Similar Documents at Fermi |
---|
Category:Annual Operating Report
MONTHYEARNRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0025, Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2023-04-28028 April 2023 Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-22-0033, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 20222022-08-29029 August 2022 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 2022 ML22119A1732022-04-11011 April 2022 DTE Electric Company Submittal of Fermi 3 Periodic Reports NRC-21-0044, Annual Report for Period Ending June 30, 20212021-08-30030 August 2021 Annual Report for Period Ending June 30, 2021 NRC-21-0028, 2020 Annual Non-Radiological Environmental Operating Report2021-04-29029 April 2021 2020 Annual Non-Radiological Environmental Operating Report NRC-21-0026, Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report2021-04-28028 April 2021 Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report NRC-21-0014, Submittal of 2020 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2021-04-23023 April 2021 Submittal of 2020 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-19-0056, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 20192019-08-28028 August 2019 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 2019 NRC-19-0033, Annual Non-Radiological Environmental Operating Report2019-04-30030 April 2019 Annual Non-Radiological Environmental Operating Report NRC-16-0053, Annual Report for Period Ending June 30, 20162016-08-18018 August 2016 Annual Report for Period Ending June 30, 2016 NRC-15-0088, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 20152015-08-27027 August 2015 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 2015 NRC-15-0054, Annual Non-Radiological Environmental Operating Report for 20142015-04-29029 April 2015 Annual Non-Radiological Environmental Operating Report for 2014 NRC-14-0064, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 20142014-08-28028 August 2014 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 2014 NRC-14-0033, Annual Non-Radiological Environmental Operating Report for 20132014-04-28028 April 2014 Annual Non-Radiological Environmental Operating Report for 2013 NRC-13-0048, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 20132013-08-26026 August 2013 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 2013 NRC-13-0025, Annual Non-Radiological Environmental Operating Report2013-04-24024 April 2013 Annual Non-Radiological Environmental Operating Report NRC-12-0029, Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report2012-04-27027 April 2012 Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report NRC-12-0031, Annual Non-Radiological Environmental Operating Report for 20112012-04-25025 April 2012 Annual Non-Radiological Environmental Operating Report for 2011 NRC-11-0043, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report Period Ending June 30, 20112011-08-30030 August 2011 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report Period Ending June 30, 2011 NRC-11-0016, Annual Radiological Environmental Operating Report, Radioactive Effluent Release Report and Revised Offsite Dose Calculation Manual2011-04-28028 April 2011 Annual Radiological Environmental Operating Report, Radioactive Effluent Release Report and Revised Offsite Dose Calculation Manual NRC-10-0064, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 20102010-08-31031 August 2010 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 2010 NRC-10-0038, Annual Non-Radiological Environmental Operating Report for 20092010-04-28028 April 2010 Annual Non-Radiological Environmental Operating Report for 2009 NRC-10-0036, Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report2010-04-28028 April 2010 Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report NRC-09-0051, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report Period Ending June 30, 20092009-08-27027 August 2009 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report Period Ending June 30, 2009 NRC-08-0057, Enrico Fermi, Unit 1, Annual Report for the 2nd Quarter of 20082008-08-28028 August 2008 Enrico Fermi, Unit 1, Annual Report for the 2nd Quarter of 2008 ML0812202332008-04-24024 April 2008 Fermi 2- 2007 Annual Radioactive Effluent Release and Radiological Environmental Operating Report for the Period of January 1, 2007 Through December 31, 2007 NRC-08-0031, Fermi 2- 2007 Annual Radioactive Effluent Release and Radiological Environmental Operating Report for the Period of January 1, 2007 Through December 31, 20072008-04-24024 April 2008 Fermi 2- 2007 Annual Radioactive Effluent Release and Radiological Environmental Operating Report for the Period of January 1, 2007 Through December 31, 2007 NRC-08-0026, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2008-03-31031 March 2008 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-07-0020, Annual