MONTHYEARML20217F9701999-10-14014 October 1999 Proposed Tech Specs,Incorporating ARC for Axial Primary Water Stress Corrosion Cracking at Dented Tube Support Plate Intersections ML20217E4301999-10-12012 October 1999 Proposed Tech Specs,Revising Requirements for Containment Penetrations During Refueling Operations ML20211M7341999-08-30030 August 1999 Marked-up & Revised TS Pages,Providing Alternative to Requirement of Actually Measuring Response Times ML20211K1721999-08-30030 August 1999 Proposed Tech Specs,Providing Clarification to Current TS Requirements for Containment Isolation Valves ML20209B7731999-06-30030 June 1999 Proposed Tech Specs Updating Requirmements for RCS Leakage Detection & RCS Operational Leakage Specifications to Be Consistent with NUREG-1431 ML20196F2211999-06-24024 June 1999 Proposed Tech Specs Pages for Amend to Licenses DPR-77 & DPR-79,allowing Use of Fully Qualified & Tested Spare Inverter in Place of Any of Eight Required Inverters ML20196G4701999-06-24024 June 1999 Proposed Tech Specs Pages Re Amends to Licenses DPR-77 & DPR-79,revising TS to Be Consistent with Rev to ISTS Presently Submitted to NEI TSTF for Submittal as Rev to NUREG-1431 ML20196G7961999-06-22022 June 1999 Proposed Tech Specs Bases,Clarifying Proper Application of TS Requirements for Power Distribution Systems & Functions That Inverters Provide to Maintain Operability & Providing Updated Info on Cold Leg Injection Accumulators ML20195E9841999-06-0707 June 1999 Proposed Tech Specs,Increasing Max Allowed Specific Activity of Primary Coolant from 0.35 Microcuries/Gram Dose Equivalent I-131 to 1.0 Microcuries/Gram Dose Equivalent I-131 for Plant Cycle 10 (U2C10) Core ML20206E1391999-04-29029 April 1999 Proposed Tech Spec Change 99-03, Main Control Room Emergency Ventilation Sys Versus Radiation Monitors. Changes Add LCOs 3.3.3.1 & 3.7.7 to Address Inoperability of Radiation Monitoring CREVS & NUREG-1431 Recommendations ML20206E1611999-04-29029 April 1999 Proposed Tech Spec Change 99-04, Auxiliary Suction Pressure Low Surveillance Frequency Rev. Change Deletes Surveillance ML20204H4081999-03-19019 March 1999 Proposed Tech Specs,Relocating TS 3.8.3.1,3.8.3.2,3.8.3.3 & Associated Bases Associated with Electrical Equipment Protective Devices to Technical Requirements Manual ML20207D6011999-02-26026 February 1999 Proposed Tech Specs Relocating TS 3.7.6, Flood Protection Plan & Associated Bases from TS to Plant TRM ML20207D6331999-02-26026 February 1999 Proposed Tech Specs Providing for Consistency When Exiting Action Statements Associated with EDG Sets ML20206S0131999-01-15015 January 1999 Proposed Tech Specs 3.3.3.3, Seismic Instrumentation & Associated Bases,Relocated to Plant Technical Requirements Manual ML20199K6001999-01-15015 January 1999 Proposed Tech Specs Adding New Action Statement to 3.1.3.2 That Would Eliminate Need to Enter TS 3.0.3 Whenever Two or More Individual RPIs Per Bank May Be Inoperable,While Maintaining Appropriate Overall Level of Protection ML20195H6111998-11-16016 November 1998 Proposed Tech Specs Revising EDG SRs by Adding Note That Allows SR to Be Performed in Modes 1,2,3 or 4 If Associated Components Are Already OOS for Testing or Maint & Removing SR Verifying Certain Lockout Features Prevent EDG Starting ML20154H7251998-10-0808 October 1998 Proposed Tech Specs Pages,Supplementing Proposed TS Change 96-08,rev 1 to Add CRMP to Administrative Controls Section & Bases of TS ML20238F1091998-08-27027 August 1998 Proposed Tech Specs Providing for Insertion of Limited