ML23292A196

From kanterella
Jump to navigation Jump to search
1 to Updated Final Safety Analysis Report, Questions 123.1 Through 123.9
ML23292A196
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 10/12/2023
From:
Susquehanna
To:
Office of Nuclear Reactor Regulation
Shared Package
ML23291A105 List: ... further results
References
PLA-8081
Download: ML23292A196 (1)


Text

SSES-FSAR QUESTION 123.l Pursuant to General Design Criterion 2,

safety-related structures, systems and components are to be designed for appropriate load combinations arising from accidents and severe natural phenomena.

With regard to the vibratory loads attributed to the feedback of hydrodynamic loads from the pressure suppression pool of the containment, the staff requires that safety-related mechanical, electrical, instrumentation and control equipment be designed and qu~lified to withstand effects of hydrodynamic vibratory loads associated with either safety relief valve (SRV) discharge of LOCA blowdown into the pressure suppression containment combined with the effects of dynamic loads arising from earthquakes.

The criteria to be used by the staff to determine the acceptability of your equipment qualification program for seismic and dynamic loads are IEEE Std. 344-1975 as supplemented by Regulatory Guides 1.100 and 1.92, and Standard Review Plan Sections 3.9.2 and 3.10. State the extent to which the equipment in your plant meets these requirements and the above requirements to combine seismic and hydrodynamic vibratory loads.

For equipment that does not meet these requirements provide justification for the use of other criteria.

RESPONSE

I.

.laQ£ For Susquehanna

Project, all BOP Safety related mechanical, electrical, instrumentation and control equipment located inside Primary Containment, Reactor and Control buildings, is being qualified for Seismic loads in combination with hydrodynamic vibratory loads associated with SRV discharge and LOCA blowdown.

Although the SRSS method of combination of seismic and hydrodynamic loads is acceptable, for the project to be conservative, the loads are combined by absolute sum method.

The cases which have deviations from the absolute sum method of combination will be identified in the qualification reports.

The criteria for the qualification of BOP equipment for seismic loads is described in Section 3. 7b. 3 of the FSAR.

The criteria for load combinations and methodology for the design assessment and qualification of Safety related BOP equipment for seismic and hydrodynamic loads have been described in Sections 5.7 and 7.1.7 of the Design Assessment Report (DAR) Rev. 2.

Basically the requirements of IEEE Std. 344-1975 as Rev. 46, 06/93 123.l*l

SSES-FSAR Supplemented by Regulatory guides 1.100 and 1. 92 and SRP Sections 3. 9. 2 and 3.10 are covered in the criteria with the following exception for spatial combination of three components of dynamic motion as stated in Sect ion

?.1.7.1.3 of the DAR.

The criteria states nthe response at any point is the maximum value obtained by adding the response due to vertical dynamic load with the larger value of the responses due to one of the horizontal dynamic loads by the absolute sum method."

All Susquehanna BOP equipment is being qualified for the criteria discussed above.

II.

NSSS LOAD COMBINATIONS:

These were transmitted to the NRC on 8/28/80 as Page 3 of Attachment N to PLA-536. This was in response to NRC Question 110.42.

IMPLEMENTATION OF LOAD COMBINATIONS:

The GE SQRT Program uses outputs from the GE Equipment Adequacy Evaluation Program which combines dynamic loads by SSES as accepted by the NRC in NUREG-0484.

The individual items associated with the load combinations are added as described below:

Steady State Events (e.g., Dead Load, Pressure)

Absolute Sum Time Varying Components (e.g., Maximum Seismic, Maximum Hydrodynamic} - SRSS Components of Events (e.g., Maximum X-Load Due to Y-Earthquake) - SRSS Modal Response-SRSS, except for closely spaced modes where effects are combined by Absolute Sum, Double Sum, or Grouping.

Details for each item of equipment are contained in that equipment's Design Record File which is available for audit.

Rev. 46, 06/93 123.1-2

SSES-FSAR QUESTION 123.2 Provide the following information:

(i)

Two summary equipment lists (one for NSSS supplied equipment and one for BOP supplied equipment).

These lists should include all safety related mechanical components, electrical, instrumentation, and control equipment, including valve actuators and other appurtenances of active pumps and valves.

In the lists, the following information should be specified for each item of equipment.

(1)

Method of qualification used:

(a)

Analysis of test that prepared the report number publication}.

(indicate the company report, the reference and date of the (b)

If by test, describe whether it was a single or multi-frequency test and whether input was single axis or multi-axis.

{c)

If by analysis, describe whether static or dynamic, single or multiple-axis analysis was used.

Provide natural frequency (or frequencies) of equipment.

(2)

Indicate whether the* equipment has met the qualification requirements.

(3)

Indicate the system in whi.ch the equipment is located and whether the equipment is required for:

(4) a)

hot stand-by b) cold shutdown c) both d) neither Location of equipment, elevation.

i.e.,

building, (5)

Availability for inspection (Is the equipment already installed at the plant site?)

Rev. 46, 06/93 123.2-1

SSES-FSAR (ii)

An acceptable scenario of how to maintain hot stand-by and cold shutdown based on the following assumptions:

(iii)

RESPONSE

(1)

SSE or OBE (2)

Loss of offsite power (3)

Any single failure A compilation of the required response spectra (RRS) for all applicable vibratory loads (individual and combined if required) for each floor of the nuclear station under consideration.

