Revised Monthly Operating Rept for Dec 1988 for Fermi 2
ML20245A275
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 12/31/1988
From: Anthony P
DETROIT EDISON CO.
To:
Shared Package
ML20244E243 List:
References
NUDOCS 8904250122
Download: ML20245A275 (1)


Text

_

OPERATING DATA REPORT DOCKET NO.

50-341 COMPLETED BY P. M. Anthony DATE April 17, 1989 TELEPHONE (313)586-1617 OPERATING STATUS 1.

UNIT NAME:

Fermi 2 l Notes:

l 2.

REPORTING PERIOD: December, 1988 l

l 3

LICENSED THERMAL POWER (MWt): 3292 I

  • To be determined I

4.

NAMEPLATE RATING (GROSS MWe):

1154 i

I 5

DESIGN ELECT RATING (Net MWe): 1093 I

I 6.

MAX DEPENDABLE CAP (GROSS MWe):

l l

7 MAX DEPENDABLE CAP (Net MWE):

l l

8.

IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS: None 9

POWER LEVEL TO WHICH RESTRICTED, IF ANY (MWe Net):

None

10. REASONS FOR RESTRICTION, IF ANY: None THIS MONTH YR TO DATE CUMULATIVE
11. HRS IN REPORTING PERIOD 744 8246 8246
12. HRS REACTOR WAS CRITICAL 744 5022.5 5022.5
13. REACTOR RESERVE SHUTDOWN HRS 0

0 0

14. HOURS GENERATOR ON-LINE 744 4720.8 4720.8
15. UNIT RESERVE SHUTDOWN HOURS 0

0 0

16. GROSS THERMAL ENERGY GEN (MWH) 2,388,264 13,029,452 13,029,452
17. GROSS ELECT ENERGY GEN I'fWH) 804,824 4,278,093 4,278,093
18. NET ELECT ENERGY GEN (MWH) 773,556 4,082,134 4,082,134 l'
19. UNIT SERVICE FACTOR 100 57.2 57.2
20. UNIT AVAILABILITY FACTOR 100 57.2 57.2
21. UNIT CAP FACTOR (USING MDC NET)
22. UNIT CAP FACTOR (USING DER NET) 95.1 45 3 45 3
23. UNIT FORCED OUTAGE RATE 0

24.0 24.0

24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, DURATION OF EACH)

None

25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

FORECAST ACHIEVED INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A 8904250122 890417

~

DR ADOCK 05000341 PNU