Number of Lead Test Assemblies,Beginning W/Unit 2 Operating Cycle 10 Core ML20238F3001998-08-27027 August 1998 Proposed Tech Specs Replacing 72 H AOT of TS 3.8.1.1,Action b,w/7 Day AOT Requirement for Inoperability of One EDG or One Train of EDGs ML20236G5961998-06-29029 June 1998 Proposed Tech Specs Typed Pages for TS Change 95-19, Section 6 - Administrative Controls Deletions ML20249C6371998-06-26026 June 1998 Proposed Tech Specs Lowering Specific Activity of Primary Coolant from 1.0 Uci/G Dose Equivalent I-131 to 0.35 Uci/G Dose Equivalent I-131,as Provided in GL 95-05 ML20248F0051998-05-28028 May 1998 Proposed Tech Specs for Section 6, Administrative Controls Deletions ML20217N3511998-04-30030 April 1998 Proposed Tech Specs Pages,Modifying Surveillance Requirement 4.4.3.2.1.b to Change Mode Requirement to Allow PORV Stroke Testing in Modes 3,4 & 5 W/Steam Bubble in Pressurizer Rather than Only in Mode 4 ML20203J1681998-02-25025 February 1998 Proposed Tech Specs Pages,Revising EDG Surveillance Requirements to Delete Requirement for 18-month Insp IAW Procedures Prepared in Conjunction W/Vendor Recommendations & Modify SRs Associated W/Verifying Capability of DGs ML20202J7601998-02-13013 February 1998 Proposed Tech Specs Section 3.7.9 Re Relocation of Snubber Requirements ML20202J7141998-02-13013 February 1998 Proposed Tech Specs Adding New LCO That Addresses Requirements for Main Feedwater Isolation,Regulating & Bypass Valves ML20202J6961998-02-13013 February 1998 Proposed Tech Specs Incorporating MSIV Requirements to Be Consistent W/Std TS (NUREG-1431) ML20198T4311998-01-21021 January 1998 Proposed Tech Specs Re New Position Title & Update of Description of Nuclear Organization ML20199K4571997-11-21021 November 1997 Proposed Tech Specs Adding one-time Allowance Through Operating Cycle 9 to Surveillance Requirement 4.4.3.2.1.b to Perform Stroke Testing of PORVs in Mode 5 Rather than Mode 4,as Currently Required ML20211A3191997-09-17017 September 1997 Proposed Tech Specs Re Pressure Differential Surveillance Requirements for Containment Spray Pumps ML20137T0871997-04-0909 April 1997 Proposed Tech Specs Re Elimination of Cycle 8 Limitation for SG Alternate Plugging Criteria ML20137M8581997-04-0101 April 1997 Proposed Tech Specs 2.1 Re Safety Limits & TS 3/4.2 Re Power Distribution Limits ML20137C8421997-03-19019 March 1997 Proposed Tech Specs Re Conversion from Westinghouse Electric Corp Fuel to Framatome Cogema Fuel ML20136J0381997-03-13013 March 1997 Proposed Tech Specs Section 5.6.1.2,revising Enrichment of Fuel for New Fuel Pit Storage Racks ML20134P8631997-02-14014 February 1997 Proposed Tech Specs Requesting Discretionary Enforcement for 48 Hours Which Is in Addition to 72 Hours Allowed Outage Time Provided by TS Action 3.8.1.1.b ML20134K9981997-02-0707 February 1997 Proposed Tech Specs Revising TS Change Request 96-01, Conversion from W Electric Corp Fuel to Framatome Cogema Fuel (MARK-BW-17), to Ensure That Core Analysis Computer Code Output Actions Are Consistent W/Hot Channel Factor SRs ML20134L9261996-11-0808 November 1996 Proposed Tech Specs Re Placing of Channel in Trip for Reactor Trip & Engineered Safety Feature Instrumentation Sys Solely to Perform Testing as Not Requiring Channel to Be Declared Inoperable ML20129D2661996-10-18018 October 1996 Proposed Tech Specs,Removing Existing Footnotes That Limit Application of Apc for Plant S/G Tubes to Cycle 8 Operation for Both Units ML20129G7301996-09-26026 September 1996 Proposed Tech Specs 3/4.3.3 Re Fire Detection