Summary of Meeting with NRC Industry Representatives to Present a Matrix of Potential Modeling Cases for the Phase II Sensitivity, Benchmarking, and Validation Calculations in Their Advanced Finite Element Fracture Mechanics Analyses
ML071570520
Person / Time
Site: Wolf Creek, Nuclear Energy Institute, PROJ0669  Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 06/27/2007
From: Tanya Mensah
NRC/NRR/ADRA/DPR/PSPB
To: Rosenberg S
NRC/NRR/ADRA/DPR/PSPB
Mensah T
Shared Package
ML071580239 List:
References
TAC MD0694
Download: ML071570520 (7)


Text

June 27, 2007 MEMORANDUM TO: Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation FROM: Tanya M. Mensah, Senior Project Manager /RA/

Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF THE MAY 8, 2007, CATEGORY 2 PUBLIC MEETING RE: IMPLICATIONS OF WOLF CREEK DISSIMILAR METAL WELD INSPECTIONS (TAC NO. MD0694)

On May 8, 2007, a Category 2 public meeting was held between the U. S. Nuclear Regulatory Commission (NRC) staff and industry representatives at the Bethesda North Marriot Hotel and Conference Center in North Bethesda, MD. A list of attendees is enclosed. The purpose of this meeting was for the industry representatives to present a matrix of potential modeling cases for the Phase II sensitivity, benchmarking, and validation calculations in their Advanced Finite Element Fracture Mechanics Analyses.

The May 8, 2007, meeting was one of a series of public meetings related to the Wolf Creek pressurizer nozzle weld flaws found in October 2006. Other public meetings to discuss this topic were held on November 16, 2006 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML063320131), November 30, 2006 (ADAMS Accession No. ML063560371), December 20, 2006 (ADAMS Accession No. ML070330381),

March 7, 2007 (ADAMS Accession No. ML070740752), and May 1, 2007 (ADAMS Accession No. ML071360367).

The NRC staff opened the meeting by providing a status of the analysis program and an outline of the presentations to follow. The NRC staff made a presentation that provided the results of efforts to date to benchmark and verify the industrys analysis software. The NRC staff analyses provide reasonably similar results to the industrys analyses. The NRC staff also discussed plans for further software benchmarking and verification efforts. A more detailed summary of the NRC staffs presentation is provided in its presentation slides (ADAMS Accession Nos. ML071350651 and ML071350648).

The industry representatives made a presentation discussing proposed resolution of issues raised in the letter from NRC to NEI dated April 4, 2007 (ADAMS Accession No. ML070940186), on analysis methods. This discussion was concluded with agreements to review additional material and continue discussions at a future meeting. Industry

representatives also presented material on weld residual stress validation efforts, a concept for the analysis matrix and sensitivity cases, and leak rate calculations. At the conclusion of the meeting, participants discussed plans for future meetings. The industry representatives presentations are provided in its presentation slides (ADAMS Accession Nos. ML071350646 and ML071350653).

Members of the public were in attendance. No public meeting feedback forms were received.

Project Nos. 669 and 689

Enclosure:

List of Attendees cc w/encl: See next page

ML071350646 and ML071350653).

Members of the public were in attendance. No public meeting feedback forms were received.

Project Nos. 669 and 689

Enclosure:

List of Attendees cc w/encl: See next page DISTRIBUTION:

