the core remains amenable to cooling.
- 5. After successful initial operation of the ECCS, the core temperature will be maintained at an acceptably low value and decay heat will be removed for the extended period of time required by the long-lived radioactivity remaining in the core.
Table 1 presents the 95th percentile peak clad temperature (PCT), maximum cladding oxidation, maximum hydrogen generation, and cooling results for V. C. Summer Nuclear Station.
Based on these results, V. C. Summer Nuclear Station has concluded that adopting the best estimate large break LOCA methodology for V. C. Summer Nuclear Station and making the proposed TS changes would not adversely affect the health and safety of the public.
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 3 of 13
- I . .I . .. )
Table I V. C. Summer Nuclear Station Best Estimate Large Break LOCA Results
- Description -Value AcceptanceCriteria 95u Percentile PCT (OF)* 1988 2200 Maximum Cladding Oxidation* 5.0 17.0
(%)
Maximum Hydrogen 0.72 1.0 Generation* (%)
Coolable Geometry Core Remains Coolable Core Remains Coolable Long Term Cooling Core Remains Cool in Long Core Remains Cool in Long Term Term
- Calculated using the methodology in the following references:
- WCAP-12945-P-A, Volume 1 (Revision 2) and Volumes 2 through 5 (Revision 1), "Code Qualification Document for Best Estimate Loss of Coolant Accident Analysis," March 1998 (Westinghouse Proprietary).
- Liparulo, N. (E) to NRC Document Control Desk, NSD-NRC7-96-4746, "Re-Analysis Work Plans Using Final Best Estimate Methodology" dated June 13, 1996.
The Re-analysis Work Plan provisions are used for the following portions of the analysis only:
The following subset of Initial Conditions Studies used the Mod 7A predecessor code version/methodology:
- Pressurizer Pressure
- Accumulator Pressure
- Accumulator Water Volume
- SI Temperature (All) Power Distribution Studies used the MOD7A predecessor code version/methodology.
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 4 of 13 5.0 REGULATORY SAFETY ANALYSIS 5.1 No Significant Hazards Consideration South Carolina Electric & Gas Company (SCE&G) has evaluated the proposed changes to the VCSNS TS described above against the Significant Hazards Criteria of IOCFR50.92 and has determined that the changes do not involve any significant hazard.
The following is provided in support of this conclusion.
- 1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated?
Response: No.
Implementation of the best-estimate large break LOCA methodology and associated TS changes is proposed to increase margin to the peak clad temperature limits defined in 10 CFR 50.46. There are no physical plant changes or changes in manner in which the plant will be operated as a result of this change. Since the plant conditions and ECCS performance assumed in the analysis are consistent with the plant's current design, the proposed change in methodology will thus have no impact on the probability of a LOCA.
When applied, the best estimate methodology shows that the ECCS is more effective than previously evaluated in mitigating the consequences of a LOCA, as lower peak clad temperatures are predicted relative to current 10 CFR 50.46 Appendix K results. Since
. the proposed best-estimate methodology is only applicable to a large break LOCA and
--sir.ne the application of the proposed rr.ethodology-shows there is a high probability that all of the acceptance criteria contained in 10 CFR 50.46, Paragraph b are met, the proposed change does not increase the consequences of an accident previously evaluated.
Therefore, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2. Does the proposed change create the possibility of a new or different kind of accident from any accident previously evaluated?
Response: No.
There are no physical changes being made to the plant. No new modes of plant operation are being introduced. The parameters assumed in the analysis remain within the design limits of the existing plant equipment. All plant systems will perform as designed during the response to a potential accident.
Therefore, the proposed change does not create the possibility of a new or different kind of accident from any previously analyzed.
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 5 of 13 1 r
- 3. Does this change involve a significant reduction in margin of safety?
Response: No.
It has been shown that the methodology used in the analysis would more realistically describe the expected behavior of V. C. Summer Nuclear Station systems during a postulated loss of coolant accident. Uncertainties have been accounted for as required by 10 CFR 50.46. A sufficient number of loss of coolant accidents with different break sizes, different locations and other variations in properties are analyzed to provide assurance that the most severe postulated loss of coolant accidents are calculated. It has been shown by analysis that there is a high level of probability that all criteria contained in 10 CFR 50.46, Paragraph b are met.
