NL-15-075, Reply to Request for Additional Information Regarding the License Renewal Application Environmental Review

From kanterella
Jump to navigation Jump to search

Reply to Request for Additional Information Regarding the License Renewal Application Environmental Review
ML15166A069
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 06/08/2015
From: Dacimo F
Entergy Nuclear Northeast, Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML15166A072 List:
References
NL-15-075, TAC MD5411, TAC MD5412
Download: ML15166A069 (7)


Text

Enteray Nuclear Northeast Indian Point Energy Center

'~Entergy 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel (914) 254-2055 Fred Dacimo Vice President Operations License Renewal NL-15-075 June 8, 2015 U.S. Nuclear Regulatory Commission Document Control Desk 11545 Rockville Pike, TWFN-2 F1 Rockville, MD 20852-2738

SUBJECT:

Reply to Request for Additional Information Regarding the License Renewal Application Environmental Review (TAC Nos. MD5411 and MD5412)

Indian Point Nuclear Generating Unit Nos. 2 & 3 Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64

REFERENCE:

NRC letter, "Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application Environmental Review (TAC Nos. MD5411 and MD5412)"

dated April 22, 2015.

Dear Sir or Madam:

Entergy Nuclear Operations, Inc. is providing, in Attachment 1, the additional information requested in the referenced letter pertaining to NRC review of the License Renewal Application for Indian Point 2 and Indian Point 3.

There are no new commitments being made in this submittal. If you have any questions, or require additional information, please contact Mr. Robert Walpole, Regulatory Assurance Manager at (914) 254-6710.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on June 6., 2015.

Sil FRD/rl A A9

Docket Nos. 50-247 & 50-286 NL-15-075 Page 2 of 2 : Reply to NRC Request for Additional Information Regarding the License Renewal Application Environmental Review : Algonquin Incremental Market (AIM) Project, Phase 2 Acoustic Survey for Indiana Bats (Myotis sodalis) and Northern Long-Eared Bats (Myotis septentrionalis),August 2014 cc: Mr. Daniel H. Dorman, Regional Administrator, NRC Region I Mr. Sherwin E. Turk, NRC Office of General Counsel, Special Counsel Mr. Michael Wentzel, NRC Project Manager, Division of License Renewal Mr. Douglas Pickett, NRR Senior Project Manager Ms. Bridget Frymire, New York State Department of Public Service Mr. John B. Rhodes, President and CEO NYSERDA NRC Resident Inspector's Office

ATTACHMENT 1 TO NL-15-075 REPLY TO NRC REQUEST FOR ADDITIONAL INFORMATION REGARDING THE LICENSE RENEWAL APPLICATION ENVIRONMENTAL REVIEW ENTERGY NUCLEAR OPERATIONS, INC.

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 & 3 DOCKET NOS. 50-247 AND 50-286

NL-15-075 Attachment 1 Page 1 of 4 Reply to NRC Request for Additional Information Regqardingq the License Renewal Application Environmental Review On April 2, 2015, the U.S. Fish and Wildlife Service FWS) published a final rule (80 FR 17973) that lists the northern long-eared bat (Myotis septentrionalis) as threatened throughout its range.

The northern long-eared bats' range includes Westchester County, New York, in which Indian Point Nuclear Generating Units 2 and 3 (IP2 and IP3) are located. Accordingly, the U.S.

Nuclear Regulatory Commission (NRC) staff intends to address potential effects to this species as part of its IP2 and IP3 license renewal review. The NRC staff requests the following information to assist in its review:

1. Provide any information that Entergy Nuclear, LLC (Entergy)has regarding the northern long-earedbat's use of the IP2 and IP3 site. Such information may include potential habitat (particularlysummer roosting habitat) or other uses of the IP2 and IP3 site by the species, observations of the species on the site, and studies or monitoringperformed to document potentialpresence of the species on the site. The FWS's final rule describes northern long-eared bat habitatin detail.

Entergy Response:

A description of the terrestrial habitat on the Indian Point Units 2 and 3 (IP2 and IP3) site is contained in Section 2.2.6.1 (Description of Site Terrestrial Environment) of the Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 38, Regarding Indian Point Nuclear Generating Unit Numbers 2 and 3 (hereafter referred to as the "SEIS"). As discussed in Section 2.2.6.1 of the SEIS, the site is located in the northeastern coastal zone of the eastern temperate forest ecoregion. The canopy of this forest includes a mixture of hardwoods such as red oak (Quercus rubra), white oak (Q.

alba), black oak (Q. velutina), chestnut oak (Q. prinus), shagbark hickory (Carya ovata),

black cherry (Prunus serotina), tulip tree (Liriodendron tulipifera), river birch (Betula nigra),

and maple (Acer spp.), as well as conifers such as eastern hemlock (Tsuga canadensis)and white pine (Pinus strobus).

As discussed in the U.S. Fish and Wildlife Service's final rule (80 FR 17973), northern long-eared bats have been documented while roosting in many species of trees, including: black oak, northern red oak, silver maple, black locust, American beech, sugar maple, sourwood, and shortleaf pine. In addition as discussed in the final rule, the majority of northern long-eared bat telemetry studies found that roost trees for this species consist predominantly of hardwoods.

Therefore, habitat for the northern long-eared bat could potentially exist on the IP2 and IP3 site. However, Entergy has not conducted onsite studies or monitoring to document the potential presence of this species. In addition, there are no current license-renewal-related plans to disturb areas within the IP2 and IP3 property.

NL-15-075 Attachment 1 Page 2 of 4 As part of the Algonquin Incremental Market Project, Spectra Energy did conduct an Indiana bat and northern long-eared bat acoustics survey. This survey is included in Enclosure 1.

