|
---|
Category:SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE
MONTHYEARML20244A8021989-03-28028 March 1989 SALP Rept 50-312/88-39 for July 1986 - Dec 1988 IR 05000312/19880391989-03-28028 March 1989 SALP Rept 50-312/88-39 for July 1986 - Dec 1988 IR 05000312/19860291986-08-12012 August 1986 SALP Rept 50-312/86-29 for June 1985 - June 1986 ML20132G1471985-09-25025 September 1985 Corrected Pages 11 & 21 to SALP Rept 50-312/85-18,correcting Typos & Editorial Errors Re Performance Analysis IR 05000312/19850181985-09-0909 September 1985 SALP Rept 50-312/85-18 for Dec 1983 - May 1985,conducted on 850807.Overall Performance Acceptable 1989-03-28
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000312/19990031999-08-31031 August 1999 Insp Rept 50-312/99-03 on 990802-06.No Violations Noted. Major Areas Inspected:Decommissioning & Dismantlement Activities,Including Organization,Mgt & Cost Controls IR 05000312/19990021999-03-19019 March 1999 Insp Rept 50-312/99-02 on 990309-11.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program, Including Access Authorization,Alarm Station & Communication & Testing & Maint IR 05000312/19980031998-08-0707 August 1998 Insp Rept 50-312/98-03 on 980706-09.No Violations Noted. Major Areas Inspected:Review of Licensee Programs Related to SFP Safety,Status of Decommissioning,Safety Review & self-assessments & Radiological Safety Programs ML20248K6301998-06-0303 June 1998 Notice of Violation from Insp on 980519-21.Violation Noted:Inspector Determined That Licensee Failed to Review & Consider All Info Obtained During Background Investigation IR 05000312/19980021998-06-0303 June 1998 Insp Rept 50-312/98-02 on 980519-21.Violations Noted. Major Areas Inspected:Announced Insp of Licensee Physical Security Program ML20202C4771998-02-0505 February 1998 Notice of Violation from Insp on 980105-08.Violation Noted: on 971222,shipment of Scrap Metal,In Form of Auxiliary Boiler,Was Released from Rancho Seco Site W/O Having Been Surveyed ML20202C4981998-02-0505 February 1998 Insp Rept 50-312/98-01 on 980105-08.Violations Noted.Major Areas Inspected:Organization,Mgt & Cost Controls,Maint & Surveillance,Cold Weather Preparation,Decommissioning Performance & Status Review & Health Physics ML20198K5451997-10-21021 October 1997 Notice of Violation from Insp on 970922-25.Violation Noted:On 970806,thermocouple for Spent Fuel Pool Temp Indicator Was Found to Be out-of-tolerance During Annual Calibration IR 05000312/19970041997-10-21021 October 1997 Insp Rept 50-312/97-04 on 970922-25.Violations Noted. Major Areas Inspected:Organization,Mgt,Cost Control,Safety Reviews,Design Changes,Mods,Decommissioning Performance & Status Review IR 05000312/19970031997-06-17017 June 1997 Insp Rept 50-312/97-03 on 970603-05.No Violations Noted. Major Areas Inspected:Records & Repts,Testing & Maint, Protected Area Barrier & Detection Aids,Assessment Aids, Alarm Station & Communication & Security System IR 05000312/19970021997-04-25025 April 1997 Insp Rept 50-312/97-02 on 970331-0403.No Violations Noted. Major Areas Inspected:Incremental Decommissioning Activities in Turbine Bldg,Radiation Protection,Sfp Activities & Quality Assurance IR 05000312/19970011997-03-21021 March 1997 Insp Repts 50-312/97-01 & 72-0011/97-01 on 970224-27.No Violations Noted.Major Areas Inspected:Licensee Planned Work Associated W/Dismantlement of Turbine Bldg & Radiological Controls Being Implemented During Work Activities IR 05000312/19960031996-09-27027 September 1996 Insp Repts 50-312/96-03 & 72-0011/96-01 on 960909-12.No Violations Noted.Major Areas Inspected:Sfp & Radiological Ts,Radiological Exposure Controls & Implementation of New 10CFR49 Shipping Regulations IR 05000312/19930061993-09-0202 September 1993 