MEMORANDUM TO:
FROM:
SUBJECT:
DATE & TIME:
LOCATION:
PURPOSE:
CATEGORY 1:*
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 18, 2013 Michael 1. Markley, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Jennie K. Rankin, Project Manager ~
Plant Licensing Branch IV
~,~0 V"
Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FORTHCOMING MEETING WITH PACIFIC GAS AND ELECTRIC COMPANY (TAC NO. MF2675)
Wednesday, October 2, 2013 1 :00 p.m. - 4:00 p.m. EDT U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room 07B04 Rockville, Maryland Pacific Gas and Electric Company (PG&E) will meet with the U.S. Nuclear Regulatory Commission (NRC) staff to discuss its plans to submit a request to use an alternative to disposition detected laminar indications at Diablo Canyon Power Plant (DCPP), Unit 2. The NRC recently approved a similar relief request, REP-1 U2, Revision 2, for the fuel cycle following the 2013 refueling outage for DCPP, Unit 2 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13232A308).
This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
- Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" (67 FR 36920), May 28, 2002.
M. Markley PARTICIPANTS:
- 2 Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).
NRC PG&E J. Tsao, NRR P. Soenen, et al.
J. Collins, NRR S. Cumblidge, NRR T. Lupoid, NRR J. Rankin, NRR, et al.
Interested members of the public can participate in this meeting via a toll-free audio teleconference. Please call or email the meeting contact listed below before Tuesday, October 1, 2013, 4:30 p.m. EDT to get the telephone number and the pass code.
MEETING CONTACTS:
Jennie Rankin, NRR 301-415-1530 jennivine.rankin@nrc.gov The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need a reasonable accommodation to participate in a meeting, or need a meeting notice or a transcript or other information from a meeting in another format (e.g., Braille, large print),
please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.html.
Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same web address above.
Docket No. 50-323
Enclosure:
Agenda cc w/encl: Distribution via Listserv
AGENDA FORTHCOMING MEETING WITH PACIFIC GAS AND ELECTRIC COMPANY REGARDING DIABLO CANYON POWER PLANT, UNIT 2 ALTERNATIVE TO DISPOSITION LAMINAR INDICATIONS Wednesday. October 2. 2013 1:00 p.m. to 4:00 p.m. EDT (10:00 a.m. to 1:00 p.m. PDT)
I.
Opening comments and introductions II.
Pacific Gas and Electric Company will make presentations on the following topics:
A.
Root cause evaluation results.
B.
Summary of the finite element analysis demonstrating that the structural integrity of the welds with laminar flaws will be maintained and that the welds satisfy the American Society of Mechanical Engineers Boiler and Pressure Vessel Code.
C.
Improvements implemented in the licensee's ultrasonic examination procedure for the pressurizer nozzles.
D.
General content and schedule for submittal of relief request.
III.
NRC staff questions and discussion IV.
Questions from the public V.
Adjourn Enclosure
M. Markley PARTICIPANTS:
- 2 Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).
NRC PG&E J. Tsao, NRR P. Soenen,etal.
J. Collins, NRR S. Cumblidge, NRR T. Lupoid, NRR J. Rankin, NRR, et al.
Interested members of the public can participate in this meeting via a toll-free audio teleconference. Please call or email the meeting contact listed below before Tuesday, October 1, 2013, 4:30 p.m. EDT to get the telephone number and the pass code.
MEETING CONTACTS:
Jennie Rankin, NRR 301-415-1530 jennivine.rankin@nrc.gov The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need a reasonable accommodation to participate in a meeting, or need a meeting notice or a transcript or other information from a meeting in another format (e.g., Braille, large print),
please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.html.
Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same web address above.
Docket No. 50-323
Enclosure:
Agenda cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrLAJBurkhardt Resource TLupold, NRRlDE/EPNB LPL4 Reading RidsOgcRp Resource WMaier, RIV RidsAcrsAcnw_MailCTR Resource RidsOpaMaii Resource TWertz, NRR RidsNrrDorl Resource RidsRgn4MailCenter Resource DRich, EDO RIV RidsNrrDorlLpl4 Resource JTsao, NRR/DE/EPNB VDricks, OPA RIV RidsNrrDeEpnb Resource JColiins, NRR/DE/EPNB OWFN Reception RidsNrrPMDiabloCanyon Resource SCumblidge, NRR/DE/EPNB TWFN Reception ADAMS Accession No. ML13260A005 NRR/DORLlLPL4/PM