|
---|
Category:TECHNICAL SPECIFICATIONS
MONTHYEARML20195B4441999-05-26026 May 1999 Proposed Tech Specs Relocating pressure-temp Curves, Predicted Radiation Induced NDTT Shift Curve & LTOP Limits to FCS Unit 1 RCS pressure-temp Limits Rept ML20205J7671999-03-31031 March 1999 Proposed Tech Specs Increasing Min Required RCS Flow Rate & Changing SRs for RCS Flow Rate LIC-99-0001, Proposed Tech Specs Relocating Three cycle-specific Parameter Limits from FCS TS to COLR1999-01-29029 January 1999 Proposed Tech Specs Relocating Three cycle-specific Parameter Limits from FCS TS to COLR ML20151U3871998-09-0404 September 1998 Revised Bases of TS Sections 1.3(8),2.0.1(2),2.1.6,2.3,2.4, 2.13,2.15,3.1 & 3.6 ML20217B8241998-03-18018 March 1998 Proposed Tech Specs Re Requirements for Alternate Shutdown Panel & Associated Auxiliary Feedwater Panel ML20217B8611998-03-18018 March 1998 Proposed Tech Specs 5.2 & 5.11.2,changing Title of Shift Supervisor to Shift Manager ML20217P2041998-03-0303 March 1998 Proposed Tech Specs Pages,Revising TS 2.6 & Basis by Replacing Refs to TS 3.5(4) W/Refs to TS 5.19 ML20199L8951998-01-30030 January 1998 Proposed Tech Specs,Reflecting Relocation of pressure-temp Curves,Predicted Radiation Induced NDTT Shift Curve & LTOP Limits to FCS Unit 1 RCS PT Limits Rept ML20199L7291998-01-30030 January 1998 Proposed Tech Specs Deleting Section 3.E Re License Term ML20202B0931998-01-30030 January 1998 Proposed Tech Specs Section 2.5 Re Steam & Feedwater Sys ML20203G4311997-12-11011 December 1997 Proposed Tech Specs,Adding New LCO to TS 2.15 Pertaining to Inoperable ESF Logic Subsystem ML20199K1391997-11-21021 November 1997 Proposed Tech Specs 5.19 Re Containment Leakage Rate Testing Program ML20217G4601997-10-0303 October 1997 Proposed Tech Specs Pages Revising TS Surveillance 3.9, Auxiliary Feedwater Sys, to Clarify What Flow Paths Are Required to Be Tested & Delete Specific Discharge Pressure ML20196J0851997-07-25025 July 1997 Proposed Tech Specs Implementing Option B of 10CFR50,App J & Allowing Frequency of Conducting ILRT & Local Leak Rate Testing to Be Based on Component Performance ML20137Y1801997-04-17017 April 1997 Proposed Tech Specs Re Administrative Changes to License DPR-40 ML20137H4941997-03-26026 March 1997 Proposed Tech Specs Incorporating Addl Restrictions on Operation of MSSVs ML20138L4361997-02-20020 February 1997 Proposed Tech Specs 5.0 Re Administrative Controls LIC-96-0183, Proposed Tech Specs 5.0 Re Administrative Controls & Table of Contents1996-11-20020 November 1996 Proposed Tech Specs 5.0 Re Administrative Controls & Table of Contents ML20129E5161996-10-24024 October 1996 Proposed Tech Specs 4.3.2,regarding Reactor Core & Control to Allow Use of Either Zircaloy or ZIRLO Cladding Proposed Additional Reference to Westinghouse Topical Report, WCAP-12610-P-A, Vantage + Fuel Assembly Rept ML20129C2621996-10-22022 October 1996 Proposed Tech Specs 5.0 Re Administrative Controls & 5.9.5 Re Core Operating Limits Rept LIC-96-0125, Proposed Tech Specs Revising Paragraph 2.B(2) of License to Allow Use of Source Matl as Reactor Fuel.Ts 4.3.2 Revision Would Include Depleted U in Describing Reactor Core1996-08-23023 August 1996 Proposed Tech Specs Revising Paragraph 2.B(2) of License to Allow Use of Source Matl as Reactor Fuel.Ts 4.3.2 Revision Would Include Depleted U in Describing Reactor Core