instrumentation,3/4.7.11 Re Fire Suppression Systems & 3/4.7.12 Re Fire Protection Penetrations ML20113G2691996-09-20020 September 1996 Proposed Tech Specs Change 96-09, Clarification of Work Shift Durations for Overtime Limits ML20117J3391996-08-28028 August 1996 Proposed Tech Specs Revising Psv & MSSV Setpoint Tolerance from Plus or Minus 1% to Plus or Minus 3% ML20117D1651996-08-22022 August 1996 Proposed Tech Specs of SQN Units 1 & 2,deleting Table 4.8.1, DG Reliability, & Revising Section 3.8.1 to Allow Once Per 18 month,7 Day AOT for EDGs ML20117D3121996-08-22022 August 1996 Proposed Tech Specs,Lowering Minimum TS ice-basket Weight of 1,155 Lbs to 1,071 Lbs.Reduced Overall Ice Weight from 2,245,320 Lbs to 2,082,024 Lbs ML20117D3141996-08-21021 August 1996 Proposed TS 3.7.1.3 Re Condensate Storage Tank ML20117D3341996-08-21021 August 1996 Proposed Tech Specs Re Deletion of Surveillance Requirement 4.8.1.1.1.b ML20112H0431996-06-0707 June 1996 Proposed Tech Specs,Revising Section 6, Administrative Controls, to Be More Closely Aligned W/Requirements of STSs ML20101N7071996-04-0404 April 1996 Proposed Tech Specs,Allowing Conversion from Westinghouse Fuel to Fuel Provided by Framatome Cogema Fuels ML20096B3761996-01-0404 January 1996 Proposed Tech Specs Extending Radiation Monitoring Instrumentation Surveillance Period Per GL 93-05 ML20096C2481996-01-0303 January 1996 Proposed Tech Specs,Revising Bases Section 3/4.7.1.2 to Indicate Current Operational Functions of turbine-driven AFW Level Control Valves Modified During Unit 1 Cycle 7 Refueling Outage 1999-08-30
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20217F9701999-10-14014 October 1999 Proposed Tech Specs,Incorporating ARC for Axial Primary Water Stress Corrosion Cracking at Dented Tube Support Plate Intersections ML20217E4301999-10-12012 October 1999 Proposed Tech Specs,Revising Requirements for Containment Penetrations During Refueling Operations ML20211M7341999-08-30030 August 1999 Marked-up & Revised TS Pages,Providing Alternative to Requirement of Actually Measuring Response Times ML20211K1721999-08-30030 August 1999 Proposed Tech Specs,Providing Clarification to Current TS Requirements for Containment Isolation Valves ML20209B7731999-06-30030 June 1999 Proposed Tech Specs Updating Requirmements for RCS Leakage Detection & RCS Operational Leakage Specifications to Be Consistent with NUREG-1431 ML20196F2211999-06-24024 June 1999 Proposed Tech Specs Pages for Amend to Licenses DPR-77 & DPR-79,allowing Use of Fully Qualified & Tested Spare Inverter in Place of Any of Eight Required Inverters ML20196G4701999-06-24024 June 1999 Proposed Tech Specs Pages Re Amends to Licenses DPR-77 & DPR-79,revising TS to Be Consistent with Rev to ISTS Presently Submitted to NEI TSTF for Submittal as Rev to NUREG-1431 ML20196G7961999-06-22022 June 1999 Proposed Tech Specs Bases,Clarifying Proper Application of TS Requirements for Power Distribution Systems & Functions That Inverters Provide to Maintain Operability & Providing Updated Info on Cold Leg Injection Accumulators ML20196G8071999-06-22022 June 1999 Revs to Technical Requirements Manual ML20195E9841999-06-0707 June 1999 Proposed Tech Specs,Increasing Max Allowed Specific Activity of Primary Coolant from 0.35 Microcuries/Gram Dose Equivalent I-131 to 1.0 Microcuries/Gram Dose Equivalent I-131 for Plant Cycle 10 (U2C10) Core ML20206E1611999-04-29029 April 1999 Proposed Tech Spec Change 99-04, Auxiliary Suction Pressure Low Surveillance Frequency Rev. Change Deletes Surveillance