Letter Sequence Other |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: ML21196A076, ML22045A053, ML22111A314, ML22193A254, ML22349A148, ML24255A332, RA-21-0307, Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - Set 1, RA-22-0023, Subsequent License Renewal Application - Response to NRC Requests for Confirmation of Information - Set 3, RA-22-0105, Subsequent License Renewal Application - Responses to NRC Requests for Confirmation of Information - Set 4, RA-22-0129, Subsequent License Renewal Application, Response to ONS SLRA 2nd Round RAI B4.1-3, RA-22-0137, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI 4.6.1-1a, RA-22-0145, Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - RAI 3.5.2.2.2.6-L, RA-22-0158, Subsequent License Renewal Application - Response to ONS SLRA Second Round RAI B2.1.9-2a, RA-22-0160, Subsequent License Renewal Application: Responses to ONS SLRA - Second Round RAIs - Trp 76 (Irradiation Structural) - FE 3.5.2.2.2.6, RA-22-0192, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4a, RA-22-0193, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4b
|
MONTHYEARRA-21-0132, Application for Subsequent Renewed Operating Licenses. Part 7 of 82021-06-0707 June 2021 Application for Subsequent Renewed Operating Licenses. Part 7 of 8 Project stage: Request ML21158A1952021-06-0707 June 2021 Application for Subsequent Renewed Operating Licenses. Part 2 of 8 Project stage: Request ML21158A1932021-06-0707 June 2021 Application for Subsequent Renewed Operating Licenses Project stage: Request ML21196A0762021-07-23023 July 2021 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review Project stage: Other ML21271A5862021-09-21021 September 2021, 22 September 2021, 28 September 2021 SLRA - RAI B2.1.27-1 Project stage: Request ML21270A2492021-09-27027 September 2021 Beyond Nuclear and Sierra Club Hearing Request Project stage: Request RA-21-0281, Subsequent License Renewal Application, Response to NRC Request for Additional Information B2.1.27-12021-10-22022 October 2021 Subsequent License Renewal Application, Response to NRC Request for Additional Information B2.1.27-1 Project stage: Response to RAI ML21295A7172021-10-22022 October 2021 Notices of Appearance for Tracey M. Leroy, Paul M. Bessette, and Ryan K. Lighty on Behalf of Duke Energy Carolinas, LLC Project stage: Request RA-21-0249, Subsequent License Renewal Application Supplement 12021-10-28028 October 2021 Subsequent License Renewal Application Supplement 1 Project stage: Supplement ML21313A2342021-11-0404 November 2021 Attachment: Oconee SLRA - Final Requests for Confirmation of Information - Set 1 Project stage: Request ML21313A2322021-11-0404 November 2021 SLRA - Requests for Confirmation of Information - Set 1 Project stage: Request RA-21-0288, Subsequent License Renewal Application Supplement 22021-11-11011 November 2021 Subsequent License Renewal Application Supplement 2 Project stage: Supplement ML21327A2772021-11-23023 November 2021 SLRA - Requests for Additional Information (Set 1) + 2nd Round RAI B2.1.27-1a Project stage: Request RA-21-0307, Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - Set 12021-12-0202 December 2021 Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - Set 1 Project stage: Other RA-21-0316, Subsequent License Renewal Application Supplement 32021-12-15015 December 2021 Subsequent License Renewal Application Supplement 3 Project stage: Supplement RA-21-0325, Response to NRC Requests for Confirmation of Information - Set 22021-12-17017 December 2021 Response to NRC Requests for Confirmation of Information - Set 2 Project stage: Request RA-21-0332, Subsequent License Renewal Application Responses to NRC Request for Additional Information Set 1 and Second Round Request for Additional Information B2.1.27-1a2022-01-0707 January 2022 Subsequent License Renewal Application Responses to NRC Request for Additional Information Set 1 and Second Round Request for Additional Information B2.1.27-1a Project stage: Response to RAI ML22007A0152022-01-0707 January 2022 Subsequent License Renewal Application, Appendix E Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information Project stage: Response to RAI ML22024A0022022-01-19019 January 2022, 20 January 2022, 21 January 2022 SLRA - Audit Report - Audit Questions Transmitted to Duke Energy Project stage: Request ML22024A0382022-01-21021 