Radiological Effluent Release and Radiological Environmental Operating Reports2007-04-27027 April 2007 Annual Radiological Effluent Release and Radiological Environmental Operating Reports NRC-05-0036, Annual Non-Radiological Environmental Operating Report for 20042005-04-29029 April 2005 Annual Non-Radiological Environmental Operating Report for 2004 NRC-04-0026, 2003 Annual Non Radiological Environmental Operating Report for Fermi 22004-04-30030 April 2004 2003 Annual Non Radiological Environmental Operating Report for Fermi 2 NRC-04-0025, 2003 Annual Reports for Fermi 22004-04-29029 April 2004 2003 Annual Reports for Fermi 2 NRC-03-0042, 2002 Annual Reports for Fermi 22003-04-28028 April 2003 2002 Annual Reports for Fermi 2 NRC-03-0041, Annual Non Radiological Environmental Operating Report2003-04-28028 April 2003 Annual Non Radiological Environmental Operating Report NRC-02-0031, 2001 Annual Non-Radiological Environmental Operating Report for Fermi 22002-04-24024 April 2002 2001 Annual Non-Radiological Environmental Operating Report for Fermi 2 2023-08-31
[Table view] Category:Environmental Report
MONTHYEARNRC-16-0031, Transmittal of 2015 Annual Non-Radiological Environmental Operating Report2016-04-26026 April 2016 Transmittal of 2015 Annual Non-Radiological Environmental Operating Report NRC-14-0033, Annual Non-Radiological Environmental Operating Report for 20132014-04-28028 April 2014 Annual Non-Radiological Environmental Operating Report for 2013 ML14121A5392014-04-24024 April 2014 Fermi 2, License Renewal Application, Appendix E, Page 3-170 Through Page 9-23 ML14121A5382014-04-24024 April 2014 Fermi 2, License Renewal Application, Appendix D Through Appendix E, Page 3-169 NRC-14-0028, License Renewal Application, Appendix E, Page 10-1 Through End2014-04-24024 April 2014 License Renewal Application, Appendix E, Page 10-1 Through End NRC-14-0073, Response to LRA Environmental RAIs - Final Threatened and Endangered Species Survey and Assessment Report - Part 1 of 32013-10-16016 October 2013 Response to LRA Environmental RAIs - Final Threatened and Endangered Species Survey and Assessment Report - Part 1 of 3 ML14344B0032013-10-16016 October 2013 Response to LRA Environmental RAIs - Final Threatened and Endangered Species Survey and Assessment Report Part 3 of 3 NRC-14-0073, Response to LRA Environmental RAIs - Final Threatened and Endangered Species Survey and Assessment Report - Part 2 of 32013-10-16016 October 2013 Response to LRA Environmental RAIs - Final Threatened and Endangered Species Survey and Assessment Report - Part 2 of 3 NRC-14-0073, Response to LRA Environmental RAIs - Final Threatened and Endangered Species Survey and Assessment Report Part 3 of 32013-10-16016 October 2013 Response to LRA Environmental RAIs - Final Threatened and Endangered Species Survey and Assessment Report Part 3 of 3 ML14344B0012013-10-16016 October 2013 Response to LRA Environmental RAIs - Final Threatened and Endangered Species Survey and Assessment Report - Part 1 of 3 ML14344B0022013-10-16016 October 2013 Response to LRA Environmental RAIs - Final Threatened and Endangered Species Survey and Assessment Report - Part 2 of 3 NRC-13-0025, Annual Non-Radiological Environmental Operating Report2013-04-24024 April 2013 Annual Non-Radiological Environmental Operating Report NRC-14-0073, Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 2 of 52011-04-30030 April 2011 Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 2 of 5 NRC-14-0073, Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 1 of 52011-04-30030 April 2011 Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 1 of 5 NRC-14-0073, Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 3 of 52011-04-30030 April 2011 Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 3 of 5 NRC-14-0073, Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 4 of 52011-04-30030 April 2011 Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 4 of 5 ML14344B0062011-04-30030 April 2011 Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 2 of 5 ML14344B0052011-04-30030 April 2011 Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 1 of 5 ML14344B0072011-04-30030 April 2011 Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 3 of 5 ML14344B0082011-04-30030 April 2011 Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 5 of 5 NRC-14-0073, Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 5 of 52011-04-30030 April 2011 Response to LRA Environmental RAIs - Ducks Unlimited Wetland Investigation Report April 2011 - Part 5 of 5 NRC-10-0036, Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report2010-04-28028 April 2010 Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report ML0936401362009-12-15015 December 2009 Information Regarding License Termination Plan NRC-09-0080, Fermi, Unit 1 - Information Regarding License Termination