Text
'
t%sN r ort;nA t ton MAuvAL 8
e?
w Volume 05 05-1-02-I-2 Sect ion 02 Revis ion:
10 Date:
3-17-82 I
OFF-NORMAL EVENT PROCEDURE TURBINE AND CENERATOR TRIPS SAFETY RELATED Prepared:
f-
/
t Reviewed:
/ A - /b
/
Nuclear Plant Quality Superintendent Technical Review Rev iewed :
M O, t. 3_
Operat io is, Superintendent Approved:
?
j Atis is t ant Plant Manager
!/d b PSRC:
t List of Ef fective Pages:
Page:
Revision:
1-4 10 09 8206300235 820625 PDR ADOCK 05000416 p
PDR I
GKAku GULi huCLt,Ad h t Ai tui.
ver.svawuu.
.....a c m n,..ui..u.
I A
b<
l T it*t e : Turbine and Generator lNo.: 05-1-02-I-2 l Revision:
10 lPage:
3 i
l Trips I
I I
l h) 2.2.15 Generator distance relay 2.2.16 Generator field breaker open 2.2.17 Voltage balance 2.2.18 Pilot exciter short circuit 2.2.19 Rotor ground 3.0 AUTOMATIC ACTIONS I
3.1 TSV closure 3.2 TCV ramp closed 3.3 Reactor scram if > 30% power.
3.4 Auto start on Auxiliary Oil Pump at 1350 RPM, and Shaft Lif t Pump at 510 RPM.
3.5 Turbine Turning Gear MOV's Open at 210 RPM.
3.6 Primary water standstill pump auto starts.
-l.I,^.
3.7 Recire. pump shif t to low fre'quency M-G.
3.8 Bypass valves open if vacuum > 12" Hg.
3.9 Generator Output Breakers Open on Generator Trip, or Reverse Power _ after 7
'5 second time delay.
4.0 IMMEDIATE OPERATOR ACTIONS 4.1 Verify automatic actions.
4.2 If a scram occurred, complete ONEP 05-1-02-I-1, Reactor Scram.
4.3 Verify turbine bearing oil is maintained during coastdown.
4.4 If a reactor scram did not occur (power < 30%), be prepared for a reactor power increase due to decreasing feedwater temperature. Control reactor power as necessary to prevent a scram.