Pursuant to 10 CFR 50.91, the preceding analyses provide a determination that the proposed Technical Specifications change poses no significant hazard as delineated by 10 CFR 50.92.
5.2 Applicable Regulatory Requirements/Criteria 10 CFR 50.46, Acceptance Criteriafor Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors, requires that the ECCS system be designed to satisfy the 5 criterialisted in the regulation. These criteria are:
- 1. Peak cladding temperature
- 2. Maximum cladding oxidation
- 3. Maximum hydrogen generation
- 4. Coolable geometry
- 5. Long-term cooling.
V. C. Summer Nuclear Station has determined that the proposed changes do not require any exemptions or relief from regulatory requirements, other than the TS, and do not affect conformance with any general design criteria as contained in 10 CFR 50, Appendix A, differently than described in the safety analysis report. The proposed change is consistent with the requirements identified in 10 CFR 50.46 below. The conclusions of the analysis are that there is a high level of probability that:
- 1. The calculated maximum fuel element cladding temperature (peak cladding temperature) will not exceed 22000 F.
- 2. The calculated total oxidation of the cladding (maximum cladding oxidation) will not exceed 0.17 times the total cladding thickness before oxidation.
- 3. The calculated total amount of hydrogen generated from the chemical reaction of the cladding with water or steam (maximum hydrogen generation) will not exceed 0.01 times the hypothetical amount that would be generated if all of the metal in
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 6 of 13 the cladding cylinders surrounding the fuel, excluding the cladding surrounding the plenum volume, were to react.
- 4. The calculated changes in core geometry are such that the core remains amenable to cooling.
- 5. After successful initial operation of the ECCS, the core temperature will be maintained at an acceptably low value and decay heat will be removed for the extended period of time required by the long-lived radioactivity remaining in the core.
10 CFR 50, Appendix A, General Design Criteria, Criterion 35, Emergency Core Cooling states that the system safety function shall be to transfer heat from the reactor core following a loss of reactor coolant such that fuel and clad damage that could interfere with effective cooling is prevented and any metal water interaction is kept to negligible amounts.
The proposed change does not impact the ability of the system to perform its design function, as there are no plant hardware changes. The Emergency Core Cooling system will continue to perform to the same high reliability and availability standards.
-410. (FR.50,.Appendix K, ECCS Evaluation Models, lists. required and acceptable features that have to be included in all evaluation models. ' -
The BELOCA methodology has been generically approved by the NRC. NRC approval of the methodology is documented in the safety evaluation appended to the topical report (WCAP 12945-P-A, "Code Qualification Document for Best Estimate LOCA Analysis", March 1998). A plant specific analysis for the V. C. Summer Nuclear Station has been performed using the approved methodology. The BELOCA methodology relaxes some of the requirements in Appendix K without a loss in safety to the public.
Regulatory Guide 1.157 was issued to provide guidance on use of the best estimate codes.
Generic Letter 97-04: Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps.
The BELOCA methodology does not alter the amount of inventory dumped into the recirculation sumps. The water level and therefore the net positive suction head are unchanged under this methodology. The values of major plant parameters assumed in the best-estimate LOCA analysis will be documented in the VCSNS Final Safety Analysis Report (FSAR).
tI go lo Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 7 of 13 Generic Letter 98-04: Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System after a Loss-of-Coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment.
The response provided to Generic Letter 98-04 is not altered by the change in Large Break LOCA methodology. The quantities and types of debris are unchanged. The system operation is unaffected and the 10 CFR 50.46 acceptance criteria remains satisfied. The sump blockage issue is separate and is being resolved under Generic Safety Issue (GSI) 191.
Bulletin 86-03: Potential Failure of Multiple ECCS Pumps Due to a Single Failure of an Air Operated Valve in Mini Flow Recirculation Line.
Single failures and failure modes analysis were performed for the Emergency Core Cooling System (ECCS) during initial plant design. The change in Large Break (LB)
LOCA analysis methods from BASH to Best Estimate has no impact on the probabilities of this or any other type of failure that could prevent the system from performing its design function.
Bulletin 93-02: Debris Plugging of Emergency Core Cooling Suction Strainers.
