ML23292A196

From kanterella
Jump to navigation Jump to search
1 to Updated Final Safety Analysis Report, Questions 123.1 Through 123.9
ML23292A196
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 10/12/2023
From:
Susquehanna
To:
Office of Nuclear Reactor Regulation
Shared Package
ML23291A105 List: ... further results
References
PLA-8081
Download: ML23292A196 (1)


Text

SSES-FSAR QUESTION 123.l Pursuant to General Design Criterion 2, safety-related structures, systems and components are to be designed for appropriate load combinations arising from accidents and severe natural phenomena. With regard to the vibratory loads attributed to the feedback of hydrodynamic loads from the pressure suppression pool of the containment, the staff requires that safety-related mechanical, electrical, instrumentation and control equipment be designed and qu~lified to withstand effects of hydrodynamic vibratory loads associated with either safety relief valve (SRV) discharge of LOCA blowdown into the pressure suppression containment combined with the effects of dynamic loads arising from earthquakes.

The criteria to be used by the staff to determine the acceptability of your equipment qualification program for seismic and dynamic loads are IEEE Std. 344-1975 as supplemented by Regulatory Guides 1.100 and 1.92, and Standard Review Plan Sections 3.9.2 and 3.10. State the extent to which the equipment in your plant meets these requirements and the above requirements to combine seismic and hydrodynamic vibratory loads. For equipment that does not meet these requirements provide justification for the use of other criteria.

RESPONSE

I. .laQ£ For Susquehanna Project, all BOP Safety related mechanical, electrical, instrumentation and control equipment located inside Primary Containment, Reactor and Control buildings, is being qualified for Seismic loads in combination with hydrodynamic vibratory loads associated with SRV discharge and LOCA blowdown.

Although the SRSS method of combination of seismic and hydrodynamic loads is acceptable, for the project to be conservative, the loads are combined by absolute sum method. The cases which have deviations from the absolute sum method of combination will be identified in the qualification reports.

The criteria for the qualification of BOP equipment for seismic loads is described in Section 3. 7b. 3 of the FSAR. The criteria for load combinations and methodology for the design assessment and qualification of Safety related BOP equipment for seismic and hydrodynamic loads have been described in Sections 5.7 and 7.1.7 of the Design Assessment Report (DAR) Rev. 2.

Basically the requirements of IEEE Std. 344-1975 as Rev. 46, 06/93 123.l*l

SSES-FSAR Supplemented by Regulatory guides 1.100 and 1. 92 and SRP Sections 3. 9. 2 and 3 .10 are covered in the criteria with the following exception for spatial combination of three components of dynamic motion as stated in Sect ion

?.1.7.1.3 of the DAR. The criteria states nthe response at any point is the maximum value obtained by adding the response due to vertical dynamic load with the larger value of the responses due to one of the horizontal dynamic loads by the absolute sum method."

All Susquehanna BOP equipment is being qualified for the criteria discussed above.

II. NSSS LOAD COMBINATIONS:

These were transmitted to the NRC on 8/28/80 as Page 3 of Attachment N to PLA-536. This was in response to NRC Question 110.42.

IMPLEMENTATION OF LOAD COMBINATIONS:

The GE SQRT Program uses outputs from the GE Equipment Adequacy Evaluation Program which combines dynamic loads by SSES as accepted by the NRC in NUREG-0484.

The individual items associated with the load combinations are added as described below:

Steady State Events (e.g., Dead Load, Pressure)

Absolute Sum Time Varying Components (e.g., Maximum Seismic, Maximum Hydrodynamic} - SRSS Components of Events (e.g., Maximum X-Load Due to Y-Earthquake) - SRSS Modal Response-SRSS, except for closely spaced modes where effects are combined by Absolute Sum, Double Sum, or Grouping.

Details for each item of equipment are contained in that equipment's Design Record File which is available for audit.

Rev. 46, 06/93 123.1-2

SSES-FSAR QUESTION 123.2 Provide the following information:

(i) Two summary equipment lists (one for NSSS supplied equipment and one for BOP supplied equipment).

These lists should include all safety related mechanical components, electrical, instrumentation, and control equipment, including valve actuators and other appurtenances of active pumps and valves. In the lists, the following information should be specified for each item of equipment.

(1) Method of qualification used:

(a) Analysis of test (indicate the company that prepared the report, the reference report number and date of the publication}.

(b) If by test, describe whether it was a single or multi-frequency test and whether input was single axis or multi-axis.

{c) If by analysis, describe whether static or dynamic, single or multiple-axis analysis was used. Provide natural frequency (or frequencies) of equipment.

(2) Indicate whether the* equipment has met the qualification requirements.

(3) Indicate the system in whi.ch the equipment is located and whether the equipment is required for:

a) hot stand-by b) cold shutdown c) both d) neither (4) Location of equipment, i.e., building, elevation.

(5) Availability for inspection (Is the equipment already installed at the plant site?)

Rev. 46, 06/93 123.2-1

SSES-FSAR (ii) An acceptable scenario of how to maintain hot stand-by and cold shutdown based on the following assumptions:

(1) SSE or OBE (2) Loss of offsite power (3) Any single failure (iii) A compilation of the required response spectra (RRS) for all applicable vibratory loads (individual and combined if required) for each floor of the nuclear station under consideration.