ML20206E1391999-04-29029 April 1999 Proposed Tech Spec Change 99-03, Main Control Room Emergency Ventilation Sys Versus Radiation Monitors. Changes Add LCOs 3.3.3.1 & 3.7.7 to Address Inoperability of Radiation Monitoring CREVS & NUREG-1431 Recommendations ML20204E8501999-03-21021 March 1999 Plant,Four Yr Simulator Test Rept for Period Ending 990321 ML20204H4081999-03-19019 March 1999 Proposed Tech Specs,Relocating TS 3.8.3.1,3.8.3.2,3.8.3.3 & Associated Bases Associated with Electrical Equipment Protective Devices to Technical Requirements Manual ML20207D6331999-02-26026 February 1999 Proposed Tech Specs Providing for Consistency When Exiting Action Statements Associated with EDG Sets ML20207D6011999-02-26026 February 1999 Proposed Tech Specs Relocating TS 3.7.6, Flood Protection Plan & Associated Bases from TS to Plant TRM ML20206S0131999-01-15015 January 1999 Proposed Tech Specs 3.3.3.3, Seismic Instrumentation & Associated Bases,Relocated to Plant Technical Requirements Manual ML20199K6001999-01-15015 January 1999 Proposed Tech Specs Adding New Action Statement to 3.1.3.2 That Would Eliminate Need to Enter TS 3.0.3 Whenever Two or More Individual RPIs Per Bank May Be Inoperable,While Maintaining Appropriate Overall Level of Protection ML20195H6111998-11-16016 November 1998 Proposed Tech Specs Revising EDG SRs by Adding Note That Allows SR to Be Performed in Modes 1,2,3 or 4 If Associated Components Are Already OOS for Testing or Maint & Removing SR Verifying Certain Lockout Features Prevent EDG Starting ML20154H7251998-10-0808 October 1998 Proposed Tech Specs Pages,Supplementing Proposed TS Change 96-08,rev 1 to Add CRMP to Administrative Controls Section & Bases of TS ML20238F1091998-08-27027 August 1998 Proposed Tech Specs Providing for Insertion of Limited Number of Lead Test Assemblies,Beginning W/Unit 2 Operating Cycle 10 Core ML20238F3001998-08-27027 August 1998 Proposed Tech Specs Replacing 72 H AOT of TS 3.8.1.1,Action b,w/7 Day AOT Requirement for Inoperability of One EDG or One Train of EDGs ML20209J1631998-08-0707 August 1998 Rev 41 to Sequoyah Nuclear Plant Odcm ML20236G5961998-06-29029 June 1998 Proposed Tech Specs Typed Pages for TS Change 95-19, Section 6 - Administrative Controls Deletions ML20249C6371998-06-26026 June 1998 Proposed Tech Specs Lowering Specific Activity of Primary Coolant from 1.0 Uci/G Dose Equivalent I-131 to 0.35 Uci/G Dose Equivalent I-131,as Provided in GL 95-05 ML20248F0051998-05-28028 May 1998 Proposed Tech Specs for Section 6, Administrative Controls Deletions ML20217N3511998-04-30030 April 1998 Proposed Tech Specs Pages,Modifying Surveillance Requirement 4.4.3.2.1.b to Change Mode Requirement to Allow PORV Stroke Testing in Modes 3,4 & 5 W/Steam Bubble in Pressurizer Rather than Only in Mode 4 ML20203J1681998-02-25025 February 1998 Proposed Tech Specs Pages,Revising EDG Surveillance Requirements to Delete Requirement for 18-month Insp IAW Procedures Prepared in Conjunction W/Vendor Recommendations & Modify SRs Associated W/Verifying Capability of DGs ML20202J7651998-02-13013 February 1998 Technical Requirements Manual ML20202J7141998-02-13013 February 1998 Proposed Tech Specs Adding New LCO That Addresses Requirements for Main Feedwater Isolation,Regulating & Bypass Valves ML20202J6961998-02-13013 February 1998 Proposed Tech Specs Incorporating MSIV Requirements to Be Consistent W/Std TS (NUREG-1431) ML20202J7601998-02-13013 February 1998 Proposed Tech Specs Section 3.7.9 Re Relocation of Snubber Requirements ML20198T4311998-01-21021 