January 2022 Breakout Questions - Trp 76 - Irradiated Conc Steel Project stage: Request RA-22-0023, Subsequent License Renewal Application - Response to NRC Requests for Confirmation of Information - Set 32022-01-21021 January 2022 Subsequent License Renewal Application - Response to NRC Requests for Confirmation of Information - Set 3 Project stage: Other ML22045A0532022-02-14014 February 2022 SLRA - Audit Report Project stage: Other RA-22-0036, Responses to NRC Request for Additional Information Set 22022-02-14014 February 2022 Responses to NRC Request for Additional Information Set 2 Project stage: Response to RAI RA-22-0040, Subsequent License Renewal Application: Responses to NRC Request for Additional Information Set 32022-02-21021 February 2022 Subsequent License Renewal Application: Responses to NRC Request for Additional Information Set 3 Project stage: Response to RAI ML22024A1392022-03-11011 March 2022 SLRA - Request for Withholding Information Project stage: Withholding Request Acceptance ML22081A0032022-03-21021 March 2022 SLRA - 2nd Round RAI B4.1-3 Project stage: Request RA-22-0105, Subsequent License Renewal Application - Responses to NRC Requests for Confirmation of Information - Set 42022-03-22022 March 2022 Subsequent License Renewal Application - Responses to NRC Requests for Confirmation of Information - Set 4 Project stage: Other RA-22-0111, Subsequent License Renewal Application, Follow-up Request for Additional Information Set 2 and 3 Updates2022-03-31031 March 2022 Subsequent License Renewal Application, Follow-up Request for Additional Information Set 2 and 3 Updates Project stage: Request RA-22-0129, Subsequent License Renewal Application, Response to ONS SLRA 2nd Round RAI B4.1-32022-04-20020 April 2022 Subsequent License Renewal Application, Response to ONS SLRA 2nd Round RAI B4.1-3 Project stage: Other RA-22-0124, Subsequent License Renewal Application Responses to NRC Request for Additional Information Set 42022-04-22022 April 2022 Subsequent License Renewal Application Responses to NRC Request for Additional Information Set 4 Project stage: Response to RAI ML22122A1292022-04-27027 April 2022 SLRA - 2nd Round RAIs (FE 3.5.2.2.2.6) Project stage: Request ML22111A3142022-05-0202 May 2022 Limited Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review Project stage: Other ML22124A1422022-05-0303 May 2022 SLRA - 2nd Round RAI B2.1.7-4a Project stage: Request RA-22-0145, Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - RAI 3.5.2.2.2.6-L2022-05-11011 May 2022 Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - RAI 3.5.2.2.2.6-L Project stage: Other RA-22-0137, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI 4.6.1-1a2022-05-20020 May 2022 Subsequent License Renewal Application Response to ONS SLRA Second Round RAI 4.6.1-1a Project stage: Other RA-22-0159, Subsequent License Renewal Application Response to ONS SLRA Request for Additional Information (RAI) 3.1.2-12022-05-27027 May 2022 Subsequent License Renewal Application Response to ONS SLRA Request for Additional Information (RAI) 3.1.2-1 Project stage: Request ML22154A2002022-06-0101 June 2022 SLRA - 2nd Round RAI B2.1.7-4b Project stage: Request RA-22-0157, Subsequent License Renewal Application First Annual Amendment to the License Renewal Application and Subsequent License Renewal Application Supplement 42022-06-0707 June 2022 Subsequent License Renewal Application First Annual Amendment to the License Renewal Application and Subsequent License Renewal Application Supplement 4 Project stage: Supplement RA-22-0158, Subsequent License Renewal Application - Response to ONS SLRA Second Round RAI B2.1.9-2a2022-06-0808 June 2022 Subsequent License Renewal Application - Response to ONS SLRA Second Round RAI B2.1.9-2a Project stage: Other ML22192A0622022-06-28028 June 2022, 6 July 2022, 18 July 2022 SLRA - Summary of June 30, 2022 Public Meeting Project stage: Request RA-22-0193, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4b2022-07-0808 July 2022 Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4b Project stage: Other RA-22-0160, Subsequent License Renewal Application: Responses to ONS SLRA - Second Round RAIs - Trp 76 (Irradiation Structural) - FE 3.5.2.2.2.62022-07-25025 July 2022 Subsequent License Renewal Application: Responses to ONS SLRA - Second Round RAIs - Trp 76 (Irradiation