Thelhange in analysis methodology Wviil not have tanyrimpact on the quantity or types Of debris generated or transported to the recirculation sumps. The sump blockage issue is separate and is being resolved under GSI-191.
Bulletin 2003-01: Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized Water Reactors.
GSI-191 is being used by the industry and the NRC to resolve concerns related to the potential for clogging the recirculation screens/strainers on the ECCS system. The change to the analysis methodology to a best estimate model will not have any impact on the current capability of the ECCS system. Any changes that may be made to the sump design will only affect resolution to the generic safety issue. The assumptions on available inventory in the sumps are the same for both analysis models. The best estimate methodology has the same initial conditions and assumptions as the current licensed model for VCSNS and as such the response to the Bulletin will not have any impact on the analysis model.
5.3 Design Bases (FSAR)
FSAR Section 15.4.1 Major Reactor Coolant System Pipe Ruptures.
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 8 of 13 The VCSNS FSAR will require revision as a result of this LAR.
5.4 Approved Methodologies The proposed change is to adopt the best estimate methodology for the large break loss of coolant accident analysis. This methodology is contained in WCAP-12945-P-A and has been approved by the staff for use at other Westinghouse plants. The methodology conforms to 10 CFR 50.46 and Section II of Appendix K, and meets the intent of Regulatory Guide 1.157, "Best-Estimate Calculations of Emergency Core Cooling System Performance".
The analysis performed for VCSNS utilizes parameters that are bounded by the models and correlations contained in the generic methodology.
5.5 Analysis The parameters used in the VCSNS specific analysis performed with the BELOCA methodology are presented in Table 2. The results of the analysis are presented in Table 1 and demonstrate that the 10 CFR 50.46 criteria are satisfied.
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 9 of 13 Table 2 V. C. SUMMER NUCLEAR STATION BEST ESTIMATE LARGE BREAK LOCA MAJOR PLANT PARAMETER ASSUMPTIONS
.Paramneter--..- 'lValue Plant Physical Description Steam Generator Tube Plugging < 10%
Plant Initial Operating Conditions Reactor Power < 102% of 2900 MWt w/2% Calorimetric uncertainty Peaking Factors F0 =2.5, FAH=1.7 Axial Power Distribution Figure 1 Fluids Conditions RCS Tavq 572.0 + 5.3 < Tava, < 587.4 + 5.3 OF Pressurizer Pressure 2250 + 100 psia Reactor Coolant Flow > 92,600 gpm/loop Accumulator Temperature 85 < T,0 c < 115 OF Accumulator Pressure 570 < P,,c < 686 psiq Accumulator Water Volume 994 < Va~c < 1034 ft -
Accident Boundary Conditions Single Failure Assumptions 1 Train of SI Pumps (WCOBRA/TRAC Studies)
No Failures (Containment Pressure Study)
Safety Iniection Flow Table 3 Safety Injection Temperature 55 < Ts, < 95 OF Safety Injection Initiation Delay < 22 sec No-Loss Of Offsite Power (LOOP)
Time <32 sec LOOP Containment Pressure Figure 2 - -
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 10 of 13 Table 3 V. C. SUMMER NUCLEAR STATION BEST ESTIMATE LARGE BREAK LOCA TOTAL MINIMUM INJECTED SI FLOW TOTAL CHG/SI AND LHSI INTO 2 INTACT LOOPS RCS Pessiure ( sig) .Fiw - Rate (gpm) 0 2709 15 2561 20 2467 30 2270 40 2064 50 1848 60 1612 70 1356 80 1071 90 699 100 305 200 295 300 285 400 274
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 11 of 13 Figure 1 Virgil Summer Best Estimate Analysis Axial Power Distribution Operating Space
,43 .
(0.30,0.43) -
A-
,35 -.
0 Z-1 (0.30,0.28) !-,
.25 -
X4
.15 . .3 I I I I II , , , . ,_ , I I II I
.35 PMID Legend:
PBOT- Fraction of Power in lower third of the core PMID - Fraction of Power in mid region of the core
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 12 of 13 Figure 2 Virgil Summer Best Estimate Analysis Containment Backpressure 40 -
35-30
~25-
=3 co) 15 10 Time After Break (sec) 5.6 Conclusion The proposed change to the VCSNS TS is to adopt the BELOCA methodology.