January 1998 Proposed Tech Specs Re New Position Title & Update of Description of Nuclear Organization ML20199F8231997-11-30030 November 1997 Cycle 9 Restart Physics Test Summary, for 971011-971130 ML20199K4571997-11-21021 November 1997 Proposed Tech Specs Adding one-time Allowance Through Operating Cycle 9 to Surveillance Requirement 4.4.3.2.1.b to Perform Stroke Testing of PORVs in Mode 5 Rather than Mode 4,as Currently Required ML20211A3191997-09-17017 September 1997 Proposed Tech Specs Re Pressure Differential Surveillance Requirements for Containment Spray Pumps ML20203B9731997-08-0505 August 1997 Rev 1 to RD-466, Test & Calculated Results Pressure Locking ML20217J5581997-07-31031 July 1997 Cycle Restart Physics Test Summary, for Jul 1997 ML20210J1671997-04-30030 April 1997 Snp Unit 1 Cycle 8 Refueling Outage Mar-Apr 1997,Results of SG Tube ISI as Required by TS Section 4.4.5.5.b & Results of Alternate Plugging Criteria Implementation as Required by Commitment from TS License Condition 2C(9)(d) ML20137T0871997-04-0909 April 1997 Proposed Tech Specs Re Elimination of Cycle 8 Limitation for SG Alternate Plugging Criteria ML20137M8581997-04-0101 April 1997 Proposed Tech Specs 2.1 Re Safety Limits & TS 3/4.2 Re Power Distribution Limits ML20137C8421997-03-19019 March 1997 Proposed Tech Specs Re Conversion from Westinghouse Electric Corp Fuel to Framatome Cogema Fuel ML20136J0381997-03-13013 March 1997 Proposed Tech Specs Section 5.6.1.2,revising Enrichment of Fuel for New Fuel Pit Storage Racks ML20134P8631997-02-14014 February 1997 Proposed Tech Specs Requesting Discretionary Enforcement for 48 Hours Which Is in Addition to 72 Hours Allowed Outage Time Provided by TS Action 3.8.1.1.b ML20134K9981997-02-0707 February 1997 Proposed Tech Specs Revising TS Change Request 96-01, Conversion from W Electric Corp Fuel to Framatome Cogema Fuel (MARK-BW-17), to Ensure That Core Analysis Computer Code Output Actions Are Consistent W/Hot Channel Factor SRs ML20138F2581997-01-17017 January 1997 Rev 39 to Sequoyah Nuclear Plant Odcm ML20134L9261996-11-0808 November 1996 Proposed Tech Specs Re Placing of Channel in Trip for Reactor Trip & Engineered Safety Feature Instrumentation Sys Solely to Perform Testing as Not Requiring Channel to Be Declared Inoperable ML20129D2661996-10-18018 October 1996 Proposed Tech Specs,Removing Existing Footnotes That Limit Application of Apc for Plant S/G Tubes to Cycle 8 Operation for Both Units ML20129G7301996-09-26026 September 1996 Proposed Tech Specs 3/4.3.3 Re Fire Detection instrumentation,3/4.7.11 Re Fire Suppression Systems & 3/4.7.12 Re Fire Protection Penetrations ML20134J9991996-09-23023 September 1996 Fuel Assembly Insp Program 1999-08-30
[Table view] |
Text
. - -.. ..- .. . . . . . . . - - ..- . . .. ...
. . {
i ENCLOSURE 1 PROPOSED TECHNICAL SPECIFICATION (TS) CHANGE SEQUOYAH NUCLEAR PLANT (SON) UNITS 1 AND 2 DOCKET NOS. 50-327 AND 50-328 1
(TVA-SON-TS-95-20) !
LIST OF AFFECTED PAGES 4 Unit 1 3/4 6-16a Unit 2 i 3/4 6-16a i
i F
9512130168 951208 PDR ADOCK 05000327
.P-, _._ ,PDR
.]
CONTAINMENT SYSTEMS SURVEILLANCE REQUIREMENTS (Continued)
~ b.
By verifying, that on recirculation flow, each pump develops a differential pressure of greater than or equal to 143 psid at greater than or equal to 4750 gpm when tested pursuant to. R84'-
Specification 4.0.5. I
- c. At least once per 18 months during shutdown, by: ,,
_ 1.- Verifying that each automatic valve in the flow path actuates I to its correct position on a Containment Pressure High-High test signal.