Insp Rept 50-312/93-06 on 930819.No Violations or Deviations Noted.Major Areas Inspected:Licensee Employee Concerns Program IR 05000312/19930041993-08-11011 August 1993 Mgt Meeting Rept 50-312/93-04 on 930727.Major Areas Discussed:Status of Activities,Including Maint of Plant Equipment,Fire Protection Equipment & Plant Personnel Morale IR 05000312/19920071992-12-10010 December 1992 Insp Rept 50-312/92-07 on 921110-11.No Deviations or Violations Noted.Major Areas inspected:1992 Annual Emergency Preparedness Exercise & Associated Critiques & Inspector Identified Items IR 05000312/19900141990-11-14014 November 1990 Insp Rept 50-312/90-14 on 901003-04,09-11 & 1102.Violations Noted.Areas inspected:follow-up of Licensee Event Repts, Liquid Effluent,Solid Waste & Allegations IR 05000312/19900111990-07-31031 July 1990 Insp Rept 50-312/90-11 on 900527-0706.No Violations or Deviations Noted.Major Areas Inspected:Operational Safety Verification,Health Physics & Security Observations,Esf Sys Walkdown,Maint,Surveillance & Testing & QA IR 05000312/19890161989-09-21021 September 1989 Enforcement Conference Rept 50-312/89-16 on 890915. Violations Noted.Major Areas Discussed:Violations Noted in Insp Rept 50-312/89-16 & Indications That Findings Represent Decrease in Mgt Commitment to Emergency Preparedness IR 05000312/19890121989-09-21021 September 1989 Insp Rept 50-312/89-12 on 890801-04,21-25 & 30.No Violations Noted.Major Areas Inspected:Occupational Exposure,Including Alara,Radwaste Sys,Liquid & Liquid Wastes & Radwaste Mgt & Transportation PNO-V-89-056, on 890911,SMUD Board Rejected Golden State Energy Proposal to Purchase Plant1989-09-12012 September 1989 PNO-V-89-056:on 890911,SMUD Board Rejected Golden State Energy Proposal to Purchase Plant IR 05000312/19890141989-09-11011 September 1989 Insp Rept 50-312/89-14 on 890828-0901.Violations Noted Re Failure to Conduct Required Semiannual Health Physics Drill & Initial Training.Major Areas Inspected:Operational Status of Emergency Preparedness Program PNO-V-89-053, on 890901,Golden State Energy Proposal to Purchase Rancho Seco Submitted to Util,Including MOU for Purchase of Plant,Power Sale Agreement & Interim Operation & Maint of Facility & Rate Structure.Vote Expected on 8909071989-09-0505 September 1989 PNO-V-89-053:on 890901,Golden State Energy Proposal to Purchase Rancho Seco Submitted to Util,Including MOU for Purchase of Plant,Power Sale Agreement & Interim Operation & Maint of Facility & Rate Structure.Vote Expected on 890907 PNO-V-89-050, on 890823,util Announced That Board of Directors Would Meet on 890825 Re Proposed Golden State Energy Purchase of Plant.Key Issues Listed,Including MOU Addressing Power Sale Agreement1989-08-23023 August 1989 PNO-V-89-050:on 890823,util Announced That Board of Directors Would Meet on 890825 Re Proposed Golden State Energy Purchase of Plant.Key Issues Listed,Including MOU Addressing Power Sale Agreement IR 05000312/19890101989-08-10010 August 1989 Insp Rept 50-312/89-10 on 890603-0721.No Violations Noted. Major Areas Inspected:Areas of Operational Safety Verification,Health Physics & Security Observations,Maint, Surveillance & Testing & QA & Followup Items PNO-V-89-044, on 890720,util Board Voted by 4-1 Vote to Enter Exclusive Negotiations W/Quadrex Corp for Possible Sale of Plant.Key Milestone Dates Listed.Board Maintained That Several Key Issues Must Be Addressed Before Voting on Sale1989-07-21021 July 1989 PNO-V-89-044:on 890720,util Board Voted by 4-1 Vote to Enter Exclusive Negotiations W/Quadrex Corp for Possible Sale of Plant.Key Milestone Dates Listed.Board Maintained That Several Key Issues Must Be Addressed Before Voting on Sale IR 05000312/19890081989-07-11011 July 1989 Insp Rept 50-312/89-08 on 