ML20115G0041996-07-15015 July 1996 Proposed Tech Specs 4.3.2 Re Reactor Core & Control ML20112D3211996-05-31031 May 1996 Proposed Tech Specs Re LCO for Trisodium Phosphate & Increasing Min Required Amount of Trisodium Phosphate Contained in Containment Sump Mesh Baskets ML20117H6981996-05-20020 May 1996 Proposed Tech Specs,Clarifying Surveillance Test Requirements Found in TS 3-1,Tables 3-1,3-2,3-3 & 3-3A ML20117H5931996-05-17017 May 1996 Proposed Tech Specs,Relocating Operability Requirements for Shock Suppressors (Snubbers) to USAR & or Plant Procedures & Incorporating Snubber Exam & Testing Requirements Into TS 3.3 ML20097C3081996-02-0101 February 1996 Proposed Tech Specs,Allowing Increase in Initial Nominal U-235 Enrichment Limit of Fuel Assemblies That May Be Stored in Spent Fuel Pool LIC-96-0008, Proposed Tech Specs Placing Sirw Tank Low Level Channels in Bypass Rather than Tripped Condition1996-01-22022 January 1996 Proposed Tech Specs Placing Sirw Tank Low Level Channels in Bypass Rather than Tripped Condition ML20094N8631995-11-16016 November 1995 Proposed Tech Specs,Adding LCO & Surveillance Test for Safety Related Inverters & Deleting Nonsafety Related Instrument Buses ML20092G0771995-09-0606 September 1995 Proposed Tech Spec 2.7,extending Allowed Outage Time from 7 Days Per Month to 7 Days W/ Addl Once Per Cycle 10 Day Allowed Outage Time ML20087E0281995-08-0404 August 1995 Proposed Tech Specs Reducing Minimum Operable Containment Radiation High Signal Channels ML20086D5341995-06-27027 June 1995 Proposed Tech Specs Re Reformation & Clarification of TS Re Chemical & Vol Control Sys ML20091G3601995-06-26026 June 1995 Proposed Tech Specs Re Extension of Allowed Outage Time for an Inoperable Low Pressure SI Pump ML20086D3851995-06-26026 June 1995 Proposed Tech Specs Re Audit Frequencies for Plant QA Program ML20084G7751995-05-31031 May 1995 Proposed Tech Specs,Requesting Amend to Provide Addl Restrictions on Operation of CCW Sys Heat Exchangers ML20083C0091995-05-0808 May 1995 Proposed Tech Specs,Incorporating Proposed Revs Per GL 93-05 to Specs 2.3,3.1,3.2,3.3 & 3.6 ML20087G9691995-04-0707 April 1995 Proposed Tech Specs Re Relocation of Axial Power Distribution Figure for License DPR-40 ML20082J0851995-04-0707 April 1995 Proposed Tech Specs Re Administrative Changes to License DPR-40 ML20080S0291995-03-0101 March 1995 Proposed Tech Specs Reflecting Administrative Revs to TS 5.5 & 5.8,per GL 93-07 & Revs Unrelated to GL 93-07 to TS 2.5, 2.8,2.11,3.2 & 3.10 ML20078P8251995-02-10010 February 1995 Proposed Tech Specs 2.10 to Relocate Requirements for Incore Instrumentation Sys ML20077S1691995-01-0909 January 1995 Proposed Tech Specs,Reflecting Deletion of Requirements for Toxic Gas Monitoring Sys ML20078G8981994-11-11011 November 1994 Proposed Tech Specs 5.2 & 5.5,reflecting Administrative Changes ML20024J3921994-10-0707 October 1994 Proposed Tech Specs,Deleting SRs in TS 3.6(3)a for Eight Raw Water Backup Valves to Containment Cooling Coils,Deleting SRs in TS 3.2,Table 3-5,item 6 for 58 Raw Water Valves & Revising Basis of TS 2.4 to Reflect Changes ML20069H9261994-06-0606 June 1994 Proposed Tech Specs Incorporating Changes to Credit Leak Before Break Methodology to Resolve USI A-2, Asymmetrical Blowdown Loads on Rcps ML20069D8451994-05-25025 May 1994 Proposed Tech Specs Requesting one-time Schedular