Plan2009-12-15015 December 2009 Fermi, Unit 1 - Information Regarding License Termination Plan NRC-09-0070, Enrico Fermi Atomic Power Plant, Unit 1, Submittal of NRC Requested Information Regarding License Termination Plan2009-12-0303 December 2009 Enrico Fermi Atomic Power Plant, Unit 1, Submittal of NRC Requested Information Regarding License Termination Plan NRC-09-0053, Enrico Fermi Atomic Power Plant, Unit 1 - Information Regarding the License Termination Plan2009-10-23023 October 2009 Enrico Fermi Atomic Power Plant, Unit 1 - Information Regarding the License Termination Plan NRC-09-0046, Modeling Scenarios for License Termination Plan Criteria2009-08-27027 August 2009 Modeling Scenarios for License Termination Plan Criteria NRC-08-0031, Fermi 2- 2007 Annual Radioactive Effluent Release and Radiological Environmental Operating Report for the Period of January 1, 2007 Through December 31, 20072008-04-24024 April 2008 Fermi 2- 2007 Annual Radioactive Effluent Release and Radiological Environmental Operating Report for the Period of January 1, 2007 Through December 31, 2007 ML0812202332008-04-24024 April 2008 Fermi 2- 2007 Annual Radioactive Effluent Release and Radiological Environmental Operating Report for the Period of January 1, 2007 Through December 31, 2007 NRC-03-0043, Annual Radioactive Effluent Release and Radiological Environmental Operating Reports2003-04-29029 April 2003 Annual Radioactive Effluent Release and Radiological Environmental Operating Reports NRC-03-0041, Annual Non Radiological Environmental Operating Report2003-04-28028 April 2003 Annual Non Radiological Environmental Operating Report NRC-02-0031, 2001 Annual Non-Radiological Environmental Operating Report for Fermi 22002-04-24024 April 2002 2001 Annual Non-Radiological Environmental Operating Report for Fermi 2 2016-04-26
[Table view] Category:Letter type:NRC
MONTHYEARNRC-24-0007, Report of Changes to Quality Assurance Program for Radioactive Material Packages2024-01-12012 January 2024 Report of Changes to Quality Assurance Program for Radioactive Material Packages NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0079, Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 222023-12-14014 December 2023 Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 22 NRC-23-0077, Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan2023-12-0404 December 2023 Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0057, Independent Spent Fuel Storage Installation Cask Registration2023-08-31031 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval2023-08-31031 August 2023 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0060, Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0053, Independent Spent Fuel Storage Installation Cask Registration2023-08-23023 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0048, Independent Spent Fuel Storage Installation Cask Registration2023-08-0101 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0049, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-07-24024 July 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0043, Independent Spent Fuel Storage Installation, Cask Registration2023-06-27027 June 2023 Independent Spent Fuel Storage Installation, Cask Registration NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2023-06-0505 June 2023 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval2023-06-0505 June 2023 Snubber Program for the Fourth 10-Year Testing Interval NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi NRC-23-0031, Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2023-05-16016 May 2023 Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-23-0002, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-05-0505 May 2023 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0010, License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage2023-05-0505 May 2023 License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage NRC-23-0017, Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report2023-04-28028 April 2023 Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report NRC-23-0025, Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2023-04-28028 April 2023 Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-23-0018, Annual Non-Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Non-Radiological Environmental Operating Report NRC-23-0024, Levels and Sources of Property Insurance Coverage2023-04-0303 April 2023 Levels and Sources of Property Insurance Coverage NRC-23-0021, ISFSI, Decommissioning Funding Plan Update2023-03-30030 March 2023 ISFSI, Decommissioning Funding Plan Update NRC-23-0016, Decommissioning Funding Status Report2023-03-30030 March 2023 Decommissioning Funding Status Report NRC-23-0015, Decommissioning Funding Status Report for Fermi 12023-03-30030 March 2023 Decommissioning Funding Status Report for Fermi 1 