RESPONSE

The response to this question was submitted via PLA 627 (Curtis to Youngblood) dated February s, 1981.

Rev. 46, 06/93 123.2-2

SSES-FSAR QUESTION 123.3 Identify those items of nuclear steam supply system and balance-of-plant equipment requiring reevaluation and specify why reevaluation is necessary (i.e. because the original qualification used the single frequency, single axis methodology, because equipment is affected by hydrodynamic loads, or because both of the above conditions were present) for each item of equipment.

RESPONSE

Originally almost all Safety related BOP equipments for Susquehanna had been qualified for only Seismic loads. This equipment has been re-evaluated due to the inclusion of new hydrodynamic (SRV & LOCA) loads, and are being re-qualified with respect to the criteria described in DAR Section 7.17.

The qualification program for the BOP Safety related equipment is being executed in the following four phases.

Phase-I: oualification of Egµipment for Only Seismic Loads:

The only known dynamic load at the time of execution of this phase of the program was Seismic loads. During this phase, the vendors supplying the equipment were required to qualify the equipment in accordance with the requirements specified in FSAR Subsection 3.7b.3.

Phase-II: Evaluation for Combined Seismic and Hydrodynamic (SRV & LOCA) Loads; This phase was undertaken to evaluate if the existing Seismic qualification of all Safety related BOP equipment could be extended to the combined Seismic and hydrodynamic loads. The criteria used for the re-evaluation is described in DAR Section 7 .1. 7. The general problem areas identified during this evaluation and the proposed action to mitigate these problems are shown below.

Problem Additional hydrodynamic Retest and/or loads reanalysis.

Modifications to equipment of their supports if required.

Flexibility of equipment Provide response Support not considered spectre considering support flexibility Rev. 46, 06/93 123.3-1

SSES-FSAR Include Support Conditions during analysis or testing.

Inadequate Modelling Correct during reanalysis.

Inadequate Testing Retest.

Qualification by analysis.

Phase III: Regualification Efforts:

Specifically, the Problem areas identified in the previous phase are resolved during this phase by taking appropriate actions. The requalif ication reports demonstrate that the criteria of DAR Section 7.1.7 have been complied with.

Phase IV: Modifications to Equipment or Equipment Supports:

Equipment or their Supports needing modifications identified during the regulations efforts of Phase III are executed during this phase.

The following are NSSS equipment:

SYSTEM MPL I Safety Relief Valve B21F013 MSIV B21F022/

F028 Flow Element B21NOS1/

52/53/54 Recirc. Pump Motor B31C001 Gate Valve B31F023/

31/32 HCU Cl2D001 CRD Valves Cll2F009/

10/11/12 SLC Storage Tank C41A001 SLC Accumulator C41A003 SLC Pump C41C001 SLC Explosive Valve C41F004 RHR Heat Exchanger EllBOOl RHR Pump EllC002 Flow Orifice Assembly EllN012/

N014 LPCS Pump & Motor E21C001 Rev. 46, 06/93 123.3-2

SSES-FSAR Flow Orifice Assembly E21N002 MSIV Heater E32B001 MSIV Blower E32C001/

C002 HPCI Pump E41C001 HPCI Turbine E41C002 Flow Orifice Assembly E41N007 RCIC Pump ESlCOOl RCIC Turbine E51C002 Flow Orifice Assembly ESlNOOl Fuel Prep Machine E18E001 Gen. Purpose Grapple F18E011 Dryer & Separator Sling F19E008 Head Strong Back F19E009 Control Rod Grapple F20E002 Refueling Platform E21E003 In Vessel Rack F22E006 Def. Fuel Storage Cont. F22E009 Fuel Storage Vault F22E012

~ONTROL ROOM PANELS Reactor Core Cooling BB H12-P601 Power Range Monitoring Cabinet H12-P608 RPS Div. land 2 Log VB H12-P609 RPS Div. 2 and 3 Logical VB H12-P611 NSSS Temperature Recorder VB H12-P614 Feedwater & Recirculation Instrument Panel H12-P612 NSSS Process Instrument Panel H12-P613 Div 1 RHR/HPCI Relay VB H12-P617 Div 2 RHR/HPCI Relay VB H12-P6118 ADS Ch A Relay VB H12-P628 MSIV Leakage Control Div 2 VB H12-P654 HPCI Relay VB H12-P620 RCIC Relay VB H12-P621 Inboard Valve Relay Board H12-P622 Outboard Valve Relay VB Hl2*P623 Div l CS Relay VB H12-P626 Div 2 CS Relay VB H12-P627 ADS Ch B Relay VB H12-P631 MSIV Leakage Control Div 1 VB H12-P655 Radiation Monitoring Instrument Panel A H12-P606 Radiation Monitoring Instrument Panel B H12-P633 Operating BB H12-P680 Termination Cabinets H12-P700 Series Plant Operation Benchboard Hl2-P853 Rev. 46, 06/93 123.3-3