Document Control Desk Enclosure LAR 04-3385 RC-05-0097 Page 13 of 13
6.0 ENVIRONMENTAL CONSIDERATION
SCE&G has determined that the proposed amendment would not change requirements with respect to the installation or use of a facility component located within the restricted area, as defined in 10 CFR 20, or would change an inspection or surveillance requirement. The proposed amendment is a methodology change for TS 3.2.3, Heat Flux Hot Channel Factor. The methodology to be used has been generically approved for use by the NRC (WCAP 12945-P-A).
SCE&G has evaluated the proposed change and has determined that the change does not involve, (i) a significant hazards consideration, (ii) a significant change in the types of or significant increase in the amounts of any effluents that may be released offsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure. As discussed above, the proposed changes do not involve a significant hazards consideration. Accordingly, the proposed change meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51, specifically 10 CFR 51 .22(c)(9). Therefore, pursuant 10 CFR 51.22(b), an environmental assessment of the proposed change is not required.
Document Control Desk Attachment I LAR 04-3385 RC-05-0097 Page 1 of 3 ATTACHMENT I PROPOSED TECHNICAL SPECIFICATION CHANGE (MARK-UP)
Attachment to License Amendment No. 04-3385 To Facility Operating License No. NPF-12 Docket No. 50-395 Replace the following page of the Appendix A Technical Specifications with the attached revised page. The revised page is identified by amendment number and contains a marginal line indicating the area of change.
Remove Pages Insert Pages 6-16a 6-16a SCE&G -- EXPLANATION OF CHANGES Page Affected Bar Description of Change Reason for Change Section #
6:16a t 6.9.1.11 1 Revising the reference for Implementing the Best Large Break LOCA analysis Estimate Loss of Coolant methodology from BASH to Accident analysis Best Estimate. methodology.
Document Control Desk Attachment I LAR 04-3385 RC-05-0097 Page 2 of 3 Insert for Section 6.9.1.11
- c. WCAP-12945-P-A, Volume 1 (Revision 2) through Volumes 2 through 5 (Revision 1)
"Code Qualification Document for Best Estimate LOCA Analysis," March 1998 (Westinghouse Proprietary).
Liparulo, N. (_) to NRC Document Control Desk, NSD-NRC-96-4746, "Re-Analysis Work Plans Using Final Best Estimate Methodology" dated 6/13/1996.
ADMINISTRATIVE CONTROLS CORE OPERATING LIMITS REPORT (Continued) v (Methodology for Specifications 3.1.1.3 - Moderator Temperature Coefficient, 3.1.3.5 - Shutdown Rod Insertion Limits, 3.1.3.6 - Control Rod Insertion Limits, 3.2.1 - Axial Flux Difference, 3.2.2 - Heat Flux Hot Channel Factor, and 3.2.3 -
RCS Flow Rate'and Nuclear:Enthalpy Rise Hot Channel Factor.)
- b. WCAP-1 0216-P-A, Rev. 1A, "RELAXATION OF CONSTANT AXIAL OFFSET CONTROL Fo SURVEILLANCE TECHNICAL SPECIFICATION," February 1994 (W Proprietary).
(Methodology for Specifications 3.2.1 - Axial Flux Difference (Relaxed Axial Offset Control) and 3.2.2 - Heat -Flux Hot Channel Factor (Fa Methodology for W(z) surveillance requirements).)
- c. - 6-P-A, Rev. 2, "THE 1981 VERSION OFWESTI S&re - EVALUATION ML CODEiMncling Addendum 2-A, -BASH METHO OL II REL REIABLITY EN _NTSE ay 1988, (W Proprietary).
(Methodology for Specification 3.2.2 - Heat Flux Hot Channel Factor.)
- d. WCAP-12472-P-A, -BEACON CORE MONITORING AND OPERATIONS SUPPORT SYSTEM," August 1994, (W Proprietary).
(Methodology for Specifications 3.2.2 - Heat Flux Hot Channel Factor, 3.2.3 -
RCS Flow Rate and Nuclear Enthalpy Rise Hot Channel Factor, and 3.2.4 -
Quadrant Power Tilt Ratio.)