890422-0602.No Violations or Deviations Noted.Two non-cited Violations Discussed.Major Areas Inspected:Operational Safety Verification,Health Physics & Security Observations & ESF Sys Walkdown IR 05000312/19890111989-07-0606 July 1989 Insp Rept 50-312/89-11 on 890629-30.No Violations Noted. Major Areas Inspected:Licensee Radiochemical Analyses to Verify Accuracy of Measurements of Radionuclides in Release Tank Water & Sediment from Effluent Discharge Point PNO-V-89-039, on 890620,util Announced That Licensee Open to Offers to Purchase Facility Until 890630.Of All Bidders,Only Quadrex Corp Proposes to Operate Facility as Nuclear Plant. Evaluation of Bids Expected to Be Completed by End of Jul1989-07-0303 July 1989 PNO-V-89-039:on 890620,util Announced That Licensee Open to Offers to Purchase Facility Until 890630.Of All Bidders,Only Quadrex Corp Proposes to Operate Facility as Nuclear Plant. Evaluation of Bids Expected to Be Completed by End of Jul PNO-V-89-036, on 890620,SMUD Voted 3-2 to Allow 10 Days for Qualified Private Bidders to Submit Proposals to Take Over Facility.Conditions Imposed on Bidders Listed.Existing Quadrex Proposal Withdrawn1989-06-21021 June 1989 PNO-V-89-036:on 890620,SMUD Voted 3-2 to Allow 10 Days for Qualified Private Bidders to Submit Proposals to Take Over Facility.Conditions Imposed on Bidders Listed.Existing Quadrex Proposal Withdrawn PNO-V-89-035, on 890619,licensee Announced That D Keuter Had Been Appointed New Site Manager & Jr Shetler as Deputy Site Manager.Licensee Recognizes That Organizational Changes Subj to NRC Approval1989-06-20020 June 1989 PNO-V-89-035:on 890619,licensee Announced That D Keuter Had Been Appointed New Site Manager & Jr Shetler as Deputy Site Manager.Licensee Recognizes That Organizational Changes Subj to NRC Approval PNO-V-89-034, on 890615,offer to Assume Financial & Technical Responsibility for Plant Announced.Plant Presently in Cold Shutdown W/Activities Continuing Towards off-loading Reactor Core in Oct 19891989-06-16016 June 1989 PNO-V-89-034:on 890615,offer to Assume Financial & Technical Responsibility for Plant Announced.Plant Presently in Cold Shutdown W/Activities Continuing Towards off-loading Reactor Core in Oct 1989 PNO-V-89-033C, on 890609,plant Reached Cold Shutdown in Preparation for Reinstalling Refueling Bridge Into Reactor Bldg.Bridge Removed for Refurbishment/Mod.Reduction in Force of Nonessential Contractor Personnel in Progress1989-06-12012 June 1989 PNO-V-89-033C:on 890609,plant Reached Cold Shutdown in Preparation for Reinstalling Refueling Bridge Into Reactor Bldg.Bridge Removed for Refurbishment/Mod.Reduction in Force of Nonessential Contractor Personnel in Progress PNO-V-89-033B, on 890608,licensee Continuing Cooldown of Plant.Ceo Nuclear,J Firlit,Announced Resignation.Work Force Reductions Initiated Which Will Initially Involve Approx 420 Nonessential Contractor Clerical & Crafts Personnel1989-06-0808 June 1989 PNO-V-89-033B:on 890608,licensee Continuing Cooldown of Plant.Ceo Nuclear,J Firlit,Announced Resignation.Work Force Reductions Initiated Which Will Initially Involve Approx 420 Nonessential Contractor Clerical & Crafts Personnel PNO-V-89-033A, on 890607,util Shut Down Plant & Entered Hot Shutdown Due to Voter Defeat of Measure K.Util Continuing to Implement Contingency Plan to Remove Plant from Svc. Reductions in Site Work Force Under Consideration1989-06-0707 June 1989 PNO-V-89-033A:on 890607,util Shut Down Plant & Entered Hot Shutdown Due to Voter Defeat of Measure K.Util Continuing to Implement Contingency Plan to Remove Plant from Svc. Reductions in Site Work Force Under Consideration PNO-V-89-033, on 890606,voters Defeated Measure K,Encouraging Util to Cease Operating Facility.Util Board