MONTHYEARML21266A0652021-09-23023 September 2021 NEI Presentation - ROP Public Meeting 09232021 (002) ML20196L6582020-07-14014 July 2020 July 28, 2020 Public Meeting Notice on Spent Fuel Performance Margins Meeting ML19298B1102019-11-0101 November 2019 Summary of October 17, 2019, Meeting with NEI Regarding Draft Regulatory Guide-1351, Dispositioning of Technical Specifications That Are Insufficient to Ensure Plant Safety ML18331A3702018-12-0303 December 2018 Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding Use of New Probabilistic Risk Assessment Methods ML18208A3322018-07-27027 July 2018 Member Comments on Draft SSHAC Report ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML17227A0302017-09-0505 September 2017 Summary of Meeting with the Nuclear Energy Institute on NEI 15-03, Revision 1, Licensee Actions to Address Nonconservative Technical Specifications ML1122000212011-08-31031 August 2011 8/4/2011- Summary of Meeting with the Nuclear Energy Institute and the Technical Specifications Task Force Regarding Gas Accumulation Issues and TSTF-523 ML1034402692010-12-22022 December 2010 Summary of Public Meeting with Industry'S New Plant Working Group (Npwg) on Combined License Applications ML0715705202007-06-27027 June 2007 Summary of Meeting with NRC Industry Representatives to Present a Matrix of Potential Modeling Cases for the Phase II Sensitivity, Benchmarking, and Validation Calculations in Their Advanced Finite Element Fracture Mechanics Analyses ML0629101532006-10-24024 October 2006 Meeting Summary - Nuclear Energy Institute, NRC, and Representatives of Wolf Creek, Callaway, Palo Verde - Re Concerns Related to NRC Operability Determination for Callaway of the Main Steam Isolation Valves with Dual Actuator Trains ML0517301422006-01-0909 January 2006 06/08-06/09/2005-Summary of Meeting W/Nei to Discuss Nei'S COL Application Guidance Document (NEI 04-01) and the Operational Program Review Performed During the Evaluation of a COL Application ML0524300262005-10-18018 October 2005 Summary of Mtg. W/Nei to Discuss NEI 04-01, Revision D, Draft Industry Guideline for Combined License (COL) Applicants Under 10 CFR Part 52, and the Operational Program Review Performed During the Evaluation of a COL Application ML0517104492005-09-12012 September 2005 Summary of Meeting with NEI to Discuss Consolidation of Standard Review Plan, Chapter 17, Quality Assurance ML0508103602005-08-0101 August 2005 03/03-03/04/2005 - Summary of Meeting with NEI to Discuss NEI 04-01, Revision D, Draft Industry Guideline for Combined License (COL) Applicants Under 10 CFR Part 52, & the Operational Program Review Performed During the Evaluation of a COL ML0513600262005-05-25025 May 2005 Summary of Meeting with Nuclear Energy Institute Licensing Action Task Force Sub-group on Evaluation of Trends of Requests for Additional Information ML0510000022005-04-0808 April 2005 Summary of Meeting with Nuclear Energy Institute Licensing Action Task Force Sub-group on Evaluation of Requests for Additional Information ML0432902012004-12-28028 December 2004 Summary of Meeting with NEI to Discuss Applicability of 10 CFR Part 21 to ESP Applicants and Holders, EP Aspects of ESP Reviews, Inclusion of Plant Parameters in Esps, and Esp/Col Interface Issues ML0432902402004-12-28028 December 2004 Attachments 1 & 2 - 11/10/2004 Summary of Meeting with NEI to Discuss Applicability of 10 CFR Part 21 to ESP Applicants and Holders, EP Aspects of ESP Reviews, Inclusion of Plant Parameters in Esps, and Esp/Col Interface Issues ML0432902432004-12-28028 December 2004 Attachment 3 - 11/10/2004 Summary of Meeting with NEI to Discuss Applicability of 10 CFR Part 21 to ESP Applicants and Holders, EP Aspects of ESP Reviews, Inclusion of Plant Parameters in Esps, and Esp/Col Interface Issues ML0423901442004-09-0202 September 2004 Summary of Meeting with NEI to Discuss Emergency Planning (EP) Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) and Draft Early Site Permit (ESP) Template ML0319700652003-07-21021 July 2003 Summary of Meeting with NEI to Discuss ITAAC for Operational Programs and 10 CFR Part 52 COL Issues ML0309906082003-04-14014 April 2003 Summary of Meeting with NEI Regarding ESP Issues ML0305801362003-03-17017 March 2003 Meeting with NEI Regarding ESP Issues ML0303004482003-01-29029 January 2003 1/29/2003 - Meeting Agenda and Meeting Handouts ML0226605002002-10-0707 October 2002 Summary of Meeting with NEI Regarding ESP Issues ML0225903392002-08-25025 August 2002 Summary of Meeting with NEI Regarding ESP Issues ML0209900082002-04-10010 April 2002 Summary of March 13, 2002 Telephone Conversation on the Davis-Besse Reactor Vessel Head Degradation Follow-up ML0119700602001-07-12012 July 2001 Meeting Summary with NEI ML0103002442001-01-25025 January 2001 Meeting Summary NRC Technical Specifications Task Force Owners Group Meeting ML0037793292000-12-19019 December 2000 December 14, 2000, Meeting with NEI, Summary of Meeting on Part 52 Rulemaking ML0037591302000-10-11011 October 2000 Meeting Summary with Nuclear Energy Institute and Public Re Power Reactor Decommissioning Issues 2021-09-23
