PMNS20220679, Post-Shutdown Decommissioning Activities Report Public Meeting
Letter Sequence Meeting | |
---|---|
EPID:L-2019-LRL-0004, Post-Shutdown Decommissioning Activities Report (Approved, Closed) EPID:L-2019-LRL-0005, Post-Shutdown Decommissioning Activities Report (Approved, Closed) EPID:L-2019-LRL-0006, Post-Shutdown Decommissioning Activities Report (Approved, Closed) | |
MONTHYEARDCL-19-091, Letter to Inform the NRC of the Submittal Date for the Post-Shutdown Decommissioning Activities Report, Site-Specific Decommissioning Cost Estimate, and Irradiated Fuel Management Plan2019-10-31031 October 2019
[Table View]Letter to Inform the NRC of the Submittal Date for the Post-Shutdown Decommissioning Activities Report, Site-Specific Decommissioning Cost Estimate, and Irradiated Fuel Management Plan Project stage: Request DCL-19-077, Post-Shutdown Decommissioning Activities Report2019-12-0404 December 2019 Post-Shutdown Decommissioning Activities Report Project stage: Request ML20041E6012020-02-10010 February 2020 NRR E-mail Capture - Diablo Canyon Nuclear Power Plant, Units 1 and 2 - Request for Additional Information for Post -Shutdown Decommissioning Activities Report (PSDAR) Project stage: RAI ML20034E1482020-02-13013 February 2020 Letter, Notice of Receipt, Public Meeting and Request for Comment on Post-Shutdown Decommissioning Activities Report Project stage: Meeting ML20055E0632020-02-18018 February 2020 Pacific Gas and Electric Company - Diablo Canyon Power Plant, Unit Nos. 1 and 2 - Federal Register Notice Project stage: Other ML20072L8482020-03-12012 March 2020 FRN Notification of the Availability of the Post-Shutdown Decommissioning Activities Report in the Federal Register (EPID L-2019-LRL-0004)-Cancellation of Public Meeting Project stage: Meeting ML20072M0362020-03-12012 March 2020 Letter Notification of the Availability of the Post-Shutdown Decommissioning Activities Report in the Federal Register Project stage: Other DCL-21-073, Notification of Changes to Post-Shutdown Decommissioning Activities Report, Site-Specific Decommissioning Cost Estimate, and Irradiated Fuel Management Plan for Diablo Canyon Power Plant, Units 1 and 22021-10-19019 October 2021 Notification of Changes to Post-Shutdown Decommissioning Activities Report, Site-Specific Decommissioning Cost Estimate, and Irradiated Fuel Management Plan for Diablo Canyon Power Plant, Units 1 and 2 Project stage: Request L-22-003, Independent Spent Fuel Storage Installation - License Renewal Application for the Diablo Canyon Independent Spent Fuel Storage Installation2022-03-0909 March 2022 Independent Spent Fuel Storage Installation - License Renewal Application for the Diablo Canyon Independent Spent Fuel Storage Installation Project stage: Request DCL-22-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22022-03-30030 March 2022 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 Project stage: Request ML22053A2612022-06-17017 June 2022 FRN - Post-Shutdown Decommissioning Activities Report (PSDAR) Public Meeting (EPIDs L-2019-LRL-0004, L-2019-LRL-0005, and L-2019-LRL-0006) Project stage: Meeting ML22053A2412022-06-17017 June 2022 Letter - Post-Shutdown Decommissioning Activities Report (PSDAR) Public Meeting (EPIDs L-2019-LRL-0004, L-2019-LRL-0005, and L-2019-LRL-0006) Project stage: Meeting PMNS20220679, Post-Shutdown Decommissioning Activities Report Public Meeting2022-06-27027 June 2022 Post-Shutdown Decommissioning Activities Report Public Meeting Project stage: Meeting ML22238A3462022-07-21021 July 2022 Post-Shutdown Decommissioning Activities Report Public Meeting Transcript, Pages 1-132, July 21, 2022 Project stage: Meeting DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 Project stage: Request DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 Project stage: Request DCL-22-039, Irradiated Fuel Management Plan, Revision 12022-10-12012 October 2022 Irradiated Fuel Management Plan, Revision 1 Project stage: Request DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 Project stage: Request ML23122A2362023-06-20020 June 2023 Review of the Post-Shutdown Decommissioning Activities Report Project stage: Approval 2022-10-12 |