Previously Announced That Plant Would Be Shutdown If Measure K Defeated.Safe Shutdown Plan Implemented1989-06-0707 June 1989 PNO-V-89-033:on 890606,voters Defeated Measure K,Encouraging Util to Cease Operating Facility.Util Board Previously Announced That Plant Would Be Shutdown If Measure K Defeated.Safe Shutdown Plan Implemented PNO-V-89-030, on 890518,airborne Process Monitors for Reactor Bldg Stack,Auxiliary Bldg Stack & Auxiliary Bldg Grade Level Vent Inoperable.Caused by Computer Controlled Svc Air Purge Valves in Open Position.Possibly Caused by Software Errors1989-05-19019 May 1989 PNO-V-89-030:on 890518,airborne Process Monitors for Reactor Bldg Stack,Auxiliary Bldg Stack & Auxiliary Bldg Grade Level Vent Inoperable.Caused by Computer Controlled Svc Air Purge Valves in Open Position.Possibly Caused by Software Errors IR 05000312/19890071989-04-28028 April 1989 Insp Rept 50-312/89-07 on 890417-21.No Violations Noted. Major Areas Inspected:Previously Identified Items & Status of Emergency Preparedness Program IR 05000312/19890041989-03-31031 March 1989 Insp Rept 50-312/89-04 on 890114-0303.Violations Noted.Major Areas Inspected:Operational Safety Verification,Health Physics & Security Observations,Esf Sys Walkdown,Maint,Qa Surveillance & Testing & Followup Items ML20248J6521989-03-31031 March 1989 Notice of Violation from Insp on 890114-0303.Violations Noted:Engineering Change Notice Not Initiated for Rebuilt Governor for Auxiliary Feed Pump Installed on 890131 & Maint Work Request Not Reviewed Prior to Performance of Test IR 05000312/19880391989-03-28028 March 1989 SALP Rept 50-312/88-39 for July 1986 - Dec 1988 ML20244A8021989-03-28028 March 1989 SALP Rept 50-312/88-39 for July 1986 - Dec 1988 ML20244B1141989-03-27027 March 1989 Notice of Violation from Insp on 890123-0217.Violations Noted:Nonconformance Rept Not Written After Determination That Debris Caused Failure of Two Instrument Air Sys Check Valves During Performance of Test Procedure STP-774 ML20244B1161989-03-24024 March 1989 Insp Rept 50-312/89-01 on 890123-0217.Violations Noted.Major Areas Inspected:Maint Program & Implementation of Related Activities IR 05000312/19880421989-02-13013 February 1989 Insp Rept 50-312/88-42 on 881227-30 & 890125-27.No Violations Noted.Major Areas Inspected:Followup Items,Part 21 Repts,Lers & Licensee Program to Maintain Quality of Diesel Generator Fuel Oil IR 05000312/19880411989-02-13013 February 1989 Insp Rept 50-312/88-41 on 881214-890103.No Violations Noted. Major Areas Inspected:Onsite Followup of Event of 881212 & Associated Mgt Meetings on 881219 & 890103.Weaknesses Observed Re Decision to Operate Plant in Degraded State IR 05000312/19880401989-02-0606 February 1989 Insp Rept 50-312/88-40 on 881208-890113.No Violations or Deviations Noted.Major Areas Inspected:Operational Safety Verification,Health Physics & Security Observations,Esf Sys Walkdown,Maint,Qa & Surveillance & Testing ML20235T2211989-02-0606 February 1989 Exam Rept 50-312/OL-88-02 on 881206-13.Exam Results:All Seven Senior Reactor Operator Candidates Passed Written & Oral Exams ML20196B6881988-11-30030 November 1988 PNS-V-88-006:on 881126,licensee Received Telcon Alleging That Nonlicensed Equipment Operator Observed Using Illegal Drugs.Individual Submitted to Urinalysis Test & Showed Positive for Marijuana.Individual Terminated on 881130 IR 05000312/19880351988-11-21021 November 1988 Mgt Meeting Rept 50-312/88-35 on 881114.Major Areas Discussed:Licensee Operational Performance Since Restart in Mar 1988 & Progress Re Restart Commitments in Areas of Engineering,Procurement,Maint & Effluent Sys Areas 1999-08-31
[Table view] |
See also: IR 05000312/1985018
Text
. . _ - . . _ _ ._ _. . _ _ __ __._ _ _ __
4
' ' '
, . .. <
. t
-
.