The response to this question was submitted via PLA 627 (Curtis to Youngblood) dated February s, 1981.

Rev. 46, 06/93 123.2-2

SSES-FSAR QUESTION 123.3 Identify those items of nuclear steam supply system and balance-of-plant equipment requiring reevaluation and specify why reevaluation is necessary (i.e. because the original qualification used the single frequency, single axis methodology, because equipment is affected by hydrodynamic loads, or because both of the above conditions were present) for each item of equipment.

RESPONSE

Originally almost all Safety related BOP equipments for Susquehanna had been qualified for only Seismic loads.

This equipment has been re-evaluated due to the inclusion of new hydrodynamic (SRV & LOCA) loads, and are being re-qualified with respect to the criteria described in DAR Section 7.17.

The qualification program for the BOP Safety related equipment is being executed in the following four phases.

Phase-I: oualification of Egµipment for Only Seismic Loads:

The only known dynamic load at the time of execution of this phase of the program was Seismic loads. During this phase, the vendors supplying the equipment were required to qualify the equipment in accordance with the requirements specified in FSAR Subsection 3.7b.3.

Phase-II:

Evaluation for Combined Seismic and Hydrodynamic (SRV & LOCA) Loads; This phase was undertaken to evaluate if the existing Seismic qualification of all Safety related BOP equipment could be extended to the combined Seismic and hydrodynamic loads. The criteria used for the re-evaluation is described in DAR Section 7.1. 7.

The general problem areas identified during this evaluation and the proposed action to mitigate these problems are shown below.

Problem Additional hydrodynamic loads Flexibility of equipment Support not considered Rev. 46, 06/93 123.3-1 Retest and/or reanalysis.

Modifications to equipment of their supports if required.

Provide response spectre considering support flexibility

SSES-FSAR Inadequate Modelling Inadequate Testing Phase III: Regualification Efforts:

Include Support Conditions during analysis or testing.

Correct during reanalysis.

Retest.

Qualification by analysis.

Specifically, the Problem areas identified in the previous phase are resolved during this phase by taking appropriate actions.

The requalif ication reports demonstrate that the criteria of DAR Section 7.1.7 have been complied with.

Phase IV: Modifications to Equipment or Equipment Supports:

Equipment or their Supports needing modifications identified during the regulations efforts of Phase III are executed during this phase.

The following are NSSS equipment:

SYSTEM Safety Relief Valve MSIV Flow Element Recirc. Pump Motor Gate Valve HCU CRD Valves SLC Storage Tank SLC Accumulator SLC Pump SLC Explosive Valve RHR Heat Exchanger RHR Pump Flow Orifice Assembly LPCS Pump & Motor Rev. 46, 06/93 123.3-2 MPL I B21F013 B21F022/

F028 B21NOS1/

52/53/54 B31C001 B31F023/

31/32 Cl2D001 Cll2F009/

10/11/12 C41A001 C41A003 C41C001 C41F004 EllBOOl EllC002 EllN012/

N014 E21C001

Flow Orifice Assembly MSIV Heater MSIV Blower HPCI Pump HPCI Turbine Flow Orifice Assembly RCIC Pump RCIC Turbine Flow Orifice Assembly Fuel Prep Machine Gen. Purpose Grapple Dryer & Separator Sling Head Strong Back Control Rod Grapple Refueling Platform In Vessel Rack Def. Fuel Storage Cont.

Fuel Storage Vault SSES-FSAR

~ONTROL ROOM PANELS Reactor Core Cooling BB Power Range Monitoring Cabinet RPS Div. land 2 Log VB RPS Div. 2 and 3 Logical VB NSSS Temperature Recorder VB Feedwater & Recirculation Instrument Panel NSSS Process Instrument Panel Div 1 RHR/HPCI Relay VB Div 2 RHR/HPCI Relay VB ADS Ch A Relay VB MSIV Leakage Control Div 2 VB HPCI Relay VB RCIC Relay VB Inboard Valve Relay Board Outboard Valve Relay VB Div l CS Relay VB Div 2 CS Relay VB ADS Ch B Relay VB MSIV Leakage Control Div 1 VB Radiation Monitoring Instrument Panel A Radiation Monitoring Instrument Panel B Operating BB Termination Cabinets Plant Operation Benchboard Rev. 46, 06/93 123.3-3 E21N002 E32B001 E32C001/

C002 E41C001 E41C002 E41N007 ESlCOOl E51C002 ESlNOOl E18E001 F18E011 F19E008 F19E009 F20E002 E21E003 F22E006 F22E009 F22E012 H12-P601 H12-P608 H12-P609 H12-P611 H12-P614 H12-P612 H12-P613 H12-P617 H12-P6118 H12-P628 H12-P654 H12-P620 H12-P621 H12-P622 Hl2*P623 H12-P626 H12-P627 H12-P631 H12-P655 H12-P606 H12-P633 H12-P680 H12-P700 Series Hl2-P853

Condensing Chamber Condensing Chamber Condensing Chamber Condensing Chamber Condensing Chamber Condensing Chamber Reactor Water Clean-Up SSES-FSAA NUCLEAR BOILER LOCAL PANELS Reactor Vessel Level and Pressure (A)

Reactor Vessel Level and Pressure (B)

Recirculation Pump A Jet Pump B High Pressure Coolant Injection B Reactor Core Isolation Cooling A Residual Heat Removal Channel A Residual Heat Removal Div. 2 Channel B Recirculation Pumps Drywell Pressure Local Panel A Drywell Pressure Local Panel B Main Steam Isolation Valve Leakage Control Core Spray Local Panel A Standby Liquid Control Main Steam Flow A/B High Pressure Coolant Injection Leak Det.

