OPERATING DATA REPORT-DOCKET NO. 50-341 COMPLETED BY P. M. Anthony DATE April 17, 1989 TELEPHONE (313)586-1617 OPERATING STATUS 1.
UNIT NAME:
Fermi 2 INotes:
I 2.
REPORTING PERIOD: July, 1988 l
1 3
LICENSED THERMAL POWER (MWt): 3292 l
- To be determined l
4.
NAMEPLATE RATING (GROSS MWe):
1154 l
I 5.
DESIGN ELECT RATING (Net MWe): 1093 I
I 6.
MAX DEPENDABLE CAP (GROSS MWe):
l l'
7 MAX DEPENDABLE CAP (Net MWE):
l l
8.
IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS: None 9
POWER LEVEL TO WHICH RESTRICTED, IF ANY (MWe Net):
None
- 10. REASONS FOR RESTRICTION, IF ANY: None THIS MONTH YR TO DATE CUMULATIVE
- 11. HRS IN REPORTING PERIOD 744 4573 4573
- 12. HRS REACTOR WAS CRITICAL 543 2 2621.1 2621.1
- 13. REACTOR RESERVE SHUTDOWN HRS 0
0 0
- 14. HOURS GENERATOR ON-LINE 537.5 2517.8 2517.8
- 15. UNIT RESERVE SHUTDOWN HOURS 0
0 0
- 16. GROSS THERMAL ENERGY GEN (MWH) 1,669,848 6,515,540 6,515,540
- 17. GROSS ELECT ENERGY GEN (MWH) 557,802,
2,118,955 2,118,955
- 18. NET ELECT ENERGY GEN (MWH) 331, 9 2 2,016,299 2,016,299
- 19. UNIT SERVICE FACTOR 72.2 57.3 57 3
- 20. UNIT AVAILABILITY FACTOR 72.2 57 3 57 3
- 22. UNIT CAP FACTOR (USING DER NET) 65.3 40 3 40 3 f
- 23. UNIT FORCED OUTAGE RATE 27.8 8.1 8.1
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, DURATION OF EACH)
None
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
FORECAST ACHIEVED INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A 8904250113 890417 PDR ADOCK 05000341 R