OPERATING DATA REPORT j
DOCKET NO. 50-341 COMPLETED BY P. M. Anthony DATE April 17, 1989 TELEPHONE (313)586-1617 OPERATING STATUS-1.
UNIT.NAME:
Fermi 2 INotes:
l 2.
REPORTING PERIOD: November, 1988' l
l 3
LICENSED THERMAL POWER (MWL):
3292 l
- To be determined I
4.
NAMEPLATE RATING (GROSS MWe):
1154 l
l 5
DESIGN ELECT RATING (Net MWe): 1093 I
I 6.
MAX DEPENDABLE CAP (GROSS MWe):
l l
7 MAX DEPENDABLE CAP (Net MWE):
I l
8.
IF-CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS: None 9
POWER LEVEL TO WHICH RESTRICTED, IF ANY (MWe Net):
None
- 10. REASONS FOR RESTRICTION, IF ANY: None THIS MONTH YR TO DATE CUMULATIVE
- 11. HRS IN REPORTING PERIOD 720 7502 7502
0 0
- 14. HOURS GENERATOR ON-LINE 551.1 3975.8 3975.8
- 15. UNIT RESERVE SHUTDOWN HOURS 0
0 0
- 16. GROSS THERMAL' ENERGY GEN (MWH) 1,719,192 10,641,188 10,641,188
'17. GROSS ELECT ENERGY GEN (MWH) 589,080 3,473,269 3,473,269
- 18. NET ELECT ENERGY GEN (MWH) 564,668 3,308,578 3,308,578 l1
- 19. UNIT SERVICE FACTOR 76.5 53 0 53 0
- 20. UNIT AVAILABILITY FACTOR 76.5 53 0 53 0
- 22. UNIT CAP FACTOR (USING DER NET) 71.7 40.4 40.4 I
- 23. UNIT FORCED OUTAGE RATE O
27 3 27 3
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, DURATION OF EACH)
None
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
FORECAST ACHIEVED INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A 8904250120 890417
?