NRC-23-0011, License Renewal Commitment 7c: Transmittal of Core Plate Hold-Down Bolt Analysis2023-03-0707 March 2023 License Renewal Commitment 7c: Transmittal of Core Plate Hold-Down Bolt Analysis NRC-22-0026, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2022-12-16016 December 2022 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-22-0051, DTE Electric Company - Guarantee of Payment of Deferred Premiums2022-11-29029 November 2022 DTE Electric Company - Guarantee of Payment of Deferred Premiums NRC-22-0052, Replacement Files for Submittal of Revision 24 to the Fermi 2 Updated Final Safety Analysis Report (UFSAR) Through EIE on November 9, 20222022-11-17017 November 2022 Replacement Files for Submittal of Revision 24 to the Fermi 2 Updated Final Safety Analysis Report (UFSAR) Through EIE on November 9, 2022 NRC-22-0046, Submittal of Biennial Review of the Fermi 1 Safety Analysis Report2022-11-14014 November 2022 Submittal of Biennial Review of the Fermi 1 Safety Analysis Report NRC-22-0041, Evacuation Time Estimate Report2022-10-0505 October 2022 Evacuation Time Estimate Report NRC-22-0033, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 20222022-08-29029 August 2022 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 2022 NRC-22-0030, Inservice Inspection Summary Report2022-08-10010 August 2022 Inservice Inspection Summary Report NRC-22-0023, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2022-08-0404 August 2022 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements NRC-22-0022, Annual Non-Radiological Environmental Operating Report2022-04-29029 April 2022 Annual Non-Radiological Environmental Operating Report NRC-22-0021, Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report2022-04-29029 April 2022 Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report NRC-22-0020, Enrico Fermi Atomic Power Plant, Unit No. 1 & Fermi 2 Power Plant - 10 CFR 20.2206 Report of Individual Monitoring2022-04-28028 April 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 & Fermi 2 Power Plant - 10 CFR 20.2206 Report of Individual Monitoring NRC-22-0003, Submittal of 2021 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2022-04-26026 April 2022 Submittal of 2021 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-22-0019, Submittal of the National Pollutant Discharge Elimination System Permit Application for Reissuance2022-04-0404 April 2022 Submittal of the National Pollutant Discharge Elimination System Permit Application for Reissuance NRC-22-0011, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2022-03-31031 March 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report 2024-01-12
[Table view] |
Text
2 Fermi Fermi 2 6400 North Dixie Hwy., Newport, M1 48166 Detroit Edison April 24, 2002 NRC-02-0031 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555-0001
Reference:
Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
Subject:
Annual Non-Radiological Environmental Operating Report Pursuant to Section 5.4.1 of the Environmental Protection Plan, enclosed is the 2001 Annual Non-Radiological Environmental Operating Report for Fermi 2.
Should you have any questions regarding this report, please contact Lynda Craine, General Supervisor, RP Technical Services and Support, at (734) 586-4970.
Sincerely, orma NuPeterson Manager - Nuclear Licensing Enclosure cc: T.J. Kim M. A. Ring NRC Resident Office Regional Administrator, Region III Supervisor, Electric Operators, Michigan Public Service Commission A DTE Energy Company
J ~gtFermi 2 Environmental Control
- - - . .I--ýIi'YourS 2001 Annual Nonradiological Environmental Operating Report Detroit Edison - Fermi 2 6400 North Dixie Highway Newport, MI 48166 Reporting Period:
January 1, 2001 to December 31, 2001 Prepared by:
Fermi 2 Environmental Health
2001 Annual Nonradiological Environmental Operating Report Detroit Edison Fermi 2 Page 1 2001 ANNUAL NONRADIOLOGICAL ENVIRONMENTAL OPERATING REPORT TABLE OF CONTENTS Section Page Number Number 1.0 EXECUTIVE
SUMMARY
2
2.0 INTRODUCTION
3 2.1 Purpose 3 2.2 Environmental Protection Plan Overview 3 2.3 Annual Report Objectives 4 2.4 Site Description 5 3.0 TERRESTRIAL MONITORING 5 4.0 HERBICIDE MONITORING 6 5.0 AQUATIC MONITORING 7 6.0 EPP NONCOMPLIANCE 8
.7.0 DESIGN OR OPERATION CHANGES 8 8.0 UNUSUAL OR IMPORTANT ENVIRONMENTAL EVENTS 8
9.0 CONCLUSION
S 9
2001 Annual Nonradiological Environmental Operating Report Detroit Edison Fermi 2 Page 2 2001 ANNUAL NONRADIOLOGICAL ENVIRONMENTAL OPERATING REPORT 1.0 EXECUTIVE
SUMMARY
The following is a brief summary of the 2001 Annual Nonradiological Environmental Report for the Detroit Edison Enrico Fermi Unit 2 Power Plant (Fermi 2):
" No terrestrial monitoring activities were conducted, or required. Based on the findings of the terrestrial monitoring program, which was concluded in 1994, no further aerial-photographic evaluations are planned.