Core Spray Channel B Main Steam Flow C/D High Pressure Coolant Injection Reactor Core Isolation Cooling Leak Det.

Main Steam Flow A/B Main Steam Flow C/D Main Steam Isolation Valve Leakage Con.

High Pressure Coolant Injection Div. 1 A Reactor Core Isolation Cooling Div. 2 B SRM/IRM Temperature Element Temperature Element Temperature Element Pressure Switch Temperature Element Temperature Element Rev. 46, 06/93 NUCLEAR BOILER 123.3-4 B21-O002 B21-D004AB B21-D006AD B21-D007AD B21-DOOBAD B21-D009AD H23-P002 H23-P004 H23-P00S H23-P009 H23-P010 H23-P014 H23-P017 H23-P018 H23-P021 H23-P022 H23-P057 H23-P058 H23-P074 Div. 2 H23-P001 H23-P011 H23-P015 H23-P016 H23-P019 H23-P025 H23-P036 H23-P038 Div. 2(B)

H23-P041 H23-P042 H23-P073 Div. 1 H23-P034 H23-P037 H23-P030/

31/3/2/33 B21-N004 B21-N010AD B21-N014AD B21-N015AD B21-N016AD B21-N017

Vacuum Switch Temperature Element SSES-FSAR Differential Pressure Transmitter Temperature Element Differential Pressure Transmitter Level Switch Level Switch Temperature Switch Pressure Transmitter Pressure Indicator Valve, Guide Tube Miscellaneous Parts Pressure Switch Pressure Switch Limit Switch Limit Switch Level Transmitter Temperature Element Differential Pressure Transmitter Differential Pressure Transmitter Differential Pressure Transmitter Pressure Switch Switch Pressure Switch Level Switch Level Switch Temperature Element Temperature Element Flow Indicating Switch Differential Pressure Transmitter Switch Pressure Switch Flow Meter Level Switch Level Switch Level Switch Level Switch Level Switch Temperature Element Temperature Element Temperature Element Temperature Indicator Level Switch Temperature Element Temperature Element Temperature Element Temperature Element Rev. 46, 06/93 123.3-5 B21-N056AD B21-N064 B31-N014CD B31-N023AB B31-N024AB Cl2-N013AD C12-N013EF C41-N003 C41-N004 C41-R003 C51-J004AE (51-5110001 C72-N003AD C72-NOOSAD C72-N006AD C72-N008AD Ell-N008AB Ell-N009AD Ell-N013 Ell-NOlSA Ell-N015B Ell-N018 Ell-N021AB Ell-N022AB Ell-N023AB Ell-N024 Ell-N029AD Ell-N030AD Ell-N033AB E21-N003AB E21-N006AB E21-N007AB E32-N006 E41-N002 E41-N003 E14-N014 E41-N015AB E41-N018 E41-N024AB E41-N02SAH E41-N028AB through E41-N030AB E41-R002 E51-N010 E51-N011AB E51-N021AB E51-N022AB E51-N023AB

Temperature Element Temperature Indicator Temperature Element Temperature Element Temperature Element Switch Rev. 46, 06/93 SSES-FSAR 123.3-6 E51-N02SAD through E51-N027AD ESl-ROOS G33-N016AF G33-N022AF G33-N023AF G33-N044A

SSES-FSAR QUESTION 123.4 Describe the methods and criteria used to determine the acceptability of the original equipment qualification to meet the required response spectra of item 2. (iii). - 123.2 (iii).

RESPONSE

I.

BOP For cases where the original spectra for which an equipment was qualified enveloped the combined Seismic and hydrodynamic load spectra of Item 123.2 (iii), the equipment is considered qualified. Otherwise (which is true for most cases) the equipment is requalified for the combined spectra to meet the criteria discussed in response to Questions 123.1.

These criteria are described in Section 7.1.7 of the Design Assessment Report.

II.

NSSS The methods and criteria used to determine the acceptability of the original equipment qualification may be found in General Electric Company's Proprietary reports:

NEDE-24788, "Seismic Qualification Review Team (SQRT) Technical Approach for Re-Evaluation of BWR 4/S Equipment"; and NEDE-25250 "Generic Criteria For High-Frequency cutoff of BWR Equipment."

Rev. 46, 06/93 123.4-1

SSES-FSAR QUESTION 123.5 Describe the methods and criteria used to address the vibration fatigue cycle effects on the affected equipment due to required loading conditions.

RESPONSE

I.

~

As described in Subsection 3.7b.3.2 general, the design of equipment is controlled since the number of cycles in is low.

of

FSAR, in not fatigue an earthquake For combined Seismic and hydrodynamic loads for equipment qualified by analysis, the fatigue effects are implicitly considered since the stresses due to SRV (which are generally controlling for fatigue) are a small contribution to the overall equipment stresses.