Structural) - FE 3.5.2.2.2.6 Project stage: Other ML22215A2502022-07-25025 July 2022 EN 55960 - Update - Curtiss Wright Project stage: Request ML22193A2542022-08-0505 August 2022 SLRA - Audit Report Project stage: Other RA-22-0192, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4a2022-09-0202 September 2022 Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4a Project stage: Other ML22222A0072022-09-14014 September 2022 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application Project stage: Withholding Request Acceptance ML22264A0322022-10-20020 October 2022 _Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Duke Energy Letter Dated July 8, 2022 Project stage: Withholding Request Acceptance ML22298A0752022-10-27027 October 2022 – Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application – Duke Energy Letter Dated July 25, 2022 Project stage: Withholding Request Acceptance ML22301A0112022-11-0303 November 2022 – Request for Withholding Information from Public Disclosure Regarding the SLR Application - September 2, 2022 Project stage: Withholding Request Acceptance 2022-03-11
[Table View] |
|
---|
Category:Audit Plan
MONTHYEARML23269A0412023-08-22022 August 2023 Code Case N-752 Audit; August 22, 2023, E-mail Providing Additional Information Regarding Design and Quality Program Requirements ML23178A0682023-07-0303 July 2023 Audit Plan Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 & 3 Systems Section XI, Division 1 ML23075A0732023-04-0505 April 2023 – License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Supplement (EPID Number L-2021-SLE-0002) ML22111A3142022-05-0202 May 2022 Limited Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML21362A7532022-01-0606 January 2022 Regulatory Audit in Support of the License Amendment Request for One-Time Note to Technical Specification 3.7.7, Low Pressure Service Water (LPSW) System ML21263A0312021-09-21021 September 2021 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application ML21196A0762021-07-23023 July 2021 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML20036E3902020-02-11011 February 2020 Regulatory Audit in Support of Review of License Amendment Request to Revise the Licensing Basis for High Energy Line Breaks Outside of the Containment Building ML19037A0052019-02-0808 February 2019 Regulatory Audit in Support of Review of License Amendment Request No. 2018-02 ML18032A4612018-03-0505 March 2018 Regulatory Audit in Support of Review of License Amendment Request No. 2017-03 ML18004A0122018-01-0404 January 2018 Regulatory Audit in Support of Review of Proposed Alternative (CAC Nos. MF7365, MF7366 and MF7367; EPID No. L-2016-LLR-001) ML17202U7312017-07-25025 July 2017 Regulatory Audit in Support of License Amendment Request No. 2015-03 ML17177A4462017-07-0606 July 2017 Audit Plan for Licensee Responses Concerning Seismic Hazard Reevaluations Related to Request for Information -(50.54(F) Letter) Regarding Recommendation 2.1 of the Near-Term Task Force ML16259A1892016-12-0505 December 2016 Nuclear Regulatory Commission Plan for the Audit of Mitigation Strategies Assessment Submittals Related to Order EA-12-049, Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML15281A2932015-10-22022 October 2015 Plan for the Regulatory Audit Regarding License Amendment Request for Alternate Fission Gas Gap Release Fractions ML15226A1852015-09-0808 September 2015 Nuclear Regulatory Commission Plan for the Audit of Duke Energy Carolinas, LLC Interim Evaluations Associated with Reevaluated Seismic Hazard Implementing Near-Term Task Force Recommendation 2.1 - Seismic ML15160A6642015-06-10010 June 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 ML15118A4602015-05-0808 May 2015 Audit Plan for the Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1 - Flooding ML14356A0032015-02-10010 February 2015 Audit of Licensee Responses to the Expedited Seismic Evaluation Process to Support Implementation of Near-Term Task Force Recommendation 2.1, Seismic ML14083A6202014-03-26026 March 2014 Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 2023-08-22
[Table view] Category:Letter