ML22178A085 | |
Person / Time | |
---|---|
Site: | Diablo Canyon |
Issue date: | 06/27/2022 |
From: | Office of Nuclear Reactor Regulation |
To: | |
References | |
PMNS20220679 | |
Download: ML22178A085 (4) | |
Similar Documents at Diablo Canyon | |
---|---|
Category:Meeting Notice
MONTHYEARML24305A1162024-10-31031 October 2024
[Table view]Public Meeting to Receive Comments on the Draft Supplemental Environmental Impact Statement for the License Renewal of Diablo Canyon Units 1 and 2 ML24305A1182024-10-31031 October 2024 Public Meeting to Receive Comments on the Draft Supplemental Environmental Impact Statement for the License Renewal of Diablo Canyon Units 1 and 2 PMNS20240696, Notice of Meeting Between Petitioners and the U.S. Nuclear Regulatory Commission (NRC) Petition Review Board (PRB) Regarding a Title 10 of the Code of Federal Regulations (10 CFR) 2.206 Petition Submitted on March 4, 2024 (L-2024-CRS-002024-07-16016 July 2024 Notice of Meeting Between Petitioners and the U.S. Nuclear Regulatory Commission (NRC) Petition Review Board (PRB) Regarding a Title 10 of the Code of Federal Regulations (10 CFR) 2.206 Petition Submitted on March 4, 2024 (L-2024-CRS-0000) PMNS20240534, Meeting Between the U.S. Nuclear Regulatory Commission Petition Review Board and the San Luis Obispo Mothers for Peace and Friends of the Earth Regarding a 2.206 Petition Submitted on September 14, 20232024-04-19019 April 2024 Meeting Between the U.S. Nuclear Regulatory Commission Petition Review Board and the San Luis Obispo Mothers for Peace and Friends of the Earth Regarding a 2.206 Petition Submitted on September 14, 2023 PMNS20240210, Closed Presubmittal Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 22024-02-15015 February 2024 Closed Presubmittal Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 PMNS20240064, Environmental Scoping Virtual Public Meeting for the Diablo Canyon License Renewal Application2024-01-30030 January 2024 Environmental Scoping Virtual Public Meeting for the Diablo Canyon License Renewal Application PMNS20240065, Environmental Scoping Public Meeting for the Diablo Canyon License Renewal Application2024-01-22022 January 2024 Environmental Scoping Public Meeting for the Diablo Canyon License Renewal Application PMNS20230992, Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 22023-09-0606 September 2023 Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML23165A2172023-06-14014 June 2023 Pre-submittal Teleconference with Pacific Gas and Electric Company Regarding a Planned License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 PMNS20230169, Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 22023-02-22022 February 2023 Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 PMNS20221204, Public Meeting for License Renewal Application - Diablo Canyon Power Plant, Units 1 and 22022-12-0505 December 2022 Public Meeting for License Renewal Application - Diablo Canyon Power Plant, Units 1 and 2 PMNS20220933, Closed Meeting with Pacific Gas and Electric Company Regarding Planned Security Plan Changes for Diablo Canyon Nuclear Power Plant, Units 1 and 22022-09-0707 September 2022 Closed Meeting with Pacific Gas and Electric Company Regarding Planned Security Plan Changes for Diablo Canyon Nuclear Power Plant, Units 1 and 2 PMNS20220679, Post-Shutdown Decommissioning Activities Report Public Meeting2022-06-27027 June 2022 Post-Shutdown Decommissioning Activities Report Public Meeting PMNS20220467, Public Webinar to Discuss the Nuclear Regulatory Commissions 2021 Annual Assessment of Safety Performance at Region IV Plants2022-05-0303 May 2022 Public Webinar to Discuss the Nuclear Regulatory Commissions 2021 Annual Assessment of Safety Performance at Region IV Plants PMNS20220398, Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 22022-04-13013 April 2022 Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML21224A2362021-08-12012 August 2021 