2. Because the Indiana bat (Myotis sodalis), a Federally endangeredspecies that was addressedin the NRC's final supplemental environmental impact statement for IP2 and IP3 license renewal, is similarin its habitatrequirements to the northern long-eared bat, please provide updated information, if applicable, on the Indiana bat'spotential use of the IP2 and IP3 site.

Enterqy Response:

The potential use of the site by the Indiana bat is discussed in Section 2.2.6.2 (Threatened and Endangered Terrestrial Species) of the SEIS. Entergy has not conducted onsite studies or monitoring to document the potential presence of this species. In addition, there are no current license-renewal-related plans to disturb areas within the IP2 and IP3 property.

Therefore, Entergy believes that the information contained in Section 2.2.6.2 of the SEIS continues to remain valid. However as previously discussed above, an Indiana bat and northern long-eared bat acoustics survey was conducted in conjunction with the Spectra Energy Algonquin Incremental Market Project. This survey is included in Enclosure 1.

3. Provide updated information, if applicable, regardingthe effects that activities associated with IP2 and IP3 license renewal and refurbishment could have on the northernlong-eared bat and Indiana bat. Such activities may include habitatloss, degradation,disturbance, or fragmentation, as well as temporary or permanent increases in noise, vibration, dust, chemical use, lighting, vehicle use, and general levels of human activity during the license renewal term that may result from refurbishment or other site activities.

Enterqy Response:

Entergy has not identified any additional license-renewal-related activities that could effect the northern long-eared bat or Indiana bat other than what is discussed in Sections 3.2.2 (Threatened or Endangered Species-Refurbishment Impacts) and 4.6.2 (Terrestrial Threatened or Endangered Species) of the SEIS. As previously stated above, there are no current license-renewal-related plans to disturb areas within the IP2 and IP3 property.

4. Describe the procedures or protocols that Entergy maintains, if any, to ensure that effects to Federally-listedbats are appropriatelyconsideredprior to site activities, such as hazardous tree removal, landscape maintenance, or other operations activities that could directly or indirectly affect bats.

Enterpy Response:

Entergy has a fleet procedure (Environmental Reviews and Evaluation) in place to ensure that environmentally sensitive areas at the IP2 and IP3 site, if present, are adequately protected during site operations and project planning. These controls, which encompass nonradiological environmental resource areas such as land use, air quality, surface water and groundwater, terrestrial and aquatic ecology, historical and cultural resources, and waste management and pollution prevention consist of the following:

0 Appropriate local, state, and/or federal permits are obtained or modified as necessary.

NL-15-075 Attachment 1 Page 3 of 4

  • Best management practices (BMPs) are implemented to protect wetlands, natural heritage areas, and sensitive ecosystems.

" Appropriate agencies are consulted on matters involving federally and state-listed threatened, endangered, and protected species, and BMPs are implemented to minimize impacts to these species.

" Appropriate agencies are consulted on matters involving cultural resources and to ensure BMPs are implemented to minimize impact to this resource.

In summary, Entergy's administrative controls ensure that appropriate local, state, and/or federal permits are obtained or modified as necessary, that cultural resources and threatened and endangered species are protected if present, and that other regulatory issues are adequately addressed as necessary.

Hazardous tree removal is typically associated with transmission line right-of-ways. As discussed in Section 4.2.1 (Electromagnetic Fields-Acute Effects) of the SEIS, the two 345-kilovolt (kV) transmission lines that distribute power to the electric grid, and the two 138-kV lines that use the same transmission towers to supply offsite (standby) power, are contained within the IP2 and IP3 property boundary, except for where they cross Broadway (a public road) to connect to the Buchanan substation, which is owned by Consolidated Edison. Since these transmission lines are situated within the industrial area of the site, no hazardous tree removal activities occur.

Landscaping activities at the IP2 and IP3 site is limited to mowing, bush trimming and herbicide application for weed control. These type activities only occur in the industrial area of the site.

5. Has Entergy observed any injured or dead bats (of any species) on the site, especially near the base of tall buildings and structures? If so, please describe these occurrencesand include the date of observation, species (if known), condition of individual(s), and any follow-up actions that Entergy took as a result of the incident(s).

Entergy Response:

Although Entergy does not have a specific program for monitoring bat or bird deaths on the site, when deaths such as this are discovered, they are typically documented in Entergy's condition reporting system. Based on review of Entergy's condition reporting system records over previous years (2010 - April 2015), no injured or dead bats (of any species) were observed within the industrial area of the IP2 and IP3 site.

6. The FederalEnergy Regulatory Commission's final environmental impact statement (FEIS) on the Algonquin Incremental Market (AIM) Project(availableat https://www.ferc.gov/industries/qas/enviro/eis/2015/01-23-15-eis.asp) indicates that acoustic surveys for the northern long-earedbat and Indiana bat detected both species at locations in Westchester County, New York (see FEIS, p. 4-113 and 4-116). As indicatedin Entergy's March 10, 2015, response to a request for additionalinformation (ADAMS Accession No.

ML15089A338), the Algonquin gas pipeline associatedwith this project would cross a portion of the IP2 and IP3 property. Is Entergy aware of whether the affected portions of the IP2 and IP3 site were surveyed for bats as part of the AIM project? Provide any available information obtained from those surveys concerningthe presence or use of the IP2 and IP3 site by the northern long-eared bat.

NL-15-075 Attachment 1 Page 4 of 4 Enterqy Response:

As previously discussed above, an Indiana bat and northern long-eared bat acoustics survey was conducted in conjunction with the Spectra Energy Algonquin Incremental Market Project. This survey is included in Enclosure 1.