Letter Sequence Other |
---|
|
|
MONTHYEARML21287A0382021-10-14014 October 2021 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of Requests for Relief from Certain Inservice Testing Requirements Project stage: Acceptance Review ML22096A3162022-04-12012 April 2022 Proposed Alternative Request RP-1 Regarding Digital Instrumentation for Inservice Testing Project stage: Other 2021-10-14
[Table View] |
|
---|
Category:Letter
MONTHYEARL-24-233, Proposed Alternative Request to Defer ASME Code Section XI Inservice Inspection Examinations for Pressurizer and Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles2024-12-18018 December 2024 Proposed Alternative Request to Defer ASME Code Section XI Inservice Inspection Examinations for Pressurizer and Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles L-24-259, ISFSI; Davis-Besse Nuclear Power Station, Unit No. 1 ISFSI & Perry Nuclear Power Plant, Unit No. 1 ISFSI - Triennial ISFSI Decommissioning Funding Plan2024-12-17017 December 2024 ISFSI; Davis-Besse Nuclear Power Station, Unit No. 1 ISFSI & Perry Nuclear Power Plant, Unit No. 1 ISFSI - Triennial ISFSI Decommissioning Funding Plan 05000346/LER-2021-001-02, Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground2024-12-0909 December 2024 Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground IR 05000346/20240102024-12-0606 December 2024 Comprehensive Engineering Team Inspection Report 05000346/2024010 L-24-227, Response to Request for Additional Information for Relief Request RR-A 12024-11-20020 November 2024 Response to Request for Additional Information for Relief Request RR-A 1 IR 05000346/20244022024-11-19019 November 2024 Material Control and Accounting Program Inspection Report 05000346/2024402 (Public) IR 05000346/20240032024-11-14014 November 2024 Integrated Inspection Report 05000346/2024003 ML24303A3282024-10-29029 October 2024 Information Request for the Cyber Security Baseline Inspection Identification to Perform Inspection ML24281A0662024-10-0404 October 2024 EN 57363 - MPR Associates, Inc. Report in Accordance with 10 CFR Part 21 on Incomplete Dedication of Contactors Supplied as Basic Components IR 05000346/20244032024-09-27027 September 2024 Security Baseline Inspection Report 05000346/2024403 ML24269A0552024-09-25025 September 2024 Submittal of the Updated Final Safety Analysis Report, Revision 35 05000346/LER-2021-001-01, Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground2024-09-19019 September 2024 Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A2382024-09-16016 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24255A8032024-09-11011 September 2024 Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1602024-09-0505 September 2024 Information Request to Support Upcoming Material Control and Accounting Inspection at Davis-Besse Nuclear Power Station L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000346/20240052024-08-22022 August 2024 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification L-24-032, Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report2024-07-15015 July 2024 Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report L-24-063, License Amendment Request to Remove the Table of Contents from the Technical Specifications2024-07-0808 July 2024 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-24-024, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-19019 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-214, Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2024-06-0505 June 2024 Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements L-24-019, Unit No.1 - Report of Facility Changes, Tests, and Experiments2024-05-22022 May 2024 Unit No.1 - Report of Facility Changes, Tests, and Experiments ML24142A3532024-05-21021 May 2024 Station—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-111, Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-05-15015 May 2024 Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations L-24-072, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 20232024-05-15015 May 2024 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 2023 L-24-031, Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage2024-05-14014 May 2024 Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 L-24-069, Occupational Radiation Exposure Report for Year 20232024-04-30030 April 2024 Occupational Radiation