MONTHYEARIR 05000269/20240032024-10-31031 October 2024 Integrated Inspection Report 05000269/2024003 and 05000270/2024003 and 05000287/2024003 (2) ML24255A3322024-10-16016 October 2024 SLRA - Revised SE Letter ML24297A6172024-10-11011 October 2024 PCA Letter to NRC Oconee Hurricane Helene ML24269A0912024-10-0909 October 2024 Request for Withholding Information from Public Disclosure ML24145A1782024-08-26026 August 2024 Issuance of Amendment Nos. 430, 432, and 431, to TS 5.5.2, Containment Leakage Rate Testing Program for a one-time Extension of the Type a Leak Rate Test Frequency IR 05000269/20240052024-08-26026 August 2024 Updated Inspection Plan for Oconee Nuclear Station, Units 1, 2 and 3 (Report 05000269/2024005, 05000270/2024005, and 05000287-2024005) 05000287/LER-2024-001, Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation2024-08-0202 August 2024 Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation IR 05000269/20240022024-07-25025 July 2024 Integrated Inspection Report 05000269/2024002 and 05000270/2024002 and 05000287/2024002 ML24192A1312024-07-15015 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24183A2352024-06-29029 June 2024 Update 3 to Interim Report Regarding a Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24179A1102024-06-27027 June 2024 Submittal of Updated Final Safety Analysis Report Revision 30, Technical Specifications Bases Revisions, Selected Licensee Commitment Revisions, 10 CFR 50.59 Evaluation Summary Report, and 10 CFR 54.37 Update, and Notification ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000269/20240012024-05-0303 May 2024 Integrated Inspection Report 05000269/2024001, 05000270/2024001 and 05000287/2024001 IR 05000269/20244022024-04-24024 April 2024 Security Baseline Inspection Report 05000269/2024402 and 05000270/2024402 and 05000287/2024402 ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 IR 05000269/20244012024-03-28028 March 2024 – Security Baseline Inspection Report 05000269-2024401 and 05000270-2024401 and 05000287-2024401 ML24088A3052024-03-25025 March 2024 Fws to NRC, Agreement with Nlaa Determination for Tricolored Bat for Oconee Lr 05000270/LER-2023-001, Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee2024-02-29029 February 2024 Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee 05000287/LER-2023-002, Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications2024-02-29029 February 2024 Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications IR 05000269/20230062024-02-28028 February 2024 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 - (NRC Inspection Report 05000269/2023006, 05000270/2023006, and 05000287/2023006) ML24045A3042024-02-16016 February 2024 Ltr. to Lisa M. Collins Chief the Wassamasaw Tribe of Varnertown Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24030A0052024-02-16016 February 2024 Ltr. to Brian Harris, Chief, Catawba Indian Nation; Re., Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2942024-02-16016 February 2024 Ltr. to Carolyn Chavis Bolton Chief Pee Dee Indian Nation of Upper Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2962024-02-16016 February 2024 Ltr. to David Hill Principal Chief Muscogee Creek Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2992024-02-16016 February 2024 Ltr. to Eric Pratt Chief the Santee Indian Organization Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3082024-02-16016 February 2024 Ltr. to Ralph Oxendine Chief Sumter Tribe of Cheraw Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3022024-02-16016 February 2024 Ltr. to Joe Bunch United Keetoowah Band of Cherokee Indians in Ok Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3072024-02-16016 February 2024 Ltr. to Pete Parr Chief Pee Dee Indian Tribe Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3032024-02-16016 February 2024 Ltr. to John Creel Chief Edisto Natchez-Kusso Tribe of Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3012024-02-16016 February 2024 Ltr. to Harold Hatcher Chief the Waccamaw Indian People Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2952024-02-16016 February 2024 Ltr. to Chuck Hoskin, Jr, Principal Chief Cherokee Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2972024-02-16016 February 2024 Ltr. to Dexter Sharp Chief Piedmont American Indian Assoc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3052024-02-16016 February 2024 Ltr. to Louis Chavis Chief Beaver Creek Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3062024-02-16016 February 2024 Ltr. to Michell Hicks, Principal Chief Eastern Band of Cherokee Re Oconee Nuclear Station Units 1,2, and 3 