.,
, .
3 ,
,
,
'
'
!. . f ,'
Errata Sheet No; 1
-
. .
SALP Board Report'No.- 50-312/85-18' ,
+
Part IV, Performance Analysis -
Section 4, Surveillance
,
- Page 11, Paragraph 3, lines 1 th' rough 4 s
.
Now Reads: -
-
"In the surveillance areas, one notice of violation.was issued during this
- SALP period;-this dealt with the procedures for safety-related battery
testing. The procedures contained numerous errors and in certain cases data
had been incorrectly recorded."
{ Should Read:
"In the surveillance area, three violations were issued during this SALP
- period. One dealt with procedures for safety-related battery testing, which
contained numerous errors including incorrect data. A second violation
concerned incomplete calibration program records for plant gages. The third
'
violation identified a failure to test additional system valves-following a
valve operational failure during testing."
'
Basis:
l' SALP report tables 1 and 2 had been updated to include Inspection Report 85-23
'
which added two additional Level IV violations in the area of surveillances.
.However, these additional violations were not discussed in the text of-
Section 4. The above change references the additional violations for
~
3
completeness and consistency with the tables.
4
a
1
1
,
t
b*
d ,
i ,
!
)
.
851M104M g $12
,
PDR ADOCK PDR
Q
P
%
u
='Fyp-- air--
i
y-- 1yb' yr ee,r-w ,,o_p ny g- ga',y,,9%-43 ,,wy_pp % m p- ge,c.qy-, p _g w
9 99 9 19, 9..pg9,..g,y 7_ 9 y 79 psyy . %yp-m_w95,.g ._7p
..
-
11
. .
4.,. Surveillance
'., The surveillance program has been inspected periodically by the
'
esident and regional inspectors throughout this evaluation period.
ring the previous SALP period the licensee exhibited a decreasing
pe formance in the surveillance program; the performance rating for
thi. area was a Category 3. This was mainly based on poor
mana . ment controls in the planning, scheduling, and performance of
surver lances required by the Technical Specification.
. During t 's SALP period, the licensee has effectively used the daily
managemen meetings to provide status of surveillance tests. This
increase in management attention has greatly reduced the amount of
missed surve llances and requests for Technical Specification
changes to de y surveillances.
In the surveilla c ae , one notice of violation was issued during
, this SALP period; t ealt with the procedures for safety-related
battery. testing. e cedures contained numerous errors and in
certain cases data h d een incorrectly recorded. The licensee has
begun a program to id tify a d correct the surveillance program.
The licensee identifie in run LERs that surveillance procedures
'
did not provide the pro r ria or were missing equipment or
were basically improperly wr to satisfy the stated purpose.
Some of the.. corrective act ns the surveillance area include:
Technical specification eq ents to be provided in the
surveillance procedure,
A t,st developed to cross r erttgfeb surveillance requirements
by surveillance procedure, ,
- A review of all pertinent Ranch Seh cuments to develop all
licensee surveillance commitment
A surveillance procedure writer's g "deline,
A review of all existing surveillance rocedures against the
writer?s guideline.