SSES-FSAA NUCLEAR BOILER Condensing Chamber B21-O002 Condensing Chamber B21-D004AB Condensing Chamber B21-D006AD Condensing Chamber B21-D007AD Condensing Chamber B21-DOOBAD Condensing Chamber B21-D009AD LOCAL PANELS Reactor Water Clean-Up H23-P002 Reactor Vessel Level and Pressure (A) H23-P004 Reactor Vessel Level and Pressure (B) H23-P00S Recirculation Pump A H23-P009 Jet Pump B H23-P010 High Pressure Coolant Injection B H23-P014 Reactor Core Isolation Cooling A H23-P017 Residual Heat Removal Channel A H23-P018 Residual Heat Removal Div. 2 Channel B H23-P021 Recirculation Pumps H23-P022 Drywell Pressure Local Panel A H23-P057 Drywell Pressure Local Panel B H23-P058 Main Steam Isolation Valve Leakage Control H23-P074 Div. 2 Core Spray Local Panel A H23-P001 Standby Liquid Control H23-P011 Main Steam Flow A/B H23-P015 High Pressure Coolant Injection Leak Det. H23-P016 Core Spray Channel B H23-P019 Main Steam Flow C/D H23-P025 High Pressure Coolant Injection H23-P036 Reactor Core Isolation Cooling Leak Det. H23-P038 Div. 2(B)

Main Steam Flow A/B H23-P041 Main Steam Flow C/D H23-P042 Main Steam Isolation Valve Leakage Con. H23-P073 Div. 1 High Pressure Coolant Injection Div. 1 A H23-P034 Reactor Core Isolation Cooling Div. 2 B H23-P037 SRM/IRM H23-P030/

31/3/2/33 NUCLEAR BOILER Temperature Element B21-N004 Temperature Element B21-N010AD Temperature Element B21-N014AD Pressure Switch B21-N015AD Temperature Element B21-N016AD Temperature Element B21-N017 Rev. 46, 06/93 123.3-4

SSES-FSAR Vacuum Switch B21-N056AD Temperature Element B21-N064 Differential Pressure Transmitter B31-N014CD Temperature Element B31-N023AB Differential Pressure Transmitter B31-N024AB Level Switch Cl2-N013AD Level Switch C12-N013EF Temperature Switch C41-N003 Pressure Transmitter C41-N004 Pressure Indicator C41-R003 Valve, Guide Tube C51-J004AE Miscellaneous Parts (51-5110001 Pressure Switch C72-N003AD Pressure Switch C72-NOOSAD Limit Switch C72-N006AD Limit Switch C72-N008AD Level Transmitter Ell-N008AB Temperature Element Ell-N009AD Differential Pressure Transmitter Ell-N013 Differential Pressure Transmitter Ell-NOlSA Differential Pressure Transmitter Ell-N015B Pressure Switch Ell-N018 Switch Ell-N021AB Pressure Switch Ell-N022AB Level Switch Ell-N023AB Level Switch Ell-N024 Temperature Element Ell-N029AD Temperature Element Ell-N030AD Flow Indicating Switch Ell-N033AB Differential Pressure Transmitter E21-N003AB Switch E21-N006AB Pressure Switch E21-N007AB Flow Meter E32-N006 Level Switch E41-N002 Level Switch E41-N003 Level Switch E14-N014 Level Switch E41-N015AB Level Switch E41-N018 Temperature Element E41-N024AB Temperature Element E41-N02SAH Temperature Element E41-N028AB through E41-N030AB Temperature Indicator E41-R002 Level Switch E51-N010 Temperature Element E51-N011AB Temperature Element E51-N021AB Temperature Element E51-N022AB Temperature Element E51-N023AB Rev. 46, 06/93 123.3-5

SSES-FSAR Temperature Element E51-N02SAD through E51-N027AD Temperature Indicator ESl-ROOS Temperature Element G33-N016AF Temperature Element G33-N022AF Temperature Element G33-N023AF Switch G33-N044A Rev. 46, 06/93 123.3-6

SSES-FSAR QUESTION 123.4 Describe the methods and criteria used to determine the acceptability of the original equipment qualification to meet the required response spectra of item 2. (iii). - 123.2 (iii).

RESPONSE

I. BOP For cases where the original spectra for which an equipment was qualified enveloped the combined Seismic and hydrodynamic load spectra of Item 123.2 (iii), the equipment is considered qualified. Otherwise (which is true for most cases) the equipment is requalified for the combined spectra to meet the criteria discussed in response to Questions 123.1. These criteria are described in Section 7.1.7 of the Design Assessment Report.

II. NSSS The methods and criteria used to determine the acceptability of the original equipment qualification may be found in General Electric Company's Proprietary reports: NEDE-24788, "Seismic Qualification Review Team (SQRT) Technical Approach for Re-Evaluation of BWR 4/S Equipment"; and NEDE-25250 "Generic Criteria For High-Frequency cutoff of BWR Equipment."

Rev. 46, 06/93 123.4-1

SSES-FSAR QUESTION 123.5 Describe the methods and criteria used to address the vibration fatigue cycle effects on the affected equipment due to required loading conditions.

RESPONSE

I. ~

As described in Subsection 3.7b.3.2 of FSAR, in general, the design of equipment is not fatigue controlled since the number of cycles in an earthquake is low.

For combined Seismic and hydrodynamic loads for equipment qualified by analysis, the fatigue effects are implicitly considered since the stresses due to SRV (which are generally controlling for fatigue) are a small contribution to the overall equipment stresses.

Fatigue effects in BOP equipment qualified by testing are accounted for by repetition of the tests.