Fatigue effects in BOP equipment qualified by testing are accounted for by repetition of the tests.

Typically tests are done for 5 OBE (or 5 upset conditions, i.e., OBE + SRV + LOCA) followed by 1 SSE (or 1 faulted condition, i.e., SSE+ SRV + LOCA) in each of front-to-back/vertical and side-to-side/vertical biaxial configurations. In addition, on some selected pieces of equipment, vibratory table testing is carried out for an extended duration of time (such as 30 to 60 minutes) beyond the combined loading test.

The input motions for the extended du rat ion tests will be such that the generated test response spectra for any segment of the extended duration tests will envelope the SRV spectra. Furthermore, it will be ascertained that the equipment performs its intended function before, during and after the vibratory table tests. The results of the extended duration tests will be documented in the respective qualification reports.

II.

NSSS Vibration fatigue cycle effects for NSSS equipment designed to ASME code requirements was reviewed at GE by NRC consultants from Battelle Pacific Northwest Laboratories on October 7, 1980.

The consultants stated satisfaction with the GE approach which encompasses OBE, SRV, thermal and pressure cycles.

Rev. 46, 06/93 123.5-1

SSES-FSAR Non-ASME Code components qualified by test address the "strong motion" phase of seismic and SRV dynamic motion sufficient to generate maximum equipment response.

These loads are controlling.

GE testing generally consists of 5 upset and 1 faulted test of 30 seconds each which is about 50% greater than required to address strong motion vibration.

Non-ASME Code components qualified by analysis generally have not, in the past, had to address vibration fatigue cycle effects.

In most cases, such effects are not now part of the qualification record.

Rev. 46, 06/93 123.5-2

SSES-FSAR QUESTION 123.6 Based on the methods and criteria described in items 4 and 5, provide the results of the review of the original equipment qualification with identification of (1) equipment which has failed to meet the required response spectra and required requalification, and (2) equipment which was found acceptable, together with the necessary information to justify the adequacy of the original qualification.

RESPONSE

I.

BOP For cases where the original seismic reports can be extended to qualify an equipment for combined seismic and hydrodynamic loads by inspection and subsequent concurrence by vendor, such documents form a part of the qualification package.

The following pieces of equipment bought under the indicated purchase order (P.O.) fall into this category:

(1)

Cooling and chilled water pumps (P.O. #M-327)

(2)

Expansion Tanks and Air Separator Tanks (P.O. #M-302)

{3)

Nitrogen Gas Accumulators (P.O. #M-156)

The rest of the BOP equipment is being qualified for the criteria described in Section 7.1.7 of the Design Assessment Report. The qualification reports for this equipment will provide the appropriate documentation.

II.

~

Refer to the Response to Question 123. 3 for the list of equipment reevaluated by GE on the Susquehanna SQRT Program.

All of the equipment listed in qualified to SQRT Criteria with the exception of the following:

B211-F022/

F028 B31-F031/

F032 Cl2-F009/F012 F011/F012 Rev. 46, 06/93 MSIV Gate Valve CRD Valve 123.6-1 Data required from vendor Operability deflection analysis required Operability deflection analysis required

C41-A003 C41-F004 E32-B001 E41-C002 E51-C002 F22-EOO6 F22-E0O9 H12-P608 H23-PO3O

-PO31

-PO32

-P033 163Cl158 272A8005 272A8006 SSES-FSAR SLC Accumulator SLC Explosive Valve MSIV Heater HPCI Turbine RCIC Turbine Invessel Rack Def. Fuel Storage Cont.

Power Range Monitoring Cabinet SRM/IRM Panels Flow Transmitter on H23*P0?4 Switch on H12-P853 Switch on H12-P853 A/E pipe accelerations required A/E pipe accelerations required Test required Test required Analysis of lube oil piping required Analysis required Analysis required Test required Test required Test required Test required Test required Information to justify qualification of the equipment selected by the NRC for the Site Audit will be available at the site for NRC inspection.

Information to justify qualification of the remainder of the equipment is available for NRC audit at GE-San Jose.

Rev. 46, 06/93 123.6-2

SSES-FSAR QUESTION 123.7 Describe procedures and schedule for completion of each item identified in item

6. (1) 123.6 (1) that requires requalification.

E,ESPONSE:

I.

BOP Typically, the qualification program is executed in the following steps.

o Determine Qualification Awards Request Vendor (or Consultant) Quote Receive and Evaluate Quote Place Purchase Order o

Perform Qualification Review Test Procedure Review Analysis Methodology Begin Analysis or Testing o

Final Completion Receive and review Requalification Reports Final Approval of the Report The schedule for the completion of the qualification program is shown in the attached Table 123.7-1.

II.

NSSS The response to Question 123. 6 lists the equipment found by GE to require requalification along with a statement defining the work to be performed.

All requalification will b~ completed on a schedule sufficient to permit NRC review prior to fuel load.

Rev. 46, 06/93 123.7-1

SSES-FSAR TABLE 123. 7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REOUALIFICATION SORT No. of hems/

CompTetion Form No.