" Nine herbicides were approved and seven were utilized on site. All herbicide applications were recorded and maintained, as required by the Environmental Protection Plan (EPP).
" During the period covered by this report, there were no changes to station design that created an unreviewed environmental question, per the requirements and definitions of the EPP.
"* No unusual or important environmental events, as defined by the EPP, occurred.
Accordingly, no nonroutine reports were submitted.
2001 Annual Nonradiological Environmental Operating Report Detroit Edison Fermi 2 Page 3 2001 ANNUAL NONRADIOLOGICAL ENVIRONMENTAL OPERATING REPORT
2.0 INTRODUCTION
2.1 Purpose The purpose of this report is to provide the Nuclear Regulatory Commission (NRC), site personnel, and the public with information regarding the implementation of the Nonradiological Environmental Protection Program at the Detroit Edison Enrico Fermi Unit 2 Power Plant (Fermi 2). This report is due prior to May 1 of each year and meets the requirements specified in section 5.4.1 of the Fermi 2 Nonradiological Environmental Protection Plan (EPP), which is included in Appendix B of Facility Operating License No. NPF-43.
2.2 Environmental Protection Plan Overview As part of the application for the nuclear power plant construction permit and operating license, extensive environmental studies were conducted to evaluate potential nonradiological environmental risks that could result from the construction and operation of Fermi 2. In August 1981, the NRC published the Final Environmental Statement (FES) for the operation of Fermi 2. The FES was developed pursuant to the guidelines of the National Environmental Policy Act of 1969 (NEPA) and Title 10 of the Code of Federal Regulations (CFR), Part 51.
The EPP was prepared, based on the potential environmental risks and monitoring requirements identified in the FES. The purpose of the EPP is to provide for the protection of environmental values during any additional construction and the continued operation of Fermi 2. The principle objectives of the EPP are as follows:
- 1. Verify that Fermi 2 is operated in an environmentally acceptable manner, as established by the FES and environmental impact assessments.
- 2. Coordinate NRC requirements and maintain consistency with other Federal, State and local requirements for environmental protection.
- 3. Keep the NRC informed of the environmental effects of facility construction and operation, and of actions taken to control those effects.
2001 Annual Nonradiological Environmental Operating Report Detroit Edison Fermi 2 Page 4 The components of the EPP are as follows:
- 1. A terrestrial monitoring program to detect long-term or sudden changes in vegetation that may be attributable to the dispersion of Fermi 2 cooling tower vapor. The terrestrial monitoring program was completed in 1994, after 4 successive monitoring cycles were completed, as required.
- 2. A program to establish the controlled use of herbicides.
- 3. A program to ensure that changes to Fermi 2's design or operation and potential tests or experiments are adequately reviewed prior to implementation to avoid adverse environmental impacts not previously evaluated. Changes in plant design, operation, tests or experiments which do not affect the environment or which are required to achieve compliance with other Federal, State or local environmental regulations, are not subject to the requirements of this EPP.
- 4. Routine monitoring for evidence of unusual or important environmental events.
- 5. Any changes, renewals or stayed appeals to the Fermi 2 National Pollution Discharge Elimination System (NPDES) permit, or the State certification, must be reported to the NRC within 30 days.