Pre-submittal Teleconference with Pacific Gas and Electric Company Regarding a Post-Shutdown Emergency Plan License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 PMNS20210563, Public Webinar to Discuss the NRCs 2020 Annual Assessment of Safety Performance at Arkansas Nuclear One, Columbia, Comanche Peak, Cooper, Diablo Canyon, Palo Verde, River Bend Station, South Texas Project, Waterford, and Wolf Creek2021-04-29029 April 2021 Public Webinar to Discuss the NRCs 2020 Annual Assessment of Safety Performance at Arkansas Nuclear One, Columbia, Comanche Peak, Cooper, Diablo Canyon, Palo Verde, River Bend Station, South Texas Project, Waterford, and Wolf Creek ML21006A2042021-01-0606 January 2021 Notice of Pre-Application Meeting - PG&E to Discuss Upcoming Submittal of the Application for Renewal of the Diablo Canyon Independent Spent Fuel Storage Installation License ML20328A2102020-11-0606 November 2020 Presubmittal Teleconference with Pacific Gas and Electric Company Regarding a Permanently Defueled Technical Specification License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML20170B1872020-06-19019 June 2020 Public Webinar to Discuss the Nrc'S Assessment of Safety Performance at Region IV Plants for 2019 ML18298A0762018-10-26026 October 2018 Notice of Forthcoming Closed Meeting with Pacific Gas and Electric Company to Discuss Security-Related Information for Diablo Canyon Power Plant, Units 1 and 2 ML17283A0892017-10-10010 October 2017 Notice of Forthcoming Closed Meeting with Pacific Gas and Electric Company to Discuss Security-Related Information for Diablo Canyon Power Plant, Units 1 and 2 (CAC Nos. MG0255 and MG0256; EPID L-2017-LRM-0019) ML16357A0862016-12-22022 December 2016 Forthcoming Closed Meeting with Pacific Gas and Electric Company to Discuss the Proposed Change to the Defensive Strategy and 10 CFR 50.54(P) Documentation for Diablo Canyon Power Plant ML16119A5002016-04-29029 April 2016 Notice of Forthcoming Closed Meeting with Pacific Gas & Electric Company to Discuss Proposed Change to Defensive Strategy and 10 CFR 50.54(p) Documentation for Reduction in Minimum Staffing Requirements at Diablo Canyon ML15233A4912015-09-0101 September 2015 August 5, 2015, Public Scoping Meetings for the Environmental Review of the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Application ML15152A2562015-06-0101 June 2015 Meeting Notice with Public Outreach and Pacific Gas & Electric (Pg&E) to Discuss the Current Operating Performance for Diablo Canyon Power Plant for the Period January 1 - December 31, 2014 ML14363A5542014-12-29029 December 2014 Regulatory Conference with Diablo Canyon Nuclear Power Plant ML14057A2002014-02-26026 February 2014 Notice of Forthcoming Meeting with Pacific Gas and Electric Company Regarding the Digital Replacement of the Process Protection System (TAC Nos. ME7522 and ME7523) ML14043A2032014-02-19019 February 2014 Federal Register Notice Regarding the 612th ACRS Meeting, March 6-8, 2014 ML13339A9612013-12-0505 December 2013 Public Meeting Notice ML13312A6462013-11-25025 November 2013 Meeting Notice with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13290A2272013-10-18018 October 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13273A4392013-09-30030 September 2013 Meeting Notice with the Pacific Gas and Electric Company to Discuss the Current Operating Performance for the Diablo Canyon Power Plant ML13282A6202013-09-24024 September 2013 Cancellation Notice of 10/23/13 Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13263A1922013-09-24024 September 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13260A0052013-09-18018 September 2013 10/2/13 Notice of Pre-Application Meeting with Pacific Gas and Electric Company to Discuss Upcoming Structural Weld Overlay Relief Request to Use an Alternative to Disposition Detected Laminar Indications at Diablo Canyon, Unit 2 ML13246A4262013-09-0505 September 2013 Notice of Meeting to Discuss Amendment Request to Adopt Technical Specifications Task Force TSTF-505, Provide Risk-Informed Extended Completion