NL-14-1385, Joseph M. Farley Nuclear Plant - Units 1 and 2 - Request for Technical Specification Amendment Adoption of Previously NRC-Approved Generic Technical Specification Changes and Other Changes

From kanterella
Jump to navigation Jump to search
Joseph M. Farley Nuclear Plant - Units 1 and 2 - Request for Technical Specification Amendment Adoption of Previously NRC-Approved Generic Technical Specification Changes and Other Changes
ML14335A623
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 11/24/2014
From: Pierce C R
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML14335A689 List:
References
NL-14-1385
Download: ML14335A623 (3)


Text

Charles R. Pierce Southern Nuclear Regulatory Affairs Director Operating Company, Inc.40 Inverness Center Parkway Post Office Box 1295 Birmingham, AL 35242 Tel 205.992.7872 S TIRN Fax 205.992.7601 COMPAN1Y November 24, 2014 Docket Nos.: 50-348 NL-1 4-1385 50-364 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant -Units 1 and 2 Request for Technical Specification Amendment Adoption of Previously NRC-Approved Generic Technical Specification Changes and Other Changes Ladies and Gentlemen:

In accordance with the provisions of 10 CFR 50.90, Southern Nuclear Operating Company (SNC) is submitting a request for an amendment to the Technical Specifications (TS) for Farley Nuclear Plant (FNP), Units 1 and 2.The requested amendment will adopt various previously NRC-approved Technical Specifications Task Force (TSTF) Travelers.

TSTF Travelers are generic changes to the Improved Standard Technical Specifications.

The requested amendment will also adopt two changes not associated with Travelers.

These Travelers and other changes were chosen to increase the consistency between the FNP Technical Specifications, the Improved Standard Technical Specifications, and the Technical Specifications of the other plants in the SNC fleet. A list of the requested changes is located in Enclosure 1.Enclosure 1 provides the basis for the proposed TS change, and the Significant Hazards Consideration and Environmental Consideration determinations.

Enclosure 2 provides the marked-up TS. Enclosure 3 contains example Bases changes that complement the proposed Technical Specification changes. The proposed Bases changes are provided for information only. The Bases will be revised under the Technical Specification Bases Control Program following NRC approval of the proposed Technical Specification changes. Enclosure 4 provides the clean-typed TS pages. Enclosure 5 provides a summary of the regulatory commitments made in this license amendment request.As described in Enclosure 1, the proposed changes have been evaluated in accordance with 10 CFR 50.91 (a)(1) using criteria in 10 CFR 50.92(c) and it has been determined that the changes involve no significant hazards consideration.

U.S. Nuclear Regulatory Commission NL-14-1385 Page 2 SNC requests approval of the proposed license amendment by December 31, 2015 with the amendment being implemented within 90 days of issuance of the amendment.

A copy of the proposed changes has been sent to Dr. D. E. Williamson, the Alabama State Designee, in accordance with 10 CFR 50.91 (b)(1).Mr. C. R. Pierce states he is Regulatory Affairs Director of Southern Nuclear Operating Company, is authorized to execute this oath on behalf of Southern Nuclear Operating Company and to the best of his knowledge and belief, the facts set forth in this letter are true.If you have any questions, please contact Ken McElroy at (205) 992-7369.Respectfully submitted, C. R. Pierce Regulatory Affairs Director CRP/JMC/Swo to and subscrib =before me this e day of 7?ae .& , ,2014.Notary Public My commission expires: Z 1

Enclosures:

1. Basis for Proposed Changes 2. Marked-Up Technical Specifications Pages 3. Example Marked-Up Technical Specifications Bases Pages 4. Clean-Typed Technical Specifications Pages 5. Summary of Regulatory Commitments U.S. Nuclear Regulatory Commission NL-14-1385 Page 3 cc: Southern Nuclear Operating Company Mr. S. E. Kuczynski, Chairman, President

& CEO Mr. D. G. Bost, Executive Vice President

& Chief Nuclear Officer Ms. C. A. Gayheart, Vice President

-Farley Mr. M. D. Meier, Vice President

-Regulatory Affairs Mr. D. R. Madison, Vice President

-Fleet Operations Mr. B. J. Adams, Vice President

-Engineering Mr. R. R. Martin, Regulatory Manager -Farley RTYPE: CFA04.054 U. S. Nuclear Requlatory Commission Mr. V. M. McCree, Regional Administrator Mr. S. A. Williams, NRR Project Manager -Farley Mr. P. K. Niebaum, Senior Resident Inspector

-Farley Alabama Department of Public Health Dr. D. E. Williamson, State Health Officer