Ack Receipt of Ltr Re Plant.Commission Decision Authorizing Low Power Testing & Fuel Loading First Step in Review. Earthquake-related Issues Will Be Addressed in Detail by Commission
ML20153C195
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 10/27/1981
From: Bradford P
NRC COMMISSION (OCM)
To: Dressendorfer
AFFILIATION NOT ASSIGNED
Shared Package
ML20151Y970 List: ... further results
References
FOIA-87-444 NUDOCS 8805060180
Download: ML20153C195 (1)


Text

.

O

")

'[

'c,.

UNITED STATES y'

NUCLEAR REGULATORY COMMISSION

{

I wAswisatoN.o.c.nosss

%.... + /,/

t October 27, 1981 opres or Twa commoNem Pat Dressendorfer 1926 Cragin Drive Bloomfield, Hills, MI 48013

Dear Hs. Dressendorfer:

Thank you very much for your letter regarding Diablo Canyon. The I

recent Comission decision authorizing low-power testing and fuel loading l

is only the first step in Comission review of this plant. Specifically, the earthquake-related issues that distinguish Diablo Canyon from most other nuclear units have not yet been addressed in detail by the Comission.

They will be reviewed before operation above five percent power is authorized.

While it may have some syt.bolic importance, a decision to authorize l

low-power testing poses very little danger to the public. The power level is so low that the operators have more than ample time to react to any problems in the plant, and the amount of radioactivity existing in the core does not begin to build up until the plant has operated for quite a while.

Sincerely.

[

b-/

peter A. Brauford Comissioner 1

l l

8805060180 800418 PDR FOIA HAMLIN87-444 PDR l