Equipment 2 Units Dete E-109-1 4 kV Switchgear 12 3-13-81 E-1O9-2 4 kV Switchgear Sub-Components 12 6-15-81 E-112 ESW and RHR Pump Motors 8

Complete E-117-1 480V Safe-Guard Load Center 8

3-27-81 Unit Substations E-118 480 V Motor Control Centers 24 4-17-81 E-119A-1 Battery Monitors 20 3-27-81 E-119A-2 Battery Fuse Boxes 16 3-27-81 E-119A-3 Battery Chargers 22 3-2 7-8 t E-1198C 24 Vdc, 125 Vdc & 250 Vdc 8

6-29-Bl Battery Cells & Racks E-120-1 125 Vdc Distribution Panels 16 3-20-81 E-120-2 24 Vdc Distribution Panels 4

4.,0-91 E-121-1 126 V & 260 Vdc Load Centers 12 3-27-8 t E-121-2 250 Vdc Control Centers 6

4-10-81 E-136-1 Electrical Penetration (Medium 12 6-15-81 Voltage)

E-135-2 Electrical Penetration (low 32 6-15-81 Voltage)

E-136 AC Instrument Transformers 14 3-27-81 E-151 Motor Generator Sets and Control 4 Sets Complete Cabinet E-152 Automatic Transfer Switches 8

Complete E-166 Control Switches 44 8-16-81 J-O38A Field Mounted Electronic Pressure 32 ComP'ete Transmitters J-038-1 thru Paner - Mounted Instruments 242 4th quarter 198 t J-038-14 Rev. 46, 06/93 Page 1 of 6

SSES-FSAR TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION (Cont'd.)

SORT No. of Items/

CompletJon form No.

Equipment 2 Units Date J-05A-14, Control Panels & Devices 31 6-30-81 (panelsl 31,33,37, 8-15-81 (devices) 10A & 8, 43,47,49,92, 93,95 & 97 J-058-1 Remote Shutdown Control Panel 1

6-30-81 (panels) 8-15-81 (devices)

J-27 Reactor Coolant Pressure Boundary 2

Complete (panels)

Leak Detection System 8-15-81 (devices)

J-31 Annubar Flow Elements 2

Complete J-59-1 thru RTO's 64 6-22-81 J-59-10 J-65-1 thru Control Valves In Nuclear Service 28 3-27-81 J-65-4 J-658-1 thru Control Valves In Nuclear Service 86 3-27-81 J-658-11 J-69-1 & 2 Pilot Solenoid Valves 8

6-15-81 J-698-1 thru 6 Pilot Solenoid Valves 74 6-15-81 J-70-1 Pressure Regulating Valves 8

6-15-81 J-70-2 Process Solenoid Valves 76 6-15-81 J-92-1 thru Excess Flow Check Valves 238 6-01-81 J-92-5 J-98 Carrier Modulator (Isolator) 6-15-81 M-11 ESW Pumps 4

Complete M-12 RHR Suction Water Pumps 4

Complete M-22-1 & 2 Reactor Building Cranes 2

4-03-81 M-30 (78 forms)

Diesel Generator 4 Sets Complete M-30 (6 forms)

Diesel Generator 4 Sets 2-27-81 M-55 Reactor Vessel Top Head Insulation 2

Complete Support Steel M-58 Diesel Oil Transfer Pumps 4

Complete Rev. 46, 06/93 Page 2 of 6

SSES-FSAA TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REOUAUFICATION (Cont'd.t SQRT No. of Items!

Completion Form No.

Equipment 2 Units Date M-60 Buried Diesel Generator Fuel Oil 4

3-27-81 Storage Tanks M-87-1 Containment Hydrogen 8

6-15-81 Recombiners M-87-2 Hydrogen Recombiner Power 4

Complete Supply M-90 Fuel Pool Skimmer Surge Tanks 2

4-27*81 M-149 Containment Vacuum Relief Valves 20 6*22-81 M-151 Suppression Pool Suction Strainers 32 Complete M-156 Containment Nitrogen Gas 60 Complete Accumulators M* 1 59-1 thru Nuclear Safetv & Relief Valves 68 6*01-81 M-159-21 M-160AC SRV Discharge Line & RHR Relief 68 6-15-81 Valve F055 Discharge Line Vacuum Breakers M-164 CRD Vent Valve Platform 2

Complete M-192 High Density Spent Fuel Pool 48 Modules Complete Racks M-302 Expansion Tanks & Air Separators 4

Complete M-307-1 thru Centrifugal Fans 6

3-13-81 M-307-3 M-308-1 Vane Axlal Fans, Reactor Building 2

6-01-81 M-308-2 Vane Axial Fans, Diesel Generator 4

Complete Building M-308-3 & 4 Vane Axial Fans, ESSW 8

Complete Pumphouse M309-1 thru Air Handling Units 12 4-17-81 M-309-4 M-310 Centrifugal Water Chillers 2

&*22-81 M-315 Reactor Building Unit Coolers 24 6*29-81 M-317 Drywell Unit Coolers 12 3-27-81 Rev. 46, 06/93 Page 3 of 6

SSES-FSAR TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REOUALIFICATION (Cont'd.)

SORT No. of Items!

Completion Form No.