Typically tests are done for 5 OBE (or 5 upset conditions, i.e., OBE + SRV + LOCA) followed by 1 SSE (or 1 faulted condition, i.e., SSE+ SRV + LOCA) in each of front-to-back/vertical and side-to-side/vertical biaxial configurations. In addition, on some selected pieces of equipment, vibratory table testing is carried out for an extended duration of time (such as 30 to 60 minutes) beyond the combined loading test. The input motions for the extended du rat ion tests will be such that the generated test response spectra for any segment of the extended duration tests will envelope the SRV spectra. Furthermore, it will be ascertained that the equipment performs its intended function before, during and after the vibratory table tests. The results of the extended duration tests will be documented in the respective qualification reports.

II. NSSS Vibration fatigue cycle effects for NSSS equipment designed to ASME code requirements was reviewed at GE by NRC consultants from Battelle Pacific Northwest Laboratories on October 7, 1980. The consultants stated satisfaction with the GE approach which encompasses OBE, SRV, thermal and pressure cycles.

Rev. 46, 06/93 123.5-1

SSES-FSAR Non-ASME Code components qualified by test address the "strong motion" phase of seismic and SRV dynamic motion sufficient to generate maximum equipment response.

These loads are controlling. GE testing generally consists of 5 upset and 1 faulted test of 30 seconds each which is about 50% greater than required to address strong motion vibration.

Non-ASME Code components qualified by analysis generally have not, in the past, had to address vibration fatigue cycle effects. In most cases, such effects are not now part of the qualification record.

Rev. 46, 06/93 123.5-2

SSES-FSAR QUESTION 123.6 Based on the methods and criteria described in items 4 and 5, provide the results of the review of the original equipment qualification with identification of (1) equipment which has failed to meet the required response spectra and required requalification, and (2) equipment which was found acceptable, together with the necessary information to justify the adequacy of the original qualification.

RESPONSE

I. BOP For cases where the original seismic reports can be extended to qualify an equipment for combined seismic and hydrodynamic loads by inspection and subsequent concurrence by vendor, such documents form a part of the qualification package. The following pieces of equipment bought under the indicated purchase order (P.O.) fall into this category:

(1) Cooling and chilled water pumps (P.O. #M-327)

(2) Expansion Tanks and Air Separator Tanks (P.O. #M-302)

{3) Nitrogen Gas Accumulators (P.O. #M-156)

The rest of the BOP equipment is being qualified for the criteria described in Section 7.1.7 of the Design Assessment Report. The qualification reports for this equipment will provide the appropriate documentation.

II. ~

Refer to the Response to Question 123. 3 for the list of equipment reevaluated by GE on the Susquehanna SQRT Program. All of the equipment listed in qualified to SQRT Criteria with the exception of the following:

B211-F022/ MSIV Data required from F028 vendor B31-F031/ Gate Valve Operability F032 deflection analysis required Cl2-F009/F012 CRD Valve Operability F011/F012 deflection analysis required Rev. 46, 06/93 123.6-1

SSES-FSAR C41-A003 SLC A/E pipe Accumulator accelerations required C41-F004 SLC A/E pipe Explosive accelerations Valve required E32-B001 MSIV Heater Test required E41-C002 HPCI Turbine Test required E51-C002 RCIC Turbine Analysis of lube oil piping required F22-EOO6 Invessel Analysis required Rack F22-E0O9 Def. Fuel Analysis required Storage Cont.

H12-P608 Power Range Test required Monitoring Cabinet H23-PO3O SRM/IRM Test required

-PO31 Panels

-PO32

-P033 163Cl158 Flow Test required Transmitter on H23*P0?4 272A8005 Switch on Test required H12-P853 272A8006 Switch on Test required H12-P853 Information to justify qualification of the equipment selected by the NRC for the Site Audit will be available at the site for NRC inspection. Information to justify qualification of the remainder of the equipment is available for NRC audit at GE-San Jose.

Rev. 46, 06/93 123.6-2

SSES-FSAR QUESTION 123.7 Describe procedures and schedule for completion of each item identified in item 6. (1) 123.6 (1) that requires requalification.

E,ESPONSE:

I. BOP Typically, the qualification program is executed in the following steps.

o Determine Qualification Awards

- Request Vendor (or Consultant) Quote

- Receive and Evaluate Quote Place Purchase Order o Perform Qualification

- Review Test Procedure

- Review Analysis Methodology

- Begin Analysis or Testing o Final Completion

- Receive and review Requalification Reports

- Final Approval of the Report The schedule for the completion of the qualification program is shown in the attached Table 123.7-1.

II. NSSS The response to Question 123. 6 lists the equipment found by GE to require requalification along with a statement defining the work to be performed. All requalification will b~ completed on a schedule sufficient to permit NRC review prior to fuel load.