Exposure Report for Year 2023 L-24-018, Submittal of Core Operating Limits Report, Cycle 24, Revision 02024-04-16016 April 2024 Submittal of Core Operating Limits Report, Cycle 24, Revision 0 ML24089A2582024-04-0101 April 2024 Request for Information for the NRC Quuadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000346/2024010 L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage ML24036A3472024-03-0707 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0076 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations IR 05000346/20230062024-02-28028 February 2024 Re-Issue Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) ML24057A3362024-02-28028 February 2024 Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station 2024-09-06
[Table view] Category:Safety Evaluation
MONTHYEARML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML22269A3582022-11-15015 November 2022 Issuance of Amendment No. 305 Revising the Emergency Plan ML22277A6012022-10-14014 October 2022 Issuance of Amendment No. 304 Revising the Design Basis for the Shield Building Containment Structure ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML22147A1492022-06-0202 June 2022 Relief Request RP-3 Regarding Fuel Oil Transfer Pump Testing ML22136A1092022-05-24024 May 2022 Proposed Alternative Request RP-2 Regarding the Inservice Testing of Certain Pumps ML22118B0382022-05-0505 May 2022 Proposed Alternative Request RP-4 Regarding the Inservice Testing of High-Pressure Injection Pumps ML22096A3162022-04-12012 April 2022 Proposed Alternative Request RP-1 Regarding Digital Instrumentation for Inservice Testing ML22082A2532022-03-29029 March 2022 Correction Letter - Issuance of Authorization of Proposed Alternative to Use ASME OM Code Case OMN-27 ML22012A2972022-01-21021 January 2022 Proposed Alternative to Use ASME OM Code Case OMN-27 ML21075A1132021-04-16016 April 2021 Issuance of Amendment Nos. 311, 200, and 302 to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, Into the Technical Specifications ML20280A8272020-11-0303 November 2020 Issuance of Amendment No. 301 to Relocate Specific Surveillance Frequencies to a Licensee-Controlled Program ML20279A4402020-10-0808 October 2020 Energy Harbor Fleet-Beaver Valley Power Station; Davis-Besse Nuclear Power Station, and Perry Nuclear Power Plant - Request to Use a Provision of a Later Edition of the ASME Engineers Boiler and Pressure Vessel Code, Section XI ML20213C7262020-08-24024 August 2020 Issuance of Amendment No. 300 to Revise the Containment Leakage Rate Testing Program ML19305B1312019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Enclosure 6, Non-Proprietary Safety Evaluation, Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML19100A3062019-06-21021 June 2019 Issuance of Amendment No. 298 to Adopt National Fire Protection Association Standard 805 ML19028A0302019-04-11011 April 2019 FENOC - Beaver Valley Power Station, Unit 1 & 2; Davis-Besse Nuclear Power Station Unit 1; and Perry Nuclear Power Plant Unit 1 - Approval of Certified Fuel Handler Training and Retraining Program ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18004A1222018-01-22022 January 2018 FENOC-Beaver Valley, Davis-Besse, and Perry - Alternative for the Use of ASME Code Case N-513-4 (CAC Nos. MG0120, MG0121, MG0122, and MG0123; EPID L-2017-LLR-0088) ML17270A1122017-10-19019 October 2017 Issuance of Amendment Revising Technical Specification Requirements for Ultrasonic Flow Meter Outage Time (CAC No. MF9080; EPID L-2017-LLA-0167) ML17256B1902017-10-12012 October 2017 Time-Limited Aging Analysis for the Reactor Vessel Internals Loss of Ductility at 60 Years ML17081A5092017-05-11011 May 2017 ISFSI, Davis-Besse ISFSI, Perry Nuclear Power Plant, Perry Nuclear Power Plant ISFSI - Issuance of Amendments Re. Application to Revise Technical Specifications to Adopt TSTF-545 Revision 3 ML17017A3402017-01-31031 January 2017 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-051 and EA-12-049 ML16328A1252017-01-23023 January 2017 Relief from the Requirements of the American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code) (TAC No. MF7780 - MF7783) ML16342C9462017-01-12012 January 2017 Issuance of Amendment Revising Emergency Action Level Scheme ML16298A3492017-01-11011 January 2017 Issuance of Amendment Revising Technical Specification Requirements for the Radioactive Effluent Controls