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24310A2262024-11-0606 November 2024 NEI Preliminary Perspectives on NRC Draft Noak Microreactor White Paper ML24303A2212024-10-29029 October 2024 NEI SDP Realism Presentation for October 30, 2024 Public Meeting ML24291A0062024-10-17017 October 2024 NEI Slide Presentation: ACRS Regulatory Policies and Practices - Draft White Paper on Nth-of-a-Kind (Noak) Micro-Reactor Licensing and Deployment Considerations - Sc - October 17, 2024 ML24267A0032024-09-25025 September 2024 NEI Slides for ROP Public Meeting Sept 2024 ML24263A2592024-09-17017 September 2024 06 Jim Slider NEI September 2024 NRC Ai Public Workshop 09-17-2024 ML24249A2012024-09-0909 September 2024 NEI Presentation - Sept 9 Public Meeting - Flooding DGs - Final ML24249A1152024-09-0505 September 2024 Power Uprate September 5, 2024 Public Meeting Slides ML24243A1612024-08-30030 August 2024 Slide Presentations for High Burnup (Hbu) Workshop V ML24228A2102024-08-20020 August 2024 2024 NEI Early Warning System (EWS) Presentation - NEI Slides ML24229A0012024-08-19019 August 2024 NEI - Spent Fuel Management: Safety and Efficiency Improvements Through Technology and Performance Margins - NRC PIRTs Public Meeting Rev. 8.15.2024 Final ML24218A1832024-07-30030 July 2024 NEI 7-30-24 Trial Use RG 1.247 Path Forward Final ML24197A0652024-07-17017 July 2024 SDP Realism Public Meeting NEI Presentation ML24172A1952024-06-27027 June 2024 NEI Slides for 06-27-2024 Public Meeting Structures as IROFS at Fuel Cycle Facilities ML24178A0372024-06-26026 June 2024 NRC Power Uprate Review Preparation June 26, 2024 Public Meeting Slides ML24164A1972024-06-17017 June 2024 Public Meeting Slides - NRC Staff Comments and Observations on NEI 10-01, Rev 2 Industry Guideline for Developing a Plant Parameter Envelope in Support of an Early Site Permit ML24130A1972024-05-0909 May 2024 NEI Presentation Slides on Rapid and Large-Scale Nuclear Reactor Deployments for Remote Industrial Applications - May 14 2024 Public Meeting ML24129A1382024-05-0808 May 2024 NEI Slides on Centralized Inspections for May 9, 2024 Public Workshop ML24114A1142024-04-18018 April 2024 NEI Supplemental Information on NRC Comments on NEI 20-07, Draft Revision E - April 18 Meeting (Non-Proprietary) ML24103A1532024-04-12012 April 2024 NEI Supplemental Information on NRC Comments of NEI 20-07 Rev E (Non-Proprietary) - Slides ML24092A3132024-04-0303 April 2024 Public Mtg_2024-04-03 Pre-submittal Meeting with the Nuclear Energy Institute (NEI) to Discuss an Update to NEI 03-12, Security Plan Template (Revision 8)_NEI Slides ML24088A2252024-03-26026 March 2024 NEI Slides for Centralized Inspections March 2024 ROP Public Meeting ML24075A2092024-03-14014 March 2024 NEI Advanced Reactor Di&C Task Force Slides - Accident Monitoring Instrumentation ML24075A2102024-03-14014 March 2024 NEI Alan Campbell Slides - Non-Safety-Related with Special Treatment – Digital Considerations ML24082A1792024-03-14014 March 2024 RIC-2024 TH18 True Slides ML24086A5342024-03-14014 March 2024 RIC 2024 TH23 Slides - the Industry’S Innovation Imperative ML24067A2592024-03-13013 March 2024 RIC-2024 W14 Slides - NEI-BHoltzman an Industry Perspective on Advanced Reactor Construction Oversight ML24067A0062024-03-0808 March 2024 1 - NRC - Workshop3 - Non-LOCA Release Fractions Feedback - Final ML24067A0072024-03-0808 March 2024 2 - NRC - Workshop3 - Non-LOCA - FFRD - Final ML24067A0092024-03-0808 March 2024 3 - NRC - Worshop3 - CR Dose Presentation - Final ML24067A0102024-03-0808 March 2024 4 - NRC - Workshop3 - EQ Presentation - Final ML24067A0122024-03-0808 March 2024 6 - NRC - Workshop3 - Best Estimate Dose ML24067A0132024-03-0808 March 2024 7 - NRC - Workshop3 - Closing Remarks ML24067A2882024-03-0808 March 2024 1 (Revised)-NRC_Workshop3_Non-LOCA Release Fraction Feedback-Final ML24043A1162024-02-13013 February 2024 3- EQ Presentation Workshop 2 ML24043A1192024-02-13013 February 2024 1- Impacts on RG 1.183 for Workshop2 ML24043A1202024-02-13013 