Rev. 46, 06/93 123.7-1

SSES-FSAR TABLE 123. 7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REOUALIFICATION SORT No. of hems/ CompTetion Form No. Equipment 2 Units Dete E-109-1 4 kV Switchgear 12 3-13-81 E-1O9-2 4 kV Switchgear Sub-Components 12 6-15-81 E-112 ESW and RHR Pump Motors 8 Complete E-117-1 480V Safe-Guard Load Center 8 3-27-81 Unit Substations E-118 480 V Motor Control Centers 24 4-17-81 E-119A-1 Battery Monitors 20 3-27-81 E-119A-2 Battery Fuse Boxes 16 3-27-81 E-119A-3 Battery Chargers 22 3-2 7-8 t E-1198C 24 Vdc, 125 Vdc & 250 Vdc 8 6-29-Bl Battery Cells & Racks E-120-1 125 Vdc Distribution Panels 16 3-20-81 E-120-2 24 Vdc Distribution Panels 4 4.,0-91 E-121-1 126 V & 260 Vdc Load Centers 12 3-27-8 t E-121-2 250 Vdc Control Centers 6 4-10-81 E-136-1 Electrical Penetration (Medium 12 6-15-81 Voltage)

E-135-2 Electrical Penetration (low 32 6-15-81 Voltage)

E-136 AC Instrument Transformers 14 3-27-81 E-151 Motor Generator Sets and Control 4 Sets Complete Cabinet E-152 Automatic Transfer Switches 8 Complete E-166 Control Switches 44 8-16-81 J-O38A Field Mounted Electronic Pressure 32 ComP'ete Transmitters J-038-1 thru Paner - Mounted Instruments 242 4th quarter 198 t J-038-14 Rev. 46, 06/93 Page 1 of 6

SSES-FSAR TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION (Cont'd.)

SORT No. of Items/ CompletJon form No. Equipment 2 Units Date J-05A-14, Control Panels & Devices 31 6-30-81 (panelsl 31,33,37, 8-15-81 (devices) 10A & 8, 43,47,49,92, 93,95 & 97 J-058-1 Remote Shutdown Control Panel 1 6-30-81 (panels) 8-15-81 (devices)

J-27 Reactor Coolant Pressure Boundary 2 Complete (panels)

Leak Detection System 8-15-81 (devices)

J-31 Annubar Flow Elements 2 Complete J-59-1 thru RTO's 64 6-22-81 J-59-10 J-65-1 thru Control Valves In Nuclear Service 28 3-27 -81 J-65-4 J-658-1 thru Control Valves In Nuclear Service 86 3-27-81 J-658-11 J-69-1 & 2 Pilot Solenoid Valves 8 6-15-81 J-698-1 thru 6 Pilot Solenoid Valves 74 6-15-81 J-70-1 Pressure Regulating Valves 8 6-15-81 J-70-2 Process Solenoid Valves 76 6-15-81 J-92-1 thru Excess Flow Check Valves 238 6-01-81 J-92-5 J-98 Carrier Modulator (Isolator) . 6-15-81 M-11 ESW Pumps 4 Complete M-12 RHR Suction Water Pumps 4 Complete M-22-1 & 2 Reactor Building Cranes 2 4-03-81 M-30 (78 forms) Diesel Generator 4 Sets Complete M-30 (6 forms) Diesel Generator 4 Sets 2-27-81 M-55 Reactor Vessel Top Head Insulation 2 Complete Support Steel M-58 Diesel Oil Transfer Pumps 4 Complete Rev. 46, 06/93 Page 2 of 6

SSES-FSAA TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REOUAUFICATION (Cont'd.t SQRT No. of Items! Completion Form No. Equipment 2 Units Date M-60 Buried Diesel Generator Fuel Oil 4 3-27-81 Storage Tanks M-87-1 Containment Hydrogen 8 6-15-81 Recombiners M-87-2 Hydrogen Recombiner Power 4 Complete Supply M-90 Fuel Pool Skimmer Surge Tanks 2 4-27*81 M-149 Containment Vacuum Relief Valves 20 6*22-81 M-151 Suppression Pool Suction Strainers 32 Complete M-156 Containment Nitrogen Gas 60 Complete Accumulators M* 159-1 thru Nuclear Safetv & Relief Valves 68 6*01-81 M-159-21 M-160AC SRV Discharge Line & RHR Relief 68 6-15-81 Valve F055 Discharge Line Vacuum Breakers M-164 CRD Vent Valve Platform 2 Complete M-192 High Density Spent Fuel Pool 48 Modules Complete Racks M-302 Expansion Tanks & Air Separators 4 Complete M-307-1 thru Centrifugal Fans 6 3 81 M-307-3 M-308-1 Vane Axlal Fans, Reactor Building 2 6-01-81 M -308-2 Vane Axial Fans, Diesel Generator 4 Complete Building M-308-3 & 4 Vane Axial Fans, ESSW 8 Complete Pumphouse M309-1 thru Air Handling Units 12 4-17-81 M-309-4 M-310 Centrifugal Water Chillers 2 &*22-81 M-315 Reactor Building Unit Coolers 24 6*29-81 M-317 Drywell Unit Coolers 12 3-27-81 Rev. 46, 06/93 Page 3 of 6

SSES-FSAR TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REOUALIFICATION (Cont'd.)