Program ML16040A0842016-06-0707 June 2016 FENOC, Beaver Valley Power Station, Unit Nos. 1 and 2; and Davis-Besse Nuclear Power Station, Unit No. 1 - Issuance of Amendments Revision to Technical Specification 5.3.1, Unit Staff Qualifications ML16083A4812016-04-27027 April 2016 Issuance of Amendment Revising Emergency Diesel Generator Minimum Voltage and Frequency Acceptance Criteria ML15302A0752016-03-0808 March 2016 Issuance of Amendment Revising the Completion Date for Milestone 8 of the Cyber Security Plan ML15251A0462015-10-20020 October 2015 Issuance of Amendment Revising Containment Spray Nozzle Surveillance Requirement ML15211A1612015-10-16016 October 2015 FENOC-Beaver Valley Power Station, Unit No. 1; Beaver Valley Power Station ISFSI, Davis-Besse Nuclear Power Station ISFSI, Perry Nuclear Power Plant, Perry Nuclear Power Plant ISFSI Annual Financial Test for a Parent Company Guarantee ML15239B2932015-10-0909 October 2015 Issuance of Amendment Related to Containment Leakage Rate Testing Program ML15182A1912015-07-16016 July 2015 Annual Financial Test for a Parent Company Guarantee Given by Firstenergy Solutions Corporation and Firstenergy Corporation ML14142A2922014-09-12012 September 2014 BVPS, Unit No. 1, BVPS (ISFSI) Davis-Besse Nuclear Power Station ISFSI, Perry Nuclear Power Plant, Unit 1, and Perry Nuclear Power Plant ISFSI - Annual Financial Test for Firstenergy Nuclear Operating Company Parent Company Guarantee (MF374 ML14030A5742014-03-31031 March 2014 Safety Evaluation Concerning Comprehensive Pump Testing Relief Request (TAC No. MF0756) (L-13-067) ML14023A7662014-03-31031 March 2014 Issuance of Amendment Related to Steam Generator Inventory Change (TAC No. MF0536)(L-13-040) ML14030A5922014-02-10010 February 2014 Safety Evaluation for Relief Requests RR-A1 and RR-B1 ML14002A4442014-02-0505 February 2014 Safety Evaluation for Relief Request RP-3 (TAC No. MF0757)(L-13-076) ML14003A2662014-01-27027 January 2014 Davis-besse Nuclear Power Station, Unit 1, Safety Evaluation for Relief Requests RP-1 and RP-1A ML13210A4672013-08-0101 August 2013 Safety Evaluation for Relief Requests RP-6 and RV-1 ML13121A4042013-05-0808 May 2013 Safety Evaluation in Support of Proposed Alternative Regarding Post-Repair Pressure Testing Requirements ML12221A4132012-10-0202 October 2012 Issuance of Amendments Change of the Name of a Owner Licensee to Firstenergy Nuclear Generation, LLC ML12242A4992012-09-11011 September 2012 Safety Evaluation in Support of 10 CFR 50.55a Requests RP-2 and RP-4 Regarding Inservice Pump Testing ML1210706862012-05-11011 May 2012 Safety Evaluation Regarding the Reactor Coolant System Pressure and Temperature Limits Report, Revision 1 ML1208604472012-04-18018 April 2012 Issuance of Amendment Modification of the Special Visual Inspection Requirement of TS 5.5.8 Steam Generator Program ML1207504812012-04-0909 April 2012 Safety Evaluation in Support of 10 CFR 50.55a Request RR-A35, Proposed Alternative to System Leakage Test Requirements ML1124305562011-09-22022 September 2011 Request for Threshold Determination Under 10 CFR 50.80 - Beaver Valley Power Station, Unit Nos. 1 and 2; Davis-Besse Nuclear Power Station, Unit No. 1; and Perry Nuclear Power Plant, Unit No. 1 ML1118903222011-07-11011 July 2011 Review of the Steam Generator Tube Inspections Performed During Refueling Outage No. 16 in 2010 2024-01-17
[Table view] |
Text
April 12, 2022 Mr. Terry J. Brown Site Vice President Energy Harbor Nuclear Corp.
Mail Stop P-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 PROPOSED ALTERNATIVE REQUEST RP-1 REGARDING DIGITAL INSTRUMENTATION FOR INSERVICE TESTING (EPID L-2021-LLR-0070)
Dear Mr. Brown:
By letter dated September 20, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21263A193), Energy Harbor Nuclear Corp. (the licensee) submitted Request RP-1 in accordance with paragraph 50.55a(z)(1) of Title 10 of the Code of Federal Regulations (10 CFR) for a proposed alternative to certain requirements of 10 CFR 50.55a, Codes and standards, for Davis-Besse Nuclear Power Station, Unit No. 1 (Davis-Besse). The September 20, 2021, letter also submitted Requests RP-2, RP-3, and RP-4, which are being reviewed separately by the U.S. Nuclear Regulatory Commission (NRC) staff. Communications regarding the NRC staffs review of Requests RP-2, RP-3, and RP-4 will be provided though separate correspondence.