- 2. Verifying that each spray pump starts automatically on a 1
/c l Containment Pressure High-High test signal.
- d. At least once Myears by performing an air or smoke flow test through each spray header and verifying each spray nozzle is-unobstructed.
4.6.2.1.2 Each RHR spray train shall be demonstrated OPERABLE:
J
- a. Per surveillance requirements 4.5.2.b.2 and 4.5.2.f.3; '\
- b. At least once p years by performing an air or smoke flow test through each spray header and verifying each spray nozzle is unobstructed. ~'
J
-)
l 1
SEQUOYAH - UNIT 1 3/4 6-16a Amendment No. )////P f
80 i August 16, 1988 l
j CONTAI MENT SYSTEMS l
SURVEILLANCE REQUIREMENTS (Continued) n
- b. By verifying that on recirculation flow, each pump develops a l differential pressure of greater than or equal to 143 psid at
' greater than or equal to 4750 gpm when tested pursuant to R71 Specification 4.0.5. ,
I
- c. At least once per 18 months during shutdown, by- 1 1' i
- 1. Verifying that each automatic valve in the flow path actuates
- to its correct position on a Containment Pressure High-High
! test signal.
- 2. Verifying that each spray pump starts automatically on a
/0 Containment Pressure High-High test signal.
- 7 L d. Atleastonceper@yearsbyperforminganairorsmokeflowtest through each spray header and verifying each spray nozzle is unobstructed.
4.6.2.1.2 Each RHR Spray train shall be demonstrated OPERABLE:
- a. Per surveillance requirements 4.5.2.b.2 and 4.5.2.f.3;
/0 -
A R61
- b. At least once per.Eyears by performing an air or smoke flow test _ through each spray header and verifying each spray nozzle is unobstructed.
SEQUOYAH - UNIT 2 3/4 6-16a Amendment No. /g 71 August 16, 1988
+. am, . s .a s a . . ~ . - - <e.a=
_ .s a --;. ..- ~rus .aaa. u m :w -s. - . - ..a-.s ma.~~-e,-a,~ . - --g.. ...~s. - - -a.,.-..,
9 i
ENCLOSURE 2 PROPOSED TECHNICAL SPECIFICATION (TS) CHANGE SEQUOYAH NUCLEAR PLANT (SON) UNITS 1 AND 2 DOCKET NOS. 50-327 AND 50-328 (TVA-SON-TS-95-20)
DESCRIPTION AND JUSTIFICATION FOR THE CONTAINMENT SPRAY / RESIDUAL HEAT REMOVAL (RHR) SYSTEMS NOZZLE SURVEILLANCE FREQUENCY REVISION
Description of Chanae TVA proposes to modify the Sequoyah Nuclear Plant (SON) Units 1 and 2 technical specifications (TSs) to revise Surveillance Requirements (SRs) 4.6.2.1.1.d and -
4.6.2.1.2.b to extend the testing period from 5 to 10 years. This change is consistent with the guidance provided in Generic Letter (GL) 93-05.
O Reason for Chanae ,
Performance of the spray nozzle surveillance requires draining of the piping leading to 4 the spray header. Since a small amount of watet may remain in the piping, there is a chance that this moisture may be ejected during the initial header pressurization through the nozzles. This could result in a contamination hazard. Another potential problem involves personnel safety. The test personnel manipulate the infrared camera
- from the top of the polar crane. The polar crane is over 100 feet from the reactor cavity floor. Additionally, this TS surveillance extension is estimated to sase SON approximately $126,000over the life of the plant. .
Justification for Chanaes The containment spray (CS) system is designed to prevent the containment pressure, during a large break loss-of-coolant accident, from exceeding its maximum design pressure. The CS system performs this function by spraying borated water through spray he::ders at the top of the containment building. The cooler spray water condanses the steam in the containment atmosphere. If additional cooling is needed, the RHR system contains two spray headers that can be aligned manually.