SORT No. of Items! Completion Form No. Equipment 2 Units Date M-320-1 Chlorine Detectors 2 6--15-81 M-320-2*1A & 1B Flow Switches 28 8-t 5-81 M-320-2-2A Flow Switches 2 8-15-81 M-320-3 Level Gauge 2 6-15-81 M-320-4 Pressure Differential Switches 4 8-15-81 M -370-5A & 5B Temperature Switches 24 6-15-81 M-320-6-1 A & 1B Temperature Switches 4 8-15-81 M-320*6-2A Temperature Switches 4 8-15-81 M-320*6-3A & 7 Temperature Switches 10 6-15-81 M-320-8 Pressure Differential Transmitter 18 8-15-81 M-320-9 Temperature Detecto, Unit 2 6-15-81 M-320-10 Level Switches 4 6-1 5-81 M-321-1 Standby Gas Treatment System

  • 4 3-06-81 Control Panels M-232C-1 Air Flow Monitoring Unit 1 3-13-81 M-323C-2 SGTS Exhaust Vent Flow 1 3-13-81 Conditioning & Sampling Probe System M-326 High Efficiency Ventilation Filters 2 Complete M -327-1 Chilled Water Pump 2 Complete M-327-2 Cooling Water Pump 2 Comptete M-334* 1 thru HVAC Control Panels & Devices 12 6-30-81 (panels)

M-334-5 8-15-81 !devices)

M-336A HVAC Dampers 195 Units 5-08-81 M-362 SGTS Centrifugal Fans 2 Complete Rev. 46, 06/93 Page 4 of 6

SSES-FSAR TABLE 123.7*1 SCHEDULE FOR COMPLETION OF EQUIPMENT REOUALIFICATION (Cont'd.)

SQRT No. of Items/ Completion Form No. Equipment 2 Unit$ Date M-365 Chilled Water Relief Valves 2 6-01-81 P-10A-1 Motor Operated Gate Valves, 800# 6 6-16-81 P-10A*2 Motor Operated Gate Valves, 900# 15 6-15-81 P-10A-3 Motor Operated Globe Valves, 9 8-15-81 9001 & 600#

P-10B Motor Operated Stop Check 2 6-15-81 Valves, 900#

P-11A-1 Motor Operated Gate Valves, 900# 2 6-15-81 P*11A*2 Air Operated Testable Check 2 6-01-81 Velves, 900#

P-12A-1 Motor Operated Gate Valves, 1 50# 24 8-15-81 P12A-2 Motor Operated Globe Valves, 11 8-15-81 300#

.P 12A-3 Motor Operated Gate Valves, 300# 20 6-15-81 P-12A-4 Gear Operated Gate & Globe 7 6-01-81 Valves, 300#

P-128-1 Motor Operated Gate Valves, 150# 4 8-15-81

& 300#

P-12B-2 Air Operated Gate Valves, 1501 14 6-01-81 P-128-3 Gear Operated Gate & Globe 13 6-01-81 Valves, 150#

P-14A Motor Operated Globe Valves, , 6* 16-81 1500#

P-14B Motor Operated Globe Valves, 1 8-15-81 1500#

P-15A Motor Operated Globe Valves, 11 8-15-81 1500#

P158-1 Motor Operated Gate Valves, 18 6-15-81 1500#

P-158-2 Air Operated Gate Valves, 1500# 2 8-01-81 P-16A-1 Motor Operated Butterfly Valves, 28 8*15-81 150#

Rev. 46, 06/93 Page 5 of 6

SSES-FSAR TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT AEOUALIFICATION (Cont'd.)

SQRT No. of Items/ Completion Form No. Equipment 2 Units Date Pl 6A-2 Air Operated Butterfly Valves, a 6-01-81 J

160#

P-16A*3 Gear Operated Butterfly Valves, 12 6-01-B 1 160#

P-17A-1 Motor Operated Gate Valves, 900# 7 6-15-81 P-17A-2 Motor Operated Globe Valves, 1 6-15-81 900#

P-17A-3 Air Operated Testable Check 2 6-01 *81 Valves, 9001 P-17A-4 Gear Operated Gate Valves, 900# 6 6-01-B 1 P-17B Air Operated Testable Check 2 6-01-81 Valves, 900#

P-18A Gear Operated Gate Valves, 160# 1 6-01-81 P-31A Air Operated Butterfly Valves, 9 6-01-81 150#

Rev. 46, 06/93 Page 6 of 6

SSES-FSAR Table Rev. 48 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT No. of Items/ Completion Form No. Equipment 2 Units Date E-109-1 4 kV Switchgear 12 3-13-81 E-109-2 4 kV Switchgear Sub-Components 12 5-15-81 E-112 ESW and RHR Pump Motors 8 Complete E-117-1 480 V Safe-Guard Load Center Unit 8 3-27-81 Substations E-118 480 V Motor Control Centers 24 4-17-81 E-119A-1 Battery Monitors 20 3-27-81 E119A-2 Battery Fuse Boxes 16 3-27-81 E-119A-3 Battery Chargers 22 3-27-81 E-119BC 24 Vdc, 125 Vdc & 250 Vdc Battery 8 5-29-81 Cells & Racks E-120-1 125 Vdc Distribution Panels 16 3-20-81 E-120-2 24 Vdc Distribution Panels 4 4-10-81 E-121-1 125 V & 250 Vdc Load Centers 12 3-27-81 E-121-2 250 Vdc Control Centers 6 4-10-81 E-135-1 Electrical Penetration (Medium Voltage) 12 5-15-81 E-135-2 Electrical Penetration (Low Voltage) 32 5-15-81 E-136 AC Instrument Transformers 14 3-27-81 E-151 Motor Generator Sets and Control 4 Sets Complete Cabinet E-152 Automatic Transfer Switches 8 Complete E-155 Control Switches 44 6-15-81 J-038A Field Mounted Electronic Pressure 32 Complete Transmitters J-03B-1 thru Panel - Mounted Instruments 242 4th quarter 1981 J-03B-14 J-05A-14 Control Panels & Devices 31 5-30-81 (panels) 31,33,37, 6-15-81 (devices) 10A & B 43,47,49,92, 93,95 & 97 J-05B-1 Remote Shutdown Control Panel 1 5-30-81 (panels) 6-15-81 (devices)