Times, RITSTF Initiative 4B at Diablo Canyon, Units 1 and 2 ML13246A4072013-09-0505 September 2013 9/25/13 Notice of Forthcoming Pre-Application Meeting to Discuss Emergency Core Cooling System Evaluations for License Amendment Request at Diablo Canyon, Units 1 and 2 ML13246A4162013-09-0505 September 2013 9/24/13 - Notice of Pre-Application Meeting to Discuss License Amendment Request for Technical Specification 3.8.1 Diesel Generator Surveillance Requirements at Diablo Canyon, Units 1 and 2 ML13246A2622013-09-0404 September 2013 9/18/13 Notice of Forthcoming Closed Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13179A0622013-07-0909 July 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13163A0242013-06-12012 June 2013 6/26/13 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13126A0872013-05-0707 May 2013 Notice of Forthcoming 5/29/13 Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13074A1182013-03-15015 March 2013 3/27/13 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13052A5512013-02-21021 February 2013 Preapplication Meeting with Pacific Gas and Electric, License Amendment Request to Adopt NFPA-805 Performance-Based Standard for Fire Protection for LWR Generating Plants, at Diablo Canyon, Units 1 and 2 ML13028A2022013-02-0404 February 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13030A2462013-01-30030 January 2013 2/12/13 Forthcoming Preapplication Meeting with Pacific Gas and Electric Company to Discuss License Amendment Requests for Degraded Voltage Protection and Control Room Dose Analysis of Record at Diablo Canyon, Units 1 and 2 ML12354A5392012-12-20020 December 2012 1/24/2013 - Notice of Meeting with Pacific Gas and Electric to Discuss Diablo Canyon, Units 1 and 2 License Amendment Request to Revise FSAR Update Related to Delayed Access Offsite Power Circuit to Conform with GDC 17 ML12355A1382012-12-20020 December 2012 1/24/2013 - Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML12348A1082012-12-18018 December 2012 Notice of 1/15/2013 Preapplication Meeting with Pacific Gas and Electric Company to Discuss License Amendment Request to Revise Diesel Generator Surveillance Requirements for Diablo Canyon, Units 1 and 2 2024-07-16 Category:Meeting Agenda MONTHYEARML24305A1162024-10-31031 October 2024
[Table view]Public Meeting to Receive Comments on the Draft Supplemental Environmental Impact Statement for the License Renewal of Diablo Canyon Units 1 and 2 ML24305A1182024-10-31031 October 2024 Public Meeting to Receive Comments on the Draft Supplemental Environmental Impact Statement for the License Renewal of Diablo Canyon Units 1 and 2 ML24269A2132024-10-10010 October 2024 End-of-Cycle Meeting Presentation - Oct. 2024 PMNS20240696, Notice of Meeting Between Petitioners and the U.S. Nuclear Regulatory Commission (NRC) Petition Review Board (PRB) Regarding a Title 10 of the Code of Federal Regulations (10 CFR) 2.206 Petition Submitted on March 4, 2024 (L-2024-CRS-002024-07-16016 July 2024 Notice of Meeting Between Petitioners and the U.S. Nuclear Regulatory Commission (NRC) Petition Review Board (PRB) Regarding a Title 10 of the Code of Federal Regulations (10 CFR) 2.206 Petition Submitted on March 4, 2024 (L-2024-CRS-0000) PMNS20240534, Meeting Between the U.S. Nuclear Regulatory Commission Petition Review Board and the San Luis Obispo Mothers for Peace and Friends of the Earth Regarding a 2.206 Petition Submitted on September 14, 20232024-04-19019 April 2024 Meeting Between the U.S. Nuclear Regulatory Commission Petition Review Board and the San Luis Obispo Mothers for Peace and Friends of the Earth Regarding a 2.206 Petition Submitted on September 14, 2023 PMNS20240210, Closed Presubmittal Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 22024-02-15015 February 2024 Closed Presubmittal Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 PMNS20240064, Environmental Scoping Virtual Public Meeting for the Diablo Canyon License Renewal Application2024-01-30030 January 2024 Environmental Scoping Virtual Public Meeting for the Diablo Canyon