UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 21, 2013 MEMORANDUM TO: Michael T. Markley, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing FROM:

Office of Nuclear Reactor Regulation James T. Polickoski, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing r ~ -

Office of Nuclear Reactor Regulation

SUBJECT:

FORTHCOMING MEETING WITH PACIFIC GAS AND ELECTRIC COMPANY (TAC NOS. MF0687 AND MF0688)

DATE & TIME: Thursday, March 7,2013 1 :00 p.m. - 3:00 p.m. EST LOCATION: U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room 0-03B04 Rockville, Maryland PURPOSE: Pacific Gas and Electric Company (PG&E) will meet with the U.S. Nuclear Regulatory Commission (NRC) staff to discuss its updated plans for the submittal of a license amendment request to revise fire protection requirements for Diablo Canyon Power Plant, Units 1 and 2. The planned revisions are intended to adopt the risk-informed, performance-based alternative described in National Fire Protection Association Standard, NFPA 805, as permitted by paragraph 50.38(c) of Title 10 of the Code of Federal Regulations.

CATEGORY 1:* This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned .

  • Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" (67 FR 36920), May 28, 2002.

M. Markley -2 PARTICIPANTS: Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC PG&E D. Harrison, NRR P. Bemis A. Klein, NRR T. Stanton R Gallucci, NRR M. Richardson J. Polickoski, NRR, et al. R Baradaran, et al.

Interested members of the public can participate in this meeting via a toll-free audio teleconference. Please call or email the meeting contact listed below before Wednesday, March 6. 2013, 4:30 p.m. EST to get the telephone number and the pass code.

MEETING CONTACTS: Jim Polickoski, NRR 301-415-5430 james. polickoski@nrc.gov The NRC provides reasonable accommodation to individuals with disabilities where appropriate.

If you need a reasonable accommodation to participate in a meeting, or need a meeting notice or a transcript or other information from a meeting in another format (e.g., Braille, large print),

please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involvellistserver/plants-by-region.html.

Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same web address above.

Docket Nos. 50-275 and 50-323

Enclosure:

Agenda cc w/encl: Distribution via Listserv

AGENDA FORTHCOMING MEETING WITH PACIFIC GAS AND ELECTRIC COMPANY REGARDING DIABLO CANYON POWER PLANT, UNITS 1 AND 2 ADOPTION OF NFPA 805 RISK-INFORMED FIRE PROTECTION REQUIREMENTS Thursday, March 7, 2013 1:00 p.m. to 3:00 p.m. EST (10:00 a.m. to 12:00 p.m. PST)

I. Opening comments and introductions II. Pacific Gas and Electric Company will make presentations on the following topics:

A. Status update on the development of its license amendment request B. Probabilistic Risk Assessment update review relative to Regulatory Guide 1.200, Revision 2 C. Updates relative to the Peer Review findings and Fragilities plan D. Integration of its Senior Seismic Hazard Analysis Committee Level 3 findings III. NRC Staff questions and discussion IV. Questions from the public V. Adjourn Enclosure

ML13052A551 *via email

  • OFFICE NRRlDORULPL4/PM NRRlDORULPL4/LA NRRlDORULPL4/BC NRRlDORULPL4/PM ~

NAME JPolickoski JBurkhardt* MMarkley JPolickoski DATE 2121113 2/21/13 2/21/13 2/21/13 II