Section 106 ML24019A1442024-02-13013 February 2024 Letter to Reid Nelson, Executive Director, Achp; Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24011A1532024-02-13013 February 2024 Letter to Tracy Watson EPA-Oconee Nuclear Sta, Unites 1, 2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants ML24030A5212024-02-13013 February 2024 Letter to Elizabeth Johnson, Director, SHPO; Re Oconee Nuclear Stations Units 1, 2, and 3 Section 106 ML24011A1482024-02-13013 February 2024 Letter to Steven M. Snider-Oconee Nuclear Sta, Unites 1,2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants IR 05000269/20230042024-02-13013 February 2024 Integrated Inspection Report 05000269/2023004, 05000270/2023004, and 05000287/2023004; and Inspection Report 07200040/2023001 ML23304A1422024-02-0101 February 2024 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staff’S Review of the Oconee Nuclear Station, Units 1, 2, & 3, Subsequent License Renewal Application ML24005A2492024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000269/20243012024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000269/2024301, 05000270/2024301, and 05000287/2024301 ML23331A7982023-12-14014 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report (01R32) ML23262A9672023-12-13013 December 2023 Alternative to Use RR-22-0174, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section XI, Division 1 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230032023-11-14014 November 2023 Integrated Inspection Report 05000269/2023003, 05000270/2023003, and 05000287/2023003; and IR 07200040/2023001; and Exercise of Enforcement Discretion ML23219A1402023-10-10010 October 2023 Audit Report Proposed Alternative to Use ASME Code Case N-752, Risk Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems XI, Division 1 ML23269A1102023-10-0606 October 2023 Letter to Steven Snider-Revised Schedule for the Environmental Review of the Oconee Nuclear Station, Unit 1, 2, and 3, Subsequent License Renewal Application ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds 2024-08-26
[Table view] |
Text
July 23, 2021 Steven M. Snider Site Vice President, Oconee Nuclear Station Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672-0752
SUBJECT:
OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 - AGING MANAGEMENT AUDIT PLAN REGARDING THE SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW (EPID NO. L-2021-SLR-0000)
Dear Mr. Snider:
By letter dated June 7, 2021 (Agencywide Documents Access and Management System Package Accession No. ML21158A193), Duke Energy Carolinas, LLC submitted to the U.S. Nuclear Regulatory Commission (NRC or staff) an application to renew the Renewed Facility Operating License Nos. DPR-38, DPR-47, and DPR-55 for Oconee Nuclear Station (ONS), Units 1, 2, and 3.
The NRC plans to conduct an Aging Management Audit from July 26, 2021 - October 8, 2021, in accordance with the enclosed regulatory audit plan. The Aging Management Audit will be conducted at NRC Headquarters and ONS site, as appropriate. If you have any questions, please contact Angela Wu at Angela.Wu@nrc.gov.
Sincerely, Digitally signed by Lauren K. Lauren K. Gibson Date: 2021.07.23 Gibson 10:12:21 -04'00' Lauren K. Gibson, Chief License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270 and 50-287
Enclosure:
Aging Management Audit Plan
ML21196A076 OFFICE PM:NLRP:DNRL LA:NLRP:DNRL BC:NLRP:DNRL NAME AWu SGreen LGibson DATE 07/15/2021 07/15/2021 07/23/2021 Audit Plan Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Aging Management Regulatory Audit July 26, 2021 - October 8, 2021 Division of New and Renewed Licenses Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Enclosure
Audit Plan Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Aging Management Regulatory Audit
- 1. Background By letter dated June 7, 2021 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML21158A193), Duke Energy Carolinas, LLC (Duke Energy or the applicant) submitted to the U.S. Nuclear Regulatory Commission (NRC or staff) an application to renew the Renewed Facility Operating License Nos. DPR-38, DPR-47, and DPR-55 for Oconee Nuclear Station (ONS), Units 1, 2, and 3. The staff is reviewing this application in accordance with the guidance in NUREG-2192, Standard Review Plan for Review of Subsequent License Renewal Applications for Nuclear Power Plants, (SRP-SLR).
In accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR)
Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, the NRC will perform an aging management regulatory audit to gain a better understanding of (1) the applicants methodology to identify the systems, structures, and components (SSCs) to be included within the scope of subsequent license renewal and subject to an aging management review (AMR), and (2) the applicants aging management programs (AMPs),
AMR items, time-limited aging analyses (TLAAs), and associated bases and documentation as applicable.
- 2. Regulatory Audit Bases License renewal requirements are specified in 10 CFR Part 54. Guidance is provided in the SRP-SLR and NUREG-2191, Revision 0, Generic Aging Lessons Learned for Subsequent License Renewal (GALL-SLR) Report, dated July 2017.
- 3. Regulatory Audit Scope of Review Scoping and Screening Review The purpose of the scoping and screening review is to evaluate the applicants scoping and screening methodology used to identify SSCs within the scope of subsequent license renewal and subject to AMR, as well as the results of the implementation of the methodology. The review is performed by evaluating the scoping and screening process and results, as documented in the subsequent license renewal application (SLRA), implementing procedures, reports, and drawings, such that the NRC staff:
Obtains an understanding of the process used to identify the SSCs within the scope of license renewal and to identify the structures and components subject to an AMR; and Has sufficient docketed information to allow the NRC staff to reach a conclusion on the adequacy of the scoping and screening methodology and results, as documented in the SLRA.
AMP, AMR, and TLAA Review The scope of the AMP, AMR, and TLAA review is to: (a) examine the applicants AMPs, AMR items, and TLAAs; (b) verify the applicants claims of consistency with the corresponding GALL-SLR Report AMPs, and AMR items; and (c) assess the adequacy of the TLAAs.
Enhancements and exceptions will be evaluated on a case-by-case basis with the results documented in the safety evaluation report (SER).
The NRC staff will audit Program Elements 1 - 10 (scope, preventive actions, parameters monitored or inspected, detection of aging effects, monitoring and trending, acceptance criteria, corrective actions, confirmation process, administrative controls, and operating experience (OE)) of the AMPs against the elements of the associated AMP described in the GALL-SLR Report. In addition, the NRC staff will verify that the conditions at the plant are bounded by the conditions for which the GALL-SLR Report program was evaluated.
The NRC staff will also examine the applicants program bases documents and related references for AMPs, AMR items, and TLAAs, and interview applicant representatives to obtain additional clarification.
The NRC staff will use risk insights to inform the prioritization of its review of documentation associated with AMPs, AMR items, and TLAAs and to focus the breadth and depth of its review of plant specific operating procedures and OE. However, the NRC staffs review is not limited to risk-significant systems and components because 10 CFR Part 54 is a deterministic rule and the NRC staff must conclude that there is reasonable assurance that activities will continue to be conducted in accordance with the current licensing basis and the effects of aging will be managed during the subsequent period of extended operation for all structures and components within the scope of 10 CFR Part 54.
The NRC staff has reviewed the list of risk-significant systems and components provided by the applicant to inform the establishment of priorities for the performance of the scoping and screening review.
- 4. Audit Activities The Aging Management Audit will consist of three parts, to be scheduled by the License Renewal Projects Branch (NLRP) safety project manager in coordination with the applicant.
Following completion of the Aging Management Audit, an Aging Management Audit report will be issued.
The three Aging Management Audit parts include:
Part #1 - In-Office Technical Review Audit During the In-Office Technical Review Audit, technical staff will review the SLRA, documentation on the applicants electronic portal (ePortal), and conduct an OE review.
The staff will have the opportunity to have discipline-specific discussions with the applicant to gain context on the SLRA to support the staffs review.
Part #2 - On-Site Audit The On-Site Audit is performed, in part, by an integrated review team, to conduct observations of areas, equipment conditions, and configurations, and an OE review, as needed. For additional information on whether activities will be performed on-site, see On-Site Audit (Aging Management Audit Part #2), below.
Part #3 - In-Office Breakout Sessions The In-Office Breakout Sessions will provide the opportunity for the technical staff to ask questions and have detailed technical discussions to identify and obtain information to complete the safety review.
Each of the three parts of the Aging Management Audit will provide the staff the opportunity to have technical discussions with the applicant to gain clarity and information regarding the SLRA.