License Renewal Application ML24030A4672024-01-30030 January 2024 Environmental Scoping Meeting for the Diablo Canyon License Renewal Application - February 1 Meeting Slides PMNS20240065, Environmental Scoping Public Meeting for the Diablo Canyon License Renewal Application2024-01-22022 January 2024 Environmental Scoping Public Meeting for the Diablo Canyon License Renewal Application PMNS20230992, Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 22023-09-0606 September 2023 Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML23165A2172023-06-14014 June 2023 Pre-submittal Teleconference with Pacific Gas and Electric Company Regarding a Planned License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML23143A2262023-06-0101 June 2023 May 3, 2023, Summary of Public Meeting to Discuss the End of Cycle Assessment and Pre-Submittal License Renewal Process Overview for Diablo Canyon Power Plant, Units 1 and 2 PMNS20230169, Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 22023-02-22022 February 2023 Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML23004A1492023-01-0606 January 2023 December 8, 2022 Public Meeting Summary of Pre-Submittal Meeting PMNS20221204, Public Meeting for License Renewal Application - Diablo Canyon Power Plant, Units 1 and 22022-12-0505 December 2022 Public Meeting for License Renewal Application - Diablo Canyon Power Plant, Units 1 and 2 ML22339A1022022-12-0505 December 2022 Pg_E Presentation for NRC Public Meeting PMNS20220933, Closed Meeting with Pacific Gas and Electric Company Regarding Planned Security Plan Changes for Diablo Canyon Nuclear Power Plant, Units 1 and 22022-09-0707 September 2022 Closed Meeting with Pacific Gas and Electric Company Regarding Planned Security Plan Changes for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML22200A0712022-07-21021 July 2022 Post-Shutdown Decommissioning Activities Report Public Meeting Slides - July 21, 2022 PMNS20220679, Post-Shutdown Decommissioning Activities Report Public Meeting2022-06-27027 June 2022 Post-Shutdown Decommissioning Activities Report Public Meeting PMNS20220467, Public Webinar to Discuss the Nuclear Regulatory Commissions 2021 Annual Assessment of Safety Performance at Region IV Plants2022-05-0303 May 2022 Public Webinar to Discuss the Nuclear Regulatory Commissions 2021 Annual Assessment of Safety Performance at Region IV Plants PMNS20220398, Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 22022-04-13013 April 2022 Closed Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML21224A2362021-08-12012 August 2021 Pre-submittal Teleconference with Pacific Gas and Electric Company Regarding a Post-Shutdown Emergency Plan License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 PMNS20210563, Public Webinar to Discuss the NRCs 2020 Annual Assessment of Safety Performance at Arkansas Nuclear One, Columbia, Comanche Peak, Cooper, Diablo Canyon, Palo Verde, River Bend Station, South Texas Project, Waterford, and Wolf Creek2021-04-29029 April 2021 Public Webinar to Discuss the NRCs 2020 Annual Assessment of Safety Performance at Arkansas Nuclear One, Columbia, Comanche Peak, Cooper, Diablo Canyon, Palo Verde, River Bend Station, South Texas Project, Waterford, and Wolf Creek ML21060B1862021-03-0101 March 2021 Enclosure 2 - 1-26-21 Diablo Canyon Renewal Pre-app Meeting Agenda ML21006A2042021-01-0606 January 2021 Notice of Pre-Application Meeting - PG&E to Discuss Upcoming Submittal of the Application for Renewal of the Diablo Canyon Independent Spent Fuel Storage Installation License ML20328A2102020-11-0606 November 2020 Presubmittal Teleconference with Pacific Gas and Electric Company Regarding a Permanently Defueled Technical Specification License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML20170B1872020-06-19019 June 2020 Public Webinar to Discuss the Nrc'S Assessment of Safety Performance at Region IV Plants for 2019 ML16119A5002016-04-29029 April 2016 Notice of Forthcoming Closed Meeting with Pacific Gas & Electric Company to Discuss Proposed Change to Defensive Strategy