J-27 Reactor Coolant Pressure Boundary 2 Complete (panels)

Leak Detection System 6-15-81 (devices)

FSAR Rev. 70 Page 1 of 5

SSES-FSAR Table Rev. 48 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT No. of Items/ Completion Form No. Equipment 2 Units Date J-31 Annubar Flow Elements 2 Complete J-59-1 thru RTDs 54 5-22-81 J59-10 J-65-1 thru Control Valves in Nuclear Service 28 3-27-81 J-65-4 J65B-1 thru Control Valves in Nuclear Service 86 3-27-81 J65B-11 J-69-1& 2 Pilot Solenoid Valves 8 5-15-81 J-69B-1 thru 6 Pilot Solenoid Valves 74 5-15-81 J-70-1 Pressure Regulating Valves 8 5-15-81 J-70-2 Process Solenoid Valves 76 5-15-81 J-92-1 thru Excess Flow Check Valves 238 5-01-81 J92-5 J-98 Carrier Modulator (Isolator) - 6-15-81 M-11 ESW Pumps 4 Complete M-12 RHR Suction Water Pumps 4 Complete M-22-1 & 2 Reactor Building Cranes 2 4-03-81 M-30 (78 forms) Diesel Generator 4 Sets Complete M-30 (6 forms) Diesel Generator 4 Sets 2-27-81 M-55 Reactor Vessel Top Head Insulation 2 Complete Support Seal M-58 Diesel Oil Transfer Pumps 4 Complete M-60 Buried Diesel Generator Fuel Oil 4 3-27-81 Storage Tanks M-87-1 Containment Hydrogen Recombiners 8 5-15-81 (Note 2)

M-87-2 Hydrogen Recombiner Power Supply 4 Complete (Note 2)

M-90 Fuel Pool Skimmer Surge Tanks 2 4-27-81 M-149 Containment Vacuum Relief Valves 20 5-22-81 M-151 Suppression Pool Suction Strainers 32 Complete M-156 Containment Nitrogen Gas 60 Complete Accumulators FSAR Rev. 70 Page 2 of 5

SSES-FSAR Table Rev. 48 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT No. of Items/ Completion Form No. Equipment 2 Units Date M-159-1 thru Nuclear Safety & Relief Valves 58 5-01-81 M-159-21 M-160AC SRV Discharge Line & RHR Relief Valve 68 5-15-81 F055 Discharge Line Vacuum Breakers M-164 CRD Vent Valve Platform 2 Complete M-192 High Density Spent Fuel Pool Racks 48 Modules Complete M-302 Expansion Tanks & Air Separators 4 Complete M-307-1 thru Centrifugal Fans 6 3-13-81 M-307-3 M-308-1 Vane Axial Fans, Reactor Building 2 5-01-81 M-308-2 Vane Axial Fans, Diesel Generator 4 Complete Building M-308-3 & 4 Vane Axial Fans, ESSW Pumphouse 8 Complete M-309-1 thru Air Handling Units 12 4-17-81 M-309-4 M-310 Centrifugal Water Chillers 2 5-22-81 M-315 Reactor Building Unit Coolers 24 5-29-81 M-317 Drywell Unit Coolers 12 3-27-81 M-320-1 Chlorine Detectors (Note 1) 2 6-15-81 M-320-2-1A & 1B Flow Switches 28 6-15-81 M-320-2-2A Flow Switches 2 6-15-81 M-320-3 Level Gauge 2 6-15-81 M-320-4 Pressure Differential Switches 4 6-15-81 M-370-5A & 5B Temperature Switches 24 6-15-81 M-320-6-1A & 1B Temperature Switches 4 6-15-81 M-320-6-2A Temperature Switches 4 6-15-81 M-320-6-3A & 7 Temperature Switches 10 6-15-81 M-320-8 Pressure Differential Transmitter 18 6-15-81 M-320-9 Temperature Detector Unit 2 6-15-81 M-320-10 Level Switches 4 6-15-81 M-321-1 Standby Gas Treatment System- 2 2-20-81 Housing FSAR Rev. 70 Page 3 of 5

SSES-FSAR Table Rev. 48 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT No. of Items/ Completion Form No. Equipment 2 Units Date M-321-2 Standby Gas Treatment System- Deluge 8 5-01-81 Drain Valves M-321-3 Standby Gas Treatment System- Control 4 3-06-81 Panels M-232C-1 Air Flow Monitoring Unit 1 3-13-81 M-323C-2 SGTS Exhaust Vent Flow Conditioning & 1 3-13-81 Sampling Probe System M-325 High Efficiency Ventilation Filters 2 Complete M-327-1 Chilled Water Pump 2 Complete M-327-2 Cooling Water Pump 2 Complete M-334-1 thru HVAC Control Panels & Devices 12 5-30-81 (panels)

