ONS-2013-036, (Ons), Units 1, 2, and 3 - Completion of Protected Service Water System Milestone 2

From kanterella
Jump to navigation Jump to search
(Ons), Units 1, 2, and 3 - Completion of Protected Service Water System Milestone 2
ML13350A021
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 12/12/2013
From: Batson S
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ONS-2013-036
Download: ML13350A021 (2)


Text

DUKE ScoffL. Batson SENERGY. Oconee Nuclear Station Duke Energy ONOIVP 17800 Rochester Hwy ONS-2013-036 Seneca, SC 29672 o: 864.873.3274 10 CFR 50.4 f 864.873.4208 Scoff.Batson@duke-energy.com December 12, 2013 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, Maryland 20852-2746

Subject:

Duke Energy Carolinas, LLC Oconee Nuclear Station (ONS), Units 1, 2, and 3 Renewed Facility Operating License Numbers DPR-38, 47, and 55 Docket Numbers 50-269, 50-270, and 50-287 Completion of Protected Service Water System Milestone 2

Reference:

NRC letter to Duke Energy, "NOTICE OF VIOLATION AND CONFIRMATORY ORDER RELATED TO A FIRE PROTECTION PROGRAM LICENSE CONDITION (OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3)," dated July 1, 2013 The confirmatory order (Reference) related to an ONS fire protection program license condition requires Duke Energy to report the completion of each milestone within 30 days of completion.

Duke Energy completed Milestone 2 on November 15, 2013. Milestone 2 requires Duke Energy to provide ONS the capability to supply electrical power from each of the Keowee Hydro Units to the PSW building switchgear and from there to the SSF switchgear, with sufficient capacity to operate all credited SSF equipment in the event of a failure of the SSF diesel generator during a fire for which the SSF is credited. The order requires this modification, along with approved plant procedures and the completion of operator training necessary to accomplish this lineup, and a combination of testing and engineering evaluation in accordance with station procedures which verifies this capability, to be completed and operational no later than July 18, 2014.

If there are any additional questions, please contact Terry Patterson, ONS Safety Assurance, at (864) 873-3163.

I declare under penalty of perjury that the foregoing is true and correct. Executed on December 12, 2013.

Sincerely, Scott L. Batson Vice President Oconee Nuclear Station 0X)cOO0c

Nuclear Regulatory Commission December 12, 2013 Page 2 cc:

Mr. Victor McCree, Regional Administrator U. S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Mr. Richard Guzman, Senior Project Manager (by electronic mail only)

Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop O-8C2 Rockville, MD 20852 Mr. Eddy Crowe Senior Resident Inspector Oconee Nuclear Site Ms. Susan E. Jenkins, Manager Radioactive & Infectious Waste Management Division of Waste Management South Carolina Department of Health and Environmental Control 2600 Bull St.

Columbia, SC 29201