- e. WCAP-13749-P-A, "Safety Evaluation Supporting the Conditional Exemption of 4 the Most Negative EOL Moderator Temperature Coefficient Measurement,"
March 1997, (Westinghouse Proprietary). J7 (Methodology for Specification 3.1.1.3 - Moderator Temperature Coefficient.)
The core operating limits shall be determined so that all applicable limits (e.g., fuel thermal-mechanical limits, core thermal-hydraulic limits, nuclear limits such as shutdown margin, and transient and accident analysis limits) of the safety analysis are met.
The CORE OPERATING LIMITS REPORT, including any mid-cycle revisions or supplements there to shall be provided upon issuance, for each reload cycle, to the NRC Document Control Desk with copies to the Regional Administrator and Resident Inspector.
SUMMER - UNIT 1 6-16a Amendment No. 88, 121, 133, 112,4fe9-
Document Control Desk 1 LAR 04-3385 RC-05-0097 Page 1 of 2 ATTACHMENT 11 PROPOSED TECHNICAL SPECIFICATION CHANGE (RETYPED)
ADMINISTRATIVE CONTROLS CORE OPERATING LIMITS REPORT (Continued)
(Methodology for Specifications 3.1.1.3 - Moderator Temperature Coefficient, 3.1.3.5 - Shutdown Rod Insertion Limits, 3.1.3.6 - Control Rod Insertion Limits, 3.2.1 - Axial Flux Difference, 3.2.2 - Heat Flux Hot Channel Factor, and 3.2.3 -
RCS Flow Rate and Nuclear Enthalpy Rise Hot Channel Factor.)
- b. WCAP-1 0216-P-A, Rev. 1A, "RELAXATION OF CONSTANT AXIAL OFFSET CONTROL FQ SURVEILLANCE TECHNICAL SPECIFICATION," February 1994 (W Proprietary).
(Methodology for Specifications 3.2.1 - Axial Flux Difference (Relaxed Axial Offset Control) and 3.2.2 - Heat Flux Hot Channel Factor (FQ Methodology for W(z) surveillance requirements).)
- c. WCAP-12945-P-A, Volume 1 (Revision 2) through Volumes 2 through 5 (Revision 1) 'Code Qualification Document for Best Estimate LOCA Analysis,"
March 1998 (Westinghouse Proprietary).
Liparulo, N. (W) to NRC Document Control Desk, NSD-NRC-96-4746, "Re-Analysis Work Plans Using Final Best Estimate Methodology" dated 6/13/1996.
(Methodology for Specification 3.2.2 - Heat Flux Hot Channel Factor.)
- d. WCAP-12472-P-A, "BEACON CORE MONITORING AND OPERATIONS SUPPORT SYSTEM," August 1994, (W Proprietary).
-. (Methodology for Specifications 3.2.2 - HeatFltix HotChanneLFactor, 3;2.3 -
RCS Flow Rate and Nuclear Enthalpy Rise Hot Channel Factor, and 3.2.4 -
Quadrant Power Tilt Ratio.)
- e. WCAP-13749-P-A, "Safety Evaluation Supporting the Conditional Exemption of the Most Negative EOL Moderator Temperature Coefficient Measurement,"
March 1997, (Westinghouse Proprietary).
(Methodology for Specification 3.1.1.3 - Moderator Temperature Coefficient.)
The core operating limits shall be determined so that all applicable limits (e.g., fuel thermal-mechanical limits, core thermal-hydraulic limits, nuclear limits such as shutdown margin, and transient and accident analysis limits) of the safety analysis are met.
The CORE OPERATING LIMITS REPORT, including any mid-cycle revisions or supplements there to shall be provided upon issuance, for each reload cycle, to the NRC Document Control Desk with copies to the Regional Administrator and Resident Inspector.
SUMMER - UNIT 1 6-16a Amendment No. 88, 121, 133, 112, 469T,
Document Control Desk Attachment III LAR 04-0440 RC-05-0097 Page 1 of 1 ATTACHMENT III LIST OF REGULATORY COMMITMENTS There are no regulatory commitments created due to this License Amendment Request.