and 10 CFR 50.54(p) Documentation for Reduction in Minimum Staffing Requirements at Diablo Canyon ML14363A5542014-12-29029 December 2014 Regulatory Conference with Diablo Canyon Nuclear Power Plant ML14057A2002014-02-26026 February 2014 Notice of Forthcoming Meeting with Pacific Gas and Electric Company Regarding the Digital Replacement of the Process Protection System (TAC Nos. ME7522 and ME7523) ML14043A2032014-02-19019 February 2014 Federal Register Notice Regarding the 612th ACRS Meeting, March 6-8, 2014 ML13312A6462013-11-25025 November 2013 Meeting Notice with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13290A2272013-10-18018 October 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13263A1922013-09-24024 September 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13282A6202013-09-24024 September 2013 Cancellation Notice of 10/23/13 Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13260A0052013-09-18018 September 2013 10/2/13 Notice of Pre-Application Meeting with Pacific Gas and Electric Company to Discuss Upcoming Structural Weld Overlay Relief Request to Use an Alternative to Disposition Detected Laminar Indications at Diablo Canyon, Unit 2 ML13246A4162013-09-0505 September 2013 9/24/13 - Notice of Pre-Application Meeting to Discuss License Amendment Request for Technical Specification 3.8.1 Diesel Generator Surveillance Requirements at Diablo Canyon, Units 1 and 2 ML13246A4072013-09-0505 September 2013 9/25/13 Notice of Forthcoming Pre-Application Meeting to Discuss Emergency Core Cooling System Evaluations for License Amendment Request at Diablo Canyon, Units 1 and 2 ML13246A4262013-09-0505 September 2013 Notice of Meeting to Discuss Amendment Request to Adopt Technical Specifications Task Force TSTF-505, Provide Risk-Informed Extended Completion Times, RITSTF Initiative 4B at Diablo Canyon, Units 1 and 2 ML13246A2622013-09-0404 September 2013 9/18/13 Notice of Forthcoming Closed Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13179A0622013-07-0909 July 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13163A0242013-06-12012 June 2013 6/26/13 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13126A0872013-05-0707 May 2013 Notice of Forthcoming 5/29/13 Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13074A1182013-03-15015 March 2013 3/27/13 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13052A5512013-02-21021 February 2013 Preapplication Meeting with Pacific Gas and Electric, License Amendment Request to Adopt NFPA-805 Performance-Based Standard for Fire Protection for LWR Generating Plants, at Diablo Canyon, Units 1 and 2 ML13028A2022013-02-0404 February 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13030A2462013-01-30030 January 2013 2/12/13 Forthcoming Preapplication Meeting with Pacific Gas and Electric Company to Discuss License Amendment Requests for Degraded Voltage Protection and Control Room Dose Analysis of Record at Diablo Canyon, Units 1 and 2 ML13024A4052013-01-24024 January 2013 Licensee Slides from 1/24/13 Meeting to Discuss Offsite Power ML12355A1382012-12-20020 December 2012 1/24/2013 - Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML12354A5392012-12-20020 December 2012 1/24/2013 - Notice of Meeting with Pacific Gas and Electric to Discuss Diablo Canyon, Units 1 and 2 License Amendment Request to Revise FSAR Update Related to Delayed Access Offsite Power Circuit to Conform with GDC 17 2024-07-16 |
Text
June 27, 2022
Title:
Diablo Canyon Nuclear Power Plant, Units 1 and 2, Post-Shutdown Decommissioning Activities Report Public Meeting (EPID L-2019-LRL-0004, EPID L-2019-LRL-0005, and EPID L-2019-LRL-0006)
Date(s) and Time(s):July 21, 2022, 06:00 PM to 09:00 PM PT
Location: San Luis Obispo County Government Building 1055 Monterey Street San Luis Obispo, CA
Category: This is a Comment-Gathering Meeting. The purpose of this meeting is for NRC staff to meet directly with individuals to receive comments from participants on specific NRC decisions and actions to ensure that NRC staff understands their views and concerns.