For the systems to operate correctly, the nozzles in the spray headers cannot be blocked. SON presently tests these nozzles every five years using hot air. The purpose of this test is to identify any degradation of the spray headers that will prevent flow through the spray nozzles.
i NUREG-1366 indicates that operating history was reviewed to determine the success of the surveillance tests performed at various plants. Of the many tests reviewed, only three tests indicated nozzle flow problems. These three problems were construction related and not due to header degradation. GL 93-05 further warns of other considerations if the piping used is carbon steel.
At BON, there have been no problems identified during testing of nozzles for unchstructed flow; therefore, the proposed change is compatible with the operating experience discussed in NUREG-1366. Additionally, the proposed change is consistent with GL 93-05. CS subsystem piping that is in contact with borated water is austenitic stainless steel.
d
. .. - - - . . - . _ . . . - . - - -....~ - - . - . . . _ - . --
i 6
i 2
i Environmental Imoact Evaluation The proposed change does not involve an unreviewed environmental question because ,
operation of SON Units 1 and 2 in accordance with this change would not: !
- 1. Result in a significant increase in any adverse environmentalimpact previously '
evaluated in the Final Environmental Statement (FES) as modified by NRC's testimony to the Atomic Safety and Licensing Board, supplements to the FES, environmentalimpact appraisals, or decisions of the Atomic Safety and Licensing -
Board.
- 2. Result in a significant change in effluents or power levels.
- 3. Result in matters not previously reviewed in the licensing basis for SON that may have a significant environmentalimpact.
i r
i i
e i
i h
i
e g O
ENCLOSURE 3 PROPOSED TECHNICAL SPECIFICATION CHANGE SEQUOYAH NUCLEAR PLANT (SON) UNITS 1 AND 2 DOCKET NOS. 50-327 AND 50-328 (TVA-SQN-TS-95-20)
DETERMINATION OF NO SIGNIFICANT HAZARDS CONSIDERATION FOR THE CONTAINMENT SPRAY / RESIDUAL HEAT REMOVAL (RHR) SYSTEMS NOZZLE SURVEILLANCE FREQUENCY REVISION
. . - . - - - - - . - .-.. _ .~. -- - -. _ . .-.- - - - - -. .- - - .
Significant Hazards Evaluation i.
4
?
4
_TVA has evaluated the proposed technical specification (TS) change and has 1 determined that it does not represent a significant hazards sonsideration based on j- . criteria established in 10 CFR 50.92(c). Operation of Sequoyah Nuclear Plant (SON) in accordance with the proposed amendment will not:
- 1. Involve a significant increase in the probability or consequences of an accident
- j. / . previously evaluated.
The TS change is consistent with the guidance provided in Generic Letter 93-05.
Containment spray (CS) systems' header piping is stainless steel; therefore, 4
corrosion will be negligible during the extended surveillance interval. Since the CS systems' headers are maintained dry, there is no mechanism that could cause blockage of the spray nozzles. Therefore, the nozzles in the CS systems will -
. remain operable, during the 10-year surveillance interval, to mitigate the Q . consequence of an ac'cident previously evaluated. Additionally, clogging or blockage has not been observed during the 5-year surveillance tests that have i
.been performed in the past at SON. Testing the CS systems' nozzles at the )
proposed reduced frequency will not increase the probability of occurrence of a . j postulated accident or the consequences of an accident previously evaluated. I i
- 2. Create the possibility of a new or different kind of accident from any previously analyzed.
l The proposed reduced frequency testing of the CS systems' nozzles does not !
change the manner in which these systems are operated. The reduced testing l frequency of the spray nozzles does not generate any new accident precursors. j Therefore, the possibility of a new or different kind of accident previously evaluated is not created by the proposed changes in surveillance frequency of the CC systems' nozzles.
- 3. n ve a significant reduction in a margin of safety.
- Reduced testing of the CS systems' nozzles does not change the way the systems are operated or the systems' operability requirements. In this ;
application, any additional corrosion of stainless steel piping will be negligible I during the extended surveillance interval. Since the CS systems are maintained ;
dry, there is no additional mechanism that could cause blockage of the nozzles. l Therefore, the proposed reduced testing frequency is adequate to ensure spray l nozzle operability. The surveillance requirements do not affect the margin of safety since the operability requirements of both the CS systems remains unchanged. The existing safety analysis remains bounding. Therefore, there is ~
no reduction in the margin of safety. l
)