2.3 Annual Report Objectives According to Section 5.4.1 of the EPP, the required objectives of the Annual Report are as follows:
" Provide summaries and analyses of the results of environmental protection activities conducted in the following areas: unusual or important environmental events; and terrestrial monitoring, which includes aerial remote sensing and herbicide applications. Where applicable, the report should compare these activities to pre operational studies, operational controls, observed environmental impacts, and previous nonradiological environmental monitoring reports. If harmful effects or evidence of trends towards irreversible damage to the environment are identified, provide detailed data analysis and a proposed course of action to correct the problem.
" Describe any changes to Fermi 2's design, operation, tests or experiments that were implemented without adequate review that adversely impacted, or could have adversely impacted, the environment, in accordance with Section 3.1 of the EPP.
"* Describe any noncompliance with the EPP and the corrective actions taken to correct the situation.
2001 Annual Nonradiological Environmental Operating Report Detroit Edison Fermi 2 Page 5
- Describe any nonroutine reports submitted to the NRC as the result of an unusual or important environmental event, in accordance with Section 5.4.2 of the EPP.
2.4 Site Description Fermi 2 operates a 1,217 megawatt (gross) General Electric Boiling Water Reactor 4 Nuclear Power Plant. The Fermi 2 power block is situated in the northeast quarter of a 1,120-acre site that is located approximately 8 miles east-northeast of Monroe, Michigan and 20 miles southwest of Detroit, Michigan. The site is fenced with locked or guarded gates.
Also on site is the Enrico Fermi 1 Power Plant (Fermi 1). Fermi 1 was an experimental fast breeder reactor that is presently in a SAFSTOR condition and is currently undergoing decommissioning. Subsequent to shut down, an oil-fired boiler was constructed.
Operation of this boiler ceased in 1980 and it was removed from site in 1999. The Fermi 1 general service water system is still in use.
Contiguous to the site are four oil-fired combustion turbine generators, which are periodically operated during periods of high electricity demand.
The site is bounded on the north by Swan Creek, on the east by Lake Erie, on the south by Pointe Aux Peaux Road, and on the west by a private road owned by Detroit Edison. The northern and southern areas of the site are dominated by large lagoons. The western side of the site is predominately covered by several wood lots and a series of small quarry lakes. Site elevation ranges from approximately 25 feet above lake level on the western edge of the site to lake level on the eastern edge.
3.0 TERRESTRIAL MONITORING Overview Section 4.2.1 of the Fermi 2 EPP requires that a special surveillance program be conducted to evaluate changes to vegetative communities within a 1 kilometer radius of the cooling towers. This program involves analysis of low altitude overflights prior to harvest utilizing color infrared photography, backed up by field reconnaissance inspections to verify areas of vegetative stress and nonstress along with soil sampling and analysis. The first flights and report were required after one year of plant operation and then every alternate year for 3 successive periods.
It should be noted that the above-described studies were not conducted to assess radiological impacts to the terrestrial environment, because discharge from the cooling towers is not radiologically active. The discharge consists of water vapor containing naturally occurring dissolved-solids at slightly higher concentrations than typical for lake water.
2001 Annual Nonradiological Environmental Operating Report Detroit Edison Fermi 2 Page 6 Activities and Controls The final required aerial photographic events were performed in 1994 and a final terrestrial monitoring report summarizing all collected data was completed in April 1995.
The report concluded the following:
"* No long-term accumulation of dissolved-solid deposition was detected in any of the soil samples collected within the survey area.
"* No vegetative stress associated with cooling-tower emission was observed in any of the survey reports.
" No correlation was observed between the distribution of stressed vegetation areas and the calculated deposition of dissolved solids and other materials contained within the vaporous cooling-tower discharge.
"* The absence of observed impacts attributable to the cooling towers is consistent with findings in the scientific literature.
No terrestrial monitoring activities were conducted, or required, in 2001. Based on the findings and conclusions of the above-described study, no further aerial-photographic evaluations are planned.
4.0 HERBICIDE MONITORING Overview Section 4.2.2 of the Fermi 2 EPP requires that herbicide use meet the following conditions:
- 1. Herbicides used must be registered by the United States Environmental Protection Agency (EPA) and utilized in accordance with EPA-approved use instructions.
- 2. Herbicides used must be approved by State authorities and applied in accordance with state instructions.
