Fermi, Unit 1 - Information Regarding License Termination Plan
ML093640136
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 12/15/2009
From: Plona J H
DTE Energy
To:
Document Control Desk, NRC/FSME
References
NRC-09-0080
Download: ML093640136 (2)


Text

Joseph H. Plona Site Vice President 6400 N. Dixie Highway, Newport, MI 48166 Tel: 734.586.5910 Fax: 734.586.4172 DTE Energy-December 15, 2009 NRC-09-0080 U.S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, D.C. 20555

Reference:

1) Enrico Fermi Atomic Power Plant, Unit 1 NRC Docket No. 50-16 NRC License No. DPR-9 2) Detroit Edison Letter, NRC-09-0017, "Proposed License Amendment

-License Termination Plan", dated, March 25, 2009 Enrico Fermi Atomic Power Plant, Unit 1 Information Regarding the Fermi 1 License Termination Plan-

Subject:

The NRC requested that certain documents be submitted and docketed to aid in the technical review of the EF1 License Termination Plan (LTP). The answers and documents are to be docketed to aid in the technical review of the EFl LTP.

USNRC December 15, 2009 NRC-09-0080 Page 2 The following documents are being submitted for review: 1. ENG-00 1 through ENG-006 2. Impact of Revised Unsaturated Zone Thickness on Fermi 1 Soil DCGL Values.3. RESRAD reports to support "Impact of Revised Unsaturated Zone Thickness on Fermi 1 Soil DCGL Values" Should you have any questions, please contact Lynne Goodman, Manager, Fermi 1 at (734)586-1205 Sincerely, Joseph H. Plona JHP/ME/lj d Attachments (19)cc: NRC Regional Administrator, Region III T. Smith, NRC (Washington, D.C.)NRC Resident Inspector-Fermi 2 P. Lee, NRC Region III T. Strong, (Michigan Dept. of Environmental Quality)