Purpose:
The purpose of this meeting is to receive public comments on the Diablo Canyon Nuclear Power Plant, Units 1 and 2 (Diablo Canyon) post-shutdown decommissioning activities report (PSDAR), including the site-specific decommissioning cost estimate (SSDCE), and the irradiated fuel management plan (IFMP). The Diablo Canyon PSDAR, IFMP, and notification of changes are available in the U.S. Nuclear Regulatory Commission's (NRCs)
Agencywide Documents Access and Management System (ADAMS) under Accession Nos. ML19338F173, ML19338F260, and ML21293A120, respectively. The publicly available version of the SSDCE is available in ADAMS under ML19345D344 and ML19345D345. A notice of receipt, availability, the purpose of the public meeting, and request for comments was published in the Federal Register on June 23, 2022 (87 FR 37533).
Contact:
Samson Lee Marlayna Doell 301-415-3168 301-415-3178 Samson.Lee@nrc.gov Marlayna.Doell@nrc.gov
Participants:
NRC External Office of Nuclear Reactor Regulation Pacific Gas and Electric Office of Nuclear Material Safety and Safeguards Region IV
Teleconference: Bridge Number Conference ID Pass Code (301) 576-2978 661493523#
Webinar: URL Meeting Number Password https://teams.microsoft.com/l/meetup-na na join/19%
3ameeting_NjljZDliOWEtNDUzOC00NTFlL Tk3NWEtODhhOWU4YTQzMDNk%
40thread.v2/0?context=%7b%22Tid%22%
3a%22e8d01475-c3b5-436a-a065-5def4c64f52e%22%2c%22Oid%22%3a%
22b266920c-d86d-4312-9099-b7f386561b36%22%7d
Docket No: 05000275 05000323 The NRC provides reasonable accommodations to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in a meeting or need a meeting notice or the transcript or other information from a meeting in another format (e.g. braille, large print), please contact Anne Silk, NRC Reasonable Accommodations Coordinator, at Anne.Silk@nrc.gov or call directly at 301-287-0745.
Determinations on requests for reasonable accommodation will be made on a case-by-case basis. Ten (10) days advance notice is requested to try to ensure availability; however, every effort will be made to address a request for reasonable accommodations with less notice.
PUBLIC MEETING AGENDA
Diablo Canyon Nuclear Power Plant, Units 1 and 2, Post-Shutdown Decommissioning Activities Report Public Meeting (EPID L-2019-LRL-0004, EPID L-2019-LRL-0005, and EPID L-2019-LRL-0006)
July 21, 2022, 06:00 PM to 09:00 PM PT
San Luis Obispo County Government Building 1055 Monterey Street San Luis Obispo, CA ADAMS Accession Number: ML22178A085
Distribution:
Office NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA NRR/DORL/LPL4/BC NRR/DORL/LPL4/PM Name SLee PBlechman JDixon-Herrity SLee Date 06/23/2022 06/23/2022 06/23/2022 06/27/2022 OFFICIAL RECORD COPY
Link to meeting details:https://www.nrc.gov/pmns/mtg?do=details&Code=20220679
Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" 86 FR 14964, March 19, 2021 ADAMS No. ML21050A046 https://www.nrc.gov/reading-rm/doc-collections/commission/policy/index.html