These items are at different stages of completi n but are scheduled
to be completed late in 1985. .This program shou d identify areas ,
were some surveillance procedures have failed to clude all i
pertinent criteria from the Technical Specificatior and provide the j
licensee further assurance that the surveillances a testing the i
systems in a manner appropriate with the systems func ion. l
The licensee is also discussing the concept of system e ineering,
where one engineer is responsible for a given system. Th s would
include maintenance, modifications, operational requiremen s,
industry problems, and surveillance trending of the system. This
should enhance the surveillance program by providing addition 1
'
levels of assuring the systems operability.
l
1
"0RIGINAL PAGE" 1
t I
i
11
.
.
4. Surveillance
The surveillance program has been inspected periodically by the
resident and regional inspectors throughout this evaluation period.
During the previous SALP period the licensee exhibited a decreasing
performance in the surveillance program; the performance rating for
this area was a Category 3. This was mainly based on poor
management controls in the planning, scheduling, and performance of
surveillances required by the Technical Specification.
During this SALP period, the licensee has effectively used the daily
management meetings to provide status of surveillance tests. This
increase in management attention has greatly reduced the amount of
missed surveillances and requests for Technical Specification
changes to delay surveillances.
In the surveillance area, three violations were issued during this
SALP period. One dealt with procedures for safety-related battery
testing, which contained numerous errors including incorrect dcLt.
A second violation concerned incomplete calibration program r tocds
for plant gages. The third violation identified a failure to test
additional system valves following a valve operational failure
during testing. The licensee has begun a program to identify sad
correct the surveillance program. The licensee identified in ulr.e
LERs that surveillance procedures did not provide the proper
criteria or were missing equipment or were basically improperly
written to satisfy the stated purpose. Some of the corrective
actions in the surveillance area include:
Technical specification requirements to be provided in the
surveillance procedure,
- A list developed to cross reference surveillance requirements
by surveillance procedure,
A review of all pertinent Rancho Seco documents to develop all
licensee surveillance commitments,
- A surveillance procedure writer's guideline,
- A review of all existing surveillance procedures against the
writer's guideline.
These items are at different stages of completion but are scheduled
to be completed late in 1985. This program should identify areas
were some surveillance procedures have failed.to include all
pertinent criteria from the Technical Specifications and provide.the
licensee further assurance that the surveillances are testing the
systems in a manner appropriate with the systems function.
The licensee is also discussing the concept of system engineering,
where one engineer is responsible for a given system. This:would
include maintenance, modifications, operational requirements,
industry problems, and surveillance trending of the system'. -This
~
should enhance the surveillance program by providing additional
levels of assuring the systems operability. -
'
" CORRECTED PAGE"
.
_ _ _______
o
Errata Sheet No. 2
- SALP Board Report No. 50-312/85-18
Part IV, Performance Analysis
Section 9, Quality Programs and Administrative Controls
Page 21, Paragraph 2, lines 1 and 2
,
Now Reads:
"A total of eight violations (Level IV and V) were issued in this functional
area. An additional nine violations (Level IV and V) in...."
Should Read:
,
"A total of 10 violations (Level IV and V) were issued'in this functional
area. An additional 8 violations (Level IV and V) in...."
Basis:
SALP table 2 lists a total of 18 violations, eight of which were identified as
PAB findings, including one violation with two examples. The above change
corrects the text of Section 9 to be consistent with the tables.
.
a
w y -.._ --
, . .- . . ,
. 21
e -
'
.
report's recommendations are su'fficient to ensure substantial
uality program improvement occurs at Rancho Seco.
A tal of eight'Vi_olations (Level IV and V) were issued in this
fun ional area. ,An3 additional nine violations (Level IV and V) in
this rea were issued as a result of.the Performance Appraisal
Branch (PAB) inspection performed in November 1983. These PAB
finding although~ issued as violations during the present SALP
cycle,1w e actually used to evaluate the previous SALP period and
thus were ot used for the present assessment. The violations
identified uring this period were all of a minor nature, but are an
indication-t t the need to follow the details of administrative ,
requirements eds em hasis.