The American Society of Mechanical Engineers (ASME), Operation and Maintenance of Nuclear Power Plants, Division 1, Section IST (OM Code), as incorporated by reference in 10 CFR 50.55a, specifies requirements for the inservice testing (IST) of nuclear power plant components. Proposed alternative Request RP-1 would allow the licensee to use digital instruments for certain comprehensive pump testing that do not meet the selection criterion in subparagraph ISTB-3510(b)(2) of the 2017 Edition of the ASME OM Code, as incorporated by reference in 10 CFR 50.55a, for the fifth 10-year IST interval at Davis-Besse.
The regulations in 10 CFR 50.55a(z)(1) states, in part, that alternatives to the requirements in paragraphs (b) through (h) of 10 CFR 50.55a may be authorized by the NRC if the licensee demonstrates that the proposed alternative provides an acceptable level of quality and safety.
The NRC staff has reviewed Request RP-1 and concludes, as set forth in the enclosed safety evaluations, that the licensee has adequately addressed the regulatory requirements set forth in 10 CFR 50.55a(z)(1). Therefore, the NRC staff authorizes the use of proposed alternative Request RP-1 at Davis-Besse for the fifth 10-year IST interval, which is scheduled to begin on September 21, 2022, and end on September 20, 2032.
All other ASME OM Code requirements for which an alternative was not specifically requested and authorized remain applicable.
If you have any questions, please contact Blake Purnell at 301-415-1380 or via e-mail at Blake.Purnell@nrc.gov.
Sincerely, Nancy L. Salgado, Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
Safety Evaluation cc: Listserv Robert F.
Kuntz Digitally signed by Robert F. Kuntz Date: 2022.04.12 09:19:18 -04'00'
ML22096A316 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DEX/EMIB/BC(A)
NAME BPurnell SRohrer ITseng DATE 04/07/2022 04/07/2022 03/25/22 OFFICE NRR/DORL/LPL3/BC NAME NSalgado (RKuntz for)
DATE 04/12/2022
Enclosure SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION PROPOSED ALTERNATIVE REQUEST RP-1 ENERGY HARBOR NUCLEAR CORP.
ENERGY HARBOR NUCLEAR GENERATION LLC DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 DOCKET NO. 50-346
1.0 INTRODUCTION
By letter dated September 20, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21263A193), Energy Harbor Nuclear Corp. (the licensee) submitted Request RP-1 in accordance with paragraph 50.55a(z)(1) of Title 10 of the Code of Federal Regulations (10 CFR) for a proposed alternative to certain requirements of 10 CFR 50.55a, Codes and standards, for Davis-Besse Nuclear Power Station, Unit No. 1 (Davis-Besse). The letter also included three other requests that are being reviewed separately by the U.S. Nuclear Regulatory Commission (NRC) staff. This safety evaluation (SE) is only for Request RP-1.
The American Society of Mechanical Engineers (ASME), Operation and Maintenance of Nuclear Power Plants, Division 1, Section IST (OM Code), as incorporated by reference in 10 CFR 50.55a, specifies requirements for the inservice testing (IST) of nuclear power plant components. Proposed alternative Request RP-1 would allow the licensee to use digital instruments for certain comprehensive pump testing that do not meet the selection criterion in subparagraph ISTB-3510(b)(2) of the 2017 Edition of the ASME OM Code, as incorporated by reference in 10 CFR 50.55a, for the fifth 10-year IST interval at Davis-Besse. Pursuant to 10 CFR 50.55a(z)(1), the licensee requested the proposed alternative on the basis that it provides an acceptable level of quality and safety.
2.0 REGULATORY EVALUATION
The regulations in 10 CFR 50.55a(f)(4) state, in part, that throughout the service life of a boiling or pressurized water-cooled nuclear power facility, pumps and valves that are within the scope of the ASME OM Code must meet the IST requirements (except design and access provisions) set forth in the ASME OM Code and addenda that become effective subsequent to editions and addenda specified in 10 CFR 50.55a(f)(2) and (3) and that are incorporated by reference in 10 CFR 50.55a(a)(1)(iv), to the extent practical within the limitations of design, geometry, and materials of construction of the components.
The regulations in 10 CFR 50.55a(z) state, in part, that alternatives to the requirements in paragraphs (b) through (h) of 10 CFR 50.55a may be authorized by the NRC if the licensee demonstrates that: (1) the proposed alternative provides an acceptable level of quality and safety, or (2) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
3.0 TECHNICAL EVALUATION
3.1 Licensees Request ASME Code Components Affected ASME Code Class 3, Group A, component cooling water pump Nos. P43-1, P43-2, and P43-3.