The audit is coordinated to support the development of the reviewers reasonable assurance for the safety finding to be documented in the SER. The staff may require additional information from the applicant for some technical areas, while finding that information on the ePortal is sufficient for other technical areas. Accordingly, some technical areas may not require inclusion in Part #2, the On-Site Audit.
The NLRP safety project manager will coordinate all communications with the applicant. Staff requests for communication with the applicant will require approval of their respective technical branch chief and the NLRP branch chief.
In-Office Technical Review Audit (Aging Management Audit Part #1)
The purpose of the In-Office Technical Review Audit is for the staff to review the information contained in the SLRA and the applicants ePortal, including the license renewal drawings.
Using telecommunications, the in-office technical review portion of the Aging Management Audit also allows the applicant to provide context on the ePortals contents and configuration, the methods used to develop the SLRA, the corresponding results, and any areas unique to the ONS SLRA.
The staff will have the opportunity to have discipline-specific discussions with the applicant to discuss the approaches used for evaluation and development of AMPs, TLAAs, AMR items, with the consideration of OE. In addition, the staff may identify specific technical areas where the staff would benefit from a presentation or discussion to provide additional context to support the staffs review.
The staff is to review the information needed to perform the safety review and use the information, to the extent possible, to begin developing draft input for the SER (resulting in an SER with holes).
The staff will audit areas related to OE:
(1) Applicants Process to Identify OE Used in Development of AMPs. The staff requests that the applicant provide a presentation on the process used to identify and evaluate the pertinent OE that was used to inform the development of the AMPs as discussed in the SLRA and basis documentation.
(2) Use of OE Contained in AMP Report-Out Documents. The staff requests that the applicant discuss how the OE contained in the AMP report-out documents (e.g., reports of inspections, assessments, AMP effectiveness reviews) is in alignment with information contained in the corrective action program (CAP) database and how the process described in (1) along with the use of the report-out information would include any pertinent OE otherwise contained in the CAP database. The applicant should demonstrate that OE identified by the process or included in the report-out documents is bounding of OE that should be considered for developing the SLRA. Additionally, the applicant should provide examples of the report-out documents and corresponding corrective action reports.
(3) Staffs Review of Age-Related OE Contained in the CAP Database. Following the applicants presentations on the process to identify and evaluate OE as well as the information included in the report-out documents, the staff should determine if there are any specific areas of OE that have not been sufficiently addressed or if there is a need to sample the information discussed by the applicant to verify the applicants results. If the staff identifies such a need, the staff will have an opportunity to perform an independent review of age-related OE contained in the CAP database, as necessary, to provide reasonable assurance that the applicant has adequately identified and evaluated pertinent OE in the development of the SLRA in Part #2 of the Aging Management Audit.
At the conclusion of the In-Office Technical Review Audit, the staff must identify any areas requiring inclusion in the On-Site Audit, Part #2 of the Aging Management Audit. The identified areas may include OE that should be further considered and the need for observation of areas, equipment conditions, or configurations.
On-Site Audit (Aging Management Audit Part #2)
The purpose of the On-Site Audit is to perform make visual observations of areas, equipment conditions, and configurations, and conduct an OE review, as needed. Due to ongoing health guidelines related to travel and gatherings, the ONS On-Site Audit may be conducted using telecommunications when appropriate.
The staff will perform necessary visual observations of areas, equipment conditions, and configurations, as previously approved by the technical branch chief as having an adequate basis for the need to perform such observations. The NLRP safety project manager shall provide the applicant the information on the areas, equipment conditions, and configurations prior to the On-Site Audit to ensure access and verify that licensee support is available.
On an as needed basis, the staff should perform an independent review of age-related OE contained in the CAP database to provide reasonable assurance that the applicant has adequately identified and evaluated pertinent OE in the development of the SLRA.
In-Office Breakout Sessions (Aging Management Audit Part #3)
During the In-Office Breakout Sessions, the NRC staff will have the opportunity to discuss various basis documents, references, condition/corrective action reports, and to obtain additional clarification related to the SLRA safety review with applicant.
The In-Office Breakout Sessions will be performed using telecommunications. A schedule will be developed by the NLRP safety project manager along with applicant input in order to allow for staff and applicant availability.