One of the major we ss identified by PAB (and factored into the
previous SALP res t. > 'as in the area of administrative controls of
the safety review mm Ttees, that.is, the Plant Review Committee
(PRC) and the Manage ent Safety Review Committee (MSRC). The
inspectors have note erf mance improvement in both of these
committees,.not only f in administrative viewpoint but, more
importantly, from the v wpt(fht of. safety and the depth of
evaluating and resolving 'ssqm. Examples of the improved
thoroughness of these comm~tt were noted during recent problems
with reactor trip breakers. d nt concerns with the auxiliary
.feedwater system.
i The Quality Assurance organizat'on ' If has undergone a
!
reorganization and expansio'n dur g 's SALP cycle and appears to
have made some improvements and c tr tions in the area of
surveillances of daily routine act1 it such as health physics
practices and operations. In additi n,. Quality Control
organizations, which have previously een separate organizations
(one reporting to plant engineering an the o her to nuclear
engineering through construction) have en combined into one
organization which now reports to Qualit Assurance. This
reorganization has the potential for impro ing the independence and
effectiveness of quality control. However, notwithstanding these
changes, the staff considers that the Qualit Assurance organization
must-expand the scope of their activities and ecome more agressive
in areas'such as engineering, construction, an maintenance.
Management needs to continue to support the Qual ty Assurance effort
l and demand that it be a strong and viable tool to .nsure quality.
Close scrutiny of progress is needed.
A root cause program has been created in the regulato compliance
organization during this SALP cycle. The purpose of t 's group is
to determine the cause of plant events so as to minimiz the
l potential for similar future events. This program is co idered to
l
be extremely valuable and management should continue to su ort its
,
development and implementation. It is too early to tell if it will
! be effective.
j In summary, it is obvious that the management of Rancho Seco an the
l SMUD Board of Directors have made a change over the past several
"0RIGINAL PAGE"
r
-
- _ , _ _ . - ~ . _ - , - __ -,_. ,.___ - . _ . _.
_ _ _
.*
L - 21
, .- .
report's recommendations are sufficient to ensure substantial
quality program improvement occurs at Rancho Seco.
A total of 10 violations (Level IV and V) were issued in this
functional area. An additional 8 violations (Level IV and V) in
this area were issued as a result .of the Performance Appraisal
Branch (PAB) inspection performed in November 1983. These PAB
findings, although issued as violations during the present SALP
cycle, were actually used to evaluate the previous SALP period and
thus were not used for the present assessment. The violations
identified during this period were all of a minor nature, but are an
indication that the need to follow the details of administrative
requirements needs emphasis.
,
One of the major weakness identified by PAB (and factored into the
previous SALP results) was in the area of administrative controls of
the safety review committees, that is, the Plant Review Committee
(PRC) and.the Management Safety Review Committee (MSRC). The
inspectors have noted performance improvement in both of these
committees, not only from an administrative viewpoint but, more
importantly, from the viewpoint of safety and the depth of
evaluating and resolving issues. Examples of the improved
thoroughness of these committees were noted during recent problems
with reactor trip breakers and recent concerns with the auxiliary
feedwater system.
The Quality Assurance organization itself has undergone a !
reorganization and expansion during this.SALP cycle and appears to
have made some improvements and contributions in the area of
surveillances of daily routine activities such as health physics
practices and operations. In addition, the Quality Control
l organizations, which have previously been two separate organizations
I (one reporting to plant engineering and the other,t'o nuclear
engineering through construction) have been combined into one
~
organization which now reports to Quality, Assurance. This
reorganization has the potential for improving the independence and
effectiveness of quality control. However, notwithstanding these
! changes, the staff considers that the Quality Assurance organization
must expand the scope of their activities.and become more agressive
in areas such as engineering, construction,'and maintenance.
I Management needs to continue to support the Quality Assurance effort
i and demand that it be a strong and viable tool to ensure quality.
Close scrutiny of progress is needed.
A root cause program has been created in the regulatory compliance
organization during this SALP cycle. The purpose of this group is
to determine the cause of plant events so as to minimize the
potential for similar future events. This program is considered to
be extremely valuable and management should continue to support its
development and implementation. It is too early to tell if it will
be effective.
In summary, it is obvious that the management of Rancho Seco and the
SMUD Board of Directors have made a change over the past several
" CORRECTED PAGE"
. . - - _ _ _ - - - .- _
-