ASME Code Class 2, Group B, high pressure injection pump Nos. P58-1 and P58-2.
ASME Code Class 3, Group A, service water pump Nos. P3-1, P3-2, and P2-3.
Applicable Code Edition and Requirements The applicable ASME OM Code edition for the fifth 10-year IST program interval at Davis-Besse is the 2017 Edition of ASME OM Code, as incorporated by reference in 10 CFR 50.55a with conditions. Subparagraph ISTB-3510(b)(2) of the ASME OM Code states: Digital instruments shall be selected such that the reference value does not exceed 90% of the calibrated range of the instrument.
=
Reason for Request===
The licensee stated, in part, that:
Plant process computer points may be used as digital instrumentation for inservice testing of pumps. The computer points may be used in lieu of the associated analog indicators in order to meet the ASME OM Code instrument accuracy requirements. In addition to using computer points, temporary digital instruments are also used as measuring and test equipment for pump testing. In some cases, the reference value exceeds 90 percent of the digital instruments calibrated range during comprehensive pump testing.
Proposed Alternative The licensee proposes to select digital instruments to verify the required action levels of the ASME OM Code, Tables ISTB-5121-1, Centrifugal Pump Test Acceptance Criteria, and ISTB-5221-1, Vertical Line Shaft Centrifugal Pump Test Acceptance Criteria, such that the reference value shall not exceed 94 percent of the calibrated range for comprehensive pump testing. The licensee requested NRC authorization to use this proposed alternative for the duration of the fifth 10-year IST program interval at Davis-Besse, which is scheduled to begin on September 21, 2022, and end on September 20, 2032.
3.2
NRC Staff Evaluation
The licensee proposed an alternative to the digital instrumentation requirements in subparagraph ISTB-3510(b)(2) of the ASME OM Code for the comprehensive testing of the pumps listed in SE Section 3.1. The licensee stated, in part, that:
Plant process computer points or temporary digital instruments may be used for comprehensive pump testing. The computer points use permanent plant instrumentation as input, and by design, the ranges are selected to account for all expected operating and testing conditions. Surveillance tests are written such that the temporary instrumentation is not over-ranged. In addition, digital instrumentation is significantly less susceptible to damage from over-ranging, and the digital instrument is accurate throughout its full calibrated range.
Subparagraph ISTB-3510(b)(2) of the ASME OM Code requires that reference values of digital instruments do not exceed 90 percent of the calibrated range of the instrument. Tables ISTB-5121-1 and ISTB-5221-1 of the ASME OM Code list the acceptance criteria for comprehensive pump testing. These tables state that the maximum acceptable values for both the measured flow and differential pressure is 106 percent of the reference value.
For the proposed alternative to subparagraph ISTB-3510(b)(2) of the ASME OM Code, the licensee would select digital instruments for comprehensive pump testing such that the reference value would not exceed 94 percent of the calibrated range. The licensee stated, in part, that: This ensures that when the digital instrument used during performance of comprehensive pump testing is reading the maximum action level of 106 percent of the reference value, the reading is within the calibrated range of the instrument.
The NRC staff determined that the proposed alternative for selecting digital instruments for the comprehensive pump testing is acceptable because the maximum acceptable values (i.e.,
106 percent of the reference value) for both the measured flow and differential pressure would be within the calibrated range of the instruments. Therefore, the NRC staff finds that the proposed alternative provides an acceptable level of quality and safety for the comprehensive testing of the pumps listed in SE Section 3.1.
4.0 CONCLUSION
As set forth above, the NRC staff finds that proposed alternative for the selection of digital instruments for the comprehensive testing of the pumps listed in SE Section 3.1 will provide an acceptable level of quality and safety. Accordingly, the NRC staff concludes that the licensee has adequately addressed the regulatory requirements set forth in 10 CFR 50.55a(z)(1).
Therefore, the NRC staff authorizes the use of proposed alternative Request RP-1 at Davis-Besse for the fifth 10-year IST interval, which is scheduled to begin on September 21, 2022, and end on September 20, 2032.
All other ASME OM Code requirements for which an alternative was not specifically requested and authorized remain applicable.
Principal Contributor: Y. Wong, NRR/DEX/EMIB Date: April 12, 2022