Eric Olson Site Vice President DTE Electric Company 6400 N. Dixie Highway, Newport, Ml 48166 Tel: 734.586.5025 Fax: 734.586.5295 Email: eric.olson@dteenergy.com DTE November 14, 2022 10 CFR 50.7l(e)

NRC-22-0046 10 CFR 50.4(b)(6) 10 CFR 50.54(a) 10 CFR 50.59(d)(2)

U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 Enrico Fermi Atomic Power Plant, Unit No. 1 NRC Docket No. 50-16 NRC License No. DPR-9

Subject:

Submittal of Biennial Review of the Fermi 1 Safety Analysis Report Pursuant to 10 CFR 50.71(e) and 10 CFR 50.4(b)(6), DTE Electric Company (DTE) hereby submits the biennial review of the Fermi 1 Safety Analysis Report (Fl SAR) for the period of November 2020 through October 2022.

In accordance with 10 CFR 50.71(e), a review of the Fl SAR was completed and determined that no content changes were made since November 2020.

There were no changes to the Fermi 1 Quality Assurance (QA) Program during this period.

There were no activities during this period that required a 10 CFR 50.59 evaluation.

No new commitments are being made in this submittal.

Should you have any questions or require additional information, please contact Mr. John F.

Lacasse, Fermi 1 Custodian, at (734) 748-8052.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on November 14, 2022,

~Q£__

Eric Olson Site Vice President

Enclosure: