ML20097H751
ML20097H751 | |
Person / Time | |
---|---|
Site: | Columbia |
Issue date: | 04/23/1992 |
From: | Harold L WASHINGTON PUBLIC POWER SUPPLY SYSTEM |
To: | |
Shared Package | |
ML20093B989 | List: |
References | |
FOIA-94-137 10.25.89, NUDOCS 9208280288 | |
Download: ML20097H751 (87) | |
Text
{{#Wiki_filter:,. . M ji a L VERIFY PRIOR To UsE
..........uc...
SUPPLY SYSTEM 15 ATE / / 1/27 /s u WNP-2 PLANT PROCEDURES MANUAL PROCEDURE NUMBER APPROVED BY . DATE
*10.25.89 ,'
VOLUME NAME MAINTENANCE PROGRAMS AND PROCEDURES SECT!oN l ELECTRICAL MAINTENANCE PROCEDURES 4 TITLE ONE HOUR - THREE HOUR FIRE BARRIER INSTALLATION TABLE OF CONTENTS Page No. , 1.0 PURPOSE ................................................ 5
2.0 REFERENCES
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 3.0 PREREQUISITES ........................................... 7 4.0 PRECAUTIONS AND LIMITATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 5.0 MATERIALS, TOOLS, AND TEST EQUIPMENT . . . . . . . . . . . . . . . . . . . . . . 8 6.0 PROCEDURE (THERMO-LAG) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 6.1 Fabrication and Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 i 6.1.1 Cable Tray Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
- a. Direct Spray or Trowel Application Over Stress Skin . . . . . . . . . 10
- b. Prefabricated Board ............................. 12 6.1.2 Conduit and Instrument Tubing .......................... 12
- a. Direct Spray or Trowel Application Over Stress Skin . . . . . . . . . 12
- b. Prefabricated Board ............................. 13
- c. Installation of the One Hour /Three Hour Fire Barrier Design Utilizing Pre Shaped Conduit Sections . . . . . . . . . . . . . 13 PROCEDURE NUMBER REVISION FACE 10.25.89 - 9 1 of 87 0I
$2D821'O M f 0h '
'Q .
t
- r TABLE OF CONTENTS (Continued)
Page No.
- d. Installation of a One-Hour /Three-Hour Preshaped Conduit Section Design Mounted Immediately Adjacent to a Concrete ;
Wall . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 - ,
- e. Direct Spray Application .......................... 14
- f. Interface Application with 3M. 3 Hour Rated Wrap . . . . . . . . . . 14 6.1.3 Cable Drops . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
- a. Direct Spray or Trowel Application Over Stress Skin . . . . . . . . . 15 6.1.4 Cable Drop Junction With Cable Tray Or Conduit . . . . . . . . . . . . . . . 16
- a. Conduit Junction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 ,
- b. Cable Tray Junction - Open End (Attachment 9.2, Page 6) ..... 16 6.1.5 Cable Drop / Conduit Junction With Bottom or Side of Cable Tray . . . . . 17
- a. Direct Spray or Trowel Application Over Stress Skin . . . . . . . . . 17 6.1.6 Cables Within Cable Trays - Direct Spray . . . . . . . . . . . . . . . . . . . . 17
- a. Cleanliness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
- b. Fire Break or RG 1.75 Barrier Application . . . . . . . . . . . . . . . 18
- c. Application as a One Hour Barrier . . . . . . . . . . . . . . . . . . . . 19
- d. Coating Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
- c. Vertical Fire Stops . . . . . . . . . . . . . . . . . . . . . . . . . . n . 19 6.1.7 Junction Box . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 0
- a. Direct Spray or Trowel Application Over Stress Skin . . . . . . . . . 20
- b. Prefabricated Board ............................20 6.1.8 Structural Steel Supports or Cable Tray Hangers . . . . . . . . . . . . . . . . 20
- a. Direct Spray or Trowel Application . . . . . . . . . . . . . . . . . . . 21
- b. Areas of Support Steel / Hangers to be Covered . . . . . . . . . . . . . 21
- c. Typical Application for Instrument Tubing Supports . . . . . . . . . . 22 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 2 of 87
[ TABLE OF CONTENTS Page No. 6.1.9 Coating Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
- a. Fire Retardant Thermo-Lag 270 . . . . . . . . . . . . . . . . . . . . . 23 1
- b. One-Hour Barriers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - 23 1 1
- c. Three-Hour Barriers . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 l 1
- d. Spray Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 j
- e. Required Wet Film Thickness . . . . . . . . . . . . . . . . . . . . . . 24 g
6.1.10 Fire Stops ........................................ 25'
- a. Examples of fire stops . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 ;
6.2 Repair - Thermo-Lag 330-1 or Prefab Application . . . . . . . . . . . . . . . . . . . . 26 - 6.2.1 Thermo-Lag 330-1 or Prefab Application . . . . . . . . . . . . . . . . . . . 26 6.2.2 Thermo-Lag 270 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 6.3 Repair - Structural Steel, Hangers or Supports . . . . . . . . . . . . . . . . . . . . . 26 6.4 Inspection ........................................... 27 6.4.1 Cleanliness - Structural Steel . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 6.4.2 Cleanliness - Fire Walls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 6.4.3 In-Process Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 , 6.4.4 Final Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28 6.4.5 Identification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28 7.0 PROCEDURE (3M FIRE PROTECTION SYSTEM - 3 HOUR) . . . . . . . . . . ... . . . 28 L 7.1 Preparation ..........................................28 7.2 Material ............................................29 1 7.2.1 Suppons .......................................29 1 7.2.2 E-50 Series Mat . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 f 7.2.3 Facing Tape (T-49) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 7.2.4 Caulk (CP-25) (98-04004250-7) . . . . . . . . . . . . . . . . . . . . . . . . . . 30 7.2.5 P u tty (3 03) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 0 7.2.6 Composite Sheet (CS-195) . . . . . . . . . .................... 30 i i in , PROCEDURE NUMBER REVISION PAGE 10.25.89 9 3 of 87
'ev -~ ~ -- .v,.a _, .,.m .r-a ,
e
TABLE OF CONTFETS Page No. 7.2.7 Banding Straps ................................... 30 7.2.8 Wire Mesh . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 0 3 7.2.9 Washers .......................................30 7.3 In spection . . . . . . . . . . . . . . . , . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 7.4 Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 7.5 Proper Repair of Any Gaps or Cuts in the System . . . . . . . . . . . . . . . . . . . . 31 ; 8.0 D OCUMENTATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 9.0 ATTACHMENTS ..........................................31 9.1 Inspection Form ....................................... 36 O.2 Specific Applications /Thermo-12g ............................37 9.3 Thickness Requirements for Thermo-12g . . . . . . . . . . . . . . . . . . . . . . . . . 66 9.4 Fire Stops /Thermo-I.ag 35 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72 , 9.5 3M 3 Hour Fire Protection Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74 l l l
)
1 l l FROC DURE NUMBER REV1SION FAGE 10.25.89 9 4 of 87
I 1.0 PURPOSE L The purpose of this procedure is to provide the basic steps involved in the fabrication and fire installation barrier. Drawing of a defines E948 Thermo-I.ag the 1 and 3type fire hour fire barrier barrier and/or a 3M requirements. u Flexible Wr
2.0 REFERENCES
2.1 Factory Mutual Bulletin OE6AS.AF (Factory Mutual Approval of TSI Thermo-Lag 270)
'2.2 TSI Technical Note 1130-83A, CVI 02-999-00-6 2.3 Interim Fire Protection Products Flexible Wrap System 2.4 Contract 215 Specification, Section 15S, Appendix 6, Technical Specifications for 3M Fire Protection System
! 2.5 WPTSI-C20610-F-001 through 0025, Requests for Clarification from TSI l 2.6 Engineering Calculation No. NE-02-86-23, Temperature Response of Structural Components to Appendix R Fire E 2.7 Engineering Calculation No. NE-02-8644, Temperature Response of Cables in One Hour Fire Areas 2.8 Engineering Calculation No. NE-02-86-39, Evaluation of Structural Supports to One Hour Fire Barriers 2.9 Engineering Calculation No. NE-02-88-10, Appendix R Analysis - Vital Instrument Sensing Line Supports 2.10 Engineering Calculation No. CE-02-89-20, Tubing Support Under Apprendix R-Fire 2.11 PER 291-0217 A {2.11} 2.12 PER 292-026, Potential Thermo-I.ag Installation Deficiencies l ! 2.13 WPBR-F-82-239, IOM, Use of Self Adhesive Insulation Pins and 14 Gauge Wire as a i Construction Aid 2.14 E948 APP. R Conduit Tray Plans and Sections 1 4
; PROCEDURENUMBER REVISION PAGE
} 10.25.89 9 5 of 87
, o 44 ~
I l 2.15 ITL Report 82-11-80, One Hour Fire Endurance Tests Conducted on Test Articles Containing Generic Cables Protected With Thermo-bg 330-1 Subliming Coating Envelope System 2.16 ITL Report 82-11-81, Three Hour Fire Endurance Tests Conducted on Test Articles Containing Generic Cables Protected With Thermo-Lag 330-1 Subliming Coating Envelope System 2.17 ITL Report 82-11-240, One Hour Fire Endurance Tests Conducted on the Thermo-Lag 330-1 Subliming Coating System Applied by Direct Spray-on Design to 4-inch Diameter Standard Electrical Conduit for Washington Public Power Supply System 2.18 ITL Report 82-5-355A, One Hour ASTM E119 Fire Simulation Facility Fire Tests Water Hose Stream Impacts Tests and Electrical Circuity Continuity Tests on Nuclear Facility Class IE Cable Trays and Conduit Test Assemblies Protected With a One Hour Fire Rated Design of the Thermo-bg 330-1 Subliming Coating Envelope System 1 2.19 ITL Report 82-5-355B, Three Hour Fire Endurance Tests on Thermo-Lag 330-1 Subliming Coating Envelope System for Washington Public Power Supply System Nuclear Projects 2.20 ITL Report 83-5-472, One Hour Fire Endurance Tests Conducted on the Thermo-Lag 330-1 Subliming Fire Barrier System Applied by Direct Spraying, Rolling and Troweling Methods to Class IE Electrical Cables in a Modified L. adder Cable Tray Test Article for Washington Public Power Supply System Nuclear Plants 2.21 ITL Report 84-12-181, Three Hour Fire Endurance Tests Conducted on a Ladder Cable Tray with a P-1000 Unistrut Attachment and Transition Section Protected with the Thermo-Lag 330 Fire Barrier System 2.22 ITL Report 87-5-77, One Hour ASTM Fire Endurance Test Conducted on a Ladder l Cable Tray with a P-1000 Unistrut Attachment Protected with the Thermo-Lag 330 Fire Barrier System Test performed to demonstrate the fire barrier design meets the 325*F cable surface temperature limitation, and that a protection of a 9" heat flow path will not degrade the electrical integrity of the protected assembly. 2.23 ITL Report 87-5-76, Three Hour Fire Endurance Test Conducted on a Two Inch Diameter Conduit Test Section Protected with the Thermo-Lag 330 Fire Barrier System Interfacing with Interam E-50D/E-54A Series Flexible Wrap System I i FROCEDURE NUMBER REVISION FACE l 10.25.89 9 6 of 87 l l . _ - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . - - - - - - . - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -------------------J
2.24 ITL Report 87-4-3, One Hour Fire Endurance Test Conducted on Four Inch Diameter Washington Public Power Supply System "In-Situ" Steel Conduit Sections Protected With the Thermo-Lag 330 Fire Barrier System Previously Applied by Washington Public Power Supply System Using a Low Pressure Extrusion Procedure 2.25 ITL Report 84-5-235, Three Hour ASTM E199 Fire Endurance Conducted on a Fire Wall Test Assembly Protected with the Thermo-lag 330 Fire Barrier System Test provided by TSI in 6-14-88 letter per TSI recommendation for protection of block wall by use of 1/2" dry film thickness of Thermo-Lag 330-1 applied to the proposed fire exposed side of the wall. 2.26 PPM 1.3.7, Maintenance Work Request 2.27 PPM 1.3.10, Supply System Fire Protection Program 2.28 PPM 1.11.8, Radiation Work Request 2.29 PPM 10.2.23, Concrete Anchors 2.30 PPM 10.25.54, Cable Pulling Instruction and Inspection 3.0 PREREOUISITES i 3.1 Obtain permission and signature from the Shift Manager before starting work. 3.2 As applicable, follow the requirements of the Radiation Work Permit per PPM 1.11.8. 3.3 Installers must be trained and certified to apply Thermo-Lag and/or 3M Fire Protection System. 3.4 Quality Control Inspectors must be traiaed and certified in the application of Thermo-Lag and/or 3M Fire Protection System. 4.0 PRECAUTIONS AND LIMITATIONS 4.1 When attaching materials together, always make sure you can see the wire / mechanical fastener being used. "Do not work in the blind". Do not probe installation materials with sharp tools such as awls, nails or. stiff wire. ! 4.2 Thermo-Lag 330-1 trowel or spray grade requires 30 day cure after installation to l achieve a 1-hour or 3-hour fire rating. Fire impairments shall not be removed until l the material has fully cured. c. PROCEDURE NUMBEA REVISION PAGE 10.25.89 9 7 of 87
4.3 Spraying of material may cause skin and/or eye irritation on contact. Therefore, the use of eye goggles is required, protective gloves, and long sleeve clothing is recommended where exposure exists. 4.4 All discrepancies encountered during installation shall be noted and reported to your
'immediate Supervisor and the Shift Manager.
5.0 MATERIALS. TOOLS. AND TEST EOUIPMENT 5.1 Thermo-I2g 5.1.1 Airless Spray Equipment 5.1.2 Hand Trowels 5.1.3 Fastening Material
- Tie Wire,18 gauge minimum stainless steel
- Staples, industrial grade 8 {2.11}
5.2 3M Fire Protection System j 5.2.1 Razor Knife i A razor knife shall be used to cut the 3M mat material to the required configurations. NOTE: 12rge scissors or snips may be used. Also, electric scissor-blade shears may be used to cut straight or curved pieces of the 3M mat material. 5.2.2 Rubber Roller ; A rubber roller or approved equal shall be used to insure the proper adhesion of the aluminum foil tape. NOTE: A plastic scraper or pliable straight-edge may be used to insure the proper adhesion of the aluminum foil tape. 5.2.3 Straight-Edge A straight-edged implement shall be used to aid in cutting straight pieces of l 3M mat material. l PROCEDURE NUMBER REVISION FAGE 10.25.89 9 8 of 87
~
. . . . - - - - ~ . . _ - . . - -_ - __ .
O l- 5.2.4 Marking Pen l i Marking pens shall be used to identify each layer of the 3M mat material by l individual number. I NOTE: Only those marking pens approved by the Chemistry group shall be , used in the Power-block area of WNP-2. ! 5.2.5 Measurine Taoe 1
\
A measuring tape or equal shall be used to properly size the pieces of 3M i mat material. ; 1 l
- 5.2.6 Electric Drill i An electric drill with carbide drill bits or approved equal shall be used to drill holes into the 3M CS-195 composite sheet and into the concrete.
5.2.7 Electric Saw l An electric hand jigsaw or sabre saw with metal cutting blade shall be used to cut the 3M CS-195 composite sheet. i 1 NOTE: Bandsaws, hacksaws, bench saws and the like may be used to cut j the 3M CS-195 composite sheet, l 5.2.8 Band Tensioner A band tensioner or approved equal may be used as an aid in securing the i banding straps around the 3M three (3) hour fire protection system. NOTE: Should crimp-type seals be used to secure the bands, a crimping tool or approved equal shall be used. l l l l I l
- I i
PROCEDURE NUMBPJL REVISION PAOE 10.25.89 9 9 of 87
i.
' 6.0 PROCEDURE (THERMO-LAG) .
i 6.1 Fabrication and Installation CAUTION: All 1 HOUR and 3 HOUR , Thermo-I2gging requires that a support analysis for extra loads has beer. completed and approved.
.QAUTION: Whra attaching materials together, always make sure you m see the wire / mechanical fastener :
being used. 'Do not work in blind". Do not probe ; installation ma erials with sharp tools such as awls, i nails or stiff wire. NOTE: A ONE HOUR Thermo-Lag raceway fire barrier consists of prefabricated board with a (dry film) thickness of 0.625 i 0.125 inches, with the stress skin facing i inwards towards the protected raceway. j NOTE: A THREE HOUR Thermo-I.ag raceway fire barrier may consist of one prefabricated panel with a (dry film) thickness of 1.250 i 0.125 inches with I embedded inner and outer layers of Stress Skin Type 330-69. Alternately, a THREE ; HOUR raceway barrier may consist of two one hour prefabricated panels, with j thickness as described above, applied to the raceway such that the embedded Stress l Skin forms the innermost and outermost layers of the barrier. l NOTE: THREE HOUR 'Ihermolag raceway fire barriers consisting of an inner layer of Stress Skin 330-69, a dry film thickness of 0.625 i 0.125 inches, a second layer of Stress Skin 330-69, and a second layer of Thermo-Lag with a dry film 1 thickness of 0.625 0.125 inches are installed in the plant. These barriers have a l third layer of hardware cloth or stress skin without V-stiffeners attached by staples as l the outermost layer. This configuration MAY NOT be used for the installation of new barriers. 6.1.1 Cable Tray Anoliention
- a. Direct Spray or Trowel Anolication Over Stress Skin (Attachment 9.2, Pages 1, 2, and 7)
- 1) Stress Skin 330-69 material shall be cut to ensure a sealed envelope around the applicable cable tray. This application shall be in accordance with approved drawings.
l I U PROCEDURE NUMBER REVISION PAGE 10.25.89 9 10 of 87 i
D
- 2) Stress Skin shall be cut in sections as depicted in Attachment 9.2, Page 1, or molded around the tray with a minimum overlap of one (1) inch to facilitate fastening.
- 3) Stress Skin may be applied around the cable tray and attached directly to the fire rated wall as discussed in item 5 below.
l]
- 4) All edges, flanges or overlapping surfaces of Stress Skin shall i be fastened together by using mechanical fasteners or minimum size 18 ga. stainless steel (SS) tie wire placed no greater than on twelve (12) inch centers.
- 5) When the fire rated wall is used as a portion of the fire barrier installation, Stress Skin shall be attached to the wall by the use ,
of mechanical fasteners as noted below. l i
- Hilti Kwik Bolts and Hilti Drop-in Concrete Anchors shall i be installed per PPM 10.2.23.
1
- Fastener penetration depth shall be 1-1/8" minimum. The fasteners shall be of such length to give at least this [
penetration while accommodating various thicknesses of l material being fastened. ' 1 i Fastener installation to be in accordance with l . manufacturer's recommendations and approved fastener f
- installation procedures. t i
The minimum distance between the two pin fastener's shall be 3" with a desired spacing of 12" center to center.
- Fastener edge distance from concrete shall be 2" minimum and minimum 1-1/2" from stress skin edges.
Use 1/4" Hilti Kwik Bolts /HDIs and PPM 10.2.23 or , attach to existing embedded unistrut with 1/4" diameter spring nuts, bolts and washers. Self adhesive insulation pins are acceptable for holding the Thermo-Lag until it has cured. Self adhesive insulation pins may be used only , for installations that are supported by the covered unit. ~
- 6) Apply required thickness (es) of Thermo-Lag 330-1 subliming coating in accordance with Section 6.1.9.
1
. PROCEDURENUMBER REVISION PAGE 10.25.89 9 11 of 87 h I
- b. Prefabricated Board (Attachment 9.2, Pages 7, 8, 9,-18, and 19)
- 1) Prefabricated board may be cut into individual pieces or scored -
for case of mounting to the applicable cable tray. Precoat edges on adjoining sections with a 1/4 to 1/2 inch bead of Thermo-Lag 330-1 subliming trowel grade material as necessary to ensure joints are filled to full depth of the prefabricated panel.
- 2) Prefabricated board may be temporarily held in place with the use of 14 ga. stainless steel tie wire spaced no greater than two-(2) feet on center.
- 3) Prefabricated boards shall be attached to each other by use of mechanical fasteners or minimum size 18 ga. stainless steel tie wire placed no greater than on twelve (12) inch centers.
- 4) When a fire wall is used as a portion of the fire barrier envelope, the material shall be attached to the wall using approved fasteners and installed in accordance with Section 6.1.1.a.5.
6.1.2 Conduit and Instrument Tubing (Attachment 9.2, Pages 14,15,21, and 22) NOTE: Instrument tubing shall be covered under direction of Design Engineering. A support analysis shall have been completed prior to any installation.
- a. Direct Sprav or Trowel Anoliention Over Stress Skin (Attachment 9.2, Page 14)
- 1) To achieve a fire barrier envelope around conduit, Stress Skin may be formed in sections and attached or molded around the conduit in one (1) piece.
- 2) Stress Skin flanges, edges or overlapping sections shall be fastened with mechanical fasteners or minimum size 18 ga.
stainless steel tie wire placed no greater than on 12 inch centers. l
- 3) Stress Skin may be formed to fit around the conduit and attached to the fire wall by using approved mechanical fasteners per Section 6.1.1.a.5.
- 4) Apply required thickness (es) of Thermo I.ag 330-1 subliming coating in accordance with Section 6.1.9.
PROCEDURE NUMBER REVISION PAOB
-10.25.89 9 12 of 87
- b. Prefabricated Board (Attachment 9.2, Page 14)
- 1) Prefabricated board shall be cut to allow the material to surround the conduit. The fire wall may be used as any portion
' 1 of the fire barrier envelope. i
- 2) When the fire wall is used as one side of the envelope, the !
prefabricated board shall be attached to the wall using j mechanical fasteners in accordance with Section 6.1.1.a.5. ;
- c. Installation of the One Hourfrhree Hour Fire Barrier Desien Utilizine Pre-Shaped Conduit Sections (Attachment 9.2, Pg 21)
- 1) Precoat the edges on one (1) of the Thermo-I.ag Preshaped ;
Conduit Sections with a 1/4 to 1/2 inch bead of Thermo-12g i 330-1 Subliming Trowel Grade Material. l
- 2) Mount the coated section and one (1) other section on the conduit, cable drop or instrument tube with the edges flush with j each other to form a cylindrical section around the conduit, j cable drop or instrument tube. Fasten the two sections together ,
using 18 ga. minimum stainless steel tie wires at a maximum of
)
twelve (12) inch intervals as shown in Attachment 9.2, Page 20. l
- 3) Apply a 1/4 to 1/2 inch bead of Thermo-Lag 330-1 Subliming '
Trowel Grade Material to the end of the installed section, and attach the next section, making sure that the ends are butted and , fluth.
- d. Installation of a One-Hour /Three-Hour Preshnoed Conduit Section Il Desien Mounted Immedintelv Adiacent to a Concrete Wall !
(Attachment 9.2, Page 22) l l
- 1) Cut one (1) of the Thermo-I.ag Preshaped Conduit Sections to fit flush with the surface of the concrete wall, and then cut this section in half to facilitate installation.
- 2) Precoat the edges on the other section with a 1/4 to 1/2 inch bead of the Thermo Lag 330-1 Subliming Trowel Grade Material.
i d . PROCEDURE NUMBER REVISION PAGE 10.25.89 9 13 of 87 i
- 3) Mount the coated section and the cut to fit section on the conduit, cable drop or instrument tubing with the edges flush with each other and the concrete wall, to form a cylindrical shaped section around the conduit, cable drop or instrument tube. Fasten the two (2) sections together with 18 ga. minimum stainless steel tie wires at a maximum of twelve (12) inch intervals as shown in Attachment 9.2, Page 22.
- 4) In those cases .where the conduit, cable drop or instrument tubing make a 90 degree turn into the concrete wall rather than running between floors, cut an end cap section from an equally rated Thermo-bg Prefabricated Panel and attach the cap section -
to the installed Thermo-Lag Preshaped Conduit Sections using machine screws.
- 5) Apply a 1/4 to 1/2 inch bead of Thermo-I.ag 330-1 Subliming Trowel Grade Material to the end of the installed section and attach the next section, making sure that the ends are butted and flush.
- 6) Caulk alljoints and the transition area between the installed Preshaped Conduit Sections and the concrete wall using the Thermo-bg 330-1 Subliming Trowel Grade Material.
- e. Direct Sprav Apolication i
- 1) Conduit may have Thermo-Lag 330-1 sprayed directly to the unit until the required thickness is achieved. This application is approved for one-hour areas only. i NOTE: Be careful when spraying conduit to avoid overspray onto other equipment and materials, shield these areas.
- f. Interface Aeolication with 3M. 3 Hour Rated Wrao (Attachment 9.2, Page 23) l
- 1) When interfacing TSI Thermo-bg 330-1 with 3M 3 hour rated i
wrap, E-50D/E-54A MAT, refer to Attachment 9.2, Page 23. This detail applies to conduit only in 3 hour areas. L 2) Overlap the last two layers ofInterim E50D/E-54A by two (2) L inches at the interface with the Thermo-Lag 330-1. i PROCEDURE NUMBER REVIslON PAGE l 10.25.89 9 14 of 87
y 1 i
- 3) Secure the 3M material with 0.5" x 0.020" minimum stainless
- . steel banding material spaced at approximately six (6) inch L mtervals.
- 4) Caulk the third and fourth layer 3M material with 3M-CP-25 caulk around the entire perimeter of the seam interface.
6.1.3 Cable Drops (Attachment 9.2, Pages 4 and 16) CAUTION: Stress skin should N.QI be allowed to 3 l come into direct contact with reactor safe shutdown cables. " Butter" cables with 330-1 Thermo-Lag before applying the Stress Skin or wrap 1 hour prefabricated board around these cables. This will provide the proper mechanical protection. I CAUTION: No sharp edges are allowed next to or near cable (s). ! a. Direct Sprav or Trowel Application Over Stress Skin Anolication f , (Attachment 9.2, Page 4) L
- 1) Cables shall be wrapped with Stress Skin and fastened at a l maximum of six (6) inch intervals with minimum size 18 ga.
- stainless steel wire.
l
- 2) The first coat of Thermo-Lag 330-1 shall be sprayed or trowelled onto the Stress Skin to a depth of approximately 1/8th inch (3-hour only) and then let dry. Apply remaining layers in l 1/8th inch increments until the maximum fill is obtained, let each layer dry between coats.
- 3) Conformable blanket 330-70 shall be wrapped tightly around the coated Stress Skin and secured in place with minimum size 18 gauge stainless steel tie wire.
- 4) A layer of Stress Skin shall be applied around the cable drop and secured with mechanical fasteners or minimum size 18 ga.
stainless steel wire and coated with the required thickness of ; Thermo-Lag 330-1 coating material. j s k FROCEDURE NUMBER REVIs3ON FACE 10.25.89 9 15 of 87
I
, ,/
,1 l 6.1.4 Cable Droo Junction With Cable Trav Or Conduit (Attachment 9.2, Pages 5 and 6) 1 L 1
- a. Conduit Junction (Attachment 9.2, Page 5) i
- 1 l 1) Thermo-Lag Stress Skin shall be applied to both the conduit and cable drop in accordance with Sections 6.1.2 and 6.1.3. ;
- 2) A minimum of twelve (12) inches of Stress Skin shall be :
wrapped around the junction with approximately six (6) inches overlapping the conduit. i ! 3) Cut and place pieces of conformable blanket 330-70 into the l open end and around the cable drops to insure that the open end ; is relatively sealed. ) l
- 4) Fasten Stress Skin to cable drop using mechanical fasteners or l minimum size 18 ga. stainless steel tie wire and coated with the required thickness of Thermo-Lag 330-1 coating material. l l
- b. Cable Trav Junction - Onen End (Attachment 9.2, Page 6)
- 1) Apply Stress Skin to the cable tray and cable drop in accordance with Sections 6.1.2 and 6.1.3. i i
- 2) A minimum of twenty-four (24) inches of Stress Skin shall be '
wrapped around the junction with approximately six (6) inches i covering the cable tray secured with minimum size 18 ga. stainless steel wire at five (5) inch intervals. i i
- 3) Cut and place pieces of conformable blanket 330-70 into the open end and around the cable drops to insure the end is sealed.
1
- 4) Place approximately six (6) inches of conformable blanket 330-70 into the cable tray to protect the installed cables.
- 5) Fasten the Stress Skin to the cable drop with minimum size 18 ga. stainless steel tie wire and coated with the required
, thickness of Thermo-Lag 3310-1 coating material. i. 4 b i .
. PROCEDURE NUMBER REVISION PAOB
/ 10.25.89 9 16 of 87 1
s. i !- 6.1.5 Cable Droo/ Conduit Junction With Bottom or Side of Cable Trav i, (Attachment 9.2, Pages 10,11,16 and 17) I ( : l- a. Direct Sorav or Trowel Anolication Over Stress Skin i l
- 1) Apply Stress Skin to the cable drop, conduit and cable tray in accordance with Secdons 6.1.2, 6.1.3 and 6.1.4.
- 2) The Stress Skin shall be applied to the conduit / cable drops so that it extends into the cable tray.
- 3) Cut a section of Stress Skin, form a collar flange of sufficient !
length to go around the conduit / cable drop and butt to the cable j tray installation. ! l
- 4) Attach the collar to both the conduit / cable drop and the cable l
^
l tray with mechanical fasteners or minimum size 18 ga. stainless l steel tie wire. , [ 5) Apply required thickness of Tiiermo-Lag 330-1. 6.1.6 Direct Sprav Anplication to Cables Within Cable Trays (Attachment 9.2, Page 24 and Attachment 9.2, Page 2' 5) Type A, B, C - Attachment 9.2, Page 24 - Application of Thermo-Lag 330-1 as fire break to non-dedicated trays in Cable Spreading Room ! Type D - Attachment 9.2, Page 24 - Application of Thermo-I.ag 270 as RG 1.75 barrier. t' Attachment 9.2, Page 25 - Application of Thermo-Lag 330-1 as a one-hour barrier to dedicated or non-d~IiW trays.
- a. Cleanliness
- 1) Prior to the application of the Thermo-Lag coating, the cables ,
and adjacent surfaces, including the outside and bottom of the tray, shall be cleaned of excessive dirt, dust, pulling compound or gross foreign material. p-4 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 17 of 87 , 9
i l L
- b. Fire Break or RG 1.75 Barrier Application (Attachment 9.2, Pages 24, Type A,B,C,D)
- 1) The bottom and sides of solid trays may be used as a portion of the fire break of a solid bottom tray.
l
- 2) As a field option prefabricated board may be used at bottom or sides of the fire break for ladder trays.
l l Boards shall be held in place by attaching to the trays
- 3) l i approximately every two feet with minimum size 18 gauge l stainless steel wire, r
- 4) Individual cables or cable bundles held in place within the cable trays by use of tie downs shall not be cut loose from the cable tray rungs unless realignment of cables is necessary to minimize ;
Thermo-Iag application, in this case refer to PPM 10.25.54 for i tie-wrap spacing. l
- 5) Cable bundles shall not be separated, but sprayed as a single i
- unit.
- 6) When installing Thermo-Lag 270, where open tray interfaces with covered tray, the Thermo-Lag 270 shall be installed beyond
[ the covered tray a minimum of: : t a) 6'-0" for 24" tray b) 4'-6" for 18" tray, and/or c) 3'-0" for 12" tray 1 per Attachment 9.2, Page 24, Type C. The tray cover shall be ; removed, the Thermo Lag installed to the required distance and + then have the tray cover reinstalled.
- 7) On ladder trays both the top and bottom of cables require spray, to form a complete encapsulation. Refer to Attachment 9.2, l Page 24, Type C and D of this PPM.
l 1 PROCEDURE NUMBER REVINON PAGE
- . 10.25.89 9 18 of 87 1
- c. Application as a One Hour Barrier l
- 1) Cables shall be sprayed in place per Section 6.1.6.b.4 and 6.1.6.4.b.5 above.
- 2) All steel components that penetrate the raceway barrier for dedicated safe shutdown cables require Design Engineering and Fire Protection Engineering evaluation for heat flow path -1 protection.
- 3) Thermo-Lag 330-1 material for Attachment 9.2, Page 25 shall be applied in a dry film thickness of 5/8" 1/8" to provide a fire barrier rating of I hour,
- d. Coatine Procedure
- 1) Thermo-lag shall be sprayed directly on cables and adjacent surfaces.
- 2) The Thermo Lag shall be applied to meet the requirements of Section 6.1.9.c.
- 3) Measurements of the wet film thickness shall be made between the outer edge of the cable or cable bundle and the outer surface of the protective envelope.
- e. Vertical Fire Stops l
- 1) Designated cable trays shall have a five (5) foot area of Thermo-lag 330-1 applied directly to the cables at locations to be specified by Design Engineering.
- 2) The Thermo-I.ag material shall be sprayed directly on the cables to a thickness of 1/4" 1/8".
PROCEDURE NUMBER REV1530N PAGE 10.25.89 9 19 of 87
6.1.7 Junction Box (Attachment 9.2, Page 12)
- a. Direct Sprav or Trowel Anolication Over Stress Skin l
4
- 1) Stress Skin shall be cut to form an envelope around the junction -
box. Holes may be cut to allow matenal to be formed around conduits or cables.
- 2) Stress Skin, as required, may be attached to the wall with the use of self-adhesive insulation pins.
- b. Prefabricated Board *
- 1) Prefabricated board may be cut to fit around thejunction box and conduits / cable in accordance with Section 6.0.2 and 6.0.3.
l
- 2) Precoat edges on adjoining sections with a 1/4 to 1/2 inch bead ,
of Thermo-Lag 330-1 subliming trowel grade material as necessary to ensure joints are filled to full depth of prefabricated panel. ;
- 3) Prefabricated board shall be attached to the wall using mechanical fasteners in accordance with Section 6.1.1.a.5.
6.1.8 Structural Steel Supoons or Cable Trav Haneers (Attachment 9.2, Page 13 and Attachment 9.3) ;
- a. Direct Sorav or Trowel Application (Attachment 9.2, Page 13) l l
NOTE: Stress skin is N.QI required to be installed on structural steel. l l
- 1) Stress Skin may be used to enclose cable tray hanger units in accordance with approved drawings.
- 2) Stress Skin sections shall be held in place by mechanical fasteners or minimum size 18 ga. stainless steel tie wire placed no greater than on twelve (12) inch centers.
- 3) Stress Skin may be attached to a fire wall in accordance with Section 6.1.1.a.5.
PROCEDURE NUMBER REVISION PAGE 10.25.89 9 20 of 87
- b. Recuired Protectictpf Supoort Steel - Three Hour Raceway Fire Barriers ,
- 1) All support steel necessary to support the gravity loading shall be covered with the designated thickness of Thermo-Lag in accordance with Attachment 9.3 i EXCEPTION: Analysis has been performed to demonstrate that certain embedded steel plates and embedded unistrut for existing Thermo-Lag installations do not require Thermo-Lag protection (Reference 2.6).
- 2) Attachments to, or extensions of, the gravity loading supports shall be covered with the designated thickness of Thermo-Lag in accordance with Attachment 9.3. The length of the attachment or extension to be covered shall be the GREATER OF:
- a) A minimum distance of eighteen (18) inches from the
2 outer surface of the barrier on the dedicated raceway. 1 b) A minimum length of nine (9) inches from the point of attachment or extension. ) 3) Thermo-lag shall be applied along ALL heat transfer paths. Where the heat flow path changes direction, the minimum coverage length shall be measured along the centroid of the structural members. Refer to Attachment 9.2, pages 28 and 29, I for clari5 cation.
- 4) All open ends of tubular or box members of the protected steel shall be capped or sealed with a minimum thickness of one (1)
, inch of Thermo-Lag.
- 5) Anti-sweat insulation which penetrates a three-hour rated I raceway barrier shall have the insulation removed and replaced with Thermo-Lag for the distance necessary to meet the heat flow path protection requirements specified in Items 6.1.8.b.2 and 6.1.8.b.3. l l
l PROCEDURE NUMBPJL REVIB10N PAGE 10.25.89 9 21 of 87
1.__
. 1
- c. Required Protection of Supoort Steel - One Hour Raceway Fire Barriers
- 1) All support steel necessary to support the gravity loading shall be covered with the designated thickness of Thermo-Lag in accordance with Attachment 9.3 for a minimum distance of nine (9) inches from the point of attachment to the dedicated raceway fire barrier.
- 2) Attachments to, or extensions of, the gravity loading supports shall be covered with the designated thickness of Thermo-Lag in accordance with Attachment 9.3 for a minimum distance of nine (9) inches from the outer surface of the barrier on the dedicated raceway.
- 3) Thermo-Lag shall be applied along ALL heat transfer paths.
Where the heat flow path changes direction, the minimum coverage length shall be measured along the centroid of the structural members.
- 4) All open ends of tubular or box members of the protected steel shall be capped or sealed with a minimum thickness of one-half (1/2) inch of Thermo-lag.
- 5) Anti-sweat insulation which penetrates a one-hour rated raceway barrier shall have the insulation removed and replaced with l Thermo-Lag for the distance necessary to meet the heat flow l path protection requirements specified in Items 6.1.8.c.2 and 6.1.8.c.3.
- d. Recuired Protection of Supoort Steel - Three Hour Instrument Sensing Line Fire Barriers
- 1) Application of Thermo-Lag 330-1 Panel / Trowel Grade / Spray Grade, shall conform to Attachment 9.3 thickness requirements for three-hour rated assemblies.
- 2) No Thermo-In, 330-1 shall encapsulate or in anyway capture or inhibit the movement of the instrument tubing.
- 3) Should there be more than one (1) Stainless Steel Block Clamp, end to end, apply 330-660 flex blanket to the support such that the blanket extends, as a minimum, to the end of the row of 1 block clamps (Attachment 9.2, Page 27 of 29).
l PROCEDURE NUMBER REVISION PAGE 10.25.89 9 22 of 87
- 4) Thermo-Lag 330-1 panel may butt up to the ends of the block clamp (s), however it may not encapsulate the instrument tubing.
(Refer to paragraph 2.)
- 5) The 330 660 flex blanket may be overlapped and secured by using Thermo-Lag 330-1 panels and securing the panel with stainless steel tire wire, minimum 18 ga.
l
- 6) Use 330-660 bulk grade caulk to fill any voids / joints in the areas of the flex blanket to block clamp /panelinterface.
- 7) Upon completion of the Thermo-Lag installation the tubing support shall be identified as dedicated per Section 6.4.5.
l 6.1.9 Coatine Procedure
- a. Fire retardant Thermo-Lag 270 direct spray application to electrical cables:
- 1) The minimum dry film thickness of Thermo-Lag 270 shall be 1/16".
- 2) For wet film thickness refer to Section 6.1.9.e.1 of this PPM.
- b. One-Hour Barriers For all installations except those for structural steel members, the MINIMUM required dry coating thickness of Thermo-I2g 330-1 is 1/2 inch with a tolerance of -0.00 inch, and an average thickness of no greater than 5/8 inch, and a maximum thickness of 3/4 inch, except locations immediately adjacent to, and including, any joints or flanges.
l I PROCEDURE NUMBER REVISION PAGE 10.25.89 9 23 of 87
- c. Three-Hour Barriers For all installations except those for structural steel members, the MINIMUM required dry coating thickness of Thermo-Lag 330-1 is one inch, with a tolerance of -0.00 inch, and an average thickness of no greater than 1-1/8 inch, and a' maximum thickness of 1-1/4 inch, except locations immediately adjacent to, and including, any joints or flanges.
- 1) Three-hour barriers may be constructed of two (2) separate layers of prefabricated board or a minimum of 1" 3301 Subliminal Thermo-Lag Coating, with total thickness . tolerance as stated above.
- 2) All three-hour barriers will have Stress Skin mounted to the outside of the finalinstallation, except for structural steel applications or where Thermo-Lag material has a factory applied Stress Skin on both sides. Refer to Notes, Section 6.1.
- d. Sprav Anolication
- 1) Thermo Lag 3301 removed from warehouse shall be agitated or stirred for fifteen (15) minutes prior to application. No further mixing is required. '
- 2) Apply the material in as many passes as required to provide the required film buildup of the coating thickness, taking care to avoid slumping or sagging of the coating. :
i
- 3) Take wet film thickness measurements every five (5) square feet I or every two (2) running feet of coated surface.
- c. Recuired Wet Film Thickness l
- 1) Fire Retardant Thermo T ma 270 ;
I a) Minimum of 3/32" (2.4 mm) b) Maximum of 1/4" is desired for economy l PROCEDURE NUMBER REVISION PAOB 10.25.89 9 24 of 87 l
, 2) One (1) Hour Thermo-bg 330-1 a) Minimum of 5/8" r b) Normal Maximum of 15/16" c) Average thickness between 5/8" and 13/16"
- 3) Three (3) Hour Thermo-Las 330-1 a) Minimum of 1-1/4" .
b) Normal. Maximum of 1-9/16" c) Average thickness between 1-1/4" and 1-7/16"
- 4) Structural Steel (Sprav Acolication of Thermo-be 330-1) a) Wet film thickness for one (1) hour and three (3) hour shall be no less than that listed in Attachment 9.3.
6.1.10 Fire Stops
- a. Examples of fire stops used in dedicated cable trays and/or conduits are shown in Attachment 9.4. Also shown are typical fire barrier terminations inside of a non-dedicated tray in lieu of total tray ;
coverage. ' 4 i l I l
)
nocuounamnasa navmon nos 1 10.25.89 9 25 of 87 1
6.2' Repair - Thermo-Lae 330-1 etPrefab Anolication , 6.2.1 Thermo-I2e 330-1 or Prefab Application CAUTION: Do not cut cables located inside the , Thermo-Lag.
- a. Remove damaged and loose materials using a knife and scraper. Cut area until sound adhering material is reached.
- b. The edges should be undercut to form a beveled edge as in plaster repair. ,
- c. Remove all foreign matter from the substrate using a wire brush.
- d. If the Stress Skin material is found to be damaged, enough 330-1 material shall be removed to allow for repair or replacement.
- e. Spray or trowel Thermo-bg 330-1 into the patch area, per Section 6.1.6.e. Thermo-Lag 330-1 will be applied in accordance with .
Section 6.1.9.b or 6.1.9.c.
- f. For acceptable repair of pre-formed panel removed from Thermo-Lag cable trays, see Attachment 9.2, Page 3.
6.2.2 Thermo-In 270
- a. Remove all loose material at damaged area. Use only a bristle brush or similar tool to ensure cable insulation is not damaged.
- b. Spray or brush Thermo-bg 270 over the damaged ama to the proper thickness as specified in Section 6.1.9.a of this PPM.
6.3 Recair - Structural Steel. Hanners or Sunoorts 6.3.1 Remove all damaged matter to a surface that meets the requirements of Section 6.4.1, dovetail the edges to be followed by caulking with Thermo-Lag 330-1 at the edges and filling in the space required to be repaired, by either spraying (which is the preferred method), or trowelling, where the areas are smaller. PROCEDURE MMBER REYWON PAGE 10.25.89 9 26 of 87 i
t 6.4 Inspection 6.4.1 Cleanliness - Structural Steel Ensure that the surfaces of the structural steel, hangers or conduits are free of gross dirt, scale, rust, grease, oil or other contaminants prior to applying Thermo-lag 330-1 Subliming material. Surfaces that are galvanized are suitable for direct application of Thermo-Lag 330-1. . 6.4.2 Cleanliness - Fire Walls Ensure that applicable surface area of any fire rated wall is free of gross dirt, grease or other contaminants prior to the application of Stress Skin and 330-1 materials. 6.4.3 In-Process Insnection
- a. For every installation, ensure that the Stress Skin has been applied in accordance with this procedure and applicable figures. Areas to check as a minimum shall be as follows:
- 1) Overlap distances
- 2) Fastener distances
- 3) No open or damaged areas
- 4) No loose application
- b. Perform wet film thickness tests during the spray application of the Thermo-Lag 330-1 Coating to ensure uniform application. Wet film thickness is required when dry film thickness is not practical.
- 1) Wet thickness tests shall be performed every five (5) square feet ,
or two (2) running feet of surface area using a scaled ! penetrating measuring device.
- c. Ensure that prefabricated boards are installed in accordance with approved details.
- 1) Prefabricated boards shall be checked for thickness, damage and unsealed areas.
- 2) Ensure all edges or joints between installed boards are scaled full depth of the prefabricated panel.
PROCEDURE NUMBER REVISION FAGE 10.25.89 9 27 of 87
- . - . - - - . - - . - . . . - - - - . . - - ~ ~ - - - - - - -
l 4 - 6.4.4 Final Insoection !
- a. Ensure edges and joints are closed and sealed.
l i
- b. Ensure all released structures are covered or filled to the requirements l of the applicable fire rating. i
- c. Quality Control (QC) shall document all phases of the Thermo-Lag !
application on the Inspection Form, Attachment 9.1. l
- d. All gaps or cracks in the Thermo-Lag envelope shall be repaired.
- e. Verify dry film thicknesses per Section 6.0 where such measurements I may be taken without damage to the installed barrier. i l
1 6.4.5 Identification '
- a. All Thermo-Lag applied to dedicated trays and conduit shall be identified with a red painted stripe. Instrument tubing supports shall ,
be identified with a red painted stripe. The painted stripe shall be ! visible from the floor elevation, if possible. i i 7.0 PROCEDURE (3M FIRE PROTECTION SYSTEM - 3 HOUR) ; 7.1 Preoaration l 7.1.1 Prior to any 3M fire protection mat material being applied to an open top cable tray greater than twelve (12") inches wide, a strapping system shall be applied around or across the cable tray at a maximum spacing of twelve (12") inches on center and underneath all seams. This stmpping system shall be used to minimize sagging of the 3M three (3) hour fire protection , mat material. Any strapping system used shall have a minimum tensile i strength of five hundred pounds (500 lbs.). The following are possible options, l
- a. A minimum of two (2) wraps of three-quarters (3/4") inch wide or i wider filament type tape. -l l
- b. Most one-half (1/2") inch wide or wider polyester or nylon strapping. l
- c. Metal strapping. ;
l
- d. Metal or plastic bridging across the top of the cable tray.
1 PROCEDURE NUMBER REVBION FAOE 10.25.89 9 28 of 87 l
I l
- t .
l 7.1.2 Prior to any installation of 3M E-50D mat material to the safe shutdown i conduit (s), the support steel and attached steel base plate shall have the ; required layers of E-50D mat material installed. When this process has been completed, the E-50D mat material and the concrete beneath shall have ; the required bolt holes drilled to accept concrete fasteners (i.e. at least one ' and one-half (1-1/2") inches perpendicular penetration into the concrete). 7.1.3 Supports and Heat Transfer Items
- a. Partial I2neth Protection - 5 layers for 12"
+
If the final user of the 3M Interim E-50D 3-hour Fire Protection System has determined that the st ength of the bare supports holding a ! critical fire protected item would be sufficient if exposed to an ASTM E-119 time-temperature fire curve, then the supports and any heat transferring item must be fire protected with five layers of E-50D a minimum of 12" from the point of contact to the critical item. Also, i any heat transferring item within a 12" conductive heat transfer path i from the critical item must also be fire protected with five layers of l E-50D. l
- b. Full 12neth Protection - 3 layers entire length and basenhte If the above criteria for the high temperature strength of bare supports is not met, or as an alternative the above partial length protection, the entire length of the support and the baseplate must be fire protected with three layers of E-50D. Also, any heat transferring item that I physically contacts the suppon must be fire protected with three layers l of E-50D a minimum of 12" from the point of contact along the heat transfer path.
7.2 Material 7.2.1 Suoports
- a. Unistrut P1000 series, P5000 series and Unistrut sceruaries as manufactured by the Unistrut Corporation, Wayne, Michigan or approved equal,
- b. Structural steel members shall be manufactured and fabricated per ASTM A-36 or approved equal.
- c. Concrete fasteners shall be Hilti Drop-Ins (HDI), or Kwik-Bolt II as manufactured by the Hilti Fastening Systems, Stramford, Conn. or !
approved equal. 1 FROCEDURE NUMBER REVISION PAGE 10.25.89 9 29 of 87 I
7.2.2 E-50 Series . Mat . 7.2.3- Facing Tape (T-49) 7.2.4 Caulk (CP-25) (98-04000250-7) 7.2.5 Putty (303) , 7.2.6 Composite Sheet (CS-195)' 7.2.7 Bandine Strans 1
- a. Straps shall be one-half (1/2) inch by 0.020 inches thick, ASTM A-240 stainless steel or approved equal.
- b. Straps attached to concrete elements shall be five-eighths (5/8) inches by 0.020 inches thick.
7.2.8 Wire Mesh j l
- a. Wire mesh shall be a minimum of two (2) by two (2) mesh (nominal 1/2 inch square opening) with a wire diameter of 0.060 inches or larger.
- b. Wire mesh shall be stainless steel or approved equal.
7.2.9 Washers
- a. Washers shall be a minimum one and one-quarter (1-1/4) inches in !
diameter with a one-quarter (1/4) inch concentric hole.
- b. Washers shall be fabricated from ASTM A-36 steel or approved equal.
7.3 Insoection 7.3.1 Inspections shall be performed as follows but not necessarily in this order:
- a. Cleanliness before the start of E-50D mat material installation (i.e.,
cleanliness of dedicated item).
- b. Verify the installation of each layer of E-50D mat material and
,. number each layer. raocuounamnena nevamow -r4as ; 10.25.89 9 30 of 87
- c. After all caulk or putty is applied, verify application.
- d. Verify the entire restraining system is installed.
- e. After the concrete fastener bolt holes are ddlled, verify minimum
- depth one inch per Attachment 9.5. :
- f. After the concrete fasteners are installed and set, verify sub-set of 1/4 inch 0 HDI per Attachment 9.5.
7.4 Installation Installation of the 3M Interim TM three (3) hour fire protection system shall be performed in accordance with 3M installation drawings and instructions and the alternate details provided as Attachment 9.5. t 7.5 Proner Repair of Any Gaps or Cuts in the System ; 7.5.1 For foil tears, holes, rips, or gaps in the mat less than 1/4", simply cover the area with aluminum foil tape. 7.5.2 For tears, holes, rips, or gaps in the mat 1/4" or greater in the first four inner layers, fill the void with a piece of E-50D mat with butt joints and , cover with aluminum foil tape.
- 7.5.3 For tears, holes, rips, or gaps in the mat 1/4" or greater in the last layer, either (a) fill the void with Interim CP-25 caulk and cover with aluminum foil tape; or (b) cover the void with E-50D mat following the 2" overlap rules for the last layer and hold in place with stainless steel banding.
8.0 - DOCUMENTATION The completed inspection form shall be filed in Maintenance Work Request File per PPM I.3.7. 9.0 ATTACHMENTS 9.1 Insnection Form 9.1.1 Fill in all blanks of Attachment 9.1, Inspection Form. N/A (Non-Applicable) shall be placed in areas that would otherwise be left blank. PROCEDURE NUMBER REVISION PAGE 10.25.89 9 31 of 87
9.1.2 Attachment 9.1 shall be filled out according to the following steps:
- a. Section A
- 1) Thermo.ima Barrier Rating - Place the number of the MWR that directed the work and the BDC/PVR that identified the barrier rating required.
- 2) OC Insoection Plan No. - QC will enter the appropriate IPR number upon completion of their hold-point review.
- 3) Thermo Tia P.O. - For material traceability and qualification, the P.O. number / lot number / expiration date shall be entered.
- 4) Comoonent Identification - Enter component type, i.e., cable tray, conduit hanger, etc. Enter identification number.
- 5) Drawing Number - Place the applicable drawing number here.
- b. Section B
- 1) Insoection Requirements - As required.
NOTE: N/A shall be entered on all lines not applicable to the installation being inspected.
- 2) Ouality Control Insnector - Enter QC signature and date inspected.
- c. Section C
- 1) Resoonsible Engineer - Signature of the Supply System engineer responsible for a final acceptance. The responsible engineer must be trained in 3M or Thermal Lag installation or have 1 year experience in fire protection requirements. A{2.11} l
- 2) Reviewed By - Signed by the person responsible for review of the documentation prior to closing the MWR.
9.1.3 All areas not numbered are self-explanatory and shall be filled out with the required information. PROCEDURE NUMBER REVBION PAGE 10.25.89 9 32 of 87 t- -
I ~ l 9.2 Specific Aoplications/Thermo-Tu l Page No.
- 1. Thermo-Lag Stress Skin Type 330-69, Typical Lay-out for Cable Tray Sections.
- 2. Cross Sectional View of Thermo-bg 330-1, Applied to a Typical Cable Tray. l
- 3. Typical Repair of Prefabricated Board Removed from Cable Tray.
- 4. Cross Sectional View of Thermo-Lag 330-1 Subliming Coating Envelope ,
System Applied to Cable Drops. !
- 5. Cross Sectional View of Thermo-bg 330-1 Subliming Coating Envelope System, Applied to Conduit and Cable Drop Junctions. )
\
- 6. Cross Sectional View of Thermo-Lag 330-1 Subliming Coating Envelope System, Applied to Conduit and Cable Tray and Cable Drop Junctions.
- 7. Typical Raceway Thermo-bg Interfacing with Penetration Seal, (1-Hour Rating, Spray Application).
- 8. Typical Thermo-bg Raceway Interfacing with Penetration Seal, (1-Hour Rating, Prefabricated Panel).
- 9. Typical Thermo-Lag Tray Covering Interface with Penetration Seal, (1-Hour Rating).
- 10. Typical Non-Protected Conduit Interface with Protected Tray (1-Hour Rating).
- 11. Typical Non-Protected Cable Interfacing with Protected Tray.
- 12. Thermo-bg 330-1 Applied to Junction Box Assembly.
- 13. Cross Sectional View of Thermo-Lag 330-1 Subliming Coating Envelope System, Applied to Structural Steel Members.
- 14. Typical Prefab Panel Conduit Covering,1-Hour Rating,1/2" Thick Thermo-Lag 330-1,
- 15. Typical Tray Spray Application Barrier with Wall as Portion of Barrier, (3-Hour Rating).
- 16. Typical Non-Protected Conduit Interface with Protected Tray, (3-Hour Rating).
PROCEDURE NUMBER REYlSION PAGE 10.25.89 9 33 of 87
~
Pare No.
- 17. Cable Drop Typical Non-Protected Cable Interfacing with Protected Tray, (3-Hour Rating).
- 18. Typical Tray with Thermo-bg Covering Interfacing with P;netration Seal, (3-Hour Rating).
- 19. Typical Tray with Thermo-Lag Covering Interfacing 'vith Penetration Seal, (3-Hour Rating).
- 20. Typical Instrument Tubing or Conduit Covering, 3-Hour Rating (2) - 1/2" Thick Thermo-bg 330-1 Panel with Outer Layer of Stress Skin 330-69.
- 21. Typical One-Hour and Three-Hour Prefabricated Conduit Section Application Techniques for Conduit and Cable Drops.
- 22. Typical One-Hour and Three-Hour Conduit / Instrument Tubing Using Premolded Conduit Sections with a Wall as a Portion of the Barrier.
- 23. Cross-Sectional View of Three-Hour TSI Thermo-Lag 3301-1 Interface with 3-M Interim E-50D/E-54A Applied to Conduit.
- 24. Four Typical Insulation Styles for Cables on Trays.
- 25. Typical Cable Tray Thermo-bg 330-1 Covering 1 Hour Rating Applied By Direct Spray, Rolling or Troweling Application Methods.
- 26. Typical Structural Steel Shapes Covered With Thermo-Lag Prefabricated Panel Configurations.
- 27. Typical Thermo-lag installation for instrument tubing, supports only.
- 28. Cable tray and support steel Thermo-Lag per criteria.
- 29. Clarification for measuring conduit 18" requirement (typ). ;
I 9.3 Thickness Reauirements for Thermo-Tu : I
- 1. Thermo-bg Dry Thickness Requirements for Structural Steel (Pages 1-3)
- 2. Thermo-Lag Wet Thickness Requirements for Structural Steel (Pages 4-6)
) - Pit 0CEDURENUMBER REVISION PAGE 10.25.89- 9 34 of 87
9.4 Fire Stops /Thermo-Tw Pace No.
- 1. Fire Barrier Termination Inside of Non-Dedicated Tray in lieu of Total Tray Covenge (Page 1)
- 2. Dedicated Cable Tray and Conduit Fire (Page 2) 9.5 3M 3 Hour Fire Protection Firures
- 1. Alternate Rework of Unistrut Supports.
- 2. Alternate Rework of Unistrut Supports.
- 3. Alternate Base Plate Detail. ,
- 4. Detail for Cabletray and Dedicated Conduit for 3-Hour Fire Rating.
- 5. Detail for Junction Box and Dedicated Conduit for 3-Hour Fire Rating.
- 6. Detail for Dedicated or Non-Dedicated Conduit Intruding into the 3-Hour Fire Protection System.
- 7. Detail for Structural Member Intruding into the 3-Hour Fire Protection System.
- 8. Alternate Detail for 3-Hour Fire Protection System of Unistrut Conduit Support Attached to Concrete.
- 9. Internal Detail for 3-Hour Fire Protection System of Unistrut Conduit Support Attached to Concrete. i
- 10. Detail of Required I.ayers of 3M Mat Material Intruding Elements Intruding in ;
the 3-Hour Fire Protection System.
- 11. Alternate Methods of Securing 3M Mat Material for 3-Hour Fire Rating.
- 12. 3M/TSI Conduit Interface Details.
- 13. Detail of Conduit Support of Dedicated Conduit for 3-Hour Fire Rating. L
- 14. Detail of Conduit Support of Dedicated Conduit for 3-Hour Fire Rating.
l FROCEDURE NUMBER REVISION PAGE 10.25.89 9 35 of 87 l l
WNP-2: THERMO-LAG INSTALLATION / INSPECTION FORM SECTION A THERMO-LAG BARRIER RATING: QC INSPEC. PLAN NO: MWR/BDC/PMR No.: THERMO-LAG P.O./ RCPT. INSP. RPT. NO.: BATCH NO: l NAME(S) OF TSI CERunto INSTALLER (S) , EXPIRATION DATE: l l COMPONENT TYPE / IDENTIFICATION NO.: LOCATION: BUILDING: ELEVATION: COLUMN LINE: i REFERENCE DRAWING NUMBER: FIRE AREA. 3 l SECTION B OC INSPECTOR'S SIGNATURFJDATE INSPECTION FOR CABLE DAMAGE (IF REQUIRED) ! COMPONENT CLEANLINESS INSPECTION PROPER INSTALLATION OF THERMO-LAG 270 PROPER INSTALLATION OF STRESS SKIN 330-69 ! PROPER INSTALLATION OF THERMO-LAG 330-1 PROPER INSTALLATION OF 330-1 PREFAB PANEL PROPER WET COAT THICKNESS (SPRAY APPL. ONLY) i PROPER DRY COAT THICKNESS OTHER (SPECIFY) SECTION C l RESPONSIBLE SUPPLY SYSTEM ENGINEER: DATE: REVIEWED BY: DATE: COMhENTS: Attachment 9.1 PROCEDURE NUMBER REVISION FAOE 10.25.89 9 36 of 87
THERMO-LAG STRESS SKIN TYPE 330-69 TYPICAL LAYOUT FOR CABLE TRAY SECTIONS. TCP SECTION , Stiffner "V" Type 6* Max. 4 9 a , ~T I *i i l i 1 1 I i i W.4 1 I t h l l l 1 l . l
.JL 8 '
1* l- Length Ib' l\= BOTTOM and SIDE SECTIONS h
, q _ __. ,.___ ,1 _ .u ___ . __9 # 4 - 51de g _:, _ __ ,,. _ . _ .. _u. _ _ __w I
I g . I I 8 W 8 i ~ I g-- Bottem W +4a d l h l I l t ) I , i 1 L.__ ___ _ _ ___ _ _ _ _ ,_ 8 H +4" 1 4 _ Side ' d _ ,_ _ _ . , _ , ___4 1%* f Length - J 1 J l f Attachment 9.2 Page 1 of 29 PROCEDUKE NUMBER BEVISION PAGE 10.25.89 9 37 of 87
CROSS SECTIONAL VIEW OF THERMO-LAG 330-1 SUBLIMING COATING ENVELOPE SYSTEM APPLIED TO A TYPICAL CABLE TRAY 1 f
- c. s
, / i Thermo-La'g ., 1 330-1 Subliming Coating y . s'(s .;; ..sy aff , a a . g, / f~ * / .eT. '. . . 1 -: : . f .$ ~~ . ' *.W */ y[ f l
Thermo-Lag Stress Skin lll ' ,a ble Tray ihell
/ .[J g3.Tt 7- 4 . // . - Type 330-69 /
_; _g g , g v g I_ _ ( (U k . Cables . 9 Attachment 9.2 Page 2 of 29 FROCEDURE NUMBER REVISION FACE 10.25.89 9 38 of 87
_ _ _ _ _ _ - _ _ _ _ _ _ _ _ . _ . . _ . _ . . _ . . . . _ _ . _ ~ . _ - - . . _ . . _ _ . _ . . _ - . . . _ . _ _ . . REPAIR OF PRE-FABRICATED PANEL DESIGN ON CABLE TRAYS THERMO-LAG 330-1 ^ TROWEL GRADE MATERIAL PREFABRICATED 1" PANEL o . . ,
. . / .. .. . . . .y _. . . .
y_. _Jl SMM~ E l'N % W ;
/ ...._'..
4 2" ? S* 2" - M THERMO-LAG 330-1 PREFABRICATED 1/2" PANEL TROWEL GRADE MATERIAL THERMO LAG 330-1 PREFABRICATED 1" PANEL
/ / . /_ / j THERMO-LAG 330-1_
l
}REFABRICATED 1/2 PANEL Attachment 9.2 Page 3 of 29 PAGURENUMBER REVIsloN PAGE 10.25.89 9 39 of 87
CROSS SECTIONAL VIEW OF THERMO-LAG 330-1 SUBLIMING COATING ENVELOPE SYSTEM APPLIED TO CABLE DROPS i
/ Cable Drop Inner Thermo-Lag V ' g' /
Stress Skin y
- Edge }
- Folded Back ,
~
Extra Thermo-Lag (As Spacer) . Thenne-Lag 330-1 - Thermo-Lag Stress Skin r Conformable Cermic Blanket : Ther:no-Lag Stress Skin r Cables y j I Fastener A Tie Wire Attachment 9.2 Page 4 of 29 PROCEDURENUMBER REVISF N PAGE 10.25.89 9 40 of 87
f CROSS SECTIONAL VIEW OF THERMO-LAG 330-1 SUBLIMING COATING ENVELOPE SYSTEM APPLIED TO CONDUIT AND CABLE DROP JUNCTIONS Ccnduit Der =c-4.ag 230-1 ; V V - ; D2r.no-Lag Stress Skin . V k , Beveled Edge of Ccnformable Carsmic Blad=* - a g .
' Thermo-Lag 330-1 -
Typical Cable Oreps I _ nermo-Lag Stress Skin
~
Der.co-Lag Ccnfor=able Carsmic Elankd Tnermo-Lag Stress Skin 'dith LIS* j Wet Layer of 220-1 i NOTE: Protect cable insulation from damage by stress skin by inserting approximately six inches of Thermo-Lag conformable blanket into the conduits. Attachment 9.2 Page 5 of 29 FROCEDURE NUMBER REVISION PAGE 10.25.89 9 41 of 87
l - , CROSS SECTIONAL VIEW OF THERMO-LAG 330-1 SUBLIMING COATING ENVELOPE SYSTEM APPLIED TO CONDUIT AND CABLE TRAY AND CABLE DROP JUNCTIONS 2 I
/ l / /
^ Cable Tray '; ~ l Spray or Trowel grade # Der::o-Lag 220-1 y .
/ /% l Thermo-Lag 220-1 7_ /
N p / s d\ M# //
~ /s s \s . \ sy R % /
B ermo-Lag Stnss. Skin . / Conformable Caramic - 31ankat
/ , / ' ~
l A nermo-Lag 220-1 k 'nermo-Lag S nss Skin Typical Cable Orops-
- k ner=o-Lag Conformable Caramic Slanket
,,, \ hermo-Lag Stnss skin with 1/8" 'det Layer of 330-!
NOTE: Protect cable insulation from damage by stress skin by inserting approximately six inches i of Thermo-Lag conformable blanket into the cable tray. Attachment 9.2 Page 6 of 29 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 42 of 87 l
. . .. - . . . ~ - - - . . . .. . - . . -.-.-..__ _ _ .. .._ . . - - . .--- .
TYPICAL RACEWAY THERMO-LAG INTERPACING %TTH PENETRATION SEAL
; (1-HOUR RATING SPRAY APPLICATION) 1 I STRESS SKIN & THERMO-LAG 4 SPRAY APPLICATION , ~ .. f[#
CONCRETE FASTENERS l CONCRETE WALL (see notes below) , f +q.,~ 9.,b
,- y j
THERMO-LAG g 6*. --
- 330-1 . s.: y FIRE RESISTANT l j QREFABPANEL D '
PENETRATION SEAL i ywwmte %
**[ [ j- TRAY OR CONDUIT u l
i n V//I////S) & P=~.r.. ,^ 6 l I p, l! , 2 1/2" MINIMUM (TYP.) l
, J, , (Note 5) l STRESS SKIN -go .r , l w j l FASTEN - 18 Ga. SS WIRE, M **+:' .c/ A ?d> *'A- NOTE: SILICON FOAM LACING OR BOLTING - , b A ', A . -
DAMMING BOARD
,y j .v] REMOVED /N f%
Refer to Section 6.1.1.a.5 for concrete fastener installation notes. Attachment 9.2 Page 7 of 29 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 43 of 87
l TYPICAL THERMO-LAG RACEWAY INTERFACING WITH PENETRATION SEAL (1-HOUR RATING PREFABRICATED PANEL)
~ '
CCNcK M .FA57D825 ,, pv F-',.4 y C.ONCEETE WfQ,L, . (3EENdTE. 3) ,, h, :d' ,1 ,-3'D (?,pgAy02. + 4 - pt a,( Ras 1*NT w m- :GtABE) sac-s > 'A'< =:12< ~ F**
~ !'r PEMETRAT1cWSErt ~
l
' RLL' tM. . . 'f #s TitAY6R CCNEMrT lu/LU//Ulv ////// ,
t ; _/ -
, . - ~ ' N ' / -
1
' _V// //fif7////////ff/4 ~'
l
' s I R E 9:Es t $ TANT l s3za=t aw ) , RG-MFM.W (McTE.7.) ! % i-,y, ;; .S : '
_r L - '-mm"w ' - ' - -* A
,i - +
i,' ,$.. L. . -] 4 ,
'l-i $..gpf.-
l g.
.l w !
E *' '
/ 7/ / / / / // // 'I . . . .
SECTIOk "A-A" . HQIE:
- 1. Damming Board Removed.
- 2. Mechanical Fasteners required at stress skin joint if stress skin is cut.
- 3. All joints and fillins shall be sprayed with Thermo-Lag 330-1 wherever possible (Typ. for all details).
Attachment 9.2 l I Page 8 of 29 nocsonamman ammoN non i 10.25.89 9 44 of 87
TYPICAL THERMO-LAG TRAY COVERING IhTERFACE WITH PENETRATION SEAL (1-HOUR RATING) coNCRETii WALL cogCgai e /*
* : i' '- A .
FASTEMERS 7 l (TYPtCAQ {I',, F;'
' 's "A s. 'h'FiEr misTAur THE.a:go-LAG .
PEETRATicM SEAL 4 r-TRAY CR.ccNoutT ;
/tH/U//T/A x i % :-mauea. I f T-l IT/ / // ft / /~/ // f/] *
k.A O -WOC L ' . . ; ,. ,,,
*w a scAS:.0 TW '.'.il,,i,--
SY cTWEKS
' I' 7 .
flNSTit ' CM rcR. e,F s $ . .*, ~. l ** P* m TicR SEAQ , N.
'330-I SFRNY APauCXficM ("7YPICAQ NOTE: Damming board for silicone foam installation left in place.
Attachment 9.2 Page 9 of 29 PROCEDURE NUMBER REVISION FACE 10.25.89 9 45 of 87
TYPICAL NON-PROTECTED CONDUIT INTERFACE WITH PROTECTED TRAY (1-HOUR RATING) 330-1 MIM ' qtt ' 5" Thermo Lag 330-1 (ula) e.j..=:==
/ / / / J.] ///f s / / /
u . ss c, n-J* /
,.- .=, /' X /_ / ~
l . c,= 1 '00 O r tungY i i i iir _NEU17. L (u2UinuicC~cED Cs!1 ORMA5LE CEKANIC, S.AMXET THERMo-l.:Ae 330-14 CAELE TRAY YPROTECTED) . STRESS SKIM HQIE: Flex conduit, Thermo-I.ag coverage shall completely cover the flex up to and including the rigid conduit attachment. Attachment 9.2 Page 10 of 29 PROCEDURENUMBER REY!sION FAGP. 10.25.89 9 46 of 87
CABLE DROP TYPICAL NON-PROTECTED CABLE INTERFACING WITH PROTECTED TRAY (1-HOUR RATING) ONFCRMABLE CERAMIC ELANKET 4" _ CABLE TRAY (gjN) (PROTECTED T c a 3 ; _i _> i.i is i!
<1 siiiii . r . . u.. ,.o . . .... . : . ..m . @5' 1- - ^ ^ ~ '& J.L.,.
W/ f- i / / / f G* / ^O O $ OC tMIU V O0000 . 1.LA'fER OF STRESS i SKlu OMLY <
'THERMO;Lh&330-ri, STRESS SKIN SN&LE OR MULTI-COMDUCTOR CAELE.
CMOM PROTECTE.D1 . Attachment 9.2 Page 11 of 29 PROCEDURENUMBER REV153ON PAGE 10.25.89 9 47 of 87
CROSS SECTIONAL VIEW OF THERMO-LAG 330-1 SUBLIMING COATING ENVELOPE SYSTEM APPLIED TO JUNCTION BOX ASSEMBLY L Conduit Covered with
,r thermo-Lag 330-1 and /" Thermo-Lag Stress Skin Thermo-Lag 330-1 -
Subliming Coating ' Thermo-Lag Around J \
- Edges to Make on Envelope if 4 # j s, ,
' . , =% / r- Thermo-lag 330-1 I ~
N; ' *- % g :~ J: Q'q$ l
'd , % -
J ' a a l
*.s. T * ; % a. s .
y II
- id i ,
8 AS3embly Thermo-Lag *** ION 330-1 Applied [ *g - p \, i _ ,~ to Thermo-Lag q ^ ;* \. ? S ress Skin Thermo-L.a9 t t f t ,i. g 18 Front Plate Section 7
/
I p' c g b- . g
/
s ). /e Non
' s. % . i. , *f , N 0edicated I J, Conduit
{ Stre Yn 1 m 5" Thermo-Lag 330-1 Seal NOTE: All non-dedicated conduits penetrating a dedicated junction box shall receive Thermo-Lag coverage rated equal to that required on the junction box for a minimum of 18". In addition a minimum 5" deep Thermo-Lag 330-1 seal shall be installed in the interior of all non-dedicated conduits at the point of penetration into the junction box. l Attachment 9.2 Page 12 of 29 PROCEDURE NUMBER REVISION FACE 10.25.89 9 48 of 87
J. CROSS SECTIONAL VIEW OF THERMO-LAG 330-1 SUBLIMING COATING ENVELOPE SYSTEM APPLIED TO STRUCTURAL STEEL MEMBERS Fasteners'
/
s
/
V-5tif'eners y , s,
,i .g.. .
o e , [
- 1
*' Ther=o-Lag 320-1 1 Subliming coating 'll 5 '. ,l ll, Casteners ,
c U-channel - s V-Stif'ener - N-T -
'I I//4i/ / Then::c-Lag c 330-1 I Beam or &
[f - .%~M " Subliming Square Tube ( Coaeing 1
-N <
lil &; ' '
.// O- 1 / ,
s NO]I: As an acceptable option, Thermo-Lag 330-1 may be directly sprayed over hot dipped galvanized structural members using the thicknesses provided in Table 4A. When painted surfaces are to be Thermo-Lagged by the direct spray application, Thermo-Lag 351-2 primer must be applied per manufacturer's recommendations. Attachment 9.2 Page 13 of 29 FILOCEDURE NUMBER REVISION PAGE 10.25.89 9 49 of 87
TYPICAL PREFAB PANEL CONDUIT COVERING 1-HOUR RATING,1/2" THICK THERMO-LAG 330-1 i 1 1 i l Cod 4DOIT I
, / /, / / / / / k / A / / / / / ~
xm>
/+ vnv1 l \ 'CCWCE'E7'E) .' -
p j FA:n -Eit. /
- . '-UNISTKUT CDMDJC SU -r:n @3YsVii//ff7A=4 (MW.2}
T ,:,E A % 4 M 4 I 3 #~ RLLIM
'h $ (=.55 SMd kUiK.XTdE32MC-U,G 3M4 TAEAxe J.,x4 3w-49 P25 Aa PAMEL NOTE:
- 1. Thermo-Lag 330-1 fillin can be spray application grade or trowelable grade.
- 2. Extend Thermo-Lag 330-1 envelope to unistrut and support bolt. Continue envelope 18 inches beyond support bolts for thickness, see Attachment 9.3.
- 3. For an acceptable option, see Attachment 9.2, Figure 19B.
Attachment 9.2 Page 14 of 29 FROCEDURE NUMBER REVISION FACE 10.25.89 9 50 of 87
-_. _ . _ _ _ _ _ _ . . . _ . . _ _ . _ _ . _ _ _ _ ~ _ _ _ _ . _ _ _ _ _ _
TYPICAL TRAY SPRAY APPLICATION BARRIER WITH WALL AS PORTION OF BARRIER (3-HOUR RATING) WALL
\ THERMO-LAG 330-f FLAREP IMTO WALL '
(UO NASTENER RE.GulRED3 250 N y .000 .
\
[E 1///////////[ u i i f y Php A uno a rJN WITH .10tMT LOC.ATFP TO SU fT f . mr war ev R l
\
- C- 9e sG CASD N ? / ,
k
///////////) % / ThiERMO- LAC- 350-1. SFRAY AFF it ATiON, LAYERS MEED TO EE IMSTAI r ep Ag COUDITIOMS WARR/4JT STRESS $R/N INSTAU.A.o Psa, se.cTioN '4.I F1ECES OF STRE5s SKIN TO FILLVolD5,USb A5 KEGU1 RED.
Attachment 9.2 Page 15 of 29 FROCEDURE NUMBER REVISION PAGE 10.25.89 9 51 of 87
TYPICAL NON-PROTECTED CONDUIT INTERFACE WITH PROTECTED TRAY (3-HOUR RATING) CABLE (NON PROTECTED) CONDUIT SEAL 18" 5" Minimum of Thermo-Lag w l (Min.)
, , , , , i i s u > < i a \ ****., , / / / / / Lf / ,' ! A _' ' ' '
K T.% .4.--_ - _
- 3. r; N CABLE TRAY (PROTECTED)
-],.:i"' 7Z ~ 7.- ! I 'd CQ /C[ ,
OWO 4 (Min.) Q,- ,,,i<s
,L -
THERMo -LAG 330-1 & STRESS SKIN
' CONFORMABLE CERAMIC (STRESS SKIN INSIDE & OUTSIDE)_
BLANKET THERMO-LAG 330-1 FILL IN l Attachment 9.2 l Page 16 of 29 PROCEDURE NUMBER REVIS10N PAGE 10.25.89 9 52 of 87
CABLE DROP TYPICAL NON-PROTECTED CABLE INTERFACING WITH PROTECTED TRAY (3-HOUP ".ATING) Thermo-ug 230-1 Confomable Ceramic Fill In ; Blanket i 18 " (Min.) s 1 Layer Of Themo-Lag a / stress Skin 0nly' ,
, , ri r , , , ,
c,
. -i ~- ' ' '
f Cable
' Ek x$T ~
I" cable Tray ((:[. ' .
, } (Protected) , **44 s ft 1, : t'l ! ' ' '
- s J / / / _/
3 ty / p n a y ,,
~6"(Min.T g ,- ,- ,
m if g J /_ / / \/ l} I Conformable ceramic Blanket
* \ f ,
Cab 1'e (Unprotected) - Therre-Lag 330-1 And_ ~ Stress Skin (One Stresi Sk'.n Inside and One Ouuida) Attachment 9.2 i Page 17 of 29 l FROCEDURE NUMBER REVISION PAGE 10.25.89 9 53 of 87 t I
._ _ ____ _ __ _ __________ __________ __ _________ __ J
1
- TYPICAL THERMO-LAG TRAY COVERING INTERFACING WITH PENETRATION SEAL l (3-HOUR RATING) l -
s ! ~ . l
$5M m -
2$.I; }.' - ccMcRETE WALL
.:, ..s <- . 1 i j p.n gg R.5(a sT ANT . . ,~:f..6. mynm<m_ (po rf 2)
_Nd 'I*/ U* l .
- s / AwNNNNXNNk p%Y cit.CCNDutT W////J////A i
O % \\\\W '
'////////I % . ..
a .s ~('
=
e 33c-1 FIL! -!M (ygar at ,Q Q .~. " e Fa, '.,.4- . mwasau sm) l I THERMO-LAG INSTAT T Fn PER SECTION 6.1 l l NOTE: i
- 1. Damming board removed.
- 2. Fire resistant penetration seal is to be installed to fully block / seal the penetration.
Attachment 9.2 Page 18 of 29 PROCEDURE NUMBEA REVISION PAGE l 10.25.89 9 54 of 87
TYPICAL THERMO-LAG TRAY COVERING INTERFACING WITH PENETRATION SEAL (3-HOUR RATING) Nc 4. . DAMMING ECARD ;"cR 51LLCOMP. FCAM - - INSTM ' AT!cN LEFTIMPt.M".E - :PrT -
-s r-ce coucxaTs FAsTsurz- .6 - " W- ht=c-(;T'yP ~~i5h' O h_0. - .*-i?
4 c. aWA4d utrire "E5c-1 FILLIN S ~
,, - i ~h ~3,'.t -.
(nra muu.u an=q gngw
--:~ &. s. a :. s .-,
ena warwt
...y> ,Pulg7zr7twm %%%%\\\%\\%\NIQ 1
(#075 2) 97/?/HHM/HHAD L 4xgggggggxNgNygNgg. . L M @COCUU g.....-
.* ga - ;< ., -1 l s:, . a . - - - -- s c , a ' ~ ,.
KACWock #30AAD ( EV cTriiEit.S) THERMO-LAG INSTALLATION PER SECTION 6.1 NOTE:
- 1. Damming board for silicone foam installation left in place for concrete fastener specs, refer to Figure 6. I 1
- 2. Fire resistant penetration seal is to be installed to fully block / seal the penetration.
Attachment 9.2 Page 19 of 29 l l PROCEDURE NUMBER REVISION PAGE 10.25.89 9 55 of 87
i -. I . I TYPICAL INSTRUMENT TUBING OR CONDUIT COVERING 3-HOUR RATING (2) - 1/2" THICK THERMO-LAG 330-1 PANEL WITH OUTER LAYER OF STRESS SKIN 330-69 l l APPROVED STAINLISS
- d. I STm TIEWi8tas ..;. I l 1
. .,.:p . * . Y. $;;7- * . . . - .s ,' . . . . . . .. 4; .
f: s ,,....-
.,g.2 ." . - ~ ..a:.? ' %. .?'
2pi't. ' .
- pgacAutK wits ~**' ~: . . .- N .0-LAG 330-1 SU3 LIMING .,..c. *?o .* p * /
2,'. . id.ATERI.E - TROWEL GRADE OHLT
,. .... ~
4 ,, _ m '0-LAG ONE OR THREZ HOUR 711E RATID
.Y ., .~' ,. ,,f. PRESEA?ID CONDUIT SECTION . r ..
f .
; APPROVED STAINLISS STIIL TII km CONDUIT, CA3LE DROP OR INSTRUMENT TUBING i
l Attachment 9.2 Page 20 of 29 PROCEDURE NUMBER REV1510N PAGE 10.25.89 9 56 of 87 l
THERMO-LAG 330 FIRE BARRIER SYSTEM PRESHAPED CONDUIT SECTION DESIGN FOR CONDUIT, CABLE DROPS AND INSTRUMENT TUBING 2' (Max.) , , e e
' P 1/4" Concrete Anchor
[;,J Tl T [ Bolts (TYP) See Note l THERMO-LAG 330-1 . , Below l Prefab Panels - '-
- i a*
A (Scored as req'd) - , -
'j q , P :=
_y
?
i
\ Instrument Tubing l %% o/ ': .
Thermo-Lag 330-1 M I/////Mk ', Fill in as required :, ,' Y
. bNx //////M---i: r
- ',? ?E \
*h..te y.
4E 1e THERMO-LAG INSTALLATION PER SECTION 6.1 (SELF SUPPORTING THERMO-LAG SYSTEM THAT CANNOT BE SUPPORTED FROM CONDUlT. INSTRUMENTATION TUBING l OR ITS SUPPORTS. THIS APPLICATION IS FOR WALL OR j CEILING USE.) Attachment 9.2 ! Page 21 of 29 FROCEDURE NUMBER REVISION PAGE 10.25.89 9 57 of 87
l 1 PnTAnazcArzD PANC. CAP
- PRE-MOLDED CONDUIT SECTION 7-~". USING WALL AS PORTION OF BARRIER r- ,- %. .i---
, , ., 1 l
i .s g
- * )-
i, .... l , gs . .- l Q 4, _- -j.g.r= l
! . t .. . l I' ;.j! .
j lL s:h* ig
,.i:. .
i
. *r. . ? .Ik . '. I I. ' 1 If 1- .
I. g; l330 TROWEL GRADE MAT'L l i1 .. - s 1.* -
*l ,
i'I .
....C. ,
P g. *. ii 1.Ei l
\1 . g:.
- I I
... *' *:**
- b- .
I : ::* .
*4 -.m.
CCNCIETE v.u.t. gl - I * .
,, , ,, M -
jli rusmza
., .e 4 ceuonE ..-.. 1 t
SECTICH v: . o. . a ij ., 1 - ,A.. - Is : ' .. ..~ .. lli ll i, . A, i:1.e ,A - - si- . i:t.. - II ! a -
.l Ig . ..
I
;g *.. l' ~
330 PRESHAPED CONOUlT SECTION .
.*- l.
I (t . ij , [,
,1.l .(, -
NOTE: Fasten system togeth'.:r with 18 I .,g, ga. minimum stainless steel tie wire. gl-
, .,f The wall must have a rating greater g -:a7 than or equal to the Thermo-Lag i ;.T -
Barrier rating.
!! 3fy " Typical Installation Details" Attachment 9.2 Page 22 of 29 PROCEDURE NUMBER REVISION FACE 10.25.89 9 58 of 87
CROSS SECTIONAL VIEW OF TSI THERMO-LAG 330-1 INTERFACE WTIE 3-M INTERIM E-50D/E-54A APPLIED TO CONDUIT , 3 HOUR RATING Stainless steel banding is used on the E-500/e-54A mat overlap. CP-25 caulk around en* ire
. perimeter of seam interface.
i m l . .
~
I i g .- l _ _ _ _
\
l )
} ;-- -
g i 2. ..
\ ,
Thermo-Lag 330-1 _ 2" min. overlap of E500/E-54A onto non-3M product. (TSI Thermo-Lag 330-1) l i Attachment 9.2 Page 23 of 29 l noczouammassa amsmw nos 10.25.89 9 59 of 87 i i
t 4 I DIRECT SPRAY APPLICATION 4 i 2bles l . 'i Cable Tray . Themo-Lag 330-1 [ (solid. Bottom) \ 0000 0' rO0000 TYPE A -For Non-Dedicated Tray Only
- Cables Cable Tra Th m u g 330-1 (Spray) i (Ladder Type) ,
i
- Themo-Lag _
0 00 00 . : TYPE 5 -For Non-Dedicated Tray Only l
- 1
+ Cables !
- Cable Tray Ther:no-Lag 330-1
! (LadderType) # (Spray) l j lThrmo-Lag 330-1 - g- [ooOo o
- j. (Spray ) -
d TYPE C -For Non-Dedicated Tray Only I Cabl n , Cable Tray j 1 (LadderType) ' nemo-Lag 270 (spray) ,
. I i '
Thsrmo-Lag 270 - m Ooo _ 0 0% m i i (IE"3Y) TYPE O -For Use For R.4.1.75 Barrier Only } Attachment 9.', a Page 24 of 29
~
PROCEDURE NUMBER REV1310N PAGE
; 10.25.89 9 60 of 87
1 l TYPICAL CABLE TRAY THERMO-LAG 330-1 COVERING, 1 HOUR RATING APPLIED BY DIRECT SPRAY, ROLLING OR TROWELING APPLICATION hETHODS i CABLES CABLE TRAY 4 (Solid Bottom or Ladder Type)
\
l= ' w _
- Y 1 - Thermo-Lag 330-1 Applied by Direct Spray, Rolling and >
Troweling Application Methods 1
~n . -s Attachment 9.2 Page 25 of 29 FROCEDURE NUMBER REYlSION FAGE 10.25.89 9 61 of 87 l
THERMO-LAG PREFABRICATED PANEL CONFIGURATIONS FOR STRUCTURAL STEEL SHAPES 1-HOUR AND 3-HOUR APPLICATION E f/$ > /
= ->o=
APPROVED STAINLESS [ STEEL TIE WIRES (OPTION) , gh APPROVED STAINLESS STEEL g . BANDING (OPTION) a APPROVED STA M MS STEEL TIE WIRE (OPTION)
~
z -'
/
APPROVED STAINLESS STEEL BANDING
- VSTAINL
, l '
(O m 0N) S M TIE
; p WIRE (OPTION) / ~f f. a '
h kV TOUR
\
INDIVIDUAL SECTIONS 1, ! 0F PREFABRICATED PANEL Thermo-Lag installation per Section 6.1 as f 8
/ TWO "L" SHAPED applicable , n .', SECTIONS OF PREFABRICATED STRUCTURAL I - BEAM Attachment 9.2 Page 26 of 29 l
PROCEDURENUMBER REV1510N PAGE 10.25.89 9 62 of 87
- - .- _ . = . - . - - . - . = . . . . -
TYPICAL THERMO-LAG INSTALLATION FOR INSTRUMENT TUBING, SUPPORTS ONLY
- O
- s -
sS "c -
- u ,
da s-9 e
.s. a ~; ., =:
L*
?. J 5.i-- ; g>-
85 s-
, rg e"
i!;: :N d .
, Ni.I bb " e ~ "qm:.g 2 - % 3 '
d .f. ~ 4 g ai
't-g :I :i 55 tt .j 2 g j
- 2 1-
~ ,) !!
cd
$d> I ., 3 a s o
I I m Giv-', w~68 i C'ci Y E j 55 w : "I i mm-a --. Sj. t
! M C.
- M ~
15 9" 8 5 2 9.f g [ "5asssd a<- l ~ g ,1
. =I .i 4 ; ;5 IC 3 l
E E: RE d;.
-*- .r;; % . '. .n. .n r* 'W1 .; . y tp EQ. ; ?.}.yl gl L w -- -ge m a y g?'i%?
gu h . ?
~
a e Wldl{),_
< ?? . ~
t$ e s e 2. a %, 2 = ,
- 3 -
e e
< l.s I 2', ,i s s v \
s
- 5
-t!
- 5
; ! 5 8i ~
l ;E 5
+ E s
w Attachment 9.2 Page 27 of 29 PROCEDURE NUMBER N PAGE 10.25.89 9 63 of 87
-. __- - _ ~ . __ _ . _ . . ___ _ ~~~
. , . ~g '
-l Q*-~ -E=V2K 2C.L=:SU**mt:r=:* ~ .
M!N . j i M 9'Miw. /
.t 4. . '.' gg j [
rxim.--x )..::n.M,l
=.xIS*'n 'k~ *"" '~32D
- dmer ==,ses = = =
c > ; . . . au on Cs Dw- . o u ac..s.--.. g - I \ CAUNJ./ARY"52.5/AIC g ';$res ' ) * . - ' l _
. 1, -
- 1 , . .
1 I
=9" il . l y ./4 ^ !" 9 sh a-7 --- .1
( p 1 i ' y l _ . I l ll . wA . I v.d'
- @ '. ' "l - ]$ - r- tm f 4 , 1-6% w - - T . *2 EE}
h . 1 & ' CAh!.E.~iW.THEKMD ~._ . r I usa n: W fna : - ?A .g;.auign .rigsmo.us-
~
ENVEL.Dff*0KD!DiCATED E
.CW F.M VEL *J:.c::"~Su.wC"..
TAAY.'*(ALSD MLJ.52KED 10 .57.Ki.4,:. (CAtJWAM CNLY)
/s'Amts. zvsr.e.suoc -
CKPEE~Y6 Y ~ ANO. 5.0 ppt 2RT.. STEEL.._ '
- : TR&RMo _LXG~~~PECCKZWK/K~ -
\ -~
A NGL.S 'WCKHme/D .. .ARGl.S ~~~s CERM0/O ' =l * '!" G ZS L7tMENSied ~ $/Z& .D/M F/J3/B M l S g S 4 2/4 - 7/g " . (, * (. * / . . / 4" - A > l S'4 vM A 7/s /".. . Ya2Vr'jer/ 4 % to e i 3 /. 8 $W. x W. / ". '. aA v.
.. 4 4Gx # h . y. 2F,W uu4 /._. 'g # ' ~ :/Ys" ..* :~~te x 4-$ J/6 J. w 4 st.2/s '
Ys .1*g st% u / 4 v 4 w.. h '/ 1" '
- lt::To~i4 s & 1 = 2 'pI * <e h.,y ,
- 5 e 6 W J/4. / % .". -. .) CEud a /. . ; v.e 2 f/s'W 9'f c t:0 t. '
5=5#/ r '/ %" " ' T .2- Sv3 v. #A V ' /.it' s a.M'm r
- b s 4 n d/J.,
l' ~/* % " *.T' CicE.s V: _._ _. Y s 1%" gay
,, ,,a ,"YoQ' Attachment 9.2 Page 28 of 29 PROCEDt!RE NUMBER REVISION FAOB 10.25.89 9 64 of 87
. _ _ _ _ . . _ _ _ . _ . - . _ . _ . ~ _ _ _ _ _ . . _ _ . _ _ . . . _ _ . _ - . _ . _ . _ . _ _
4 i; 4 1 4 4
.x .y . '
h . p e m b . m a s.7 Ea r. N
'-(,s.at46-tMaasd ~ .. . 3. ' -
TMek % ~ I -
'gggdp.'
i ' . @AT '$rRti MY' '. - ! . . C, a N R W an, Tis 4 M - a _
~
- l.l * .
S. , l -
~
gn ~ . W
.j.
c- =- 7
.,..,p Hcasue sD CQoWOWE? $0tL of 5T*ER Ho - L9Ce i'
L9QiF[CRT[0N R R M E R C LA R I 4 4ORW T h6-- 1 4 l Attachment 9.2 Page 29 of 29 raoczouanmmnea mzymon FACE 10.25.89 9 65 of 87
.. .. -. _..~ _. . . . - _ _ - - . . . _ _ . _ . _ _ _ _ _ _ . _ . . ~ . . . . . _ _ _ _ . .
1 ' '~ THERMO-LAG DRY THICKNESS REOUIREMENTS FOR STRUCTURAL STFFT. i l ( l' :
- 1. SOUARE STRUCTURAL TUBING: DRY THICKNESS (IN) ;
SJZE 1-HOUR 3-HOUR l 2 x 2 x 3/16 ' 3/16 11/16 - l x 1/4 3/16 5/8 i 3 x 3 x 3/16 3/16 5/8 ! l x 1/4 3/16 9/16 ' i 4 x 4 x 3/16 3/16 5/8 l x 1/4 3/16 9/16 l x 3/8 3/16 1/2
- 5 x 5 x 1/4 3/16 9/16 x 5/16 1/8 1/2 x 3/8 1/8 1/2
- 6 x 6 x 1/4 3/16 9/16 ,
- l. x 5/16 1/8 1/2 l x 3/8 1/8 1/2
- 8 x 8 x 3/8 1/8 1/2 !
! x 1/2 1/8 9/16 i 10 x 10 x 1/2 1/8 7/16 x 5/8 1/8 3/8 ! i i l
- 2. RECTANGULAR STRUCTURAL TUBING: DRY THICKNESS (IN)
SIZE 1-HOUR 3-HOUR 8 x 4 x 5/16 1/8 1/2 x 3/8 1/8 1/2 6 x 4 x 3/8 1/8 1/2 x 1/2 1/8 7/16 !
+
Attachment 9.3 !
- hge l of 6 i PROCEDURE NUMBER REVISION PAGE l 10.25.89 9 66 of 87
~
t 4 THERMO-LAG DRY THICKNESS REOUTREMENTS FOR STRUCTURAL STFFI. (continued) ;
- 3. ANGLES: DRY THICKNESS (IN)
SIZE 1-HOUR 3-HOUR 3 x 3 x 1/4 - 3/4 l 3 x 3 x 3/8 3/16 5/8 ' 3% x 3% x 3/8 3/16 5/8 x 1/2 3/16 9/16 3 x 3 x 3/8 3/16 5/8 4 x 4 x 3/8 3/16 5/8 x 1/2 3/16 9/16 ! 5 x 5 x 3/8 3/16 5/8 5 x 5 x 3/4 1/8 7/16 x1 1/8 3/8 6 x 6 x 3/4 3/16 7/16 x1 1/8 3/8 8 x 6 x 1/2 3/16 9/16 x1 1/8 3/8 6 x 4 x 3/8 3/16 5/8 x 1/2 3/16 9/16 x1 1/8 3/8
- 4. CHANNELS: DRY THICKNESS (IN)
SJ2E 1-HOUR 3-HOUR MC 3 x 7.1 3/16 11/16 C 3 x 4.1 1/4 7/16 C 4 x 5.4 1/4 7/8 x 7.25 3/16 11/16 C 6 x 8.2 1/4 13/16 x 10.5 13/16 11/16 C 8 x 11.5 1/4 13/16 10 x 15.3 1/4 3/4 Attachment 9.3 Page 2 of 6 FROCEDURE NUMBER REVislON PAGE 10.25.89 9 67 of 87 4
l - l !- THERMO-LAG DRY THICKNESS REOUIREMENTS FOR STRUCTURAL .l STEEL (continued) l l I
- r. <
l
- 5. WIDE FLANGES: DRY THICKNESS (IN) l I
l SIZE 1-HOUR 3-HOUR I W 4 x 13 ' 3/16 3/4 i W 5 x 16 3/16 11/16
- x 18.5 3/16 5/8 l W 6 x 8.5 1/4 15/16 x 15.5 3/16 11/16 )
W 8 x 10 1/4 7/8 l x 13 3/16 3/4 l x 15 3/16 9/16 x 24 3/16 9/16 l x 28 3/16 1/2 l W 10 x 11.5 3/16 13/16 i x 15 3/16 11/16 + x 29 3/16 1/2
- 6. UNISTRUT SECTION: DRY THICKNESS (IN) l SIZE 1-HOUR 3-HOUR P 1000 5/16 1-1/8 1001 5/16 1-1/8 1001 C3 5/16 1-1/8 1004 A 3/16 1-1/8 P 3000 5/16 1-1/8 3001 5/16 1-1/8 P 5000 5/16 1-1/8 l 5001 5/16 1-1/8
- 7. EMBEDDED PLATES: 3/8 IN. MINIMUM DRY FILM THICKNESS Attachment 9.3 Page 3 of 6 l PROCEDURE NUMBER REVISION FACE i 10.25.89 9 68 of 87
THERMO-LAG WET THICKNESS REOUIREMENTS FOR STRUCTURAL STEEL
- 1. SOUARE STRUCTURAL TUBING: WET THICKNESS (IN)
SIZE 1-HOUR 3-HOUR 2 x 2 x 3/16 1/4 7/8 x 1/4 1/4 13/16 3 x 3 x 3/16 1/4 13/16
; x 1/4 1/4 3/4 4 x 4 x 3/16 1/4 13/16 x 1/4 1/4 3/4 x 3/8 1/4 5/8 5 x 5 x 1/4 1/4 3/4 x 5/16 3/16 5/8 x 3/8 3/16 5/8 6 x 6 x 1/4 1/4 3/4 x 5/16 3/16 5/8 x 3/8 3/16 5/8 8 x 8 x 3/8 3/16 5/8 x 1/2 3/16 9/16 10 x 10 x 1/2 3/16 9/16 x 5/8 3/16 1/2 l
l
- 2. RECTANGULAR STRUCTURAL TUBING: WET THICKNESS (IN) !
l SIZE 1-HOUR 3-HOUR 8 x 4 x 5/16 3/16 5/8 x 3/8 3/16 5/8 6 x 4 x 3/8 3/16 5/8 x 1/2 3/16 9/16 Attachment 9.3 Page 4 of 6 I raOcsounawuwssa arvmON PAGE j 10.25.89 9 69 of 87
)
l 4
THERMO-LAG WET THICKNESS REOUIREMENTS FOR STRUCTURAL STEEL (continued)
- 3. ANGLES: WET THICKNESS (IN)
SIZE 1-HOUR 3-HOUR 3 x 3 x 1/4' - 1 3 x 3 x 3/8 1/4 13/16 3% x 3% x 3/8 1/4 13/16 x 1/2 1/4 3/4 4 x 3 x 3/8 1/4 13/16 4 x 4 x 3/8 1/4 13/16 x 1/2 1/4 3/4 5 x 3 x 3/8 1/4 13/16 5 x 5 x 3/8 1/4 13/16 ; 5 x 5 x 3/4 3/16 9/16 i x1 3/16 1/2 6 x 6 x 3/4 1/4 9/16 x1 3/16 1/2 8 x 6 x 1/2 1/4 3/4 x1 3/16 1/2 l 6 x 4 x 3/8 1/4 13/16 x 1/2 1/4 3/4 x1 3/16 1/28
- 4. CHANNEI3: WET THICKNESS (IN)
SIZE 1-HOUR 3-HOUR MC 3 x 7.1 1/4 7/8 ! C 3 x 4.1 5/16 1% C 4 x 5.4 5/16 1% x 7.25 1/4 7/8 C 6 x 8.2 5/16 1-1/16 x 10.5 1/4 7/8 C 8 x 11.5 5/16 1-1/16 10 x 15.3 5/16 15/16 Attachment 9.3 Page 5 of 6 FAOCEDURE NUMBER REVEION PAGE 10.25.'89 9 70 of 87
- , z . _.
THERMO-LAG WET THICKNESS REOUIREMENTS FOR STRUCTURAL STEEL (continued)
- 5. WIDE FLANGES: WET THICKNESS GN)
SIZE 1-HOUR 3-HOUR W 4 x 13 1/4 15/16 : W 5 x 16 1/4 7/8 x 18.5 1/4 13/16 W 6 x 8.5 5/16 1-3/16 I x 15.5 1/4 7/8 W 8 x 10 5/16 1-1/8 x 13 1/4 15/16 x 15 1/4 7/8 x 24 1/4 3/4 ; x 28 1/4 5/8 W 10 x 11.5 1/4 1-1/16 , x 15 1/4 7/8 x 29 1/4 5/8-
- 6. UNISTRUT SECTION: WET THICKNESS GN)
SIZE 1-HOUR 3-HOUR P 1000 7/16 1-9/16 1001 7/16 1-9/16 1001 C3 7/16 1-9/16 1004 A 7/16 1-9/16 i P 3000 7/16 1-9/16 ! 3001 7/16 1-9/16 P 5000 7/16 1-9/8 5001 7/16 1-9/8
- 7. Refer to dry film thickness for embedded plates.
. Attachment 9.3 Page 6 of 6 raocuounammnen nevmon r4aa ]
10.25.89 9 71 of 87 i
, _ .______.____._O
_ . . _ _ _ _ _ _ _ _ _ . _ _ . . _ _ _ _ _ _ _ . . _ _ _ . _ _ _ . . ~ . _ _ _ _ . _ . . _ _ HEnop @ MErdc) (9 MET @[9 [P.tus.t2ED). gl. TD \ A din N -t Mm m /mowh.r . / noe miRm!c-mkt of Q
\(, ggl mmcuMasap;t7l TYP. ALL METacht 4 , , - -
h riS k g],
<36j cn.l{ [g'lf cd [pg l
f- fQX-. 3, hk kT
-h Q'iff' w / H s.T e 6 ).
s2 e b (c o M.- .5,wcedi) ,
' ScARDS ovER CAS#5 -
hosure fLActe unen ,gg.g TROW EL
- w % lbonno Eu b ?ieces cAs.es .5EMovW c;,ggag,. .p; q w
,pe C4 To REST cN 530 1 , ~ '5AMsfFanM 'EMNM- 7gp df CABL?f S ON d.AELES , l"TRic<- * # ' .Wf g . gip ,- ' . ;11%e - ow Exti"5ecioni$. .
I* j < a 7 ,
- i y sEii. t4 ATE C.
W s5 $ = ::: j_, i if: l I.i I
% crima A 4 (ror m w w.rD,db 4@) .f 4.
i . NNi
._6- ~
NOTES: 1-TOP TRAY DEDICATED. 6-0.K. TO TAPER WIOTH FROM 2-LOWER TRAY FALLS INTO 18" RULE PROTECTED AREA. SUPPORT TO MIDTRAY AS LONG 3-ASSURE 18" COVERAGE AS REQ'O.EITHER SIDE OF AS 18" IS MAINTAINED.*
. SUPPORT.W=2L+5W. .
7-W= WIDTH 4-TIE WIRES 18 GA 55 MIN OR'.020X SS BANDING '- ' L= LENGTH PER TSI 20684.
. SW= SUPPORT WIOTH -
5-TIE WIRES OR BANDS MAY GO IN AND OUT OF ENVELOPE WITHOUT CONCERN. Mei 'EbanteR T!EHINATicN Nsite. c5 NdN bcbtfMEd'TYAY IN LIEU OF TdIAL TbY 18' Rut.E. (9t.t. Tuas. (j) MiTecos swu Aewe. Mr. Au.sPraet E y HEr8co *@ is PRtfERRE Attachment 9.4 Page 1 of 2 PROCEDURE NUMBER REVISION PACE 10.25.89 9 72 of 87
~ .cwtes W l 't l l' I . A co 2-l #+ Faxet.s .cx nn __ . l 1.weap c.sai.1 sey :
wt fn.exp. ll\ Dl, jt
,a .fC' MM.
W /i*H .2"d d 4 M c .o M i
.5GCR. in dxni; EM.vsLat*E l .l, U-HR 4="c= .l m. T r l'+
2t2A '
. >ji: .
t2 . , W "*v/c ist.m._2 M ~'. N// '\\\ i
,' +
d
/
_u -
. - . - - de -
l __ _ __ _ -. .-._ _y
~--- _ _. u. - '
i i
,sf \
- j . !
l. j N ___ ___ _ _ . - _. . - I l _ _ _ __ , -- .... y. .
.i 1 I I s i < e- .... ;
- iy
! j li- 16IM!N. Y
- Ext.st Owicmro y; l
.g. l
- Co, n.a- , ;
l l 'EXI$#.. Mod = . 2 Odcwer**m _psw.t.:c 1 . '
/
OECJCA c.C Cl8f,5 ?ANY .FtxE.S7cP
~
(.&fN. ETCo'Vst)- i
.itl C.7~KERMCGr-C&3 - , l .26C/C1750 CdBlU TMai' - t//////l/f///) *C/.Mn d5 * ' rI* .2.2Gt///.ZQ m.
Et!.Si~MEMc-f 4r dto /. fed- -
. OGC/G i'!O C CM C Wi".
l Jj, /'/hxxixNNNNhNN1 lf I . -
- , . . . . _ . . . . . . : . ~. . . . : . . . . =- ,x c . ._2.asn wca-cectur.o.
J 7 \NNN\\h\Wh\\\J _1 . . NCC9?.i , . _J A (////g/' /A///1 $:' eat 10. '. M*23: R.Ect.//KLC. I -
" ~-
M r/t. s y o _ , -ne w e t c 2AD E ( 5 "Mi N.) ,,
' C C A.? O U / 7~ f / 2 2 S i~C F Attachment 9.4 Page 2 of 2 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 73 of 87
i:. r 1 f AWIR WR.4/ CF 3M INrGAAM
- I f-% D F/KE PA' o rfC7/Ch/ Md?" W/tv y
?' kh W
. 40 Curl 4C' 44 YEA CF 57.CNLds3 5r227., .
MdSN W/21 CLetW CeyfA/N4 $NT'/A6 $U//CA/" l i du
~~~~ ' ~ $ ZYZ h/AfM63N W//~A %,' SCd4/?./ C/trA//Nff 8 ~]~ ' $ .040' OA l=A/i$tY W/Af O/As) CAU4K W
ftMM 44Ytt. W/rH CP-25 . . ,
" I, '.- L' J%.-
e ; , ( 6x'1511 Copt .
& CAW 4//75 i McNeAs & .* -
l W f.LAYEK WL4F ef 3M ZATEA4M *f-500 l
% b -_ k g F/Af f4ranoM M47. . .
l
$ F'ul .
l .R.:.NY / 3'MIM.G NDTh . A \ \ GA. S/06 0F: .
- s
, )A , J."o.c.r ..
/"ae. Ot" f'7 auisraun'Trn) i z (rgj { { r yt o (r yt:) TjY/.) -
C 4'A . l i d AA r '
+ -,I + /. -
[ .
+I frist proco ea u .
l+ k$
%y s f/000 t/Wl$rgyf ($ff McTE) k
- l s' .
q .cors: lt 4 . As AN AL.YERNAT& AEWeAX Fed DVERLCAD&D TYPE 3Y tuttner.t, 'Ad Apoco .fdrtaer L , A Y. arwas riu eye-m surm wu es Y
+' '-+ -N / ,+ ' xtrAu-@
l cosenae. Ar~7H6 M/MPM of TNG bdDuff ttb S' wa;
. ALTEAWATE R'EWORK OF M )
- UMtS7~Rur SUPPOR73 SEc7 tom A-A ,
Attachment 9.5 Page 1 of 14 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 74 of 87
\ . sse Mars 'tSX155 erwf,/A//$/~Auf* - \
m*., 4&~ MEW L'wa: ire s c ~. .
' 0 / bk 4. %f."
A (5 2
- (y ,A +7 %s-ucac exk g,ce ,, .
A r- ' : . Fx/sn(se R' D I
+ pi f.' - l gl 'ia? k' f .. * .u ~ - [tdMDW/f5 l .' y '. ,
5SC770N A-A ; 61/C* CcA.*. C1 : . y -
- AWM - tA flor-4:- .
- 1. M4KE'. Suxf' 7~Ma~A:cGD M at l
' UNIsr2xn 5/r RysN MA/As?"
7 , 1
- c o n c R s r f 3 5:~c c f Ts M u i M 4
, 1 rNg$
4 SeG5. A 5f 47EE WA4P OF EM ZS73%C4M* - 4- E'EbO FILE 7/cfrc.77cp n.g;- s a.'.~ ; ~ B,
.5.l. A.YEE. WK4P of GM NfEKAM" *6*SCD F/As PRoi' sci ~/cd MA7" . .W /fM W n.0ZC'"Jn~ f.C.3 0 /N1 ES$
b- . 57~s 1 f.:.3 4 N C S 3 -t- .yll .C.Adt.K .7Hd.F/N.44. .f,.ME/L W/TH 4 e . 68 6 .
%' N - 4'# A-:n sa.rs wir:t ?!+rxxo Lecd 'WArad25 ;HD MuT'. (Tdf.5 CAdd St26 CF E.<tsn UNI.;;ntv7*) ' ..r- --r ,! .$ l.
il j i _) AUERNATE RE'WDAF Oi=
-SGC7*1cN 8-o ~UN/3rRur SUPPCRTS Attachment 9.5 Page 2 of 14 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 75 of 87
' & LAYE2 WA4P W BM ZN7"sAAM'"-s-50.0
- F/Al PACI'EC7"/CNivji' W/77/4// Cddi~fA A Lt ys: of s1..si.iitsss sisitasss piixs i' y-t ;7 *?
Cf oTH CCY121MC fMT/f.E Sd5E Ptsimi?.(3: . W /A.a M 1 5 H W / r H .l4,T $ D t M A t 4*f 2 N / N d.5 A o C a e " l i z W .'? *:R ct L1,eu./ wi.es viaperzx.X ' . wb T UI 6 04/0 4//7*5 f !^
~~
N E- , Et/s7 coac.,. " ~ E LAYEA wx4r es SM i Ancycts 3; -- g
. .l '[ ZMit4H"s-sco six.c
- k
. P r : r s c. rr e d M A N 5.f AYEK wx* ce SM ZNTEKAW" 'h . .6-500 M25 F4rrier/cMMsr.
Q.a. +-
.-w.
m - A. y . h. b I'!m. 4 % t 4%.a 4% irl* - ycrA crms c.ri:.) L crrc.7 l fcrYFr p -.
+ + -t .
y* ' -
, . $X/$1" St!f?Cx7" 6[ '+
s f14tc ptxr - i/ t* . 1* (;4wM As tewsr.es7ica exty. hk
^ =
- l i cs+< ss say c eye ~.isa see ;,a a a 1.r-ug s g '
GQ * - g g- y ;- 3 ~ d. 7 a + \+ . 41 Qq ll$2KNATE &As& PLATE u P G 7"A L SGC77 cat 4 -A _ 1 Attachment 9.5 Page 3 of 14 1 1 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 76 of 87 i
- W =\ n " 6xtsrtM4 C.4 3 4 4 7, u"* r W/rH YHERMc-!4G (AJ7s4/A 77/GRMe -L44) .'E. .t. _ .. . . . , i i } ,UfW 7,WiiWMe=
I
- l$j 2 l
/ 4 4 f/A's St sp 2 ll .i . . . . - _.. , l t . f 1 Qas I i 2.: .; t . s..' . i ~~ , {$ > 5-4 Ext 3f'?d4 s . A. ,, ,
u %.
4 dor &e.dr2 1
- i '
wg f 5 . L NLd;
; X - . .7 .;,. 1. t '
N j w "4 9-}.- t. W4
.4 Gewowr PM~El .
B r N G I,, E ! 4- g a-ZHTaCCtM.*.2 50# mar YaA (AD 'Ax=' - TM Znie'i!x.tM 6-SoO mar
,C54/UC 540~24HC's. "
l l -Fi n' 79 M 47"CM 7"NERMc-T -TAG- O 3 M . s -50 0-
- a b 8,._ C.p p o t,//1'
.. I m--
t
~ ~ =- - - -
hh'rlr&go.t.,;g
~ .'ch1 W:., CAM?"_ T.B** ERMC-2.M - - i E-$oD. t$47' * ~ l 7 0 . f x ts ?". C t 8 4.6 r R A Y '
DET~$L F R CADLE TM*Y #ND DEO/c~AYe*,0 *
'CCMDu/7 FOR. .&-MeuK F/Rs RArJNG (A475KM476)
X,MAY.250wAE:McD/F/t.'41" led diWS/D UF-cd F/AE 7157 1 Basut rs) Attachment 9.5 Page 4 of 14 PROCEDURE NUMBER REVEK)N PACB 10.25.89 9 77 of 87
c
- 1 l
1 i l l l l l ' exisrtaa . Oy = 7x+v. Aco fra trop e i
- j
; t,#.*!-fr+" ppa rNs rcP W TNA oforur.co'.eceovir i 1 t 's t e_, fx s-soo ~m@ : 1_* wo ssa sc4. Fox esr:4tLs lMoras u^o act l .
__- _ _ ', 4. .cdote.orro coxcuir t w-3, --
; j
- i l
} l I
- l. f#.W$ 07d5CCHOUt73 X-f" &CX \
, i _ '.3. . kira MtW/ Mux 5*sa 1 . rAGent.o-L 44 r-e *.Ftx s sr v P en Etisnu..s . coitczere U\ C8 CcHrdiMA4GNr: S/2.L -
- kt"l
.a 5
l C2.SZ4/J FC.A dt.7R.GDOAf 80X. A%lD.2"?fDICAtTED. I CCNdu/T' E02 5;Hd?2R PJRS 84r/M4 I Attachment 9.5 Page 5 of 14 1 1 FROCEDURE NUhtBER REVISION PAGE 10.25.89 9 78 of 87 I
- . . . - . . - ~. --- . - - - - - - - - - - - -
ExtS7" conc. ECAM 5.h .. l,6x/sf. EM5a~DCfD Sag pirAIL / ~ .
,wq S M P' Pl47'l* .. .~ . b= ., ~*g o. ., - --,T- ,
s t.- cn- . 050/CA7'fD CcMDU/f 5A ; 6M ZNffA4M .F/Af' Al0H- OCD/l::A rf D C.CMDU/r fporteflod FJ20t* reArIsravocs /Mrs rNf 5 YSffM1.W/Y"W Y$ ?$.l.#x 'O'NA A4720 F/AS . Lggg,*r)( A$ ff4YOggrz PAprEC7"Ic4 SY.~575M. p:.x-rs csaae.e.ft *rsrs fwMo29475. 7"M WD l 4Ye725) 6 ' A *0. C -
. 8 d rA 7L./=0K CO N D U/75 . i } ,-{..,,,, .4 _n _, _ _ _ _n ,e %,
MlmMuM 5 o
'%~ l l
l Edt! TnAERCS Y1'/.752 FAD./.70/fex/47#As ! sus 4cenevy -
.' Leo's. exs nJ ruu '
( f.g'Mia.) , rMt?.EAD. AS&C Nur AEG'O. CA V4"$ Sct.7~x t dNGrg A s R e a '.o . . OGr*4/t / 1 l Detail for Cedicated ana Non-Oedicated Conduits Intruding into the 3-}iour fire Protection System. Attachment 9.5 Page 6 of 14 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 79 of 87
l l 1
\
2 4 5ttsr Ccdc BA4M ff5 OsrML / m yw. c,) ,. . Sn.sf GM.SfDDC
" S r p.i e P t 4 7" E ' ,49 ..
p, . . -.s,,,,',
. .r .
_r ~ .M
-W !w.unit'~4 Mt A
5s.acrun.a Ms+1 ace 5M INTEL 4M R'f ff.sp f 4 C f / d d 5 W
$ y's 7'sM WFM. $$ Xl',$ $ 7" FEE.-
L@F,,H&T)/. XS AGE 2 'D'( G,i.ef PL4rG. rn - giconestri TMMb'o 6 67'G"XS}d. Y"OC 0fi?&f/,,, &A b/?UCTUAN. $5N5ES Detail for Struc*Jral Member Int uding ina the 3-Hour Fire Protec:icn System Attachment 9.5 Page 7 of 14 PR e m M ER rey 1SION PAGE 10.25.89 9 80 of 87
~ / / j l l I 8 l I ! I 1
F i I 1 f
\
3 A 7- ! 1' II 3 l ._ . NI __ I I I A
)1] l I I 1 3: l l g: :
l 'q '1 3 A I I e
..48 / , *t L' 3 e ; - / 1 1 1 I . . I 1 . I I i 1 I . A< -
wran E-50o on coneuit and band according to 6300-C1.
- Apply CP-25 caulk to At support interface, E-500 final layers of E-500 must be cut to fit.
at conduit and support interfaces Apply 5.5. banding to restrain E-500 onto support as shown.
- gi. ::
4
- /
- i c: . . . . .
. /
i D
, , i Q. j. ,
- s. . . >
. ::y. ..7 9>, /
A 'L 1 . g \ v
.s ,
A
. . . 4 . ,
Apply CP-25 caulk to all straight ' line seems 'on final E-500 layer ,
. i Alternate Detail # 3-P.:ur F12 Prctaction System of Unistrut Conduit Support Attached to Concrete Attachment 9.5 Page 8 of 14 ,
1 PROCEDURE NUMBER REVISION PAGE 10.25.89 9 81 of 87
Wrap E-500 on conduit and Install 3 E-500 pie:es en band ac::rding to drawing top of support which are 6300-C1. At support interface, - cut to fit. E-500 must be cut to fit. N - 6..-": :.
. . e . . .:. -
I "; .
, , ." ,7 . ' ,
- l. ,.
, .. . lg .. C' : ' r . ...... :.'. .,:. g. . ~ I . . . l l
[:.: I N' h
~
I$,~ .h.k,
~: . ,i I ; i . = 3. ~~*. '.:. ~ .. ~ .. 4:
r 1, 1 o; f G'
~y, .. .t . }
d,
- . R~ . . . , / '
l.V A , y
, y --
e ,/. Wrap 3 layers of E-500 around Apply CP-25 caulk.to all straight support, be sure to include line seams en final E-500 layer. 2" min. overlap per layer. Internal Detail of 3-Hour Fire Protection System of Unistrut Conduit Support Attached p Concrete Attachment 9.5 Page 9 of 14 FROCEDURE NUMBER REV!SION PAGE 10.25.89 9 82 of 87
~'
P: r inta:fering heat t=ansfer items rce in w. = with a fire p:-xected itu, sfer to the ! fol.1 caring: - , l j < Pbr ew.:y layer Wich, can be.placed beten an 1 tterfering beat transfer its and the fi:n p ctocted itmo a layer may be renoved f==m the d ruzaber cf lay's:s required to wrap the j heat tra::sfer it.as. ; hamples of a fi:n protected Mdt and an ieaMng e -er*mit in her2:
-r- . . % .A r , . b . e. ..,
q.,. l 12" min. 12" min. l 2 layers 1771d
,u ., ,L. ..,
h .
' ~
Interfe::ini - 3 layers j emedait with - i J 3 fire protectad. A hyers , j conduit,with i
~' "
1 layer fully ~ vrapped s .:., _
, ,[,, , '
- 4 I *
. i .. .
f
^ '
8 12" min. t cal
~ ' /d ' " . \ ,
12a min. 3 laye:s # 1#7* 8 cypical
- fully vrapped 7 Wr*PPed 4
. l , ,7 ,~ . . . 2 layers 1 layer
- Detail of Required Layers of 3M Mat Material for Intruding Elements Intruding in the 3-Hour Fire Protection System Attachment 9.5 Page 10 of 14 PROCEDURENtHBER REVISION PAGE 10.25.89 9 83 of 87
CeacF G7G '
~
a E-Tcb itt A T' L K.';'C S,
~
4
- CoMc.nETE F A ST ENER. W t~M
' 4 d ; , W Fr5 H E R.'
e J -
<._ e _:. _ _._ _ J. _ _ __ A
- s. .
CASE I s -
- M id. = . sl.. q / . :. m . / ./ ~
een w a
'/t" TH ICX ITEC! G A A. T 70 C.M 9 . d CbMek.ETE FAsTENEA 4, . . /* . */ */ > /
li-fcb MAT L A V EA..!
# /. ./ ' . . ./ ,/ *L */ <
- _
s s - 4 1 " gia. . 3 sit uar ~ cesg 2. d .
* , YCTF, : foR. 4 "4 @ O ,A M . $G6-TET SHAL4 SE Y '
q v y g .Fr.os co cc.sre sauses ro vor or Aucace). Alternate Methods of Securing 3M Mat Material for 3-Hour Fire Rating Attachment 9.5 Page 11 of 14 PROCEDURE NUMBEA REVISION PAGE 10.25.89 9 84 of 87
. c 1". s.
. .+1 "! -
o 2==ser w, . .r aI ) N .I- kl~ _
, , ,.t ,
1 . .- ,
, - - t . . ., 52 . . . sq .
, a
- i. '
i E. t.S - ,~ ...
- i
*[ t i i , g.
l
,t t -sko (TYPO CASE l l 2 ==wma. ? 1 emu.w d
x = s o
\ - r r 1 t . . . n. i..
[ ._) 5 1 - .. , 3 J u \
- f. .
.,. 2, . l....<
o , , _t $ 1
, x, i bAMD CNP-) t -
s . Cd5E 2 5M /T51 CSu Dt 117 IRrER,cAcE DETAlL5 Attachment 9.5 Page 12 of 14 FROCEDURE NUMBER REVISION PAGE 10.25.89 9 85 of 87 ; i
- . ~ - - - . . - _ - . - .
~
m% CS-/95.SH4ir P!A% cur ro ftr e b ] .f -f/2.6 72.orSCr/cH mar *AAowuo 3M IWiEKAM g-Soo 5 $G
~ 3.R , /
M q q
- Te * % UYER W/.+t' CP .f/4 ZN12ni?A.M Q4v_c ,e. T ~ 5 0 0 ftS 4 f.p rCaC ric M M A r '
, f EtIST. ' ,! t -
UM!srMT
\-, 5 UY6A WRA P oP .9M TMrdtAM * $-500 ftAn PR.ofdcrtoM M,+r. wird C /I V . C s N c. , Vs"y .c2o " in/Cd. Gr4lN't sss 3rsc4 AN BAppG. 8 " c.c. (BANO3 /N57444s:p ar9M ' ) "I I s.2_ m ;ri.xy,x) . c. s .t . ': .v: l Q' C4/51' CoMC, W4ft. OR ds/4/d4 A .' .. OETA/t. 8F COA /L;%;/tr**5VPP57 0F'OGD/C4TED . . ConDutr for S - NouR' fire 2n ,stGe 4"c.c ,rl" ~gsctYt) v ~
5 N ' b$ dd n [9 -
$e 'N -
Sik SL(.erc A A-SO/G
'Yh ]t ' '
I
+_
L ( f '4"o.cfrYR) - ji" I ]lI:+ %6x'/ST/ l k M f*'foce e4 P/ coo UNItrau1~ _, , 4 sr' !l;t
%~Cin, $& ET7")<*NGD 70 KfA4/ '
O. (i * . 14trA 'Z. - Cos/42.arre
* + .
FMreiens c sec port Fis.O S Ec7 tom 4-A..... . Attachment 9.5 Page 13 of 14 PROCEDURE NUMBER REVI5!ON PAGE 10.25.89 9 86 of 87
cs-/95 SHEET P! Ars' Cur a s -
- f/r ,4EDWHO YM 5452 Pt 475 =X/K CA Mo 3M JNTEK4M 5-S00 f/Af WAu. Sa f;2crGct*IcW Met:
CstuM4 s- " 5 s/YEg wx49 ef 3 M INri!M *
. . . g. ,9--- 5-50 D F/AE.PAcrEC.r/CH' man fxtS7: Co r. :Y i + -,
w aans --
.<+r f ----Exisr Sress Q LAYCA e-Soo firn.wA.+P. of EM ZNrEAAM P.aordersed M4-n .
cf e sruff ersw sw w sraz Mar.c a% &!.:, wtnHCEAAMtc F/SE2 Msw44trew ano est efssxo on sysw.cryx)
. , ~ . Asp.ur .
yc Mic't .conexsrs As.srswegtryr) DErNL. 0E. CONDV/rSWPPoKr DF .Dsotd.4720 _CcN6 air 7-o.e 5-Nec.i.e p'ide Agr/N4 1%, ?I~ 4Lt M..1cf' xtc s.c.- e,c; - s.c - W '
- t '
at 4., {. + ZT 7ew/.sr surfcar 4
.W $ l __.
l7!. SHvWAL k5 M4I5. Qgg - l p.p . Il4tS, T.TE'M j-
,G y(t Q l.
Q " M7d:Gz HM s& A+tY C@cu2At-G=4 oa. Sl;otsA kS Il t.USTe~-moH d f_ " '
! cw!N.
l gar .
~{I q g
Sferiae A-A . Attachment 9.5 Page 14 of 14 MGM NER REVISION PAGE 10.25.89 9 87 of 87 )
- o
s 1 31 4 i U.S. DEPARTMENT OF COMMERCE NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY Gaithersburg, MD 20899 , l 1 i REPORT OF TEST FR 3987 April 29,1992 i' TOXICOLOGICAL EVALUATION OF THE COMBUSTION PRODUCTS FROM A THERMAL BARRIER MATERIAL DECOMPOSED UNDER FLAMING AND NONFLAMING CONDITIONS i Barbara C. Levin, Richard H. Harris, Jr. and Magdalena Navarro i Submitted to: Office of the Inspector Ggneral , United States Nuclear Regulatory Commission Washington, DC 20555 96 ?, $ W'
v. I
-TOXICOLOGICAL EVALUATION OF THE COMBUSTION PRODUCTS FROM A THERMAL BARRIER MATERIAL DECOMPOSED UNDER FLAMING AND NONFLAMING CONDITIONS' B. C. Levin, R. H. Harris, Jr., and M. Navarro ABSTRACT The toxicity of a sample of the material used in nuclear power plants as a fire protdction barrier for cable trays, was examined under both flaming and non-flaming conditions in the radiant heat smoke toxicity apparatus. The procedure was modified slightly to account for the long burning and decomposition time of this material.
Carbon monoxide, CO2 , HCN, and O2concentrations were monitored in each test. Hydrogen chloride, HBr, HF, and NOxwere measured initially and determined to be produced in insufficient quantities to warrant further monitoring. A total of eight LC3o values (based on animal tests) and their equivalent N-Gas values were determined for the various combinations of flaming or non-flaming conditions, for loaded or consumed masses, and for the deaths that occurred during the 30 minute exposures or for those that occurred during the 30 minute exposures plus the 14 day post exposure observation periods. A comparison of the LC50 values based on e consumed mass and within plus post-exposure deaths for the flaming or non-flaming modes showed the material sample to be about as toxic as Douglas fir or flexible poly-urethane foam which were tested previously in the same apparatus. In the flaming mode, the N-Gas values indicate that the toxic gases monitored were probably responsible for the deaths that occurred. In the non-flaming mode, it appears that one or more additional gases or other factors are contributing to the toxicity. The intumescent char layer that remains following the 30 minute exposures was removed 2 from the non-flaming test residues and heated at 50 kW/m in a separate non flaming test. Compared to the gas yields from the other non flaming tests, the intumescent char generated more CO and CO2 and an amount of HCN which fell within the mean and one standard deviation of the HCN generated from the complete samples. Keywords: combustion products; flaming: inhalation;3oLC : N-Gas model; non-flaming; radiant heat; toxicology. .
)
i i 1 This report is a contribution of the National Institute of Standards and Technology and is not subject to copyright. 1
1.0 INTRODUCTION
A sample of a material used in nuclear plants as a fire protection barrier for cable trays was provided to the National Institute of Standards and Technology (NIST) by the Office of the Inspector General of the United States Nuclear Regulgtory Commission (NRC) to determine the toxicity of the fumes emitted during thermaldecomposition. The Fire Hazard Analysis group at NISTevaluated the toxici-ty of the material under both flaming and nonflaming laboratory conditions using a bench-scale radiant heat smoke toxicity procedure [1].2 2.0 MATERIALS AND METHODS 2.1 Materials The material was designated by NRC as Exhibit #3, prefabricated subliming material approximately 25 mm (1 inch)lhick and identified by invoice #3-91-006. 2.2. Gases In all tests, chemical analyses were conducted to determine the concentrations of carbon monoxide (CO), carbon dioxide (CO 2), hydrogen cyanide (HCN), and oxygen (O2 ). In some tests, hydrogen chloride (hcl), hydrogen fluoride (HF), hydrogen bromide (HBr) and total nitrogen oxides (NO3 ) were also measured to determine if sufficient quantities would be generated to warrant further monitoring. Calibration gases (CO, CO 2, HCN) were commercially supplied in various concentrations in nitrogen. He concentrations of HCN in the commercially supplied cylinders were routinely checked by silver nitrate titration [2], since it is known that the concentration of HCN stored under , these conditions will decrease with time. Nitric oxide (NO)in nitgen, a standard reference material, was obtained from the Gas and Particulate Science Division, Nu,I Carbon monoxide and CO2were measured continuously during each test by non-dispersive infrared analyzers. Oxygen concentrations were measured continuously with a paramagnetic analyzer. Syringe samples (100 pt) of the chamber atmosphere were analyzed for HCN approximately every three minutes with a gas chromatograph equipped with a thermionic detector [3]. The concentration of NO, was measured continuously by a chemiluminescent NO, analyzer equipped with a molybdenum converter (set at 375*C) and a sampling rate of 25 mUmin. He change from a stainless steel converter to a molybdenum converter prevented interference from HCN. All combustion products and gases (except HCN, NO,, and the halogen gases) that were removed for chemical analysis were returned to the chamber. The CO, CO2 ,0 and 2 NO, data were recorded by an on-line computer every 15 seconds. , The halogen gases, HF, hcl, and HBr, were analyzed by ion chromatography. He combustion products were bubbled into 30 mL impingers containing 25 mL of 5 mM KOH at a rate of approximately 30 mUmin for the 30 minute tests. Tne flow was monitored every five minutes and averaged cver the 30 minute run to determine the amount of gases collected. The resulting solution was analyzed for F, CI', and Br by the modified method A-106 as described in reference [4]. In this modified method, the elvent was changed from a 2.5 mM lithium hydroxide solution to a 5 mM KOH 2 Numbers in brackets refer to references listed at the end of this report. 2
e solution, a manualinjector was used instead of an automatic injector, and a 590 programmable pump was employed instead of the 510 solvent delivery module. For each test, the reported gas concentrations are the time-integrated average exposure values which were calculated by integrating the area under the instrument response curve and dividing by the exposure time [i.e., (ppm x min)/ min or, in the case of O2 , (% x min)/ min]. The calculated CO and CO2concentrations are accurate to within 100 ppm and 500 ppm, respectively. The calculated HCN concentrations are accurate to 10% of the HCN concentrution. The calculated NO, concentrations are accurate to 10% of the NO, concentration. 2.3. Animals Fischer 344 male rats, weighing 200-300 grams, obtained from Taconic Farms (Germantown, NY),8 were used in these tests. They were allowed to acclimate to our laboratory conditions for at least 7 days prior to testing. Animal care and maintenance were performed.in accordance with the procedures outlined in the National Institutes of Health's " Guide for the Care and Use of Laboratory Animals." Each rat was housed individually in suspended stainless steel cages and provided with food (Ralston Purina Rat Chow 5012) and water ad libitum. Twelve hours of fluorescent lighting per day were provided using an automatic timer. All animals (including the controls) were weighed daily from the day of arrival until the end of the 14 day post-exposure observation period. 2.4. Radiant Heat Smoke Toxicity Procedure l i All exposures were conducted using the combustion system, the chemical analysis system, and the animal exposure system that were designed for the radiant heat smoke toxicity method [1]. Figures 1 and 2 are a diagram and schematic drawing of the experimental arrangement, respectively. To prepare the test samples, the sheet was cut into pieces of predetermined weight to obtain the desired test concentrations (defined as grams of material loaded or consumed in the furnace divided by the exposure chamber volume in cubic meters, i.e., g/m3). i i Tests were conducted in both flaming and non flaming modes. The flaming mode tests were l 2 conducted at a flux of 50 kW/m with a spark ignitor kept on until the flaming ceased. Tests to ; determine a non-flaming flux showed that this material would not flame even at 50 kW/m2 as long as the spark ignitor was off. Therefore, the only difference between the flaming and non-flaming tests is that the spark ignitor was only used in the flaming mode. The radiant heat smoke toxicity method is a closed design in which all the gases and smoke are kept in a 200 liter rectangular chamber for the duration of the test. The samples are decomposed in the furnace located directly below the animal exposure chamber such that all the combustion products from the test sample evolve directly into the chamber. Six rats are exposed in each test. Each animal 3 Certain commercial equipment, instruments, materials or companies are identified in this paper to specify adequately the experimental procedure. Such identification does not imply recommendation or endorsement by the National Institute of Standards and Technology, nor does it imply that the materials or equipment identified are necessarily the best available for the purpose. 3
4 is placed in a restrainer and inserted into one of six portholes located along the front of the exposure chamber such that only the heads of the animals are exposed. In the tests conducted to determine LC 3ovalues, the weighed sample was placed onto a load cell in the combustion chamber and an: mal exposures started when the radiant lamps were turned on. Animal exposures continued for 30 minutes. In the first flaming test, it was noted that the material was still vigorously flaming at 15 minutes, the time at which the lamps would usually be turned off, since the thermal decomposition of most previously tested materials was complete by 15 minutes. Since the material was obviously still being decomposed, the decision was made to leave the radiant heat on until the end of the animal ; exposures to assure that the underlying layers would also be exposed. In addition to the continuous mass loss data from the load cell, the test specimens were weighed before and after the exposure to determine the total mass of material consumed. The toxicological endpoint was the LC o3 values, which were calculated based on the deaths that occurred either during the 30 minute exposures or the 30 minute exposure plus 14 day post-exposure observation period. The percentage of animals dying at each fire efiluent concentration was plotted to produce a concentration-response curve from which the LC 3o values were calculated. The LC 3o in these cases is defined as the mass of material loaded in the furnace or consumed by the exposure divided by the animal exposure chamber volume (g/m3 ) which caused 50% of the animals to die during the exposure only or during the exposure plus the 14-day post-exposure observation period. It is important to note that the lower the LC o3 value, the greater the toxicity. The LC 3a values and their 95% confidence limits were calculated by the statistical method of Litchfield and Wilcoxon [5]. For this study, eight LC3o values were determined for the conditions shown in Table 1. The N-Gas values (determined as shown in Section 2.5) that were equivalent to these LC 3a values were also , calculated. 4 4
1 Table 1. Test Conditions for LC 30 Determinations LC30 Conditions number , Flaming Non-Flaming Mass Loaded Mass Consumed WE WE & PE 1 X X X 2 X X X 3 X X X 4 X X X 5 X X X 6 X X X 7 X X X 8 X X X WE. Deaths occurring within the 30 min exposure. WE & PE. Deaths occurring during the 30 min exposure and the 14 day post-exposure period. i e 2.5. Determination of Unusual Toxicity In previous studies, NIST has examined the toxicological interactions of six gases, CO, CO2, HCN, reduced O2, hcl and HBr, to provide enough data to predict the toxic potency (based on mass) and determine whether that toxicity is usual (i.e., the toxicity can be explained by the measured gases) or is unusual (i.e., additional gases are needed to explain the toxicity). These studies have resulted in the empirically derived N-Gas Model [6-9] shown in equation (1). l 1 N-Gas Value = m[CO) . [HCN] , H] 2
, [ hcl) , (HBr] (gy
[CO2 1-b LCg HCN 21-LC ,02 LCg hcl LCg HBr , l where the numbers in brackets are the time-integrated average atmospheric concentrations during a 30 minute exposure period [(ppm x min)/ min or for O 2 (% x min)/ min). If the N-Gas value equivalent to the LC3o value is approximately 110.2(95% Confidence interval), then the gases monitored are probably responsible for the deaths that occurred. If the N-Gas value equivalent to the LC 3ovalue is below 0.8, then additional gases or toxicological factors are probably contributing to the toxicity and the combustion products from the material would be considered unusually toxic. 5
The N-Gas approach has been shown to work well in different combustion systems (radiant as well as convective heat sources; bench-scale as well as full-scale room tests) [11-14]. 3.0 RESULTS AND DISCUSSION 3.1 Flaming Tc.sts 3.1.1 Determination of '&st Test Conditions . 2 The one inch thick material was exposed to a radiant flux of 50 kW/m with the spark ignitor on. ) In the first test (Table 2, Expt. A-1), the material began emitting smoke at 35 seconds, started flaming l intermittently about 1.25 minutes, began burning intensely and consistently abe 't 7 minutes, and . l continued burning until the radiant heat was curned off and the shutter between the combustion chamber and animal chamber was closed at 15 minutes. Analytical sampling continued for another , 15 minutes. Examination of the sample at the end of the 30 minute exposure showed that the q material had intumesced approximately 0.75 inches above the original heigh l Since the material was still burning vigorously at 15 minutes and only 30% of the sample had. decomposed by this time, a decision was made to allow the radiant heat to continue beyond the 15 minutes in future tests to permit as much of the material to decompose as possible during the 30 minute exposure. In this way, lower layers of the material would also be exposed to the heat. We considered the test sample fully decomposed wben the CO concentrations had reached equilibrium. l Table 2 indicates the times at which the samples experienced the various stages of smoke and flaming. l Comparison of test A-1 with test A-3 in which the same amount of material was loaded into the l furnace shows that in the first case (where the s. ample was exposed to 15 minutes of heat), only 30% , l l of the sample was consumed; whereas, in the second case (where the sample was exposed to 30 minutes of heat),53% was consumed. In all the other tests, between 53 and 56% of the sample was consumed. As would be expected from tbe increased mass consumed, the time-integrated concentrations of CO, CO ,2 and HCN all increa: sed and O2decreased. In most cases, the rate of CO generation was rapid during the flaming stage. slowed significantly after the flaming stopped and reached equilibr:ium shortly thereafter. The CO generation in the test in which the radiant heat was turned off and the shutter was closed at 15 minutes (ExpL A-1) and in an test where the radiant heat was kept on and the shutter was kept open for the full 30 minutes (Expt. R-3) is illustrated in Figure
- 3. Table 3 provides the time-integrated average concentrations. In these two tests, approximately the same amount of material was consumed, although almost twice as much of the material was loaded into the furnace in the 15 minute heat exposure. The results show that the CO generation .
was significantly greater when the radiant heat was kept on for the full 30 minutes. Comparison of l the HCN generation in Expt. A-1 (radiant heat off and shutter closed at 15 minutes) and other tests i (radiant heat on and shutter open for 30 minutes) shows that Expt. A-1 generated the lowest i concentration of HCN even though the amount of mass consumed was similar to that of many of the other tests (Fig. 4 and Table 3). , 1 To confirm that we were exposing the complete sample to the radiant heat, we also compared a thinner sample with a larger surface area (the thinner sample was prepared in our laboratory by shaving the thick sample) and a thicker sample with a smaller surface area (Fig. 5). The same amount was loaded in the furnace and exposed to the radiant heat for the full 30 minutes; about the same amount was consumed. The time-integrated average gas concentrations were about equal 6
(Table 4). Examination of the production of the gases over time indicated that the thinner sample started to generate the gases earlier (O2 concentrations dropped earlier), but, eventually, they reached the same equilibrium levels: the one exception was the HCN concentration where the thicker sample seemed to generate a higher maximum level of HCN (Fig. 5). Since we decided to leave the radiant heat on for the full 30 minutes, a control test without any material was conducted to examine the effects of just the heat from the radiant lamps and any stress that the animals may have experienced from undergoing the test conditions (Table 3, Expt. RC-1) The animals were exposed 2 to the same conditions'as the other flaming tests (except A-1), i.e., a . radiant flux of 50 kW/m with the shutter open for the full 30 minutes and the ignitor on for 20 ' minutes. In this control exposure, the average 30 minute temperature measured at animal positions l 1,3, and 6 was 26.5*C and the highest temperature was 28.8*C. These temperatures were slightly lower than those observed in some of the flaming material tests in which the average animal exposure temperatures ranged from 24.5 to 33*C and the highest temperat6res ranged from 26.2 to 42.9'sC. This heat control test appeared to have little or no effect on the animals. Their appearance and activity levels were fine followmg the exposure and their post-exposure weight gain was similar to the control animals which were kept in their cages and weighed daily (Fig. 6). The analytical chemical results from this control heat exposure show the increased CO2 which comes from the animals' respiration and a small amount of NO, which comes from the spark ignitor. These results indicate that keeping the heat on for the full 30 minutes did not add any undue stress on the animals. These results supported our decision that leaving the radiant heat on for the full 30 minutes would provide a more realistic toxicological profile of the material's behavior in an actual fire. It would also allow us to use smaller sample sizes to produce a toxic atmosphere and prevent the possibility of overloading the system. s 3.1.2 Determination of LC 3a Values and Equivalent N-Gas Values ' Table 3 presents the chemical and toxicological data for all the flaming tests except the thin shaved sample. Three tests were conducted for chemical analytical data only and five tests were conducted to determine the toxicological as well as the chemical data. Hydrogen chloride, HBr, HF, and NO x were not routinely measured, since their concentrations were relatively low or not detectable. 7 l 1
'Iable 2. Smoke and Raming Data from Raming Tests Mass Test Smoke Rame Rame Rame Ignitor CO equilbrium !
Type - noted intermittent steady out off .; 4 number o loaded . consumed (min sec) (min:sec) (min:sec) (min sec) (min:sec) (min) (g/m3) (g/m3) 225" 68 A-1 0:35 1:15 7:00 15:00 15:00 SGU @ 15 min ; 129- 70 A-2 0:13 1:20 1:30 17:30 18:00 22 l 223 118 A-3 immediately 1:20 NR 16:40 17:05 ~ SGU @ 30 min ! t 94 53 R-2 NR NR 1:45 17:10 17:40 SGU @ 30 min ,-
- 114 63 R-3 NR 1
- 50 2:15 14:55 21:35 21 I b i 129 69 R-4 0:13 0:40 1:30 7:25 9:20 23 y
129 71 R-5 0:15 0:58 1:55 21:20 20:50 22 ,
- a. In this test, the radiant lamps were shut off at 15 minutes. In all other tests, the radiant lamps were left on for the full 30 minutes. i
- b. Some of gases leaked out of chamber during test. F A. Analytical chemical test; no animals exposed. '
N R. Not recorded. R. Rat test; animals exposed and chemical analyses conducted. SGU. Carbon monoxide concentrations were still increasing at time noted. l l i 8
.i.
I
--- ~ . . . . . . . . . _ _ _ _ . _ = _ - _ - _ _ . . _ _ _ _ - - = - _ . _ _ _ _ _ - . . _ - . _ _ _ _ _ _ _ _ _ _ -_- - - _ - _ _ - - _ - - - _ . - _ _ . - _ - _ _ _ _ . - -_
v.-. e.,,~. , . u m a ..
S Table 3 - 2 Chemical and Thxicological Data from Material Sample Decomposed in the Flaming Mode at 50 kW/m in Radiant IIcat Smoke Toxicity System Test type- Mass Chemical Analytical Data
- Toxicological Data number loaded consumed CO CO 2 IICN 02 NO, 11C1 Illir llF # died N-Gas %Iue (g/m3 ) (g/m3 ) (ppm) (ppm) (ppm) (ppm) (ppm)
Day (%) (ppm) (ppm) # tested of 2 death Wfi WE& WII Wii , Pli & Pli i A-1 6 225 M 770 17900 60 18.3 NM 10 ND 30 NA NA 0.63 0.74 - A-2 129 70 1530 22300 130 17.8 NM 10 ND 16 NA NA 1.14 1.36s - A-3 ; 223 118 1790 26700 120 16.9 NM trace ND 30 NA NA 1.23 1.43 - RC-1 0 0 0 5000 6 20.4 30 NM NM NM OM OM 0.07 0.t18 - R-2 94 53 1100 20400 90 18.1 NM NM NM NM 3M 3M 0.83 0.98 . R-3 114 63 1230 19400 120 18.3 5 NM NM NM SM 6M 0.98 1.17 I R-4d 129 69 490 8700 80 19.9 NM NM NM NM 4M 6/6 0.56 0 69 2,I 1 R-5 129 71 1110 23400 100 17.7 10 NM NM NM SM SM 0.92 1.08 -
- a. lime-integrated average concentrations.
A. Analytical chemical test, no animals exposed. ' t b. R. Shutter on combustion system, radiant heat and ignitor were turned off at 15 minutes even though r..aierial was still flaming vigorously. Test in which both analytical chemical and animal exposure data were collected. C. Control Test with animals to determine effect of heat; no sample was decomposed. d. Gases min:see. leaked from exgunnre chamber; sample flamed only until 7:25 min:see; whereas, in nit other tests, the shortest time at which 55 the material st NA. Not applicahic. N D. Not detected. NM. Not measured. W E. Within exposure Wii&Pli Within exgusure plus post-exposure. 9 l
3 lable 4 - - Comparison of Chemical and Toxicological Data from the Material Sample Cut into Thick, Smaller Surface Areas and Thin, Larger Surface Arcas and Decomposed in the Flaming Mode Test type- Mass ! Sire Chemical Analytical Data
- N-Gas %lue ,
numlier loaded consumed thickness surface CO CO 2 IICN 02 llCl 3 NO, Illir IIF (rfm') (r/m ) (cm) area (ppm) (ppm) (ppm) (%) (ppm) (ppm) (ppm) (ppm) WE - WE A 2 (cm ) PE l 1hin Sample 130 72 0.6 34 1700 28o00 120 16.8 NM NM NM NM 1.19 1.3R A-2 129 70 3.0-3.2 8.6 1530 22300 130 17.R NM 10 ND 16 1.14 1.36 ; r
- a. Time-integrated average concentrations.
L l
)
1 A t-5 6 10 i 5 6
Table 5 gives the LC a3 values and their equivalent N-Gas values based on tests in Table 3. Animals that survived the exposures experienced difficulty breathing, were gasping loudly, and had extensive mucus discharges from their noses and mouths. Some exhibited tremors. Since there were few post-exposure deaths, the LC30 values were essentially the same for the deaths that occurred during the 30 minutes and those that included,both within and post-exposure deaths. One death occurred as late as 11 days post-exposure. The LC3a value based on the mass loaded in the furnace was 94 g/m 3 for the within and within plus post-exposure and the LC 3o value based on mass consumed was 53 3 g/m . At this mass (either loaded or consumed), the N Gas values were 0.90 for the within exposure deaths and 1.07 for the within plus post-exposure deaths. Both of these values are in the range where one would expect some deaths to occur; an indication that the gases monitored are probably the gases responsible for the deaths. The slightly lower N-Gas value for the within exposure deaths may be due to the high levels of HCN which occur during the latter half of the exposures (Fig. 4) and which are not obvious from the time-integrated average concentrations. Table 6 lists both the time-integrated average and the maximum HCN concentrations. The N-Gas values equivalent to the LC50 values were calculated a second time excluding Expt. A-3 which looked as though this large sample loading could have overloaded the system (compare HCN generation of Expt. A-3 with A-2 in Table 6). The results of the N-Gas calculations without this point are shown in Table 5 and indicate that the N-Gas values are about the same as when the calculation included Expt. A-3.
/
11
- , i Table 5 l l
LC 3o Values, Confidence Limits and Equivalent N-Gas Values for the Material Sample { ! Decomposed in the Flaming Mode l Conditions LC 95% Confidence Limits N Gas Value". N-Gas Valueb . ! (g/m ) (g/m3) . 1
. Mass loaded 94 77 - 114 0.90 0.84 ;
WE i Mass loaded ' 94 78 - 113 1.07 1.00 i WE & PE ' Mass consumed 53 45-63 0.90 0.85 WE Mass consumed 53 45 - 63 1.07 1.00 WE & PE a. N Gas value at the LC o3 based on a least squares linear regression analysis of mass i (loaded or consumed) vs. N-Gas value for tests A-2, A-3, R-2, R-3, and R-5 in Table l 3. Other tests not used for reasons listed in legend of Table 3. {- b. N-Gas value at the LC 50 based on a least squares linear regression analysis of the mass (loaded or consumed) vs. the N-Gas value for all tests used in a. except A 3 < which was eliminated from the calculation due to a possible overload condition. '
- l. WE: Values based on animals that died during the 30 minute exposures. '
WE & PE: Values based on animals that died during the 30 minute exposures plus the 14 day post-exposure observation period. l i 1 l [ l 12 r
s Table 6. Hydrogen Cyanide Concentrations in Flaming Tests
- Test Mass , HCN type-Number loaded consumed time-integrated average maximum 4 (g/m3) (g/m3 ) (ppm) (ppm)
A-1 225 68 60 90 A-2 129 70 130 300 A-3 223 s 118 120 300 RC-1 0 0 6 7 R-2 94 53 90 150 R-3 114 63 120 290 R-4 129 69 80 160 R-5 129 71 100 190 [ 13
3.2 Non-Flaming Tests 3.2.1 Determination of the Non Flaming Flux To determine the aux at which the non-flaming tests should be conducted, we started by examining 2 a flux of 25 kW/m without the spark ignitor (Table 7, Expt. A-1). No flaming occurred and only 3 26% of the mass loaded (151 g/m ) was consumed in the 30 minute exposure. As in the flaming mode, the material also intumesced. The concentrations of the gases were low providing N-Gas values of 0.09 (within exposure) or 0.11 (within exposure plus post-exposure). These extremely low N-Gas values indicated that we were not close to a fire effluent concentration that would be lethal to the rats. The next flux tested was 35 W,m 2(Table 7, Expt. A-2). No flaming was observed,45% of the mass 3 loaded (154 g/m ) was <':xomposed, and the N-Gas values were 0.27 (within exposure) and 0.35 (within exposure plus post-exposure). Again, these values indicated that these fire atmospheres would not be very toxic. 2 We then tested a flux of 50 kW/m , which is the same as that used for the flaming combustion mode, except without the spark ignitor (Table 7, Expt. A-3). No flaming occurred,52% of the mass loaded 3 (159 g/m ) decomposed, and the N-Gas values were 0.56 and 0.72 for the within exposure and the within exposure plus post-exposure, respectively. As expected, the highest flux (50 kW/m2) generated the greatest concentrations of gases. The effect of Dux on the evolution of HCN over time is illustrated in Fig. 7. , Two more analytical tests at higher mass loadings were conducted to try to achieve higher N-Gas values. However, even though the amount loaded into the furnace was doubled, the concentrations of the gases did not change very much and the final N-Gas values were about the same or lower (Table 7, compare Expt. A-4 and A 5 with A-3). In these tests,it appeared that mass loadings above 3 200 g/m or consumed masses above 100 g/m3 overload the system. 3.2.2 Determination of LC Values 50 and Equivalent N-Gas Values The first animal exposure (Table 7, Expt. R-9) was conducted with a mass loading of 607 g/m3 in an effort to achieve higher N-Gas values. At this loading, about 30% of the material was consumed and we obtained N-Gas values of 0.77 (within exposure) and 0.96 (within plus post-exposure). At these N-Gas values, we would expect no deaths within exposure and only some deaths post-exposure. However, all of the animals died during the 30 minute exposure at times ranging from 16.5 to 27 min; an indication that the material is probably generating a toxic gas that we are not taking into account with our N-Gas equation. The non-flaming LC50 values, their 95% confidence limits and their equivalent N-Gas values are given in Table 8. De N-Gas values equivalent to the LC30 values are calculated from a least squares linear regression analyses of individual test N-Gas values vs. mass (loaded or consumed) from Expts. R-1 through R-9. To determine if there was any difference due to a possible overload of the system 3 from sample sizes above 200 g/m , these values were also calculated from a least squares linear regression analyses of individual test N-Gas values vs. mass (loaded or consumed) from Expts. R-1 14
through R-6 in Table 7. These results show that in the non-flaming mode, the N-Gas values which are equivalent to the LC o3 values (regardless of whether the possible overload was considered) are lower than those expected if the gases in the model were the only gases contributing to the toxicity. ' Many of the animals that survived the 30 minute exposures had difficulty breathing (were gasping for breath) and had brownish, watery discharges from their mouths. Some exhibited convulsions or tremors. Eight animals died beyond 24 hours following the exposures and three died as late as 8 days post exposure (Figs. 8 and 9). These post-exposure deaths beyond 24 hours also indicate that gases other than those considered in the N Gas Model or additional factors are probably contributing to the toxicity. As in the flaming tests, the HCN continued to increase during the last 15 minutes of exposure (Fig. 10). The time-integrated average HCN concentrations do not reflect the high maximum levels reached towards the end of the exposures (Table 9). Alt' hough not specifically examined, the possibility exists that the animal deaths are resulting from the high levels achieved during the latter half of the exposures. The N-Gas model is based on steady-state pure and mixed gas exposures. Additional research may be needed to examine the effects of continuously increasing concentrations. J
)
a l 1 l l 1
- \
i 15 ! 4
Tine 7. Chemical and Toxicok>gical Data from the Material Sampic Decomposed in the Non.Ilaming Mode in Radiant IIcat Smoke Toxicity System . Test type - Ilux Mass Chemical Analytical Data' Toxicological Data number (kW/mD I.oaded Consumed CO CO 2 IICN 02 NO, # died N-Gas Value Day of (g/m3) (g/m3) (ppm) (ppm) (ppm) (%) (ppm) # tested death WE WE A pE WE WE A PE A-1 25 151 39 45 1350 15 21.1 4 NA NA 0.09 0.11 NA A-2 35 154 69 130 2050 45 20.7 2 NA NA 0.27 0.35 NA A-3 50 159 83 490 4210 90 20.5 3 NA NA 0.56 0.72 NA A-4 50 299 120 660 3400 80 20.4 NM NA NA 0.55 0.68 NA A-5 50 313 130 480 3090 55 20.5 3 NA NA 0.38 0.47 NA R-1 50 52 30 370 4940 70 20.4 NM IM 3/6 0.44 0.55 8.8 R-2 50 55 31 290 5100 55 20.3 NM 0/6 1/6 0.36 0.44 8 R-3 50 56 33 280 $110 60 20.4 NM 0/6 2M 0.37 0.46 1,2 R-4 Sd 76 43 410 5530 60 20.2 NM 0/6 65 0.42 0.52 1,1,1,2,2,3 R-5 50 102 56 410 5340 100 20.5 NM 2/6 6M 0 60 0.77 1,1,1,6 R-6 50 152 81 520 6840 125 20.1 NM 2/6 6M 0.76 0.% 1,1,1,1 R-7 50 203 107 580 7420 120 20.2 NM S/6 6,6 0.75 0.% 0 R-8 50 229 110 470 6850 60 20.2 NM 4/6 6M 0.41 0.51 1,1 R-9 50 607 178 880 6930 115 20.0 NM 6/6 6M 0.77 0.% -
- n. lime-integrated average concentrations; IICI, Illir, and IIF were not measured in these tests.
A. Analytical chemical test, no animals exposed. R. lest in which both analytical chemical nad animal exposure data were collected. NA. Not applicable. NM. Not measured. WE. Within exposure. WEAPE. Within exposure plus post-exposure.
Table 8 LC3oValues, Confidence Limits and Equivalin't N-Gas Values for the Material Sample Decomposed in the Non Flaming Mode Conditions LC 95% Confidence Limits N-Gas Value' N-Gas Valueb (g/ni ) (g/m3 ) i Mass loaded 138 99 - 193 0.52 0.71 , WE ! Mass loaded 69 55 - 87 0.60 0.55 WE & PE Mass consumed 72 54 - % 0.54 0.'68 WE Mass consumed 42 32 - 55 0.58 0.58 WE & PE ! a. N-Gas value at the LC 50 based on a least squares linear regression analysis of mass l (loaded or consumed) vs. N-Gas value for tests R-1 through R-9 in Table 7.
;. b.
N-Gas value at the LC50 based on a least squares linear regression analysis of the mass (loaded or consumed) vs. the N-Gas value for tests R-1 through R 6 in Table
- 7. Tests R-7, R 8, and R-9 were eliminated from calculation due to possible overload condition. ,
WE: Values based on animals that died during the 30 minute exposures. WE & PE: Values based on animals that died during the 30 minute exposures plus the 14 day post-exposure observation period. l 17
I l
=
Table 9. Hydrogen Cyanide Concentrations in Non-Haming Tests Test Mass HCN type - number loaded - consumed time,-integrated average maximum (g/m3) (g/m3) (ppm) (ppm) A-1 8 151 39 15 28 , b A-2 154 69 45 86 A-3 159 83 90 175 ' A-4 299 120 80 1% i A-5 313 130 55 227 R-1 52 30 70 126 R-2 55 31 55 88 R-3 56 33 60 109 R-4 76 43 60 124
/
R-5 102 56 100 206 R-6 152 81 125 254 R-7 203 107 120 337 R-8 229 110 60 186 R-9 607 178 115 277 - 2 Flux level was 50 kW/m except where noted. Flaming tests had the spark ignitor on; whereas, non-flaming tests were conducted without the spark ignitor,
- a. Flux level was 25 kW/m2
- b. Flux level was 35 kW/m2 I
s
'1 e 18 e
t i e - iv - - - -
- - - - - + ~
o . . 3.2.3 Examination of the Intumescent Material In 1985, we found that heating the charred residues from a Oexible polyurethane foam that had been thermally decomposed in the non.0aming mode generated significant quantities of HCN (15]. Since the intumescent char layer from the NRC material sample increased as the HCN was generated, the question arose as to whether the HCN was produced by the intumescent char layer. A test was 3 conducted in which 194 g/m of the intumescent char layers (including the imbedded mesh) that remained following a number of 30 minute non-Daming tests were combined and exposed to the non-2 Damingconditions (radiant heat of 50 kW/m for 30 minutes, no ignitor). The amount consumed was 29 g/m . Fig.11 shows the generation of CO, CO2 , HCN, and the reduction in 02 over time (two of the HCN points appear to be the result of the obstruction of the sampling syringe and are, therefore, not connected to the main curve). The yields of the gases from this test of the intu-mescent material and from the other tests on the complete material are given in Table 10. These results show that the intumescent char layer produces yields of CO and CO2 which are greater than those produced by the whole material. Yields of HCN are within one standard deviation of the mean (x = 0.0029 0.0010 g/g) of the yields from the whole material. Table 10 Comparison of Gas Yields from the Intumescent Char Layer and the Whole Sample Decomposed in the Non-Flaming Mode. Test Gas Yields (g/g) . CO CO 2 HCN ' Intumescent Char 0.088 0.868 0.0023 A-3 0.017 0.174 0.0022 A-4 0.018 0.121 0.0017 A-5 0.011 0.094 i 0.0019 R-1 0.028 0.548 0.0046 R-2 0.021 0.510 I 0.0030 R-3 0.021 0.500 0.0036 R-4 0.021 0.399 0.0031 R-5 0.018 0.307 0.0039 R-6 0.019 0.288 0.0033 R-7 0.019 0.240 0.0034 R-8 0.014 0.221 0.0018 R-9 0.014 0.146 0.0017 . l l 19 j
s 3.3 Comparison of Toxicity of NRC Material Sample and Other Materials A number of materials have been examined by the radiant heat smoke toxicity methodology [1]. These materials (other than the material tested for this report) have been examined in the Daming 2 mode in which they were exposed to a radiant heat flux of 50 kW/m for 15 minutes. For most of these materials,15 minutes was sufficient to decompose the sample and heating the material any longer would not have generated any additional gases. For the NRC sample material to be toxic in the 15 minute exposure time, we would have had to increase the sample size and we ran the risk of overloading the system. A larger sample size and a' shorter exposure time would have generated a larger LC30 value and make the material appear less toxic than with a smaller sample size and longer exposure time as used in these tests. The lower the LC 3o value, the more toxic the material. Comparison of the values in Table 11 indicates that the sample material is one of the least toxic of the materials examined. Table 11. Comparison of LC3o Values for Various Materials Material 3 LC (g/m (-) Value 95% Confidence Limits NRC Sample 53 45 - 63 NRC Sample - (Non-flaming) 42 32 - 55 Douglas fir 56 54 - 57 ' Rigid Polyurethane Foam 22 21.6 - 22.2 PVC 26 21 - 31 Flexible Polyurethane Foam 52 46 - 59 Melamine Polyurethane Foam 13 10 - 16 Vinyl Fabric 32 28 - 37 Vinyl Fabric over Melamine 26 24 - 28 Polyurethane Foam a. LC30 values 2 in this table are based on the mass of consumed material (radiant heat flux was 50 kW/m and the mode was Daming except where noted) that caused 50% of the rats to die l during the exposures and the 14 day post-exposure observation period (WE & PE). ; i l l 20 ' I
4.0 CONCLUSION
S 1. The LC3o value of the sample material decomposed in the flaming mode was compared to the LC30 values of other materials tested in the radiant heat smoke ; toxicity apparatus ansi appears to be among the least toxic. l
- 2. The LC30 value of the sample material decomposed in the non-flaming mode also indicates a relatively low toxicity compared to materials decomposed in the flaming mode. - l l
3. The monitored gases (CO, CO2 , HCN, and reduced 02) generated in the flaming mode appear to account for the toxicity produced. 1 4. The monitored gases (CO, CO2 , HCN, and reduced O2 ) generated in the non-flaming
~
mode appear to account for only 55 to 70% of the toxicity. Therefore, one or more ]
)
additional gases or other factors may need to be considered when determining the i gases or factors responsible for the toxicity. 5. ^ The animal deaths occurring beyond 24 hours following the non-flaming exposures I also indicate an additional toxic factor which acts during the post-exposure period. 6. When heated in the non-fbming mode, the intumescent char layer generates higher j yields of CO and CO, and about the same amount of HCN as the whole material. i
)
i 1 5.0 ACKNOWLEDGEMENTS The authors are grateful for the help of Ms. Maya Paabo who performed the analytical chemical-measurements in some of the tests and Mr. Ronald McCombs who assisted in the tests, prepared the animal weight graphs, and cared for the animals. l 21
)
i
l '
6.0 REFERENCES
i
- 1. Babrauskas, V., Levin, B.C., Gann, R.G., Paabo, M., Harris, R.H. Jr., Peacock, R.D., and !
Yusa, S., Toxic Potency Measurement for Fire Hazard Analysis. NIST Special Publication, ) National Institute of Standards and Technology, Gaithersburg, MD, Deu mber,1991. ! l
- 2. Kolthoff, I.M. and Sandell, E.B., Textbook of Ouantitative Inorcanic Analysis, Second Ed., I MacMillan Co., New York, p. 546 (1953).
l 1
- 3. Paabo, M., Birky, M.M., and Womble, S.E., Analysis of hydrogen cyanide in fire environ-ments. J. Comb. Tox. 6:99-108 (1979).
- 4. Heckenberg, A.L, Alden, EG., Wildman, B.J., Krol, J., Romano, J.E, Jackson, EE., Jandik, E, and Jones, W.R., Waters Innovative Methods for Ion Analysis. Waters Manual No. 22340, l s
Revision 0.0, Millipore Corporation, Waters Chromatography Division, Milford, MA,1989. 1
- 5. Litchfield, J.T and Wilcoxon, E, A simplified method of evaluating dose-effect experiments. '
J. Pharmacol. & Exp. 'Ilerapeut., 96:99-113 (1949).
- 6. levin, B.C. and Gann, R.G., Toxic potency of fire smoke. Chapter 1, Fire and Polymers.
Hazards Identification and Prevention, Ed. by G.L Nelson, ACS Symposium Series 425, American Chemical Society, Washington, DC (1990).
- 7. Levin, B.C., Paabo, M., Gurman, J.L, and Harris, S.E., " Effects of Exposure to Single or Multiple Combinations of the Predominant Toxic Gases and Low Oxygen Atmospheres ,
Produced in Fires," Fundamental and Applied Toxicology 9: 236-250 (1987).
- 8. Levin, B.C., Gurman, J.L, Paabo, M., Baier, L, and Holt, T, " Toxicological Effects of Different Time Exposures to the Fire Gases: Carbon Monoxide or Hydrogen Cyanide or to Carbon Monoxide Combined with Hydrogen Cyanide or Carbon Dioxide," Proceedings of the i
Ninth Meeting of the U.S.-Japan Panel on Fire Research and Safety, Norwood, MA, May, i 1987. NBSIR 88-3753, National Bureau of Standards, Gaithersburg, MD, pp. 368-384 (April,1988).
- 9. Irvin, B.C., Paabo, M., Gurman, J.L, Clark, H.M., ar.U Yoklavich, M.E, "Further Studies of the Toxicological Effects of Different Time Exposures to the Individual and Combined Fire Gases - Carbon Monoxide, Hydrogen Cyanide, Carbon Dioxide and Reduced Oxygen,"
Polyurethane 88, Proceedings of the 31" SPI Conference, Philadelphia, PA, pp.249-252 (October,1988). 10. Levin, B.C., Paabo, M., Gurman, J.L. Harris, S.E., and Braun, E., Toxicological interactions between carbon monoxide and carbon dioxide. Toxicology J 4 :135-164 (1987).
- 11. Babrauskas, V., Harris, R.H., Gann, R.G., Levin, B.C., Lee, B.T, Peacock, R.D., Paabo, M.,
Twilley, W., Yoklavich, M.E, and Clark, H.M., Fire hazard comparison of fire-retarded and non-fire. retarded products? NBS Special Publication 749, National Bureau of Standards, Gaithersburg. MD (1988). 22
- 12. Braun, E., Davis, S., Klote, J.H., Levin, B.C., and Paabo, M., Assessment of the fire performance of school bus interior components. NISTIR 4347, National Institute of Stan.
dards and Technology, Gaithersburg, MD, July,1990.
- 13. Braun, E., Gann, R.G., Levin, B.C., and Paabo, M., Combustion product toxic potency measurements: comparison of a small-scale test and *real.world" fires. J. Fire Sciences 8:63 79 (1990) i
- 14. Babrauskas, V., Harris, R.H. Jr., Braun, E., i.evin, B.C., Paabo, M., and Gann, R.G., The role of bench-scale test data in assessing real-scale fire toxicity. NIST Technical Note 1284, National Institute of Standards and Technology, Gaithersburg, MD, January,1991.
- 15. Levin, B.C., Paabo, M., Fultz, M.L, and Bailey, C.S., Generation of hydrogen cyanide from flexible polyurethane foam decomposed under different combustion conditions. Fire and Materials 9:125-133 (1985).
J l l 4 23
h Gas l Return Expansion Bag CO, CO 2, O2 - Sampling Port Port . Pod I (On Side) v / l 1 / i i i- <R , s Y
.' Chimney Animal Exposure Ports 0 ' Shuner i
! s' I
",7 ' ! l '?,e />o---. .o ' ,p'Y ' NOx o o o o HCN I I ' / ', 6 Sampling Port Sampling Port I - -
- 1. i- v l
Chimney l _ /% *--Radiant Heaters
% s COMBUS' ON CELL ASSEMBLY 4 I i / $ I I I t e A
- Load Cell . >~ ,
- / /' -- 9 . ?.t;;
Combustion -
" ~ '"*""
Ce11 E~Eai*" l go. '
. w l= l-i Figure 1. Radiant Smoke Toxicity Apparatus with insert showing radiant furnace.
R
- 0.5 // min.
CO2 Detector g
= 2 // min.
Combustion Gases R ___
=
CO Animal m Detector Exposure $ ,
@ Box LL-0.5 //m.in.
Pump : @ g- ___ 4 HCN Sampling 25 m// min. ll Port i PRV _ ll . l Excess NOx i R ' Combustion Detect 6r Animal Exposure f Ports c Gases O2 Detector
- g ,
l Lo.5 // min. R - Rotameter f PRV - Pressure Relief Valve Analyzed Combustion Gases ( ,
=
L i { Figure 2. Schematic of Radiant Smoke Toxicity Apparatus showing chemical analytical instrumentation. l . _ _ _ _ _ _ _ _ - _ - - - - ---- - --- -. - .
-- - --- - - '- ' -- ^ - ~ ~
2500 . . i i . Time of Amt. Loaded / . Test # Radiant Heat Amt. Consumed pee-ed 2000 - (min) (g/m ) e ~ e R-3 30 O A-1 15 114.5/62.5 e/* 225.1/68.3 e',/ e
/
1500 e <N Flame out
- e -
1000 - O j'o Radiant Heat Off
*o / ./ 0 /
500 - e / -
//
eO
/
0 4 e c ed ' ' ' O 5 10 15 20 25 30 TIME (min) Figure 3. Effect of increased heating time on monoxide generation from sample decomposed in flaming mode.
~
4 .-
. .. m q ;.~, ,;; . ,
350 .
.j , . -> i i. i '
128.9/70.0 300 - / 17.6 Amt. Loaded / V [A-2] O [^-3} - , AmL Consumed 114.5/62.5 (g/m ) .[R-3] 250 -- [Testg] _ I ( - 200 - A i m ~
.l A' l
. .Q 150- - v y - -Y I29.0/69.4 + v q l .- lZ 4' 7 100 - 129.0/70.7 [
]
C 225.1/68.3 . [A-1] l 50 - O 2 l ' O - E' O A - ., t t l :
-50 ' ' ' '
0 5 10 :! 15 20 25- -30. 35 ! TIME (min) a , Figure 4. Hydrogen cyanide generation - from . samples dec'omposed in flaming mode. !
350 i i i i i 3500 i i . . , i 300 - O - 3000 - 0 - 2E9 - 2500 - - k 200 -
*,e - k 2000 - -
a / a z 150 -
, O * -
o 1500 -- - o - o e m / 100 - 1000 - - 50 - 500 - - e 0 '*' ' ' ' ' d 00 /A ' ' ' ' ' O 5 10 15 20 25 30 ^*[ m y,^n,[,d/ m,3 0 5 10 15 20 25 30 35 Time (min) (g/m') Time (min) 40000 , , , , , , O 128.9/70.0 25 i , , , , i e 129.8/71.5
- Y*> 24 - -
23 - - 30000 - _ 22 - E ^ g 21 4 , 20000 - 20 - - u 19 - - 18 - 10000 - 17 - 16 - C ^ o ,o - 00 15 ' O 5 10 15 20 25 30 35 0 5 10 15 20 25 30 35 Time (min) Time (min) Figure 5. Comparison of gas generation from a thicl<. smaller surface area and a thin, larger . surface area sample decomposed in the flaming mode.
~
30 -- u 4V. r _- . -
^
(A 20-- -- Cont.rols & Std. Dev. : i
,;.... .3 -
i d - : - . . : R - g - . . . . . . N 40 :
! -ji !y ^
( ~: ~ M i 10-- T. v 4 - be -
? : ' : .e4 -
m 0-- . . -
- v '$ l; . al ,. : , i' h _ -{-
f ,
.,..: +n- n v
n v a t
. . . . .s . . . . : , .
l .d i ?. . .,
~ j. . . 'i. .:. T. i ,
e4 -- . .
- 7...:,' : : : :
1 . D - T.....:-. ' . ..:'
. i.
1 . - 60
-t.. ..:-,.:-':-
Y -- .~ - . d T-2
- T 4 :-
o - i' c. i
-30 l l l l l -10 -5 0 5 10 15 l
Time (days) ; i Figure 6. Control test indicating effect of radiant heat and experimental stress on weight gain of the rats. Day 0 is the day of exposure. , l- The lines prior to Day 0 show the mean and standard deviation of the weight gain of animals who have not been exposed and the six animals
- who were used in this test. The rats were exposed in the head-only mode for 30 minutes while the furnace was heated by the radiant lamps set at a flux level of 50 kW/m 2. All the
- :iiimals lived 14 days and gained weight normally.
1I l!;lII jl _ _ - 5 3 e d i n a y c n e
, g 0 o ' 3 r d - y h
f
- . i o
n o
/ ' 5 t a
2
. r e e nd e o 4 gm e " h g t n i 0 ) n nr no a
- 2 l
i xf mlu -no 7. f ( t n a E e e A ' 5 Mhh I t t
~
1 T nn
- i ai dd d ae r s e o
/m d
eu
. ep d s hm t , o a
oo n 399 ' 0 gc 063 ne LC * /// j
- 1 idg
. . 8!
t t 94 1
- ns 555 mm( ae
/
1 1 1 hl p AA c f m o as t cm
;- ' 5 f
e o x 055 f r l u! 532 Ef F 7. Ame e _ r
- - - - u 0 O g 0 0 0 i 0 5 0 0 O F 3 2 5 0 '
2 1 1 LL
^ SCC
- ZU l I
60-- 40'-- T : : -
^
u)
- - Controls & Std. Dev. - : : : : : :
h g ,. I. I. ' T. f.
!.....!. ,.. 3..... '! ~ } l p 20-- T i i i ! ! i ! i i !
i
~
k0 r i i i i.
-!.'...i :i i
- 2 i
- 2
- 1 - ',
a . - :- t. : . . :. : .: . . . : ;. . . . .:
. . - . ' , . } , . . . - - - - e. ,.Q 0-- T T T : : : : : 1 X X
- be ,-
T : : .
.,r' : : : : : : : 1 - -
r-1 T ? .1 : 1 ,
. ..:. ::: D " :
e r . t t. . y -.- 1 i. .:. .- : 1 - -
.I.1 . '. i.-4 .: . :: . : . . ...t ;: '.i. ..
g ....: _
- - - e. a _m m . .s ..
1
- e y --
60 - d ' d - r4 U -
-60 l ! l l l -10 -5 0 5 10 15 Time (days)
Figure 8. Change in weight of test animals following exposure to a sampic decomposed in the non-flaming mode. The amount loaded - 3 3 in the furnace was 52 g/m and the amount consumed was 30 g/m . Day 0 is the day of exposure. The lines prior to Day 0 indicate the mean and standard deviation of the weight gain of animals who have not been exposed and the six animals who were used in this test. In this test, one animal died at the end of the 30 minute exposure and two animals died on day 8.
60 --
-- Controls & Std. Dev. _ _
m 40__ m d : : : : : : p . T. . . . . . . tm
- .3 . . . ,1.
,._., 20-- : : : : : : : : : a :. : 1 : : : : : : : : ; .:. .:. y
- .. :- ,. :i....i: i: :#f __
tm .:. I t I i ! i i i i i I
.s _ . :. : : : : ; -
m 0- -
- .;. : . .g.. .- .... : .
g . . - g u o #v i .i 3.,,.i..-:..
- .! "......: i .i
- i : . M.,M" ^
- ^
- m
.d ,,g.... .i... , '..j.'.~.'.: : " }. i m . .
- 1-
. f. - -
q) ,.i' g , g j j ; 1 - ho ^^ G : : ; , d - p .. o -
-60 l 1 ; m l ; -10 -5 0 5 10 15 :
Time (days) , Figurc 9. Change in 3 weight of test animals following exposure to a sampic decomposed in the non-flaming mode. The amount loade 3 in the furnace was 55 g/m and the arhount consumed was 31 g/m . Day 0 is the day of exposure. The lines prior to Day 0 i and standard deviation of the weight gain of animals who have test. one animal died on day R. ' not been exposed and the six animals who were used in this test. In this
e d o 5 m _ _ ~ - - _ - 3 g 5 9 i n G 9 1 0 7 3 0 7 1 9 1
. , . 1 3 2 m 1 /1 1
8 2 G 5 1 8 3 3 a
/ 1 1 / 4 l
6 /5
/ 1 9 / 8 /
1 3 f 3 6 1 / 9 8 53 8 - 3 7 8 /
,2 0 0 1
5 1 8 5 96 2 1 ' 0 n 6 1 1 1 3 0 / 2 1 2 1 27 3
/ 5 3_ o E y A 01 88 O 4 /1 V 9 5 n 2
5 5 5 i n g/ O O ' 5 d e s o 2 p p m v o c ~ e
, d s , o ) el , ' 0 np 2 i A m
( mas _ E m _ o . a 9 Mr f
~ , % ' 5 1
I T n i o t a r , e , j n r e g 0 4' 1 e d i n
)
d a
/ e y d
em c
)
d u n a s o n m e L o / 5 g g
. C ( o t
r mt
- d A m y A
H 0 1
- - ~ - -
0 0 0 0 0 0 0 0 e 5 0 0 5 0 5 r u 3 3 2 1 1 g i F m[ v ggZ -
100 i , i . i i 3500 i i , , , . 3000 - - 75 - - 2500 - - E E 2000 -
/* -
50 -
. - " .f h 1500 ./
m
*y . s 25 - -
[ ~ 500 - - O Ot [ .' ' ' ' ' I O 5 10 15 20 25 30 35 0 5 10 15 20 25 30 35 Time (min) Time (min) 20000 , , , , , , 25 i , , , , i 24 - 23 - - 15000 - 8
~
7 22 - - g a
- .j/ 6 21 4 - , 10000 - -
o 20 - - ta ./ 19 -
- C -
18 - - 5000 - 17 - - 16 - - 0 4V
/. ' ' ' ' ' ' 15 ' ' ' ' ' '
O 5 10 15 20 25 30 35 0 5 l'0 15 20 25 30 35 Time (min) Time (min) Figure 11. Gas generation from the intumescent char layer formed during the non-flaming tests. 3 3 The amount of material loaded in the furnace was 194 g/m and the amount consumed was 29 g/m
. .... - - . .- _- - - - .. - - - - - . - . . - - . - . -- - . - . - ~ ~
g_ g m =. x
^
o .
,j == Log # TXX-92219
- - _: File # 10010 r
=__ # 909.5 1UELECTRIC May 1, 1992 ,
William J. Cahill, Jr.
' Group Vice President U. S. Nuclear Regulatory Commission -
Attn: Document Control Desk Washington, DC 20555 -
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) , DOCKET NOS. 50-445 AND 50-446 CONFIRMATORY TESTING OF THERMO-LAG : FIRE BARRIER SYSTEM i Gentlemen: I Recent industry wide issues, relating to the Thermo-Lag fire barriers, has l prompted TU Electric to initiate a comprehensive confirmatory test program ) to envelope the full range of protected conduit and cable tray j configurations. The test program was implemented to provide further i assurance of the overall adequacy of Thermo-Lag barriers at CPSES. l Thermo-Lag testing is currently scheduled for the second week in June, 1992 (June 8-12) at the following address: OMEGA POINT LABORATORIES, INC. ) 6868 Alamo Downs Parkway San Antonio, Texas 78238 TV Electric extends an invitation to your representatives to witness the , confirmatory tes*.s at Omega Point Labs. l w n. I
,/ h l c ,3 . i e s ou sur J .k 92050 242 920501 ~
ps,g i j h A 0500p g 5- P.o. Box ico2 olen Ro.e, Texas 76043-too2 l
16 x e[, ..+> .
, - w.
i g .. ,
. ~- .,
TXX-92219-Page 2'of-2'
-l Please contact Obaid Bhatty at (817)897-5839 to confirm your arrival or if i V additional information is required. 't -t Sincerely, d Y f' jfr William J. Cahill, Jr. i i
i By: M - R. D.' Walker ! Manager of Nuclear Licensing l OB/tg. : c - Mr. R. D. Martin, Region IV *
.Mr. B..E. Holian, NRR .i Mr. T. A. Bergman, NRR l Resident Inspectors, CPSES (2) j i )
i l 1 i
' 1
3 e
.m ?. ~
W g. v . .
-- Log # TXX-92228 L ; File # 10010 r
___ =_ # 909.5 TUELECTRIC May 6, 1992 Williana J. Cahill,Jr. Group Vice Presidrat U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) DOCKET NO. 50-445 AND 50-446 EVALUATION OF THERMO-LAG 330-1 FIRE BARRIER SYSTEM REF: 1) TU Electric letter from W. J. Cahill, Jr. to the NRC logged TXX-92219 dated May 1, 1992. Gentlemen: At a meeting in Rockville, Maryland on February 12, 1992, the Nuclear Regulatory Commission (NRC) expressed concerns regarding Thermo-Lag 330-1 materials. Our understanding of the current NRC staff concerns relative to Thermo-Lag 330-1 fire - l
- barrier systems are summarized as follows
- 1. Adequacy of fire endurance testing and applicability of test results to as-installed configurations.
- 2. Adequacy of ampacity derating design bases.
- 3. Less than adequate installation and inspection processes and i procedures as recommended by Thermal Science Inc. (TSI) !
S'Jbsequent to the Rockville presentation and other recent NRC concerns. TV Electric conducted an assessment of-test results and documentation, ampacity derating design basis, and installation / inspection specifications and procedures t.pplicable to Thermo-Lag configurations at CPSES. This review concluded that I Thermo-Lag fire barrier systems at CPSES are adequately designed and installed. l Accordingly, we are proceeding with application of Thermo-Lag in Unit 2 as I contemplated by our completion plan and schedule. This review has been ! documented via an Engineering Report and includes a Design Matrix of the Thermo- . Lag configurations at CPSES with associated supporting t.ast documentation. The aforementioned Engineering Report is available at the site for your review. Specific results of TU Electric's review and related actions to the above concerns are as follows.
' 0 , ()
92051 05 920506 s f
-PDR A . 05000445 F _
PDR P. o. Box 1002 Glen Rose. Texas 760431002 ,O
\\ O
A
., ;, ~
(- e TXX-92228' Page 2 of 3
- 1. Nine fire endurance tests were reviewed to support the one-hour fire rating qualification basis for Thermo-Lag configurations installed.
These tests demonstrate that the vast majority of configurations are adequately substantiated by test and the commodities tested are representative of as-insta.lled conditions. Specific instances (small diameter conduits and large cable trays) where available test documentation could be improved or detail enhanced have been identified and further evaluation is in process. Nevertheless, to provide further assurance of the overall adequacy of the Thermo-Lag program, TU Electric has initiated a comprehensive confirmatory test program to envelope the full range of protected conduit and cable tray configurations used. TV Electric has contracted directly with Omega Point Laboratories in San Antonio, Texas to conduct this program. To f abricate the test assembly, CPSES stock Thermo-Lag products will be installed by site craft personnel in accordance , with our installation procedures and inspected by CPSES Quality Control (QC) inspectors. Per reference 1, TU Electric has submitted an invitation to your staff representatives to witness these . confirmatory tests.
- 2. The TU Electric review of the CPSES design basis for applying ampacity derating factors has concluded that conservative values have been incorporated into cable sizing criteria for raceways protected
- i with Thermo-Lag. No change to the current CPSES program is required'.
- 3. The TU Electric review has concluded that the installation and inspection controls as implemented by the Thermo-Lag specifications and applicable procedures satisfactorily address concerns identified !
during the February 12, 1992, meeting. The installation drawings l are significantly more detailed than corresponding TSI installation i guidance. In some instances, the CPSES requirements are more i conservative than TSI's recommended practices. The Thermo-Lag products are installed by CPSES site craft personnel in accordance with our installation procedures and inspected by CPSES QC inspectors. No change to'the current CPSES program is required. Upon completion of confirmatory testing activities as described above, the Thermo-Lag Engineering Report and Design Matrix will be revised to include applicable test results. The test report to be issued by Omega Point Laboratories will also be made available for review by NRC Staff personnel.
~
As discussed above in item 1 and reference 1 TU Eleewdc had submitted an invitation to your staff representatives to witness these confirmatory tests during the second week of June 1992. Subsequent discussions with your staff regarding the cure time of the trowelable grade Thermo-lag, TU electric has rescheduled the confirmatory test for June 15 through June 19, 1992. However, this is a tentative schedule. We will verbally inform your representatives in ample time if there is a change in this schedule. l l
. .- j
.p
,-4 , ,
TXX-92228 Page 3 of 3 Should you require additional information regarding this issue or details related to the testing activities, please contact Obaid Bhatty at (817) 897-5839. Sincerely, ! 1-William J. ahill, Jr. OB/ds Enclosures ; I c - Mr. R. D. Martin, Region IV
~
l Mr. B. E. Holian, NRR Mr. T. A. Bergman,.NRR Resident inspectors, CPSES (2) i 1
\
9 i
n q A' 1 O GULF STATES UTILITIES COMPANY R s !* E P.? ST A?:CN POST OFFICE Box 220 ST F,l ANCISviLLE LOUIStANA 7377! ARE A CODE 604 635 6094 346 8f 51 May 6,1992 RBG-36802 File Nos. G9.5, G9.25.1.3 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Gentlemen: River Bend Station - Unit 1 Docket No. 50-458 Please find enclosed Supplement 2 to Licensee Event Report No. 91-008 for j River Bend Station - Unit 1. This report is submitted to document corrective i actions for three fire areas for which Appendix R separation concerns had been , identified. This supplement is submitted at this time as discussed with Mr. Elmo l I Collins of the NRC. Sincerel W.H. Odell Manager - Oversight River Bend Nuclear Group grCTI'.$ O, M d EAE/PDG/JRH/DCH/MRC/kvm
~
I l 1 cc: U.S. Nuclear Regulatory Commission l 611 Ryan Plaza Drive, Suite 400 l l Arlington, TX 76011 NRC Resident Inspector ~w L gg P.O. Box 1051 ,gt St. Francisville, LA 70775 l !$ l INPO Records Center ' i 1100 Circle Parkway 1 g I $ Atlanta, GA 30339-3064 0 3 Mr. C.R. Oberg /
- 2m z
e .,.,,.n. 4UU o Public Utility Commission of Texas 7800 Shoal Creek Blvd., Suite 400 North Austin, TX 78757
/}[l . )y - A g
~ .
p # e, wC pw s ases Gets W 8 Mk8A8 W## "" g,penovte out ho 3tt04tos t a# tit s 4I30/93 LICENSEE EVENT REPORT (LER) MA i lo. LE $? So a S 8o mal
- cou 4=r atoanoe C .Ichc uaotnriuirt o to e-t asconos
$7Ev"tI?o"l! "ou',U"cf".1"'i c",IJE 2"0!n'"a*.'5?o WahAGE IN Aho yo ET. m m hCT C2 3 8 ACILITY 8tAalt lli coCatt muesta 131 raat im RIVER BEND STATION o is Io lo ;o; 41 5l8 i jorl 0 ;9 "8"'
FIRE HAZARDS ANALYSIS DEFICIENCIES INCLUDING LACK OF FIRE WRAP / INADEQUATE FIRE BARRIER SYENT DATE ISI tia sevsatta des atPoet oef t t?1 oTMEa F ACILITIEE lavo4WED tel edoltfu cav staa vgaa 58,0 ',a s ,me , Mo%t es oav vtAn sacs 6iv e manees coCatr wwwetait. O Issojoio, , , 0l 4 1l5 9 1 9l 1 0l0l8 0l2 Q5 0l6 9l 2 o isio io , o, i ,
, , , , , , y ruis atoont is suenairrt o avasv4=t to rat anoviatut=rs os se Cea 5 <Ca-e . ., *, ., , ... ,, titi escot M) M 492161 M 88Siel te 736eH2Het 73 f ttal a M esSteH1Hd 30 asieHti se 73uM3H,1 73ftte n., 11 0t0 = ==Hi Ho N 40SIsH1Hiset w mwH '
to ?3teH2Hel nri-H H H 98 73taHalesiendAl _ o,,gjj. g;.,..g v Judas 70 eettalititivl to eJteHJital 90 734eH3.tsseligt 30 assielltllel to 73(all2Hisd to734eH3Het LICth488 Co4f ACT f on inns Lia (131 4AWS ftLE*=oNG %vween L. A. ENGLAND, DIRECTOR - NUCLEAR LICENSING 51014 3 18111-1411 4 15 ConsettYt oset Lint som E ACM Comeroset.sf f aitual otecaesto th Twis aspomt (13: H*cara u MA AC pe f CAWSt Svsftw Cow *c % E % T
"$ $C yO pe g Cault $ v 5Tsw Couro44 mf p a ,LE f I I I I I I I I I I I f 't i l l I l l l I I i i l l ! I SUPPLlut4T AL atront E xetcTao ties wo%r= oav vtaa Svewssio= ~~~} ,$s n,, a.na eurcreo svowssion cars D no l q l A.,r uC r ,5. ., ,. , a . , , ,. . .. , ,,, .,.. . ,, . .. . , n e i At 1345 hours on 4/15/91, with the reactor at full power in Operational Condition 1, it was discovered that electrical cables located in fire area ET-2, which may cause spurious operation of valves-1E51*MOVF063 (RCIC inboard steam isolation valve) and 1E51*MOVF078 (RCIC vacuum breaker valve), did not have fire wrap contrary to Fire Hazards Analysis (FRA) requirements. At 1300 on 4/23/91, additional cables, which could cause the same problem were found in fire areas AB-2, C-2 and C-6. RCIC is required by the FHA for safe shutdown in these fire areas. Since those valves are required not to change position for operation of RCIC cnd fire damage to these cables may cause loss of RCIC, the cables would require wrapping in these fire areas.
Upon discovery of this condition, the affected cabltrfr-were treated as having missing fire barriers and the action statement prescribed in j Technical Specification 3/4.7.7, " Fire Rated Assemblies", was ' implemented for areas containing these cables. Errors made during the original development of the FHA were the cause for the identified cables not being wrapped in the identified fire areas. Additional deficiencies have been discovered during the FRA review. These recently discovered deficiencies concern Appendix R separation and a fire area that was not previously identified. GSU has implemented corrective actions to address each of these conditions. aC,- =.i.ni
' m - m-o - - ~
G EM 83 a/3033 UCENSEE EVENT REPORT RER) So"ll^J!/.c". FEE' MJ,','1*"uv'k*fl"Y *"o'aEI' TEXT CONTINUATION '?.M*"",6%"*a fi."d '." Ic"lf,'k'*l"' i'EUf} u,it.a.'4."l.o.%. "oe',t.,':". gt*.c e aoe =v a=o.vocir. n. oro.J".".,Eia . oc wies. PAcluTV asAast He Occust s.vesssa 121 gga wg g ,g
">a " 2".? ! "'J,:',;;
RIVER BEND STATION o s lo jo jo l4 15 l 8 9l 1 - 0 l 0l8 - 0l2 0l 2 OF 0l9 2,a .,.== . sc msnm REPORTED CONDITION At 1345 hours on 4/15/91, with the reactor at full power in Operational Condition 1, it was reported to the shift supervisor that certain electrical cables associated with valves 1E51*MOVF063 (*ISV*) (PCIC inboard steam isolation valve) and 1E51*MOVF078 (*VTV*) (RCIC vacuum breaker valve) located in fire area ET-2 (Electrical Tunnel "B" West), did not have fire wrap. This discovered condition is contrary to require.nente contained in the PHa. While working on resolution of this issue, additional cables which could cause the same problem were found in fire areas AB-2, C-2 and C-6. At 1300 hours on 4/23/91, these additional areas of concern were reported to the shift supervisor. The FHA lists Method 1 as the analyzed method of shutdown for fire areas AB-2, C-2, C-6 and ET-2. Method 1 shutdown is identified as using 3 safety relief valves (SRVs) (*RV*) for reactor i pressure vessel (RPV) (*JE*) pressure control, RCIC for RPV level control, and RHR-A for suppression pool cooling and shutdown cooling. The FHA lists these valves as " Passive Valves" required for Method 1 chutdown which means the valves must not change position due to fire
- damage on their cables. The FHA states the identified cables for these valves should be wrapped in these fire areas. l l
The affected cables did not have the required fire wrap (fire barrier) ' since plant startup; therefore, the fire barrier is considered l' inoperable per Technical Specification 3/4.7.7 and this report is submitted pursuant to 10CFR50.73 (a) (2) (i) (B) as operation prohibited by the Technical Specification. Additional reportable conditions have been discovered as a result of the FHA review. These conditions concern Appendix R separation and the discovery of a previously unidentified fire area. These conditions ch described la the Investigation section below. INVESTIGATION The River Bend Station - Unit 1 Appendix R Data Management System lists equipment, raceways, and cables by fire area. A review of this data base found inconsistencies between the data base and the FRA for the identified cables which may cause spurious operation of valves 1E51*MOVF063 and 1E51*MOVF078. The FHA indicates the cables should be wrapped in these fire areas but the data base indicates.the cables do not require wrap. FHA Section V " Fire Hazards Evaluation Conclusions" states that for fire areas AB-2, C-2, C-6 and ET-2 shutdown can be achieved by Method
- 1. FHA Sectier I and Tables 1, 2 and 6 identify Method 1 shutdown equipment. Reactor core isolation cooling (RCIC) (*BN*) is used for reactor pressure vessel (RPV) level control in Method 1 shutdown. The ,
RCIC inboard steam isolation valve 1E51*MOVF063 and the RCIC vacuum unc , sosa es,
m2
- ,,o,,,,,..,,, ,,,, - o .m....,,.,,, * ~
UCEN2kr EVENT REPORT (LER) $#.'!?,o*#"o*E.*c'Jof,'Yo"u".,,'* *?"'.7 ,"o* E'I TEXT CONTINUATIUN IT.".MID7.w*$
. '.U'.'c'1,'!E E' Eu'*cNI!
in..%. *.".!
- e. N.
- T, ".'.,'"J.vo
...,,.o n.'.".;;:n. . ,.*J.*.a .ea.u!.i", a ..ciury m ooca.1 av .a m u , ,,u, . ,,, ,. , ,
n== " M.' ' ! RIVER BEND STATION ren ,,- a.c % mw,,im o ls ]o lo t o l 415 I 8 911 - Q 0l 8 - 012 0l3 0F 0l 9 ; l breaker valve 1E51*MOVF078 are passive valves for Method 1 shutdown which means they must not change position due to fire damage. FHA l Table 2 states that cables for these two valves, which may result in ' i epurious signals, are wrapped in these fire areas. Circuit analysis on cables lICSABC001 and lICSABC004 (*CBL2*) found that fire damage can cause spurious closure of valve 1E51*MOVF063 which would prevent eteam from reaching the RCIC turbine (*TBR*). Circuit analysis on , cables 1ICSEBC001 and IICSEBC003 found that fire damage can cause ) apurious opening of valva 1E51*MOVF078 which would adversely affect ] RCIC vacuum breaker capabilities. 1 Since these valves are required not to change position for operation of RCIC and RCIC is required for safe shutdown in the affected fire areas, the valves are correctly classified in the FHA as " Passive - Method 1 Components". Therefore, to comply with the USAR, FHA, and 10CFR50 Appendix R Section III.G, the cables would require wrapping in fire. areas AB-2, C-2, C-6 and ET-2. With the exception of FHA Table 8 , with regards to fire area AB-2, the FHA correctly indicates these ) cables require wrapping in these fire areas. The Appendix R data base. , is incorrect as it indicates the cables are not required to be wrapped. Additional reportable conditions have been discovered as a result of l the FHA review. These conditions concerned Appendix R separation and ) the discovery of a previously unidentified fire area. The Appendix R ! separation concerns involve fire area C-25 (main control room), FB-1 (fuel building), and RC-5/Z-13 (containment building). The previously 4 unidentified fire area is a small electrical cable chase room located in the Northeast corner of D Tunnel on elevation 70in the auxiliary I building. These additional concerns are discussed individually below. Fire Area C-25.(main control room): The FHA identifies fire area C-25 as an area where alternate shutdown capability is provided. FHA Table 3 (method 1E - main control room fire required items) lists specific spent fuel pool cooling & cleanup , (SFC) system and fuel building ventilation (HVF) system equipment as l being required and therefore, independent of the fire in the control room. Review of circuits for this equipment determined the circuits are not electrically independent from the control room and potential fire damage could cause loss of the equipment which may. result in loss of spent fuel pool cooling. Fire Area FB-1 (fuel building): Fuel building ventilation dampers 1HVF*AOD037A, 102 and 122 are identified in the FHA as equipment required for spent fuel pool cooling. Potential fire damage to electrical cables, located in fire ) area FB-1, for these dampers may cause spurious operation of the i ere e- maa sue.
_ __ _ z-1,.---- --
'a= ,,,, ,,, _ , ,,, .- . 4... ,
UCEN2EYEVENT REPORT (LER) %"l.^.7&?.F30.3M3"L'*, cow 7 ,e,y,,,34 TEXT CONTINUATIDN 20"'"Otr.043.* A"J',1'",,c"l't,'Z".' .".**c".3
,4Cstsfy maan tu CEST U.egm L2) in.
o ".,"l"!.2.<f%"J.voon. w r -o a. lda.roc%*J.*..oc"==Wa t Les enam.R se ,Aet W
~= "ht:.V. i "?:::
RIVER BEND STATION o ls lo ]o l o l 415 l 8 911 - Q 0l 8 - 0l 2 0; 4 or 091 var ,, . - =c w armm dampers which could potentially cause loss of the spent fuel pool cooling pump and thus loss of spent fuel pool cooling. Pre-fire strategies for this area stated these. dampers must be verified to be in their proper position and if not, remove power so they fail to the correct position. Removing power to these dampers may not cause the dampers to go to the correct position since a potential hot short could cause the damper to remain'in the incorrect position. Fire Area RC-5/Z-13 (containment building): USAR Section 9A.2.2.1 states " Safe shutdown Method 1 and 2 equipment, instrumentation and electrical cables are well separated in the Containment. The east (Division II - blue) side of containment is separated from the west (Division I - red) side by the main steam tunnel on the south and by an area free of combustibles on the north. Safe shutdown by either Method 1 or 2 can be used, depending on the actual location of the fire in the containment." With a fire in the west side (Division I), safe shutdown could be achieved using Method 2 equipment (Division II).
- The FHA identifies the fact that containment unit cooler 1HVR*UC1B and related valves 1SWP*MOV502B & 503B (Method 2 equipment) are located on the< west side of containment on elevation 162'-3" in Fire Area RC-5/Z-13. Valves 1SWP*MOV502B & 503B are inlet and outlet valves controlling cooling water to the unit cooler heat exchanger. The FHA ,
states that this equipment is separated from its alternate counterpart I by 24 ft. In addition, a 10 ft. missile barrier serves as a radiant
]
cnergy shield and intervening combustibles are wrapped with a 3-hour ! rated product. Unit coolers 1HVR*UC1A & 1B are separated from each other by a minimum distance of approximately 11'-2" (not 24' as reported in the FHA). A 10' high, 18" thick reinforced concrete missile barrier, which acts os a radiant energy shield, is located between the redundant unit coolers and related SWP valves. However, electrical cables for the redundant unit coolers and valves are routed such that the missile barrier is not located between redundant cables. Electrical cables I for 1HVR*UC1B are in conduit # 1CL540BB and are routed along the i containment liner. One portion of this conduit that is located within 20' of the redundant conduit # 1CL540RC (electric cables for 1HVR*UC1A) is wrapped with a three hour rated Thermo-lag conduit fire l wrap material. The 20' dimension used was taken along the direct line between the two conduits, not horizontal distance as required by Appendix R. Since both conduits are routed along the containment liner but at different elevations, this application o the 20' rule allowed one of these redundant cables to be located directly over the other (separated by a minimum distance of 20' vertical but O' horizontal) and not provided with the fire wrap material. Cables associated with the SWP valves also do not meet the 20 ft. horizontal
=ac p=. a a iam
,,,,,,,,,,,,, ., u. toet m ..u m ,. _< . . . ... . . u,.m ' UCENSEE EVENT REPORT (LER) 'Eo't't'v%'.Pc8Ent"o"'f7a",*.' . /*.ff*?? .TT.'Jo ~ " ' TEXT CONTINUATION - ii.U's"ld/TYu'##i' .M'."IEc'UlM I,"'"NU c S!",W.*e
- 05 uamaG.u.it"O2.uo#!O.dn3 NTANO G8T,ma miseQTom DC 20043- fa'th '
PA lgsfy snaast HI 00CE87 feuesSEA tan Limes m en13 %g
)[w*si" w a RIVER BEND STATION rasia - . w. ,
woc m .nm o l5 t o lo Io (415 l8 9l1 - 0l0l8 - 0 ]2 0l 5 op 0l9 separation criteria as identified in 10CFR50 Appendix R, Section III.G. Valve 1SWP*MOVSA is listed as a component required for Method 2 safe shutdown in the FHA. This valve isolates Division II from Division 1 standby service water and is also located on the west side of the containment. This valve is located on elevation 153'-9" and is separated from its counterpart by a horizontal distance of 20'-2", however; this distance is not free of intervening combustibles. The intervening combustibles consist of electrical cables located in two 18" wide cable trays. A review of the cable rtouting for the SA valve found that the cables do not meet the 20 ft. horizontal separation criteria as identified in 10CFR50 Appendix R, Section III.G. Fire Area AB-18 (previously unidentified) During the final FHA review, all fire areas except one were found to have a fire hazards analysis and 58 of 62 fire areas were found to
- have administrative controls identified in the FHA included in their pre-fire strategies. A fire hazards analysis for the new fire area, l not previously identified in the FHA, was performed to determine l potential impact on safe shutdown capability. The analysis determined l {
that safe shutdown for this new fire area is provided utilizing Method l 1 shutdown equipment and by initiating high pressure core spray (HPCS) ' in lieu of reactor core isolation cooling (RCIC) for level control during a fire. Also, administrative controls to align valve 1SFC*MOV120 to supply cooling to the upper fuel pools were necessary.
' Modification request (MR) 92-0013 was initiated on January 27, 1992, to make necessary document changes to the FHA and USAR for the new fire area. A new pre-fire strategy was prepared to identify this information to reactor operators'and the fire brigade. Pre-fire strategies for the four fire areas were revised to include the omitted ,
administrative controls identified in the FHA. ' CORRECTIVE ACTIONS A detailed review and verification of the FHA by-an independ.ent I contractor was initiated as a result of NRC Inspection Report No. 50-458/90-02. The conditions as described in this report were identified ,I by the independent contractor during resolution of questions identified in the review and verification process. Evaluations of all questions arising from the final review of the FHA by the independent contractor were completed in January 1992. Upon discovery of the condition identified on 4/15/91, the affected l cables were treated as having missing fire barriers and the action I statement' prescribed in Technical Specification 3/4.7.7, " Fire Rated l Assemblies", was implemented for areas containing these cables. With
, . . . - _ --n.. ...s - - - - . _ ~ - - - ~ - . ~ . - - .[
, g,,m. =.2 U S NUCLEAM EGGubatoAT COM8 4 appggygDCueNo 3160 4104 E RFt&ts 4/30/92 LICINSEE EVENT REPORT (LER) L'4"1'u'#e'Nu ME M"o"','3"un,'omeo"?l ,*o'" 7.TJ ' TEXT CONTINUATlON
!?"o".Ylo'/4'u'21"ciSO'."d!'e""lM v'"' "'*NU C "5,PIfl.'eli""at%*N'! Tote?"3 fa'o'2 Ta7ei Q MANAG4WtNT ANO SwCGIT.walalNCTON. DC 2c603. ,.ciurv N.. m ooCas? Nv=ua m ti. Nu un m ,.a m n" "tM ;':::: l RIVER BEND STATION olslololoj4l5l8 9l1 q 0l 8 0 l9 0l 2 0l 6 oF rwea _ = ..._ . mc o- ma mm the exception of the Division II electrical room located in the I northeast corner of "D" tunnel on elevation 70', fire watches had been i previously in place for the affected areas due to operability '
questions associated with penetration seals. However, there is no assurance that fire watches had been in place for the entire time period since startup. For the affected fire areas, an anal'jcin han been performed to I determine what alternate system for RCIC is available (free of fire damage). The analysis determined that low pressure core spray (LPCS) (*BM*) is free of fire damage in Fire Areas AB-2, C-2, & C-6 and high pressure core spray (HPCS) (*BJ*) is free of fire damage in Fire Area ET-2. Errors made during the original development of the FHA were the cause of inconsistencies found within the FHA and between the FHA and the i Appendix R data base. These inconsistencies resulted in the l identified circuits not being protected in accordance with 10CFR50, ' Appendix R, Section III.G. A contributing factor involving these ' crrors appears to be the fact that the affected components are Division II and are required for Method 1 shutdown, which primarily uses Division I and III components. Review of this condition has determined there are also Division I cables / equipment which are required for Method 2 shutdown, which primarily uses Division II components. The cables for this type of equipment are considered
" Appendix R Crossover Cables". Analysis has determined that there are approximately 80 of these crossover cables. A review of these crossover cables was performed and with one exception no similar deficiencies exist. The exception is the Division II cable chase area located in the northeast corner of D-Tunnel. In this area, RCIC may be lost due to fire damage on crossover cables. As previously stated in the investigation, it was found that this area had not been previously identified or evaluated in the FHA. Analysis for this new fire area (AB-18) demonstrates safe shutdown capability is provided.
Since the area contains only Division II cabling, safe shutdown can be achieved utilizing Method 1 shutdown methodology and substituting HPCS l for RCIC for RPV level control. The corrective actions to address the I new fire area included the identification of the proper safe shutdown method, implementation of administrative controls to align valve 1SFC*MOV120 to provide cooling to the upper fuel pools, documentation changes to the FHA and USAR, and the preparation of a pre-fire strategy for this area. . Fire Area C-25 (Main Control Room'): Immediate actions were taken and administrative controls implemented to address the concerns with spent fuel pool cooling until permanent corrective actions could be identified and implemented. Engineering analysis determined that the time required for the spent fuel pool m e e- 3 a4 u i
~ ^ %.. _ , ,,,,,,, u.. C u E m u e .,co .' ,,, , , , , , , , , , ,,,
LICENSEE EVENT RilPORT (LER) "!$1&*e("lCd'v"o"'&c';*/u'*J "'N 038 ,y
- " ^ TEXT CONTINUATION INU'"4'#'u'If.IUSS'."!!/c'Ul'J'O'/l5cMA i
O O,P,YJ.'eWat.l8k"', ::i;P,J,ca'!MWei MANAGtWeNTANO uoGt7 nasm NGTON.DC20603 l ,aciurv =ame m ' """""*"* 8' n.. ." w:,w .m:,y l RIVER BEND STATION o ls to lo j o l4 l5 l 8 9 l1 - 0l0l8 - 0l2 0; 7 or 09 I i l temperature to reach the cooling system design limit of 155.6 degrees ! F with the existing fuel load conditions prior to RF-4 was approximately 5.3 days. Administrative controls were implemented and AOP-0031 (" Shutdown From Outside Main Control Room") was revised to , provide the necessary manual actions to restore spent fuel pool i cooling with a fire in the main control room. The entire reactor core
- was offloaded to the fuel building spent fuel pool for RF-4. With the increased heat load in the fuel pool, the minimum time required to reach the cooling system design limit of 155.6 degrees F was approximately 4 hours. This is sufficient time to take the manual actions identified in AOP-0031.
The corrective action for addressing the concerns with spent fuel pool cooling is to complete an analysis which demonstrates a design which allows a higher spent fuel pool temperature and still allows sufficient time to restore spent fuel pool cooling. With this revised design bases, the spent fuel pool cooling equipment presently identified as required by the FHA would not be immediately required. ! This analysis is scheduled to be completed by July 10, 1992. Any ' modifications found necessary will be scheduled during Fuel Cycle 5. MR 92-0038 has been approved to complete analysis of long term corrective actions. The administrative controls and manual actions discussed above will be maintained until long term corrective actions , cre implemented. Fire Area FB-1 (Fuel Building):
'The immediate action taken was to treat the electrical cables as having missing fire barriers and initiate a continuous fire watch per RBS Technical Specification. After actions identified above for the main control room was implemented and pre-fire strategies for Fire Area FB-1 were revised to identify the manual actions required to place the dambers in the correct position, the continuous fire watch was removed. The permanent corrective action for this condition will be addressed with completion of the analysis and modifications, if required, as discussed above for the main control room.
l Fire Area RC-5/Z-13 (Containment Building): -='- I The immediate action taken was to treat the cables as having missing ! fire barriers and initiate an hourly fire watch per RBS Technical Specification. i The permanent corrective action for this condition will be to provide en analysis which demonstrates th'e unit coolers are not required or install noncombustible radiant energy shields to provided separation [ dn accordance with Appendix R, Section III.G.2.f. Modification
- request (MR) 92-0037 has been approved to install the required radiant cac e.- as.4 mei
, . - . . . - - - ~ ~ - - ~ - ~ -
7 , gga U.S. ELWCLEA21 RSEWLAf tev COamst ,
'I 80 0 ' # . $3FI18$ 4/30/92 LICENSEE EVENT REPORT (LER) -
f.Un*,ll,*,A*i'd" I'Jo"'yo"ui'.,'*,ff*l?l .Tl' 75'$ !
..- ' "' TEXT CONTINUATION i=o"'EEAftf'.27s ANJ't"Ifle'IflM '"' L'CNN M?W. *,JJT*"No?Ao"' ".ng"#,m'k tua Os teamAGensclut has0 SWOGG7, wasmissGToas. DC 20003 FACILitV Isaasa 111 00 Cut? NWeseta 621 LOR poussega les gg "t'#.i* "'Jfa: )
RIVER BEND STATION o [s lo lo lo l4l5 l 8 S1 - q 0l 8 - 0l 2 08 op rav m . ur .a== a=e a. .muwm 0 l9 i energy shields if needed. The analysis to demonstrate the unit.
, coolers are not required and the preparation of MR 92-0037 will proceed concurrently. This approach will allow the analysis and/or installation of the radiant energy shields to be completed prior to i- startup from RF-4.
Similar events have been reported in LERs 87-005, 89-009, 89-036, and 90-003. LERs 87 005, 89-009 P.nd 00 003 reported installation-related deficiencies in Thermo-Lag fire barriers. LER 89-036 reported an event in which the fire hazards analysis specified that certain motor-
- operated valves (MOVs) should be normally de-energized. The actual condition of the valves was that they were energized. New issues identified during the FHA review have revealed FHA deficiencies concerning spent fuel pool cooling and a previously unidentified fire area. j SAFETY ASSESSMENT I
The FHA states safe shutdown can be achieved in fire areas AB-2, C-2, I C-6 and ET-2 using Method 1 shutdown. Method 1 is identified as using. 3 SRVs for RPV pressure control, RCIC for RPV level control, and RHR-A for suppression pool cooling and shutdown cooling. Since the affected cables were not wrapped in these fire areas, fire damage could cause loss of RCIC. With the loss of RCIC, a review was made to determine what alternate method of RPV level control was available in these fire ' areas. Analysis has demonstrated that for Fire Areas AB-2, C-2 & C-6, LPCS is free of fire damage and for ET-2 & the new fire area (AB-18), ifPCS is free of fire damage. This demonstrates that with a fire in any of these fire areas, at least one method of safe shutdown is unaffected. . Fire Areas C-25 (main control room) and FB-1 (fuel bldg.) were identified as areas where potential fire damage could cause a loss of spent fuel pool cooling. Calculation No. G13.18.14.0*46-0 was developed which demonstrates the time required for the spent fuel pool temperature to reach the design limit of 155.6 degrees F with the present fuel load is approximately 5.3 days. Abnormal Operating
. Procedure (AOP)-0031 " Shutdown From Outside Main D&ntrol Room" and pre-fire strategies for fire area FB-1 have been revised to address i '
manual actions which may be required to restore spent fuel pool ' cooling with a fire in these areas. These corrective actions and administrative controls have been implemented to address these concerns under present fuel pool load conditions until permanent corrective actions are identified,and implemented. The FHA indicates safe shutdown can be achieved in Fire Area RC-5/Z-13
-(reactor containment bldg.) using Method 1 or 2 depending on the .
location of the fire. The FHA states containment unit cooler 1HVR*UC1B is separated from its alternate counterpart by 24 ft. and a , k hO $ I e
l p,,,,,,,,,,,, m o . noes.u ..~,u, e-.
..,,1.,a,.,,,
LICENSEE EVENT REPORT (LER) ISst'.'M;'u%{" 'c%"'?lo*u"g*,fl7},' ET 'as TEXT CONTINUATION *i.E'".IMl'.*.f21"".*?M',*.1!,'c'"','!,I, v '"'"Mni'
~ '- . ' ?'!",W.e?."ra'J8;',o".'!;gg",,i.cy,'A ^;ia 09 td&8tAGhutNT ANO guOGtt,malatNGTON. DC 20 03 P ACILaty esaast til DOCKET Nueasta (21 mggy, a "t!.;;'t' atyg-RIVER BEND STATION o l5 lo lo j o l 4l5 S 9 11 -
q 0l 8 - Oj 2 0l9 or 0 l9 rurr , - a . = = = - c ac w ass .nm ; 10 ft. radiant energy shield and is being protected from intervening ! combustibles by wrapping the intervening combustibles with a 3-hour , rated barrier. Since the cables for this unit cooler were not wrapped ; in accordance with Appendix R, Section III.G requirements, fire damage ! could cause a loss of containment cooling. The affected cables were treated as having missing fire barriers and fire watch requirements i epecified in Technical Specification 3/4.7.7, " Fire Rated Assemblies" have been implemented. i NOTE: Energy Industry Identification System Codes are identified in the text as (*XX*). I J I 1 l I e I l l l
!l t 1 I
t v., i
==ce sen. e> l
*N ,*- /
S EE Log # TXX-92228 Fi1e # 10010 r _ =_ # 909.5 TUELECTRIC May 6, 1992 William J. Cahill, Jr. Group Mce President U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) DOCKET NO. 50-445 AND 50-446 EVALUATION OF THERMO-LAG 330-1 FIRE BARRIER SYSTEM REF: 1) TU Electric letter from W. J. Cahill, Jr. to the NRC logged TXX-92219 dated May 1, 1992. Gentlemen: At a meeting in Rockville, Maryland on February 12, 1992, the Nuclear Regulatory Commission (NRC) expressed concerns regarding Thermo-Lag 330-1 materials. Our understanding of the current NRC staff concerns relative to Thermo-Lag 330-1 fire - barrier systems are summarized as follows:
- 1. Adequacy of fire endurance testing and applicability of test results to as-installed configurations.
- 2. Adequacy of ampacity derating design bases.
- 3. Less than adequate installation and inspection processes and procedures as recommended by Thermal Science Inc. (TSI).
Subsequent to the Rockville presentation and other recent NRC concerns. TU Electric conducted an assessment of-test results and documentation, ampacity derating design basis, and installation / inspection specifications and procedures applicable to Thermo-Lag configurations at CPSES. This review concluded that Thermo-Lag fire barrier systems at CPSES are adequately designed and installed. Accordingly, we are proceeding with application of Thermo-Lag in Unit 2 as contemplated by our completion plan and schedule. This review has been documented via an Engineering Report and includes a Design Matrix of the Thermo-Lag configurations at CPSES with associated supporting t.&t documentation. The . aforementioned Engineering Report is available at the site for your review. Specific results of TU Electric's review and related actions to the above concerns are as follows.
. . _ . , /I 92 30005 920506 PDR ADOCK 05000445 gb F PDR P. O. Box 1002 Gien Rose. Texas 7600-1002 w \\ O
^ ~
i TXX-92228 Page 2 of 3
- 1. Nine fire endurance lests were reviewed to support the one-hour fire rating qualification basis for Thermo-Lag configurations installed.
These tests demonstrate that the vast majority of configurations are adequately substantiated by test and the commodities tested are representative of as-installed conditions. Specific instances (small diameter conduits and large cable trays) where available test documentation could be improved or detail enhanced have been identified and further evaluation is in process. Nevertheless, to provide further assurance of the overall adequacy of the Thermo-Lag program, TU Electric has initiated a comprehensive confirmatory test program to envelope the full range of protected conduit and cable tray configurations used. TU Electric has contracted directly with Omega Point Laboratories in San Antonio, Texas to conduct this program. To f abricate the test assembly, CPSES stock Thermo-Lag products will be installed by site craft personnel in accordance with our installation procedures and inspected by CPSES Quality Control (QC) inspectors. Per reference 1, TU Electric has submitted an invitation to your staff representatives to witness these confirmatory tests.
- 2. The TU Electric review of the CPSES design basis for applying ampacity derating factors has concluded that conservative values have been incorporated into cable sizing criteria for raceways protected
- with Thermo-Lag. No change to the current CPSES program is required.
- 3. The TU Electric review has concluded that the installation and inspection controls as implemented by the Thermo-Lag specifications and applicable procedures satisfactorily address concerns identified during the February 12, 1992, meeting. The installation drawings are significantly more detailed than corresponding TSI installation guidance, in some instances, the CPSES requirements are more conservative than TSI's recommended practices. The Thermo-Lag products are installed by CPSES site craft personnel in accordance with our installation procedures and inspected by CPSES QC inspectors. No change to'the current CPSES program is required.
Upon completion of confirmatory testing activities as described above, the Thermo-Lag Engineering Report and Design Matrix will be revised to include applicable test results. The test report to be issued by Omega Point Laboratories will also be made available for review by NRC Staff personnel. As discussed above in item 1 and reference 1, TU Elech.ic had submitted an invitation to your staff representatives to witness these confirmatory tests during the second week of June 1992. Subsequent discussions with your staff regarding the cure time of the trowelable grade Thermo-lag, TU electric has rescheduled the confirmatory test for June 15 through June 19, 1992. However, this is a tentative schedule. We will verbally inform your representatives in ample time if there is a change in this schedule. k
* ~ ~ ;. .o
'I ' TXX-92228 Page 3 of 3 Should you require additional information regarding this issue or details related to the testing activities, please contact Obaid Bhatty at (817) 897-5839. Sincerely, 1 William J. ahill, Jr. 08/ds Enclosures c - Mr. R. D. Martin, Region IV Mr. B. E. Holian, NRR Mr. T. A. Bergman, NRR Resident Inspectors, CPSES (2) U
i -4 0 1 O G UI.T ST);, TES UTILITIES COMPANY l
= . i- i n . :s :: u .:, ::. s 4 s: s . ...t .:. s is. :-
inga :cg 604 636 6094 346 6 W May 6,1992 RBG- 36803 I File Nos. G9.5, G15.4.1 I U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Gentlemen: River Bend Station - Unit 1 Docket No. 50-458/ Report 92-04 This letter provides Gulf States Utilities Company's (GSU) response to the i unresolved items noted in NRC Inspection Report No. 50-458/92-(M. This letter , i describes GSU's corrective actions and provides anticipated completion dates. In i addition, other fire protection issues discussed at the April 20 meeting at River i Bend Station are addressed in this response. l Should you have any questions, please contact Mr. L.A. England at (504) 381- l 4145. 1 Sincerely, W.H. Odell Manager - Oversight River Bend Nuclear Group cc: U.S. Nuclear Regulatory Commission 1 611 Ryan Plaza Drive, Suite 400, Arlington, TX 76011
',g NRC Resident Inspector /' .
P.O. Box 1051 St. Francisville, LA 70775
'[: \ ;
l i V 92t 180109 920506 _
-l \
PDR ADOCK 05000458 , J G . PDR -
ATTACHMENT 1 Response to Unresolved Item 50-458/9204-01 1 l REFERENCES 1 Inspection Report - Letter from A.B. Beach to J.C. Deddens, dated March 27,1992 Licensee Event Report No. 90-003 (Rev 3) - Letter from W.H. Odell to U.S. NRC, dated June 28,1991 Licensee Event Report No. 90-003 (Rev 2) - Letter from W.H. Odell to U.S. NRC, dated February 4,1991 Licensee Event Report No. 90-003 (Rev 1) - 12tter from W.H. Odell to U.S. NRC, dated July 12,1990 l 1 Licensee Event Report No. 90-003 - Letter from W.H. Odell to U.S. NRC, dated March 8, 1990 Revision to Informational Report - Letter from J.E. Booker to U.S. NRC, dated January 9,1990 l 1 Informational Report - Letter from J.E. Booker to U S. NRC, dated December 20,1989 l
< \
Licensee Event Report No. 89-009 - Letter from J.E. Booker to U.S. NRC, dated April 7,1989 1 Licensee Event Report No. 87-005 - Letter from to U.S. NRC, dated February ,1987 History of Thermo-lae Issues at River Bend Station In February of 1987, GSU discovered minor problems with installation of Thermo-lag fire barriers. These were identified in LER 87-005 and a commitment was made to perform a 1005"o inspection of the surface of Thermo-lag barriers. As a result of this inspection, GSU found a Thermo-lag panel with the stress skin, a wire reinforcing material, removed. This condition appeared to be common for fuel building 3-hour barriers. As a result, fire watches were verified or established for the fuel building. GSU decided to pursue qualification testing of these "in situ" conditions based on discussions with Thermal Science, Inc. (TSI) in which GSU was told that the stress skin was not necessary for a Thermo-lag barrier to meet its design function as a fire barrier. GSU and TSI developed a test procedure from August 1987 to February 1988, specifically for a 12 inch tray covered with Thermo-lag 330 with no internal stress skin or ribs. The initial test was performed on the test article with no internal stress skin on March 9,1988; however, beacuse the furnace temperature went beyond litnits, test results were invalid. The test was repeated on July 29,1988 and the fire barrier failed. GSU verified or established fire watches for 3-hour cable tray barriers in all buildings due to the possibility of this situation existing with other 3 hour cable tray barriers. 1 OF 11
^
2 An evaluation of the installation at RBS showed removal and replacement of the Thermo-lag to be undesirable. GSU attempted fire tests to upgrade cable tray barriers, in the third quarter of 1988, Southwest Research Institute (SWRI) was contracted to perform fire tests on cable tray fire barriers. A test procedure was Sepe.; 6 5WRI to test several upgrades to existing installations as well as the " original design" configuration. The test was placed on hold in the spring of 1989 after discussions with TSI. TSI offered to run " informational" fire te;ts on 12 inch trays with various upgrades as well as a full qualification test of a 30 inch tray at Construction Technologies Laboratory (CTL) in Chicago, Illinois, i The results of the informational tests run by TSI in the spring of 1989 indicated potential problems with " original design" installations for 30 inch cable trays. Of the potential upgrades developed and tested by TSi, several passed; however, all the upgrades would be difficult to install.
- i. The 30 inch cable tray test article to be tested at CTL was constructed by TSI under their QA program. The completed test article was inspected by GSU and several differences were noted between the construction of the test article and standard construction details allowed in the TSI installation manual. The test anicle successfully passed the qualification test. l Based on the differences between CTL tests and standard installation practices, GSU decided to i pursue testing at SWRI. The SWRI test included two 30 inch tray installations, one using standard Thermo-lag installation practices as allowed by the TSI installation manual and the l second using a competitor's product to compare both the installation process and fire resistance.
The test also included other miscellaneous penetration seal details. The test anicle was l constructed by GSU technicians trained and certified by TSI. The test at SWRI was completed e I on October 26,1989. The Thermo-lag barrier failed approximately 47 minutes into the test. Condition Repon (CR) 89-1144 was initiated to document the test failure and ensure that all areas with Thermo-lag had fire watches in effect. Extensive discussions were held with TSI regarding the results of the SWRI tests. TSI regarded the SWRI test as invalid, which is a point of technical disagreement between TSI and GSU. A detailed review by GSU of TSI fire tests 3 identified several areas of concern. These concerns were documented in informational repons l to the NRC dated December,1989 and January,1990. The three primary areas of concern were: size of test anicles, use of aluminum conduit, and joint construction methodology. ' To resolve both the disagreement and the GSU concerns, an agreement was reached between TSI , and GSU to jointly perform fire tests on the in situ Thermo-lag configurations as well as ' simplified upgrades. Four configurations were tested for both 1-hour and 3-hour qualification: conduit, cable tray, Unistrut suppon, and vault enclosure. The test procedure was developed from March to August,1990. The test articles were constructed in September and October 1990, and testing was performed in November 1990. The test results are summanzed in Table 1-1. i l l - 1 l I
- i. -
j: 2 OF 11
4 TABLE 1-1 SUABIARY OF IN-SITU TEST RESULTS TEST ARTICLE TEST TYPE RESULT CONDUIT 1 HR FAIL CONDUIT 3 HR FAIL CABLE TRAY 1 HR FAIL ! CABLE TRAY 3 HR FAIL SUPPORT 1 HR PASS SUPPORT 3 HR PASS VAULT 1 HR PASS VAULT 3 HR FAIL TABLE 1-2 SUABIARY OF UPGRADE TEST RESULTS TEST ARTICLE TEST TYPE RESULT l CONDUIT 1 HR PASS ) CONDUIT 3 HR PASS l CABLE TRAY 1 HR PASS CABLE TRAY 3 HR FAIL l VAULT 3 HR PASS l i I
^
3 OF 11
i
,. 1 Configuration upgrade tests were conducted on only those configurations which failed the in-situ tests. An additional upgrade configuration was tested for cable trays with a 3-hour fire rating but wa; not :cmpletely successful in that the barrier failed after 2 hours, 55 minutes. m results are summarized in Tabic l-2. An altemate product is being evaluated for 3-hour cable tray fire barriers; however, the preliminary results of an ampacity review indicate that some j cables will have to be relocated or resized. Also, a structural review will be required due to the increased weight of the barrier. A study of the cost ofimplementing Thermo-lag upgrades for i the other configurations versus a new product showed that the Thermo-lag upgrade is more economically desirable. However, due to concerns related to the recent NRC investigation of TSI, work has been stopped on implementing any upgrade. GSU's schedule for final resolution is dependent on the results of reviews and actions taken by the NUMARC ad hoc committee on Thermo-lag barriers.
GSU's Resoonse to Section 4.2.1. "Thermo-lan Removal" As part of the Fire Barrier Task Force investigation, Thermo-lag fire barriers were removed in a number of plant locations around junctica boxes, conduit seals, and wall penetrations to permit inspection of internal components. The Thermo-lag removed was not immediately re-installed since GSU had previously declared all Thermo-lag barriers inoperable, and had established fire watches for compensatory measures in accordance with the RBS Technical Specifications. The penetration and conduit seal inspections that required removal of Thermo-lag fire barrier material were documented as part of GSU's maintenance work order system. The documentation was designed to ensure that when the re-installation of Thermo-lag material began, all inspection points would be covered with the fire barrier material. The practice of not immediately re- ' installing Thermo-lag was ceased in July,1991 when Engineering informed Maintenance that a safety evaluation in a licensee event report credits existing Thermo-lag as providing some degree of protection even though it is being treated as inoperable. All removed sections of Thermo-lag have been re-installed and sections of Thermo-lag removed
- in the future will be re-installed upon completion of the work activities necessitating their initial removal.
GSU's Resoonse to Section 4.2.2. " Structural Integrity of Thermo-lar Installation" ISSUE: The inadvertent operation of f're protection systems potentially causing damage to the materials. RESPONSE: The damage to the F tunnel enclosure which was observed during the January 1992 NRC inspection was caused by a leak above the enclosure. Upon further investigation by GSU personnel, it was determined that the leak had caused degradation to the trowel grade material applied to the seams / joints of the cnclosure and that no damage to the TSI prefabricated panels used to form the enclosure had occurred. The inves.tigation included examinations to both the inside and outside surfaces of the enclosure. Repair of the trowel grade seam / joint closures will be completed during RF-4. Contrary to the assumption in the NRC Inspection Report, there is no record of actuation, inadvertent or designed, of fire protection systems WS-8L or 8M which protect inside enclosures in F tunnel. 4 OF 11
4 y ISSUE: Overall structural integrity of the enclosures, specifically drains provided for the erclosures appeared not to be d:digned te removc ai! water within the enclosures during an actuation of the cable tray sprinkler systems. PMPONSE: The design does not assume all water is removed. Since all enclosures using Thermo-lag material are designed to isolate redundant safety-related cable divisions, these enclosures are seismically designed and supported. The support framework is designed to carry the weight of the TSI prefabricated panel assemblies and the calculated weight of water introduced upon operation of the sprinkler systems. The determination of the amount of water introduced is based on review of the sprinkler contractor's calculations of water discharge by nozzles located within the enclosures. Since operation of the systems is alarmed in the control room, first by an indication of smoke detector actuations and then by a water flow alarm signaling actual flow through the nozzles, appropriate actions to respond to the event are assured. The drainage provided for the enclosures is designed to ensure that the height of water assumed in the design will not be exceeded. Following these types of events, investigation as to the condition of the enclosures and the ability to remain in full service is required. These actions are considered similar to the actions and investigations which are required in the event of any sprinkler actuation or actual fire at the plant. The worse case scenario is that associated with the degradation of the enclosure floors due to the build-up of fire suppression water. The Thermo-lag material could possibly give way and the retained water would be dumped on the tunnel floor. We believe this would take place sufficiently long enough after the actuation of the sprinkler system for the fire b'rigade to respond e to the alarm in the control room (typically 10-15 minutes). This event is discussed in GSU's response to Section 4.2.3, below. GSU's Resoonse to Section 4.2.3. "Oualification Testing of Installed Configurations" ISSUE: For assemblies that had passed previous fire tests, none of the tests had simulated the fire suppression systems being acWated both internal and external to the fire barrier enclosures as installed in the F and G tunnels. No documentation of tests or an engineering evaluation could be provided at the time of the inspection. RESPONSE: The design objective is to provide an enclosure which is structurally sound and fire resisting. The steel Unistrut support frame is designed to seismically support itself and the prefabricated Thermo-lag panels. It is also designed to carry a 15 inch deep pool of water on its floor. The prefabricated panels are rated for the required 1-hour fire resistance. For cases of external transient fire, the panels protect the Division I cables inside the enclosure. The fire suppression water discharged by the sprinkler system creates a pool of water on the floor of the enclosure and dissipates the heat that may be transferred to the supporting steel through the panel. . Typical results from the 3-hour fire endurance tests conducted by TSI on Thermo-lag 330 Conformable, Three Hour Stress Skin Fire Wall System, (Ref. I.T.L. Report No. 82-3-2) S OF 11
recorded at test conclusion an unexposed side surface temperature ranging from 190 degrees F to 250 degrees F. Based on this test information, and given that the supporting steel of the enclosure is immersed in a pool of water, it can be reasonably projected that for a 1-hour barrier, the cold side temperature including that of the supporting r. eel will not exceed 150 degrees F. The steel frame is sufficiently flexible because of the sizes of members and bolted connections to accommodate differential thermal expansions resulting from the above scenario without any . appreciable stresses and any adverse impact on the structural integrity. Therefore, the design of the barriers was judged to satisfy the design objective and special qualification testing was not considered neemry. ISSUE: An accepted and successful test configuration for an 18 inch cable tray was used to simulate the large floor / ceiling installation (approximately 10 x 12 ft) in the G tunnel, the 4 x 6 x 150 ft cable tray enclosure in the F and G tunnels, and the 4 x 6 x 6 ft instrument rack enclosure on the 98 ft elevation of the control building. No engineering evaluation was readily available that would demonstrate that a small scale design could be effectivciy extrapolated to the sizes that exist at RBS. RESPONSE: The design basis for Thermo-lag enclosures described above include the following: 1
- Configurations provided by TSI in their Technical Note 20684, Revision 3, dated i February 1985, are used as shown or adopted to suit the plant conditions. The use of i
' l Thermo-lag based on the Technical Note was considered equivalent to the use of gypsum wall board design for a specific fire rating based on U.L. standards. Project specific testing was not considered to be necessary since the Technical Note was reported to be based on actual tests.
- The enclosures isolate either the Division I or Division II cable trays and equipment so that a fire confined to one fire area will not cause a loss of both divisions. i i
- Transient fires within the enclosures are not credible since the areas within the enclosures are inaccessible. Any entrance into the enclosures for maintenance and inspection of fire protection equipment is by personnel well trained in the RBS fire protection program, including the importance of the enclosures.
All three configurations are considered appropriate applications of TSI Technical Note 20684 requirements as outlined under the design basis above, and were not originally evaluated based on similarities with the 18 inch cable tray design as reported in the NRC Inspection Report. The specific applications in the F and G tunnels and for the instrument rack are spacial enclosures rather than fire wraps around a single cable tray. They are based on the published capability of the panel designs to resist fire for the specific hourly rating required. In essence, the enclosures are considered one-way fire barriers designed to protect the cable and/or equipment within the enclosures from transient or cable induced fires located outside the enclosures. In areas, such as the F and G tunnels which have automatic fire detection and 6 OF 11
~ - >g- y
suppression systems, barrier ratings are 1-hour in conformance with the RBS USAR. Areas
. without automatic fire suppression systems have fire barriers rated for 3-hour fire resistance (SCENARIO 3).
The EBS e..:los'.tre designs use techniques ordinarily used to adapt specific small scale tested configurations to large assemblies. As in the design of gypsum board walls and floor-ceiling assemblics the more critical components of the overall design are the materials used, the spacing and anchoring of suppons, the method of attaching the gypsum boards to the support system, and the requirements to finish and close joints and seams. Using the guidance provided in TSI Technical Note 2%84, Figure 8, the RBS enclosures use prefabricated panels adequately secured to Unistrut supports at designed spacings generally not to exceed 12 inches. Cases where the 12 inch spacing is exceeded have been reviewed and approved by Engineering. All joints and seams are closed with trowel grade 330-1 subliming material. The TSI documentation does not limit the overall dimensions of the Figure 8 fire wall design. The only reference to a size limitation appears in Section 2.1 which restricts the length of a bottom section of a cable tray enclosure configuration to 6.5 feet "since longer sections are unwieldy and more difficult to install." This statement penains to an installation difficulty which was overcome by the design i details prepared for these enclosures by qualified fire protection engineers. ; ISSUE: There is no assurance that the exposed structural steel Unistruts would not fail and 1 jeopardize the integrity of the floor-ceiling assembly. RESPONSE: As noted above, the barriers in the F and G tunnels are designed as one-way I barriers. Effects of fires internal to the enclosures are discussed under SCENARIOS, below. SCENARIOS , 1 The following scenarios are provided to describe the essentials of the fire protection evaluation of the three Thermo-lag fire barrier enclosures highlighted during the NRC inspection.
=
- 1. Transient Fire. F or G tunnel - As shown in Figure 1-1, Scenario 1, this event provides an immediate challenge to the unenclosed Division II cable trays. The ionization type smoke detectors would respond within a very shon time, initiating the flow of water to the cable tray water spray systems for both the Division I and Division 11 tray stacks.
The 1-hour Thermo-lag enclosure prevents simultaneous exposure to the Division I cable trays at this time. An effect of water being discharged within the Division I cable tray enclosure is that the potential for water build up on the floor of the assembly exists. As designed, the support system is sufficient to carry the additional weight. In the unlikely event of catastrophic leakage and potential collapse of the enclosure floor, no impact to the ability to safely , shutdown the plant results. This is due to two primary effects of the leakage or collapse. The first effect would be the immediate dumping of the collected water onto the areas in which the transient is burning. thereby assisting in extinguishment and/or control. The second effect is that the water being discharged within the enclosure continues to keep the cables thoroughly wet, therefore preventing damage to the Division I cables. In addition, all tray supports (independent from the enclosure supports) are also protected from damage by the water spray deluge ocemring on the cable trays within the enclosure. 2-Since Division I cable are maintained free of damage, safe shutdown is assured. l
~
7 OF 11
0=E-Noun nw r
~ -r- /-s = < ' RATED ENCLOSURE lk Al~
1TJ 1 --: ' w *
;j" q
J-
** W ' , $c W
t / :.- c a r TRAvr mTw g MATER spray naf
*O '
ll' %_ M--mF ; N: _ v l
= , peotteneurTw) -
- c-= ,>
- v. ,
w :- ;. w
- :, r, -
t L,=; - 7,
'li._i;;; = E IL=llH1' Twrawn.-LAC ENet ne14f(VALM Ti i SCEhARIO 2 ro. em r mAmnmun a r a c '
suarr orTrenauttwj f -+- an ~% ONE-HQuq FJg - 4 ' ' l RATED ENCLOSURE g")* 123 - - ' W Sj
~
i b1 l N/ _ *' W W y w N mf s 7'--Cask.irt r TRAYS s,.ivwfn.r TH l l i' PaottennutTw) l l_ o! w -
= -- j, s l = !!lE, -e .a .' iiIIE -i ' l l--l l_;. F I-Ill-il! ll' SCENhRIO 3 I
PRO TH POETRATimd INTO EN'2.0SJE PREEA8RICATED CAaLE/ CON 0Utf I g C M mm 4 4
, THDtMO-LAG SUGLIMING i
I
< MATDt!AL 330-1 UED i l i ' TO CLOE AND EAL ALL > d i EDES AM JOINTS l i I t > I ) ,
i I ( l 4 i i I l 4 INSTRuurNT RACK (1 M*RAK1) EL 98* CONTROL SLOG. (4str6 FT) l Figure 1 -1 Fire Scenarios _ _ . 8 OF 11
l . 2. Cable Fire Within F or G Tunnel Enclosures - Figure 1-1, Scenario 2, shows a fire within a cable tray enclosure as hypothesized in F or G tunnel. The ionization smoke ! detectors within the enclosures respond and actuate the cable tray water spray sprinkler systems. Sprinkler he- ., installed to discharge wat: r on all tray: at about 8 to 10 feet intervals along the tray wih immediately extinguish the cable tray fire. Exposure to plant shutdown capabilities would not exist since the Division II cable, outside the enclosures, would not be affected and would remain fully functional. j
- 3. Instrument Rack EncingIn - As shown in Figure 1-1, Scenario 3, the 3-hour enclosure design precludes either an interior, cable induced fire, or exterior transient fire from impacting the ability to safely shutdown the plant.
l GSU's Resnonse to Section 4.2.4. " Electrical Cable Ampacity Derating" Engineering Evaluation and Assistance Request (EEAR) 91-C-0115 was initiated on November 22,1991 to document GSU's review of the Underwriters I.aboratories (UL) Report concerning ampacity derating of Thermo-lag fire wrap enclosures. The discussion below provides information regarding the history of Thermo-lag ampacity derating factors and a status of GSU's current evaluation. 1 Ampacity derating factors presently used in calculation E-218 were provided by TSI to SWEC l in a letter dated July 5,1985. This letter was in response to SWEC comments on various Industrial Test I.ab (ITL) reports containing derating factors. TSI concluded the letter by summarizing derating factors that may be used for RBS. This letter along with a telecopy listing SWEC's comments is included as Attachment 13 to Calculation E-218. < A mailgram from TSI dated October 2,1986 was appropriately sent to Stone and Webster Engineering Corporation (SWEC), GSU's RBS design agent at the time. This mailgram reported preliminary results of the UL test. GSU located copies of several SWEC interoffice memorandums which discuss the potential impact of the UL test on RBS ampacity derating factors. The correspondence indicates that SWEC dettanined that any impact would be limited to tray installations only and that accounting for actual tray fill, as opposed to the 100% fill assumed in the SWEC demting calculation, should compensate for the higher derating factors. The mailgram states that, "(TSI) conducted certain ' plant specific' ampacity tets at UL", and that the results are, " preliminary information, subject to verification, reduction, and formal reporting by UL." The mailgram further states that, "as (TSI) receives the repons from UL, (TSI) will transmit copies 'o you promptly." GSU could find no subsequent correspondence from TSI on this issue. In response to NRC concerns that non conservative ampacPy cen..ing factors may have been used at RBS, GSU has reviewed all cables addressed in calculation E-218. This review confirms the 1986 SWEC evaluation that these cables will meet acceptance criteria if derating factors reported by UL are used. In the course of this review, GSU noted that approxinately 300 additional cables are located in fire barriers that are not addressed in calculation E-218. GSU is currently reviewing these cables for impact due to ampacity derating. ! l 9 OF 11 _
, - - - - . . _- , , - . - ,- , --.-,-r e-
4 All 480 V cables in this group have been reviewed and there will ta no adverse impact if UL ampacity derating factors are applied. Three 120 V cables weic iound to be impacted by the ampacity derating. These cables supply power to heat tracing on piping for containment ; monitoring instrumentation inside the reactor building. Condition Report, CR 32-0250 hos been initiated to address these cables. Approximately 200 of the 120 V cables remain to be evaluated. This evaluation will be completed and all corrective action scheduled by the end of refueling outage (RF) 4. GSU has performed a comparison between test articles described in the UL Report and installed raceways at RBS. Several differences between test articles and typical RBS fire barrier configurations have been noted below:
- 1. UL installed the side panels first. Additional banding was used to hold the top i and bottom pieces in place.
- 2. For the one inch thick configuration, the side panels of the UL test article were l installed in the opposite direction (ribbed surface exposed) than the RBS installation. At RBS all of the cable tray enclosures were built with the flat .
surface exposed. ! l
- 3. The spacing of the stainless steel bands was greater in the UL test than what is used at RBS (18 to 24 inches at UL versus 12 inches at RBS).
4 The UL test punched holes in the underside of the 1/2 inch thick panel to secure the Thermo-lag to the rungs of the tray. This technique has never been used at ' RBS. There is no reference in the test report to indicate if the holes were patched with trowel-grade material after tightening the tie wire.
- 5. A third band was installed in the UL test for the top panel. This was not done in the RBS installation.
- 6. The UL report references a " thin coating of trowel-grade" installed between the gap formed by the top / bottom and the sidnil panels. For RBS installation this gap would be required to be " filled" witn trowel-grade material.
- 7. The ends of the UL test articles were scaled with glass fiber insulation and duct tape. A typical installation at RBS would be knowool (ceramic fiber) or low density silicon elastomer (LDSE).
- 8. Depth of cable fill is three inches in the UL test versus one and one-half inches in the TSI test and the RBS installed configuration. Since the effects of depth versus ampacity are non linear the derating factors are more severe than if a one and one halfinch depth had been tested.
- 9. Steel wire ties used to secure cable to the tray rungs could cause inductive heating if not insulated to prevent a conducting path around the cable.
10 OF 11
! 10. Ampacity for conduit with one-halfinch wrap is higher than the baseline. The l report does not rationalize this discrepancy. I 1 Since constniction differences as identified above may affect ampacity derating factors, GSU l does not believe that it is appropriate to adopt the UL ampacity derating factors. ] 4: 1 The installation method used in the UL t st for covering the four inch conduit is identical to the i method used at RBS. The derating factor identified in the UL test for conduits is lower than the l derating factor used at RBS, therefore; no further actions were taken.
- It is not clear at this time if valid ampacity-derating factors are available. The NRC concern that GSU may not have used the most conservative derating factors may be a common problem l throughout the nuclear industry. This issue was discussed at a recent meeting of a NUMARC l l ad hoc committee on Thermo-lag concerns. Final resolution of this concern will be coordinated j with other utilities through NUMARC.
l l GSU's Resnonse to Section 4.2.5. " Fire Test Accentance Criteria" ' The NRC has indicated that the fire test criteria used by GSU for fire barrier testing deviates - from the NRC criteria stipulated in Generic Letter 86-10 which states that transmission of heat ; through the barrier, "...shall not have been such as to raise the temperature on its unexposed l surface more than 250 degrees F above its initial temperature." . RBS was reviewed and licensed in 1985, prior to the issuance of NRC Generic Lette- (GL) 86-
- 10. Electrical cables which run inside 1-hour and 3-hour fire barriers at RBS have passed the
, flame test in IEEE 383-1974. Degradation of the insulation used on IEEE 383 rated cable does not begin untiljacket temperatures reach 450 degrees F to 650 degrees F. The criteria of 325 degrees F plus ambient assures that cable jacket temperatures do not reach these levels. The maximum ambient tempemture for any fire test related to RBS has been less than 90 degrees F, therefore, the criteria of 325 degrees F plus ambient assures that temperatures are suiriciently l below the temperatures where jacket degradation begins. From the aspect of elevated temperature, this assures that cables are maintained free of fire damage in accordance with Appendix R, Section III.G requirements as committed to in USAR Section 9A.2. Although this variation from Generic Letter 86-10 guidance is not explicitly addressed and accepted by the NRC in the RBS SER, it is implicitly accepted. Penetrations are an integral part of the barriers and NRC guidance in BTP CMEB 9.5-1 Section 5.a.3 requires penetrations to be sealed or closed to provide a fire resistance rating at least equal to that required of the barrier itself. Based on this, the criteria for cold side temperature would be the same for fire barriers and penetration seals. USAR Section 9B.4.13 specifically identifies the cold side temperature criteria of 325 degrees F above ambient used for penetration seals. Also, the NRC specifically reviewed and accepted in SSER-3, Section 9.5.1.4, RBS test reports for internal conduit seals which used ANI/MAERP criteria (325 degrees Fplus ambient) for cold side temperature criteria prior to the issuance of GL 86-10. Based on the above, NRC acceptance of this 325 degrees F plus ambient criteria is implied. The NRC inspection report states that this matter is with NRR for review. A decision from the NRC is required prior to implementing TSI upgrades. 11 OF 11 T-"wT ---r - p , _.
A'ITACHMENT 2 Resnonse to Unresolved Item 50-458/9204-02 REFERENCE Inspection Report - I.etter from A.B. Beach to J.C. Deddens, dated March 27, 1992. Licensee Event Report No. 91-008 (Supplement 1) - letter from W.H. Odell to U.S. NRC, dated February 18, 1992. Supplement to Response to Violation - letter from W.H. Odell to U.S. NRC, dated February 7,1992. Licensee Event Report No. 91-008 - letter from W.H. Odell to U.S. NRC, dated May 15, 1991. Response to Violation (Rev 2) - letter from W.H. Odell to U.S. NRC, dated December 12, 4 1990. Response to Violation (Rev 1) - Letter from W.H. Odell to U.S. NRC, dated September 18, 1990. Response to Violation - Letter from J.C. Deddens to U.S. NRC, dated May 7,1990. I Notice of Violation - 12tter from S.J. Collins to J.C. Deddens, dated April 6,1990. Enforcement Conference Summary - Letter from S.J. Collins to J.C. Deddens, dated March 26, 1990. Notice of Enforcement Conference - Dated March 6,1990. laspection Report - letter from S.J. Collins to J.C. Deddens, dated February 26,1990. Licensee Event Report No. 89-036 (Rev 1) - letter from J.E. Booker to NRC, dated January 31,1990. Licensee Event Report No. 89-036 - letter from J.E. Booker to NRC, dated November 16, 1989. History of Fire Hmeds Analysis Issues at River Bend Station In response to the violation identified in the Notice of Violation for NRC Inspection Report No. 50-458/90-02, GSU undertook a comprehensive review and documentation of the Fire Hazards Analysis (FHA). In January,150, Design Engineering completed an initial review of the FHA. From January 1 to February 7,1990, Quality Assurance performed a Safety System Functional Inspection (SSFI) as related to the energized valves identified in the violation. The mini-SSFI 1 OF 5
- w. Wup e e r + + ' ' y--
identified several recommendations which were implemented by March 8,1990. A detailed and thorough review of the FHA by an independent contractor was completed in January,1991. During the review of the FHA,106 discrepancies were identified which required further evaluadon. These discrepancies were prioritized for immediate corrective act:cr.s based cr. potential safety significance. Of the 106 discrepancies,23 were identified as potentially affecting Pre-fire Strategies, safe shutdown separation, or the USAR. These 23 items were reviewed and corrective actions were identified by April 15, 1991. Evaluations for the remaining 83 items were completed prior to January 24, 1992. Results of the review of all 106 items are categorized as follows: RESUL*lli OF FHA REVIEW 6 REPORTABLE CONDITIONS (LER 91-008 SUPPLEMENT 1) 9* MISSING OR INCORRECT MANUAL ACTIONS IN PRE-FIRE STRATEGIES 2 ADDITIONS TO DESIGN AND LICENSING BASIS 30 IMPROVED DOCUMENTATION 23 CORRECT INCONSISTENCIES IN DOCUMENTS 36 NO ACTION REQUIRED J
'4 REPORTABLE (LER 91-008 SUPPLEMENT 1)
GSU's Resoonse to Section 5.1.1. " Electrical Separation for Soent Fuel Pool" During the final FHA review, two fire areas were identified where loss of spent- fuel pool cooling (SFC) may occur as a result of a fire. One is Fire Area C-25 (main control room) and the other is a fire area in the fuel building (Fire Area FB-1). Both involve equipment required for SFC only and not equipment required for safe shutdown of the reactor vessel. Each area is discussed individually below. Fire Area C-25: The FHA identifies Fire Area C-25 as an area where alternate shutdown capability is provided. FHA Table 3 (Method IE - Main Control Room Fire Required Items) lists specific spent fuel pool cooling & cleanup (SFC) system and fuel building ventilation (HVF) system equipment as being required and therefore, independent of the fire in the control room. The review of circuits for this equipment determined that the circuits are not electrically independent from the control room and potential fire damage could cause loss of the equipment which may result in loss of spent fuel pool cooling. 2 OF 5
?
GSU took immediate actions and implemented administrative controls to address the concerns with spent fuel pool cooling until permanent corrective actions could be identified and implemented. Engineering analysis determined that the time required for the spent fuel pcol teniper: mire to reach the cooling system design limit of 155.6 degrees F with the existing fuel load conditions prior to RF-4 was approximately 5.3 days.
. Administrative controls were implemented and AOP-0031 (Shutdown From Outside Main Control Room) was revised to provide the necessary manual actions to restore spent fuel pool cooling in case of a fire in the main control room. The entire reactor core was offloaded to the fuel building spent fuel pool for RF-4. With the increased heat load in the fuel pool, the minimum time required.to reach the cooling system design limit of 155.6 degrees F is approximately 4 hours. This is sufficient time to take the manual actions identified in AOP-0031.
The corrective action for addressing the concerns with spent fuel pool cooling is to complete an analysis which demoastrates a design which allows a higher spent fuel pool temperature and still allows sufficient time to restore spent fuel pool cooling. With this revised design bases, the spent fuel pool cooling equipment presently identified as required by the FHA would not be immediately required. This analysis is scheduled to be completed by July 10, 1992. Any modifications found necessary will be scheduled during Fuel Cycle 5. MR 92-0038 has been approved to complete analysis oflong term corrective actions. The administrative controls and manual actions discussed above will be maintained until long term corrective actions are implemented. Fire Area FB-1: Fuel building ventilation dampers 1HVF*AOD037A,102 and 122 are identified in the FHA as equipment required for spent fuel pool cooling. Potential fire damage to electrical cables, located in Fire Area FB-1, for these dampers may cause spurious operation of the dampers which could potentially cat - loss of ventilation to the one remaining spent fuel pool cooling pump and thus loss of spent fuel pool cooling. Previously, the Pre-fire Strategies for this area stated that these dampers must be verified i to be in their proper position and if not, power must be removed so that they remain in the correct position. Removing power to these dampers may not cause the dampers to go to the correct position since a potential hot short could cause the damper to remain in an incorrect position. The immediate corrective action GSU took was to treat the electrical cables as having missing fire barriers and initiate a continuous fire watch per RBS Technical Specification. After the actions identified above for the main control room were implemented and Pre-fire Strategies for Fire Area FB-1 were revised to identify the manual actions required to place the dampers in the correct position, the continuous fire watch was removed. The permanent corrective action for this condition will be addressed with completion of the analysis and any modifications, if required, as discussed above for the main control room. . 3 OF 5
,. GSU's Resoonse to Section 5.1.2. "Iack of Automatic Control of Damoers in Fuel Buildine" This condition is addressed in GSU's response to Section 5.1.1, since it also involves the potential loss of spent fuel pool cooling.
GSU's Resoonse to 5.1.3. " Twenty Foot Seoaration in Rametor Buildine" The FHA identifie: cont:hment unit coolers 1HVR*UCIA (Method 1) and 1HVR*UC1B (Method 2) as equipment required for safe shutdown. These unit coolers are needed for equipment qualification only and are not directly, involved with safe shutdown. The FHA states that the unit coolers are separated from each other by a distance of 24 ft. and a 10 ft. missile barrier which serves as a radiant energy shield. During the final review of the FHA it was found that cables required for operation of the unit coolers did not meet the 20 ft. horizontal separation criteria as stated in 10 CFR 50 Appendix R, Section HI.G. The immediate corrective action taken was to treat the cables as having missing fire barriers and initiate an hourly fire watch per RBS Technical Specification. The permanent corrective action for this condition will be to provide an analysis which demonstrates that the unit coolers are not required for safe shutdown or install noncombustible radiant energy shields to provide separation in accordance with Appendix R, Section III.G.2.f. modification request (MR) 92-0037 has been approved to install the required radiant energy shields if needed. The analysis to demonstrate that the unit coolers are not required and the preparation of MR 92-0037 will proceed concurrently. This approach will allow the analysis to be completed and/or installation of the radiant energy shields to be completed prior to startup i from RF-4 GSU's Resoonse to Section 5.1.4. "I2ck of Fire Hnards Analysis" During the final FHA review, all fire areas except one were found to have an adequate fire hazards analysis. The additional room, AB-070-507, was believed to have been analyzed as part of an adjoining fire area, either AB-2 or AB-7. All of the areas are separated by 3-hour rated walls or floors, however, the cable chase was not assigned a fire area designation. The additional room is a small cable chase located in the northeast corner of D-tunnel. The room contains Division II cable only and is separated from adjacent fire areas by 3-hour barriers on all sides. An investigation of the cables routed through the room showed three Division II cables could cause three Division II motor operated valves, required for Method I shutdown, to become inoperable. The valves are Division H components used in the Method 1 safe shutdown analysis. These valves include two reactor core isolation cooling (RCIC) valves and one spent fuel pool cooling system (SFC) valve. The RCIC valves are used in Method I to maintain reactor vessel level. The SFC valve is used for cooling of the containment fuel pool system. As corrective action, an analysis of all the Division II cables required for safe shutdown routed through room AB-070-507 was conducted. This analysis revealed that the high pressure core spray (HPCS) system would not be affected by a fire in the room. A Pre-fire Strategy was written for room AB-070-507 which informed Operations of the possible spurious operation of 4 OF 5
1 ). the RCIC valves and that the HPCS system is free of fire damage in this room and may be used in lieu of RCIC to maintain reactor pressure vessel (RPV) water level control. For the SFC valve, the Pre-fire Strategy inforr.is Operations that a manual action may be required to maintain { cooling for the containment fuel pools and refers to the necessary proc *re for proper valve , alignment. MR 92-0013 has been initiated to revise the FHA to incorporate the evaluation of this room and will be completed by October 30,1992. Also, Licensing Change Notice (LCN) No. 9A.2-18
- has been initiated to add the room to USAR Tables 9A.2-5 and 9A.2-6.
GSU's Resnonse to Section 5.1.5. "Bresker/ Fuse Coordination Study" During the design and development of the Fire Hazards Analysis proper electrical protection coordination was employed. Standard engineering practice provides that the protective device closest to the load will open first to isolate the load and its cable from the electrical bus, thus allowing continued operation of other loads powered from the same bus. Although not required per Appendix A to BTP APCSB 9.5-1, GSU has decided to perform such an analysis and develop a single source document to enhance control of breaker / fuse coordination for 125 VDC and 120 VAC control circuits. This analysis is scheduled to be completed and design improvements, if required, identified by October 30,1992. GSU's Resoonse to Section 5.1.6. "I_ack of Hinh Impedance Fault Analysis" Multiple high impedance faults involving associated circuits as identified in Generic 1.etter 86-10, Section 5.3.8 have not been specifically analyzed. Although a high impedance fault analysis , or compensatory procedure for operator action are not required per Appendix A to BTP APCSB 9.5-1, GSU has decided to prepare a procedure which provides information necessary to recover from a multiple high impedance fault event during a fire. This procedure will be implemented, with training completed, prior to startup from RF-4. l e 5OF5
l, ATTACHMENT 3 GSU's Pame tolection 5.2. "Mananement Oversieht of the Fire Protection Area" The fire protection program at RBS is an integrated effort involving many departments. l However, overall responsibility is maintained by the Sr. Vice President - River Bend Nuclear Group, Mr. J. C. Doddens. Through his management, fire protection activities are formulated. Implementation by the individual departments is based on organizational responsibilities and specialized expertise. The coordination of these, activities is achieved through an efficient chain of communication. (See Figure 3-1) i Currently, GSU is participating in a NUMARC ad hoc committee on 'Ihermo-lag in an effort j to achieve a salient solution to the Thermo-lag issue. Also, GSU has incorporated the assistance _ i of its RBS architect and engineer, Stone & Webster Engineering Corporation, to resolve questions concerning the fire protection program. As shown through their efforts to identify and correct discrepancies in the FHA, inspect fire barriers as well as test materials and configurations, and consistently disclose findings to the NRC, GSU management's role in the RBS fire protection program has been and still remains very proactive. It is this proactive effort which will allow the correction of all known deficiencies by January,1995. I a 1 OF 2
_. . . . _ _ _ ._ _ ... _ . _ ~ _ _ . _ . _ _ . . _ . . . _ . . _ . . _ _ _ _ _ . . . . _ . . . m.. . _ - . . . .~ . . . . _ . _ Implementation . Sr. Vice President
< > Corporate Risk ""r--e. e A
if Plant if { nn- Gen. Manager l Engr. and Admin. i l 3 i l i t Administrative Plant Equipment 4
; Plant Doolgn !
Cormols operations Safe ' Maintenance ! Design undulcations Controlof . 1 shuksown Plant Plant ' y Combustibles N Fee Hazards : Design Design Anefysis ! Q Controlof Plant Preventive Engineered o riammobies operations Pre-Fire Mairnenance Features Stndegles
$ i ignman sources l
unknenance Assenes== Manuel i Fire Fl@ ting i t t i i I i
-...--..-.----**-----*-- ---+---------'-"-"***"-"*****" >
s i Coordination i L Fire Protection '
< Fke Protocelon w -> .
Enskiner i
~
_ . , _ _ _ - _ . _ __ __.___ _ _______._ _ _ _ _ _ _ _.___ _ _____________________________.._______m___ . _ _ _ _ _ _ _ _ _ _ - - _ ~ < . - - _ _ _ _ _ . _ _ _ _ _ _
A'ITACRMENT 4 i Penetration Seals Prorrem REFERENCES Licensee Event Report No. 89 010 (Rev 3) - letter from W.H. Odell to U.S. NRC, dated July 31,1990 Licensee Event Report No. 89-010 (Rev 2) - Letter from J.E. Booker to U.S. NRC, dated August 30,1989 - Licensee Event Report No. 89-010 (Rev 1) - Letter from J.E. Booker to U.S. NRC, dated June 9, 1989 Licensee Event Report No. 89-010 - 12tter from J.E. Booker to U.S. NRC, dated April 17, 1989 History of Penetration Seals Program at River Bend Station During routine sampling inspections of penetration seals, GSU identified several penetrations which were unsealed. An investigation of the open penetrations in 1989 found that conduits lacking internal seals consisted of scheduled and unscheduled conduits. Unscheduled conduits included fire detection, lighting, security and communications conduits. A review of the penetration seal data bases indicated the above described internal seals were never installed. Therefore, it is concluded they were never sealed by the subvendor responsible for sealing e penetrations during construction. Corrective Actions Taken by GSU GSU senior management review of the penetration seal program resulted in the formation of a Fire Protection Task Force consisting of Engineering, Projects, and Quality Control personnel to develop a corrective action program. Part of their task was to develop a detailed program for the complete inspection of all fire barriers including penetration seals and internal conduit seals for type of seal and adequacy of installation, and to rework or disposition the deficient penetration seals as appropriate. Inspection and rework, if required, of structural steel fireproofing was also included as part of the task force scope. A 100% inspection program of the approximately 3000 penetration seals began in February,1991 and is currently in progress. Identified construction deficiencies and degraded material are being reworked on an ongoing basis to ensure that protection remains in place. Apparently unqualified configurations will be addressed through engineering evaluation or testing. Corrective actions are scheduled to be completed by January,1994. Periodie working level meetings are held between Engineering, Quality Control and Maintenance to discuss progress and problems.. Senior management awareness of the status of the penetration seal program is maintained through monthly status reports and presentations given to the Nuclear Review Board and in senior management staff meetings. Through these means GSU management is able to continually assess progress. 1 OF 1
1 . A'ITACHMENT 5 Prefire Strategies The Prefire Strategies are a tool for operator and fire brigade use in the event of a fire, providing information and recommendations for actions. They are not a source of direction for required operator actions. In fact, the note on the first page of Section 9, " Evaluation of Fire and Shutdown," of the Prefire Strategies states:
"It is expected that Normal, Abnormal and, Emergency procedures be followed for plant shutdown / operations as required. Prefire strategies should not be misinterpreted to be the required method of shutdown..."
This clarification along with the extensive fire protection training operators receive would prevent any misinterpretation of the Prefire Strategies intended application. As an enhancement to the fire protection program at RBS, Section 9 will be removed from the Prefire Strategies and developed into an Abnormal Operating Procedure (AOP). This new AOP will be broken down by fire area for easy reference. The scheduled completion date is August, 1992. J s O l OF I -
ATTACHMENT 6 Information Notice 92-18. " Potential for Loss of Remote Shutdown Caoability Durine a Control Room Fire" References Licensee Event Report No. 92-007 - Letter from W.H. Odell to U.S. NRC, dated April 27, 1992 NRC Information Notice 92-18: Potential for Loss of Remote Shutdown Capability During a Control Room Fire" - 12tter from C.E. Ross to GSU, dated February 28,1992 On March 26, 1992, during GSU's review of NRC Information Notice 92-18, " Potential for Loss of Remote Shutdown Capability During a Control Room Fire," GSU identified a design deficiency in the control circuits for motor operated valves (MOVs) required for alternate shutdown of the plant. These control circuits could operate spuriously during a control room fire. If a fire in the control room forces reactor operators to evacuate the control room, these MOVs can be operated from the remote shutdown panel. However, energized short circuits (" hot shorts") combined with the absence of thermal overload protection, could permit bypassing of the torque switch and limit switches, and thus cause valve damage before operators are able to transfer control of the valves to the remote shutdown panel. This design is contrary to the i River Bend Station Fire Hazards Analysis and constitutes a condition outside the design basis. Therefore, a report, LER 92-007, dated April 27, 1992, was submitted pursuant to , l 10CFR50.73(a)(2)(ii)(B). The control circuit design deficiency identified by Information Notice 92-18 is an emerging generic issue in the nuclear industry. A contributing factor was the lack of thermal overload protection as specified in Regulatory Guide 1.106. Typical control circuits are designed with j thermal overload protection to protect the motor operator. The special application of a motor operated valve required for alternate shutdown combined with the Regulatory Guide 1.106 l design to bypass the thermal overloads resulted in a design deficiency. l l The control circuitry for the 50 affected MOVs will be reworked or otherwise dispositioned by the end of RF-4 so that the limit switches and torque switches cannot be bypassed by hot shorts. l The core damage frequency due to hot shorts generated by fires in main control room (MCR) i panels is not an insignificant contributor to the total core damage frequency of RBS. However, l the current probabalistic risk assessment results (rev. 0) are conservative. In addition, this contribution to the total core damage frequency is not as significant as the contribution due to ~ fires in MCR panels (without considering the hot short phenomena) or that due to internal events. Pursuant to Generic Letter 88-20, Supplement 4, RBS will be performing the Individual i Plant Examination (IPE) for External Events which will include a detailed fire risk analysis. This issue of hot shorts in MCR panels will be addressed in that analysis in a more detailed 1 manner. It is expected that the results of that analysis will identify the true importance of this ' issue in relation to overall fire risk. I l 1 l l , 1 OF 1 - j I
, ,_- - - _ . _ . . . ~, , _ _ . . . . _. . - __ -- _ _ _ _ _ _ . _ _ _ _ _ _ _ .
\/
t' A 8 May 1992 AUBIN FELDMAN. P.E. Presroent U S Nuclear Regulatory Commission Nuclear Regulatory Comnussion 11555 Rockville Pike Rockville, Maryland 20852 Attention: Mr. Ashok C. Thadani, Director ' Division of Systems Technology Office of Nuclear Reactor Regulation
Dear Mr. Thadani:
The NRC has previously received communications from Thermal Science, Inc. relating to the proposed generic letter circulated by the NRC in February 1992. The purpose of this letter is to provide you with additionalinformation on TSI's current activities. Thermal Science, Inc. has engaged Omega Point Laboratories in San Antonio, Texas to , conduct a series of fire resistive tests on 36" wide open top, ladder back cable trays and l small diameter conduits (c. 3/4"). Both one and three hour fire resistive tests are planned. The tests will be conducted in accordance with the applicable prerequisites . of: l Test Plan No. 31192-A Engineering Test Plan to Perform One Hour Fire Endurane Tests Followed by Water Hose Stream Tests On a 36 Inch Wide Steel Open Top, I. adder Back Cable Tray (With One Layer Of Generic Cables) and Steel Conduit Test Articles Protected With The THERMO-LAG 330 Fire Barrier System ANI's Bulletin B.7.2,11/87 "ANI/MAERP RA Guidelines For Fire Stop and Wrap , Systems At Nuclear Facilities - Attachment B, Standard Fire Endurance Test l Method To Qualify A Protective Envelope For Class IEEE Electrical Circuits", Revision I, dated November 1987, as applicable U S Nuclear Regulatory Commission's Generic Letter 86-10 To All Power Reactor Licensees And Applicants For Power Reactor Licenses, dated 24 April 1986 " Implementation Of Fire Protection Requirements", as applicable ASTM E119 (88) " Standard Methods of Fire Tests of Building Construction and Materials", as applicable kCh I h THERMAL SCIENCE, INC.
- 220 SSENS DR.
- ST. LOUIS, MO 63026 *(314)349 1233
{> Telex: Domestic 44-2384
- Overseas 209901
- Telecopier (314) 3491207 7
/'
e Cs 8 May 1992 Mr. Ashok C. Thadani U S Nuclear Regulatory Commission Page 2 This test program is currently underway, under the total control of Omega Point Laboratories which includes:
- The construction of the test articles,
*The installation'of the fire barrier' system materials,
- Test article instrumentation,
*The performance of the fire endurance and water hose stream tests. *The performance electrical circuitry integrity monitoring,
- All pertinent Quality Control Documentation,
- Publishing the test report An "Ad Hoc" one hour fire resistive test has just been completed at the facilities of Omega Point laboratories in San Antonio Texas. It was comprised of the following:
+36 inch wide open top ladder back cable tray l
- Loaded with one layer of generic cables
- Power, instrumentation and control cables were employed ,
*Chromel Alumel thermocouples were attached to surface of selected cables
- Selected cables were instrumented for cable to ground monitoring
*The fire simulation was comprised of ASTM E 119 type environment *No water stream tests were performed The purpose of the test was to establish the feasibility of key design features such as:
- Gap - seam width definition between adjoining sections of THERMO-LAG 330 Prefabricated Panels
- Scoring techniques used in shaping the Prefabncated Panels
*Prebuttering of adjoining surfaces of sections of THERMO-LAG 330 Prefabricated Panels used in construction of cable tray wraps 1
s et e
Mr. Ashok C. Thadani 8 May 1992 U S Nuclear Regulatory Commission Page3
- Alternate method of structural enhancement of thermo-structural integrity of joints when the gap width exceeds the maximum established limits such as:
*** THERMO-LAG Stress Skin Type 330-69 over the joint including THERMO-LAG 330 Subliming Trowel Grade Material *** Stainless steel tie wires spaced at specified distances *** Stainless steel band spacing The results of this Ad Hoc test established the feasibility of the following features of an acceptable One Hour Fire Resistive THERMO LAG 330 Enclosure for 36 inch wide steel open top, ladder back, cable trays which r.re lightly loaded with generic cable THERMO-LAG 330 Prefabricated Panel Thickness: 0.625"i 0.125 ;
Stainless Steel Banding Material (0.5" x 0.020" Min) Spacing 8 inches Maximum gap width with Prebuttering : 0.030 inches j Gaps having a width in excess of 0.030 inches require thermo-structural enhancement as follows:
*
- Either:
THERMO-LAG Stress Skin Type 330-69 with a 0.125 layer of THERMO-LAG 330-1 Subliming Trowel Grade Material wrapped over the entire , circumference of the wide gap , covering the tray at least 5 inches on both sides ! of the gap, having a overlap heki in place by stainless steel bands, with its seam fastened by spacinad mechanical fasteners. on Stainless Steel Tie Wires (0.032" minimum) placed at 6 inch intervals on ' longitudinal seams and 2 inches apart on vertical seams. 4 k e 9
9 Mr. Ashok C. Thadani 8 May 1992 U S Nuclear Regulatory Commission Page 4 Due to the "information only" nature of this test, the Laboratory only provided testing services without quality control surveillance, and a formal report is not planned. The formal test is targeted to be conducted in June utilizing the above criteria. It will be fully documented by the, test laboratory. Successful completion of this testing effort will yield a very detailed installation procedure using the results of the construction methods in the test program. It is expected to supersede previous TSI information on this subject. We will advise you as soon as the testing has been satisfactorily completed. urs tmly,
. w-Rubin Feldman President RF/ meg 1
l l
)
l l
^ - - -----A-_-_ _ __ _ , _ _ , . _ _ _ _ , , . ,
4 P l
.* May 13, 1992 1
Mr. Alex Marion l Manaaer, Technical Division Nuclear Management and Resources Council l 1776 Eye Street, N.W., Suite 300 Washington, D.C. 20006-2496 l
Dear Mr. Marion:
Our March 12, 1992, letter transmitted our intent to provide you with more i detailed information to facilitate your review of the proposed generic letter ! on Thermo-Lag fire barriers. Our review team has completed a technical report which documents its review and the technical bases for its findings and recommendations. This letter formally transmits the enclosed report, Final Report-Special Review Team for the Review of Thermo-Lag Fire Barrier Performance, dated April 17,1992,.previously hand carried to you. After you have had an opportunity to review this report, a follow-up meeting should be arranged within 30 days to discuss the draft generic letter, your previous comments, and any additional industry questions. Please forward any further comments on the draft generic letter to us prior to this meeting to allow a thorough review by our staff. Please contact Ralph Architzel at (301) 504-2804 within 30 days to arrange a meeting with our staff on this issue. We appreciate NUMARC's contribution to the development of technically sound generic communication which can provide a timely resolution to our concerns. . h@ GNED BY A.C.THADANI Ashok C. Thadani, Director Division of Systems Technology I Office of Nuclear Reactor Regulation
Enclosure:
cc w/o enc 1: ; As stated T. Murley . DISTRIBUTIONw/oen$1oNrE TSI File i Docket File RArchitzel CMcCracken ; AThadani ; GHolahan ; ! KWalker *- l EPawlik IMoghissi I D,l SPtB PLB: DST *- SPLB: DST
- SPLB: DST SPLB T IMoghissi:sb Architzel McCracken GHolohan AThadani 1 5/ /92 5/ /92 5/ /92 5/ /92 5/ 92 ,
/JJ -[
[G:MARIFELD.REA] . g
,y , l s
- see prev ous concurrence . . .. , ,.
920 CF SU 325\ k13 'J'
-d / / .~ p[ " " - " " b" l i .-}}