Equipment 2 Units Date M-320-1 Chlorine Detectors 2

6--15-81 M-320-2*1A & 1B Flow Switches 28 8-t 5-81 M-320-2-2A Flow Switches 2

8-15-81 M-320-3 Level Gauge 2

6-15-81 M-320-4 Pressure Differential Switches 4

8-15-81 M-370-5A & 5B Temperature Switches 24 6-15-81 M-320-6-1 A & 1 B Temperature Switches 4

8-15-81 M-320*6-2A Temperature Switches 4

8-15-81 M-320*6-3A & 7 Temperature Switches 10 6-15-81 M-320-8 Pressure Differential Transmitter 18 8-15-81 M-320-9 Temperature Detecto, Unit 2

6-15-81 M-320-10 Level Switches 4

6-1 5-81 M-321-1 Standby Gas Treatment System

8 6-01-81 Deluge Drain Valves M-321*3 Standby Gas Treatment System

  • 4 3-06-81 Control Panels M-232C-1 Air Flow Monitoring Unit 1

3-13-81 M-323C-2 SGTS Exhaust Vent Flow 1

3-13-81 Conditioning & Sampling Probe System M-326 High Efficiency Ventilation Filters 2

Complete M-327-1 Chilled Water Pump 2

Complete M-327-2 Cooling Water Pump 2

Comptete M-334* 1 thru HVAC Control Panels & Devices 12 6-30-81 (panels)

M-334-5 8-1 5-81 !devices)

M-336A HVAC Dampers 195 Units 5-08-81 M-362 SGTS Centrifugal Fans 2

Complete Rev. 46, 06/93 Page 4 of 6

SSES-FSAR TABLE 123.7*1 SCHEDULE FOR COMPLETION OF EQUIPMENT REOUALIFICATION (Cont'd.)

SQRT No. of Items/

Completion Form No.

Equipment 2 Unit$

Date M-365 Chilled Water Relief Valves 2

6-01-81 P-10A-1 Motor Operated Gate Valves, 800#

6 6-16-81 P-10A*2 Motor Operated Gate Valves, 900#

15 6-15-81 P-10A-3 Motor Operated Globe Valves, 9

8-15-81 9001 & 600#

P-10B Motor Operated Stop Check 2

6-15-81 Valves, 900#

P-11A-1 Motor Operated Gate Valves, 900#

2 6-15-81 P*11A*2 Air Operated Testable Check 2

6-01-81 Velves, 900#

P-12A-1 Motor Operated Gate Valves, 1 50#

24 8-15-81 P12A-2 Motor Operated Globe Valves, 11 8-15-81 300#

.P12A-3 Motor Operated Gate Valves, 300#

20 6-15-81 P-12A-4 Gear Operated Gate & Globe 7

6-01-81 Valves, 300#

P-128-1 Motor Operated Gate Valves, 150#

4 8-15-81

& 300#

P-12B-2 Air Operated Gate Valves, 1501 14 6-01-81 P-128-3 Gear Operated Gate & Globe 13 6-01-81 Valves, 150#

P-14A Motor Operated Globe Valves, 6*16-81 1500#

P-14B Motor Operated Globe Valves, 1

8-15-81 1500#

P-15A Motor Operated Globe Valves, 11 8-15-81 1500#

P158-1 Motor Operated Gate Valves, 18 6-15-81 1500#

P-158-2 Air Operated Gate Valves, 1500#

2 8-01-81 P-16A-1 Motor Operated Butterfly Valves, 28 8*15-81 150#

Rev. 46, 06/93 Page 5 of 6

SSES-FSAR TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT AEOUALIFICATION (Cont'd.)

SQRT No. of Items/

Completion Form No.

Equipment 2 Units Date Pl 6A-2 Air Operated Butterfly Valves, a

6-01-81 160#

J P-16A*3 Gear Operated Butterfly Valves, 12 6-01-B 1 160#

P-17A-1 Motor Operated Gate Valves, 900#

7 6-15-81 P-17A-2 Motor Operated Globe Valves, 1

6-15-81 900#

P-17A-3 Air Operated Testable Check 2

6-01 *81 Valves, 9001 P-17A-4 Gear Operated Gate Valves, 900#

6 6-01-B 1 P-17B Air Operated Testable Check 2

6-01-81 Valves, 900#

P-18A Gear Operated Gate Valves, 160#

1 6-01-81 P-31A Air Operated Butterfly Valves, 9

6-01-81 150#

Rev. 46, 06/93 Page 6 of 6

SSES-FSAR Table Rev. 48 FSAR Rev. 70 Page 1 of 5 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT Form No.

Equipment No. of Items/

2 Units Completion Date E-109-1 4 kV Switchgear 12 3-13-81 E-109-2 4 kV Switchgear Sub-Components 12 5-15-81 E-112 ESW and RHR Pump Motors 8

Complete E-117-1 480 V Safe-Guard Load Center Unit Substations 8

3-27-81 E-118 480 V Motor Control Centers 24 4-17-81 E-119A-1 Battery Monitors 20 3-27-81 E119A-2 Battery Fuse Boxes 16 3-27-81 E-119A-3 Battery Chargers 22 3-27-81 E-119BC 24 Vdc, 125 Vdc & 250 Vdc Battery Cells & Racks 8

5-29-81 E-120-1 125 Vdc Distribution Panels 16 3-20-81 E-120-2 24 Vdc Distribution Panels 4

4-10-81 E-121-1 125 V & 250 Vdc Load Centers 12 3-27-81 E-121-2 250 Vdc Control Centers 6

4-10-81 E-135-1 Electrical Penetration (Medium Voltage) 12 5-15-81 E-135-2 Electrical Penetration (Low Voltage) 32 5-15-81 E-136 AC Instrument Transformers 14 3-27-81 E-151 Motor Generator Sets and Control Cabinet 4 Sets Complete E-152 Automatic Transfer Switches 8

Complete E-155 Control Switches 44 6-15-81 J-038A Field Mounted Electronic Pressure Transmitters 32 Complete J-03B-1 thru J-03B-14 Panel - Mounted Instruments 242 4th quarter 1981 J-05A-14 31,33,37, 10A & B 43,47,49,92, 93,95 & 97 Control Panels & Devices 31 5-30-81 (panels) 6-15-81 (devices)

J-05B-1 Remote Shutdown Control Panel 1

5-30-81 (panels) 6-15-81 (devices)

J-27 Reactor Coolant Pressure Boundary Leak Detection System 2

Complete (panels) 6-15-81 (devices)

SSES-FSAR Table Rev. 48 FSAR Rev. 70 Page 2 of 5 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT Form No.

Equipment No. of Items/

2 Units Completion Date J-31 Annubar Flow Elements 2

Complete J-59-1 thru J59-10 RTDs 54 5-22-81 J-65-1 thru J-65-4 Control Valves in Nuclear Service 28 3-27-81 J65B-1 thru J65B-11 Control Valves in Nuclear Service 86 3-27-81 J-69-1& 2 Pilot Solenoid Valves 8

5-15-81 J-69B-1 thru 6 Pilot Solenoid Valves 74 5-15-81 J-70-1 Pressure Regulating Valves 8

5-15-81 J-70-2 Process Solenoid Valves 76 5-15-81 J-92-1 thru J92-5 Excess Flow Check Valves 238 5-01-81 J-98 Carrier Modulator (Isolator) 6-15-81 M-11 ESW Pumps 4

Complete M-12 RHR Suction Water Pumps 4

Complete M-22-1 & 2 Reactor Building Cranes 2

4-03-81 M-30 (78 forms)

Diesel Generator 4 Sets Complete M-30 (6 forms)

Diesel Generator 4 Sets 2-27-81 M-55 Reactor Vessel Top Head Insulation Support Seal 2

Complete M-58 Diesel Oil Transfer Pumps 4

Complete M-60 Buried Diesel Generator Fuel Oil Storage Tanks 4

3-27-81 M-87-1 Containment Hydrogen Recombiners (Note 2) 8 5-15-81 M-87-2 Hydrogen Recombiner Power Supply (Note 2) 4 Complete M-90 Fuel Pool Skimmer Surge Tanks 2

4-27-81 M-149 Containment Vacuum Relief Valves 20 5-22-81 M-151 Suppression Pool Suction Strainers 32 Complete M-156 Containment Nitrogen Gas Accumulators 60 Complete

SSES-FSAR Table Rev. 48 FSAR Rev. 70 Page 3 of 5 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT Form No.

Equipment No. of Items/

2 Units Completion Date M-159-1 thru M-159-21 Nuclear Safety & Relief Valves 58 5-01-81 M-160AC SRV Discharge Line & RHR Relief Valve F055 Discharge Line Vacuum Breakers 68 5-15-81 M-164 CRD Vent Valve Platform 2

Complete M-192 High Density Spent Fuel Pool Racks 48 Modules Complete M-302 Expansion Tanks & Air Separators 4

Complete M-307-1 thru M-307-3 Centrifugal Fans 6

3-13-81 M-308-1 Vane Axial Fans, Reactor Building 2

5-01-81 M-308-2 Vane Axial Fans, Diesel Generator Building 4

Complete M-308-3 & 4 Vane Axial Fans, ESSW Pumphouse 8

Complete M-309-1 thru M-309-4 Air Handling Units 12 4-17-81 M-310 Centrifugal Water Chillers 2

5-22-81 M-315 Reactor Building Unit Coolers 24 5-29-81 M-317 Drywell Unit Coolers 12 3-27-81 M-320-1 Chlorine Detectors (Note 1) 2 6-15-81 M-320-2-1A & 1B Flow Switches 28 6-15-81 M-320-2-2A Flow Switches 2

6-15-81 M-320-3 Level Gauge 2

6-15-81 M-320-4 Pressure Differential Switches 4

6-15-81 M-370-5A & 5B Temperature Switches 24 6-15-81 M-320-6-1A & 1B Temperature Switches 4

6-15-81 M-320-6-2A Temperature Switches 4

6-15-81 M-320-6-3A & 7 Temperature Switches 10 6-15-81 M-320-8 Pressure Differential Transmitter 18 6-15-81 M-320-9 Temperature Detector Unit 2

6-15-81 M-320-10 Level Switches 4

6-15-81 M-321-1 Standby Gas Treatment System-Housing 2

2-20-81

SSES-FSAR Table Rev. 48 FSAR Rev. 70 Page 4 of 5 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT Form No.