M-334-5 6-15-81 (devices)

M-336A HVAC Dampers 195 Units 5-08-81 M-362 SGTS Centrifugal Fans 2 Complete M-365 Chilled Water Relief Valves 2 5-01-81 P-10A-1 Motor Operated Gate Valves, 600# 5 6-15-81 P-10A-2 Motor Operated Gate Valves, 900# 15 6-15-81 P-10A-3 Motor Operated Globe Valves, 9 6-15-81 900# & 600#

P-10B Motor Operated Stop Check 2 6-15-81 Valves, 900#

P-11A-1 Motor Operated Gate Valves, 900# 2 6-15-81 P-11A-2 Air Operated Testable Check 2 6-01-81 Valves, 900#

P-12A-1 Motor Operated Gate Valves, 150# 224 6-15-81 P-12A-2 Motor Operated Globe Valves, 300# 11 6-15-81 P-12A-3 Motor Operated Gate Valves, 300# 20 6-15-81 P-12A-4 Gear Operated Gate & Globe 7 6-01-81 Valves, 300#

P-12B-1 Motor Operated Gate Valves, 4 6-15-81 150# & 300#

P-12B-2 Air Operated Gate Valves, 150# 14 6-01-81 P-12B-3 Gear Operated Gate & Globe 13 6-01-81 Valves, 150#

FSAR Rev. 70 Page 4 of 5

SSES-FSAR Table Rev. 48 TABLE 123.7-1 SCHEDULE FOR COMPLETION OF EQUIPMENT REQUALIFICATION SQRT No. of Items/ Completion Form No. Equipment 2 Units Date P-14A Motor Operated Globe Valves, 1500# 1 6-15-81 P-14B Motor Operated Globe Valves, 1500# 1 6-15-81 P-15A Motor Operated Globe Valves, 1500# 11 6-15-81 P15B-1 Motor Operated Gate Valves, 1500# 18 6-15-81 P-15B-2 Air Operated Gate Valves, 1500# 2 6-01-81 P-16A-1 Motor Operated Butterfly Valves, 150# 28 6-15-81 P16A-2 Air Operated Butterfly Valves, 150# 8 6-01-81 P-16A-3 Gear Operated Butterfly Valves, 150# 12 6-01-81 P-17A-1 Motor Operated Gate Valves, 900# 7 6-15-81 P-17A-2 Motor Operated Globe Valves, 900# 1 6-15-81 P-17A-3 Air Operated Testable Check 2 6-01-81 Valves, 900#

P-17A-4 Gear Operated Gate Valves, 900# 5 6-01-81 P-17B Air Operated Testable Check 2 6-01-81 Valves, 900#

P-18A Gear Operated Gate Valves150# 1 6-01-81 P-31A Air Operated Butterfly Valves, 9 6-01-81 150#

Note:

1. Chlorine detection system has been removed and detectors have been deleted.
2. The containment hydrogen recombiners have been abandoned in place.

FSAR Rev. 70 Page 5 of 5

SSES-FSAR QUESTION 123.8 Describe plans for a confirmatory in-situ impedance test and an in-plant SRV test program or other alternatives to characterize the ability of equipment to accommodate hydrodynamic loading.

RESPONSE:*

In situ tests are being performed for the determination of structural dynamic characteristics of the equipment for in-service condition. This in-situ information is being used as supporting evidence for (a) validating a mathematical model for qualification by analysis, or (b) simulating the in-service condition on the vibratory table tests for qualification by testing. The results and the usage of in-situ testing will be described in the respective qualification reports, whenever such tests are performed.

All safety related BOP equipment for Susquehanna project is being qualified £or combined seismic and hydrodynamic loads for the criteria described in Section 7.1.7 of DAR.

Susquehanna has no plans to perform an in-plant SRV test for equipment qualifications. An air bubble test was conducted in the suppression pool in an attempt to simulate the effects of an SRV air clearing transient load. The data from this test are being studied in an effort to determine the extent of conservations in the analytical prediction of applied hydrodynamics loads.

Rev. 46, 06/93 123.8-1

SSES-FSAR QUESTION 123.9 To confirm the extent to which the safety related equipment meets the requirements of General Design Criterion 2, the Seismic Qualification Review Team {SQRT} will conduct a plant site review. For selected equipment, SQRT will review the combined required response spectra (RRS) or the combined dynamic response, examine the equipment configuration and mounting, and then determine whether the test or analysis which has been conducted demonstrates compliance with the RRS if the equipment was qualified by test, or the acceptable analytical criteria if qualified by analysis.

The staff requires that a "Qualification Summary of Equipment" as shown on the attached pages be prepared for each selected piece of equipment and submitted to the staff two weeks prior to the plant site visit. The applicant should make available at the plant site for SQRT review all the pertinent documents and reports of the qualification for the selected equipment.

After the visit, the applicant should be prepared to submit certain selected documents and reports for further staff review.

RESPONSE

Susquehanna SQRT pre-visit information required for the SQRT site review has been submitted for all BOP and NSSS equipment.

"Qualification Summary of Equipment" and the pertinent documents, reports, vendor prints and all necessary information as required are available for SQRT review.

Rev. 46, 06/93 123.9-1