- 3. Records of on-site herbicide use must be maintained for a period of 5 years and contain the following information: commercial and chemical names of herbicide used; concentration of active material in formulations diluted for field use; diluting substances other than water; rates of application; method and frequency of application; location, and; date of application.
2001 Annual Nonradiological Environmental Operating Report Detroit Edison Fermi 2 Page 7 Activities and Controls Herbicide use on-site is managed according to Section 2.6 of the Chemistry and Environmental Monitoring Conduct Manual, Chapter 6 (MCE06). In accordance with this procedure, all herbicides used on site in 2001 were pre-approved per the Herbicide Application Request Form, which meets the requirements of items 1 and 2 listed above.
Once a herbicide is approved, the registered pesticide applicator must fill out a Herbicide Application Record for each application which meets the criteria specified in item 3 listed above.
In 2001, nine different herbicides were approved and seven were utilized on-site. All herbicide applications were recorded and maintained, as required.
5.0 AQUATIC MONITORING Overview According to Section 2.1 of the EPP, the NRC will rely on the Michigan Department of Environmental Quality (MDEQ) for the protection of the aquatic environment from nonradiological operational impacts via the National Pollution Discharge Elimination System (NPDES) permit. NPDES permits are issued in accordance with provisions of the Federal Water Pollution Control Act, as amended, (33 U.S.C. 1251 et seq), Michigan Act 451, P.A. of 1994, as amended, Part 31, and Michigan Executive Orders 1991-31, 1995-4 and 1995-18.
Activities and Controls Fermi 2's Chemistry Department closely monitors effluent characteristics per the NPDES requirements. Effluent discharge data are summarized in monthly Discharge Monitoring Reports, which are then submitted to the MDEQ.
No Changes to NPDES Permit No changes or stayed appeals to the Fermi 2 NPDES Permit occurred in 2001.
No NPDES Noncompliances in 2001 No noncompliances with Fermi's NPDES permit occurred in 2001.
2001 Annual Nonradiological Environmental Operating Report Detroit Edison Fermi 2 Page 8 6.0 EPP NONCOMPLIANCE Overview In accordance with Section 5.4.1 of the EPP, all occurrences of noncompliance with the EPP must be reported along with a discussion of actions taken to correct the situation.
Activities and Controls There were no incidents of EPP noncompliance at Fermi 2 in 2001.
7.0 DESIGN OR OPERATION CHANGES Overview In accordance with the Fermi 2 EPP, before engaging in additional construction or operational activities, which might affect the environment, Fermi 2 is required to prepare and record an environmental evaluation of such activity. If the evaluation should indicate that the proposed activity involves an unreviewed environmental question, Detroit Edison must provide a written evaluation of the activity and obtain prior approval from the Director, Office of Nuclear Reactor Regulation. Activities are excluded from this requirement if all measurable, nonradiological effects are confined to the on-site areas previously disturbed during site preparation and plant construction.
Activities and Controls During the period covered by this report, there were no changes to station design or operational activities, which created an unreviewed environmental question, per the requirements of the EPP.
8.0 UNUSUAL OR IMPORTANT ENVIRONMENTAL EVENTS Overview According to Section 4.1 of the EPP, any unusual occurrence or important event which indicates, or could result in, significant environmental impact causally related to plant operation must be reported to the NRC within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, followed by a written report within 30 days.
The following are considered examples of unusual or important environmental events:
"* Excessive bird impacts
"* On-site plant or animal disease outbreaks
2001 Annual Nonradiological Environmental Operating Report Detroit Edison Fermi 2 Page 9
"* Mortality or unusual occurrence of any species protected by the Endangered Species Act
"* Fish kills
"* Increase ;n nuisance organisms or conditions Activities and Controls No unusual or important environmental events occurred during 2001. Accordingly, no nonroutine reports were submitted.
9.0 CONCLUSION
S In 2001, the environmental health program at Fenni 2 successfully maintained compliance with the EPP and all applicable environmental regulations.
In 2002, Fermi 2's environmental health program will strive to continuously improve, proactively manage environmental issues, and maintain compliance with the site's EPP and all applicable environmental regulations.