Equipment No. of Items/

2 Units Completion Date M-321-2 Standby Gas Treatment System-Deluge Drain Valves 8

5-01-81 M-321-3 Standby Gas Treatment System-Control Panels 4

3-06-81 M-232C-1 Air Flow Monitoring Unit 1

3-13-81 M-323C-2 SGTS Exhaust Vent Flow Conditioning &

Sampling Probe System 1

3-13-81 M-325 High Efficiency Ventilation Filters 2

Complete M-327-1 Chilled Water Pump 2

Complete M-327-2 Cooling Water Pump 2

Complete M-334-1 thru M-334-5 HVAC Control Panels & Devices 12 5-30-81 (panels) 6-15-81 (devices)

M-336A HVAC Dampers 195 Units 5-08-81 M-362 SGTS Centrifugal Fans 2

Complete M-365 Chilled Water Relief Valves 2

5-01-81 P-10A-1 Motor Operated Gate Valves, 600#

5 6-15-81 P-10A-2 Motor Operated Gate Valves, 900#

15 6-15-81 P-10A-3 Motor Operated Globe Valves, 900# & 600#

9 6-15-81 P-10B Motor Operated Stop Check Valves, 900#

2 6-15-81 P-11A-1 Motor Operated Gate Valves, 900#

2 6-15-81 P-11A-2 Air Operated Testable Check Valves, 900#

2 6-01-81 P-12A-1 Motor Operated Gate Valves, 150#

224 6-15-81 P-12A-2 Motor Operated Globe Valves, 300#

11 6-15-81 P-12A-3 Motor Operated Gate Valves, 300#

20 6-15-81 P-12A-4 Gear Operated Gate & Globe Valves, 300#

7 6-01-81 P-12B-1 Motor Operated Gate Valves, 150# & 300#

4 6-15-81 P-12B-2 Air Operated Gate Valves, 150#

14 6-01-81 P-12B-3 Gear Operated Gate & Globe Valves, 150#

13 6-01-81

SSES-FSAR Table Rev. 48 FSAR Rev. 70 Page 5 of 5 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT Form No.

Equipment No. of Items/

2 Units Completion Date P-14A Motor Operated Globe Valves, 1500#

1 6-15-81 P-14B Motor Operated Globe Valves, 1500#

1 6-15-81 P-15A Motor Operated Globe Valves, 1500#

11 6-15-81 P15B-1 Motor Operated Gate Valves, 1500#

18 6-15-81 P-15B-2 Air Operated Gate Valves, 1500#

2 6-01-81 P-16A-1 Motor Operated Butterfly Valves, 150#

28 6-15-81 P16A-2 Air Operated Butterfly Valves, 150#

8 6-01-81 P-16A-3 Gear Operated Butterfly Valves, 150#

12 6-01-81 P-17A-1 Motor Operated Gate Valves, 900#

7 6-15-81 P-17A-2 Motor Operated Globe Valves, 900#

1 6-15-81 P-17A-3 Air Operated Testable Check Valves, 900#

2 6-01-81 P-17A-4 Gear Operated Gate Valves, 900#

5 6-01-81 P-17B Air Operated Testable Check Valves, 900#

2 6-01-81 P-18A Gear Operated Gate Valves150#

1 6-01-81 P-31A Air Operated Butterfly Valves, 150#

9 6-01-81 Note:

1. Chlorine detection system has been removed and detectors have been deleted.
2. The containment hydrogen recombiners have been abandoned in place.

SSES-FSAR QUESTION 123.8 Describe plans for a confirmatory in-situ impedance test and an in-plant SRV test program or other alternatives to characterize the ability of equipment to accommodate hydrodynamic loading.

RESPONSE:*

In situ tests are being performed for the determination of structural dynamic characteristics of the equipment for in-service condition.

This in-situ information is being used as supporting evidence for (a) validating a mathematical model for qualification by analysis, or (b) simulating the in-service condition on the vibratory table tests for qualification by testing.

The results and the usage of in-situ testing will be described in the respective qualification reports, whenever such tests are performed.

All safety related BOP equipment for Susquehanna project is being qualified £or combined seismic and hydrodynamic loads for the criteria described in Section 7.1.7 of DAR.

Susquehanna has no plans to perform an in-plant SRV test for equipment qualifications.

An air bubble test was conducted in the suppression pool in an attempt to simulate the effects of an SRV air clearing transient load.

The data from this test are being studied in an effort to determine the extent of conservations in the analytical prediction of applied hydrodynamics loads.

Rev. 46, 06/93 123.8-1

SSES-FSAR QUESTION 123.9 To confirm the extent to which the safety related equipment meets the requirements of General Design Criterion 2, the Seismic Qualification Review Team {SQRT} will conduct a plant site review. For selected equipment, SQRT will review the combined required response spectra (RRS) or the combined dynamic response, examine the equipment configuration and mounting, and then determine whether the test or analysis which has been conducted demonstrates compliance with the RRS if the equipment was qualified by test, or the acceptable analytical criteria if qualified by analysis.

The staff requires that a "Qualification Summary of Equipment" as shown on the attached pages be prepared for each selected piece of equipment and submitted to the staff two weeks prior to the plant site visit.

The applicant should make available at the plant site for SQRT review all the pertinent documents and reports of the qualification for the selected equipment.

After the visit, the applicant should be prepared to submit certain selected documents and reports for further staff review.

RESPONSE

Susquehanna SQRT pre-visit information required for the SQRT site review has been submitted for all BOP and NSSS equipment.

"Qualification Summary of Equipment" and the pertinent documents, reports, vendor prints and all necessary information as required are available for SQRT review.

Rev. 46, 06/93 123.9-1