PUBLIC RidsNrrAdro PSPB Reading File RidsNrrDpr RidsNrrDprPspb RidsNrrPMTMensah RidsNrrLADBaxley RidsOpaMail MMurphy RidsNrrDciCpnb ESullivan MYoder TLupold MGutierrez KGruss ACsontos CSheng CTucci RHardies RidsOgcMailCenter SMalik RidsNrrDci RidsAcrsAcnwMailCenter ADAMS Package Accession No. ML071580239 Meeting Notice Accession No. ML071060285 Meeting Handout Accession Nos. ML071350651, ML071350648, ML071350646, ML071350653 Meeting Summary Accession No. ML071570520 NRC-001 OFFICE PSPB/PM PSPB/LA DCI DCI/BC PSPB/BC NAME TMensah DBaxley TSullivan JTsao for MHoncharik TChan for SRosenberg DATE 6/11/07 6/8/07 6/26 /07 6/26 /07 6/ 27 /07 List of Attendees for May 8, 2007 Name Organization Ted Anderson Quest Reliability Warren Bamford Westinghouse John Broussand Dominion Engineering Jean Collin Dominion Engineering Aladar Csontos NRC Guy DeBoo Exelon Tim Gilman Structural Integrity Mauricio Gutierrez NRC Bob Hardies NRC Craig Harrington Electric Power Research Institute (EPRI)

Daniel Horner McGraw-Hill Russ Lieder FPL Energy, Seabrook Tim Lupold NRC Shah Malik NRC Mike Melton NEI Pete Riccaroella Structural Integrity Jim Riley Nuclear Energy Institute (NEI)

David Rudland NRC (Contractor)

Simon Sheng NRC David A. Steininger EPRI Edmund Sullivan NRC Greg Thorwald Quest Reliability Glenn White Dominion Engineering, Inc.

Ken Yoon AREVA NP ENCLOSURE

Nuclear Energy Institute Project No. 689 Electric Power Research Institute Project No. 669 cc:

Mr. Anthony Pietrangelo, Vice President Mr. Alexander Marion, Executive Director Regulatory Affairs Nuclear Operations & Engineering Nuclear Energy Institute Nuclear Energy Institute 1776 I Street, NW, Suite 400 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Washington, DC 20006-3708 arp@nei.org am@nei.org Mr. Jack Roe, Director Mr. Jay Thayer, Vice President Operations Support Nuclear Operations Nuclear Energy Institute Nuclear Energy Institute 1776 I Street, NW, Suite 400 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Washington, DC 20006-3708 jwr@nei.org jkt@nei.org Mr. Charles B. Brinkman Mr. John Butler, Director Washington Operations Safety-Focused Regulation ABB-Combustion Engineering, Inc. Nuclear Energy Institute 12300 Twinbrook Parkway, Suite 330 1776 I Street, NW, Suite 400 Rockville, MD 20852 Washington, DC 20006-3708 brinkmcb@westinghouse.com jcb@nei.org Mr. Gary L. Vine, Executive Director Mr. James H. Riley, Director Federal and Industry Activities, Nuclear Engineering Sector Nuclear Energy Institute EPRI 1776 I Street, NW 2000 L Street, NW, Suite 805 Washington, DC 20006-3708 Washington, DC 20036 jhr@nei.org gvine@epri.com Mike Melton, Senior Project Manager Mr. James Gresham, Manager 1776 I Street, NW, Suite 400 Regulatory Compliance and Plant Licensing Washington, DC 20006-3708 Westinghouse Electric Company man@nei.org P.O. Box 355 Pittsburgh, PA 15230-0355 Mr. David J. Modeen greshaja@westinghouse.com Vice President and Chief Nuclear Officer EPRI Ms. Barbara Lewis 1300 W. T. Harris Boulevard Assistant Editor Charlotte, NC 28262-8550 Platts, Principal Editorial Office dmodeen@epri.com 1200 G St., N.W., Suite 1100 Washington, DC 20005 Barbara_lewis@platts.com 3/8/07

Mr. John Gaertner EPRI 1300 W.T. Harris Boulevard Charlotte, NC 28262-8550 jgaertner@epri.com Ms. Rosa Yang EPRI 3412 Hillview Avenue Palo Alto, CA 94304-1338 ryang@epri.com Mr. Kenneth Huffman EPRI 1300 W. T. Harris Boulevard Charlotte, NC 28262-8550 khuffman@epri.com 3/8/07