The technical staff will inform the technical branch chief of the need for an In-Office Breakout Session. After development of the questions for the In-Office Breakout Sessions, the technical staff will request approval of the questions prior to submission to the NLRP branch chief and NLRP safety project manager. In-Office Breakout Session topics and participants will be grouped by discipline, to the greatest and most efficient extent possible.
The NRC project manager will share the technical questions with the applicant, prior to a breakout session between Duke Energy and the NRC staff for technical discussions on the questions shared.
The In-Office Breakout Sessions topics will be sequenced, to the greatest extent possible, to address more complex areas early in the In-Office Breakout Sessions schedule. The sequencing is intended to allow for sufficient time to hold any additional discussions within the timeframe of the audit.
- 5. Information and Other Material Necessary for the Regulatory Audit Throughout the Aging Management Audit, the staff will review the SLRA, as supplemented and revised, the AMP basis documents and other applicant supporting documents as appropriate and requested, which have been uploaded to the ePortal.
The staff may request additional applicant documents to be added to the ePortal over the course of the audit. The staff requests for ePortal additions shall be made, as needed, to the NLRP safety project manager, who will provide the requests to the applicant.
- 6. Team Assignments Team Member Branch/Division Naeem Iqbal PRA Licensing B (APLB)/Division of Risk Assessment Thinh Dinh APLB/DRA Duc Nguyen Long Term Operations & Modernization Branch (ELTB)/Division of Engineering and External Hazards (DEX)
Matthew McConnell ELTB/DEX Jorge Cintron ELTB/DEX Gurcharan (Singh) ELTB/DEX Matharu Hari Kodali ELTB/DEX Andrew Prinaris Structural, Civil, Geotech Engineering (ESEB)/DEX Bryce Lehman ESEB/DEX George Thomas ESEB/DEX George Wang ESEB/DEX Juan Lopez ESEB/DEX Ata Istar ESEB/DEX Zuhan Xi ESEB/DEX Andrew Johnson Corrosion and Steam Generator (NCSG)/New and Renewed Licenses (DNRL)
Brian Allik NCSG/DNRL Gregory Makar NCSG/DNRL James Gavula NCSG/DNRL Leslie Terry NCSG/DNRL Lydiana Alvarado NCSG/DNRL Matthew Yoder NCSG/DNRL Paul Klein NCSG/DNRL Tony Gardner NCSG/DNRL David Pratt NCSG/DNRL Ali Rezai Piping and Head Penetrations (NPHP)/DNRL Bart Fu NPHP/DNRL Eric Reichelt NPHP/DNRL Jay Collins NPHP/DNRL John Honcharik NPHP/DNRL Roger Kalikian NPHP/DNRL Seung Min NPHP/DNRL Carolyn Fairbanks Vessels and Internals (NVIB)/DNRL Isaac Anchondo-Lopez NVIB/DNRL David Dijamco NVIB/DNRL Jim Medoff NVIB/DNRL Joel Jenkins NVIB/DNRL On Yee NVIB/DNRL Gordon Curran Containment and Plant Systems (SCPB)/Division of Safety Systems (DSS)
Brian Lee SPCB/DSS Nageswara Karipineni SCPB/DSS Chang Li SCPB/DSS Steve Jones SCPB/DSS Angelo Stubbs SCPB/DSS Christopher Jackson Nuclear Systems Performance (SNSB)/DSS Ben Parks Nuclear Methods and Fuels (SFNB)/DSS Joey Messina SFNB/DSS Angela Wu License Renewal Projects Branch (NLRP)/DNRL Marieliz Johnson NLRP/DNRL Bill Rogers NLRP/DNRL
- 7. Logistics The Aging Management Audit will be conducted primarily using telecommunications from July 26, 2021 to October 8, 2021, with potentially a portion of the On-Site Audit (Aging Management Audit Part #2), as determined appropriate, conducted at the applicants facility.
Entrance and exit briefings will be held at the beginning and end of the audit via telecommunications.
- 8. Special Requests The NRC staff requests the applicant to make available the SLRA program basis documentation and drawings, and other documents as requested.
- 9. Deliverables An audit report should be issued to the applicant within 90 days from the end of the Aging Management Audit.