February 2024 2- CR Dose Presentation Workshop 2 ML24016A2372024-01-17017 January 2024 NEI Environmental Reviews Slides Public Meeting 1-17-24 ML24010A0202024-01-11011 January 2024 Public Meeting on SLR Efficiencies - NEI Presentation ML24008A0442024-01-0909 January 2024 NEI - Slides for NRC Workshop 1 on Revision to RG 1.183 R1 - Final - ML24008A044 ML23342A0262023-12-14014 December 2023 December 14, 2023, Presentation on NEI 23-01 Operator Cold Licensing Training Plan for Advanced Nuclear Reactors ML23347A1782023-12-13013 December 2023 12-14 NEI EPRI Presentation NRC Public Meeting 16-03 R1 ML23303A1922023-10-30030 October 2023 NEI Slides for SLR Public Meeting - Oct 31 2023 ML23324A2392023-10-24024 October 2023 S1P6 - Hilary Lane - NRC AMT Workshop - Oct. 2023 ML23261C3792023-09-27027 September 2023 NEI 22-04 Pre-Submittal Meeting with NRC - September 27, 2023 ML23258A1992023-09-20020 September 2023 NEI 99-02 Draft Rev. 8 Update for Sept 2023 ROP Public Meeting ML23242A0782023-08-30030 August 2023 Hbu Workshop IV Industry Presentation: Drive to Deploy ATF with Increased Enrichment and Higher Burnup ML23242A1662023-08-30030 August 2023 The Future of Nuclear Power: 2023 Baseline Survey (Slides) ML23230A0142023-08-22022 August 2023 Industry Slide Presentation for 8-22-23 Meeting on ARCAP-TICAP and DG-1404 Guidance Documents ML23228A0042023-08-18018 August 2023 NEI Slides for Public Meeting to Discuss Possible Efficiencies on the Subsequent License Renewal Review - August 18, 2023 ML23191A0162023-07-11011 July 2023 NEI Comments on Risk-Informed Process for Evaluation (RIPE) DORL TSG - 7/11/23 Public Meeting Slides from NEI 2024-09-09
[Table view] |
Text
Feedback on proposed ROP changes
September 23, 2021
©2021 Nuclear Energy Institute
SUMMARY
NEI understands the direction that NRC is headed with current strategy but we have questions on actions & engagement We agree that there are improvements that could be gained through incorporation of operating experience including more recent experience We agree that there are areas that were included in the SECYs that are no longer being recommended or were already completed
- We appreciate the opportunity to provide any new insights and provide perspectives on relative importance
©2021 Nuclear Energy Institute SECY 0113
We do not see any new information that would change our position on the original recommendations We acknowledge that use of licensee self-assessments are no longer being pursued As a result of the NRC request during the last public meeting, NEI has identified an area that warrants additional consideration for the scope of the triennial fire protection inspection (TFPI)
The NEI fire protection task force will reach out to the applicable technical staff to discuss
©2021 Nuclear Energy Institute TRIENNIAL FIRE PROTECTION INSPECTION (TFPI)
NEI Fire Protection Task Force re-evaluated Fire Protection recommendations in SECY-18 -0113 and SECY -19 -0067 Attributes of the TFPI are redundant to attributes of other NRC inspections
Continuing to see low numbers of Fire Protection findings based on industry performance Ready to engage NRC staff with the following recommendation:
- Reallocate unique TFPI inspection criteria to CETI and IP 71111.05, Fire Protection ©2021 Nuclear Energy Institute 4 SECY 0067
We do not see any new information that would change our position on the original recommendations We do have some questions on actions and engagement
©2021 Nuclear Energy Institute Status of Plans for Reporting Guidance Applicable to Plants with Risk-Informed Licensing Bases
September 23, 2021
©2021 Nuclear Energy Institute REPORTING GUIDANCE
NEI task force is developing guidance on how to apply reporting requirements for licensees with risk-informed licensing bases For example, 50.69(b)(1)(vii) and (viii) provide an explicit exemption to 10 CFR 50.72 and 50.73 respectively for RISC-3 and RISC-4 components 50.69(g) requires LER under 50.73(b) for any event or condition that prevented, or would have prevented, a RISC-1 or RISC-2 SSC from performing a safety significant function.
Other risk informed initiatives would also benefit from additional reporting guidance
©2021 Nuclear Energy Institute STATUS
Actions complete/in-progress Draft guidance developed Initial regulatory affairs review completed Industry operations tabletop performed Incorporate feedback from tabletop -in progress Next Steps NEI regulatory and legal review of updated draft guidance - Oct, 2021 NEI/NRC workshop - Late Fall We are interested in engaging the NRC staff for feedback