Exemption from 10CFR50.36a(2) ML20062N4211993-12-28028 December 1993 Proposed TS Tables 3-1 & 3-2 Re Min Frequencies for Checks, Calibrs & Testing of RPS & Min Frequencies for Checks, Calibrs & Testing of ESFs & Instrumentation & Controls, Respectively LIC-93-0228, Proposed Tech Specs Incorporating Changes to Leak Before Break Methodology to Resolve Unresolved Safety Issue A-2, Asymmetrical Blowdown Loads on Reactor Primary Coolant Sys1993-08-20020 August 1993 Proposed Tech Specs Incorporating Changes to Leak Before Break Methodology to Resolve Unresolved Safety Issue A-2, Asymmetrical Blowdown Loads on Reactor Primary Coolant Sys ML20045H1791993-07-12012 July 1993 Proposed TS 2.14,Table 2-1,Item 6.b Re ESF Sys Initiation, Degraded Voltage Setting Limits LIC-93-0159, Proposed Tech Specs Incorporating Administrative Changes1993-06-17017 June 1993 Proposed Tech Specs Incorporating Administrative Changes ML20128E5341993-02-0808 February 1993 Proposed Tech Specs Deleting Section 5.9.4 Re Radioactive Effluent Release Rept.Draft Chemistry Manual Procedure Encl ML20128C0461993-02-0101 February 1993 Proposed TS Figures 2-1A & 2-1B Re pressure-temp Limits for Heatup & Cooldown,Respectively 1999-05-26
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20195B4441999-05-26026 May 1999 Proposed Tech Specs Relocating pressure-temp Curves, Predicted Radiation Induced NDTT Shift Curve & LTOP Limits to FCS Unit 1 RCS pressure-temp Limits Rept ML20205J7671999-03-31031 March 1999 Proposed Tech Specs Increasing Min Required RCS Flow Rate & Changing SRs for RCS Flow Rate LIC-99-0001, Proposed Tech Specs Relocating Three cycle-specific Parameter Limits from FCS TS to COLR1999-01-29029 January 1999 Proposed Tech Specs Relocating Three cycle-specific Parameter Limits from FCS TS to COLR LIC-98-0141, SG Eddy Current Test Rept for 1998 Refueling Outage. with1998-10-27027 October 1998 SG Eddy Current Test Rept for 1998 Refueling Outage. with ML20151U3871998-09-0404 September 1998 Revised Bases of TS Sections 1.3(8),2.0.1(2),2.1.6,2.3,2.4, 2.13,2.15,3.1 & 3.6 ML20217B8611998-03-18018 March 1998 Proposed Tech Specs 5.2 & 5.11.2,changing Title of Shift Supervisor to Shift Manager ML20217B8241998-03-18018 March 1998 Proposed Tech Specs Re Requirements for Alternate Shutdown Panel & Associated Auxiliary Feedwater Panel ML20217P2041998-03-0303 March 1998 Proposed Tech Specs Pages,Revising TS 2.6 & Basis by Replacing Refs to TS 3.5(4) W/Refs to TS 5.19 ML20199L7291998-01-30030 January 1998 Proposed Tech Specs Deleting Section 3.E Re License Term ML20199L8951998-01-30030 January 1998 Proposed Tech Specs,Reflecting Relocation of pressure-temp Curves,Predicted Radiation Induced NDTT Shift Curve & LTOP Limits to FCS Unit 1 RCS PT Limits Rept ML20202B0931998-01-30030 January 1998 Proposed Tech Specs Section 2.5 Re Steam & Feedwater Sys ML20203G4311997-12-11011 December 1997 Proposed Tech Specs,Adding New LCO to TS 2.15 Pertaining to Inoperable ESF Logic Subsystem ML20199K1391997-11-21021 November 1997 Proposed Tech Specs 5.19 Re Containment Leakage Rate Testing Program ML20217G4601997-10-0303 October 1997 Proposed Tech Specs Pages Revising TS Surveillance 3.9, Auxiliary Feedwater Sys, to Clarify What Flow Paths Are Required to Be Tested & Delete Specific Discharge Pressure ML20211N7591997-10-0202 October 1997 Rev 0 to Fort Calhoun Station Unit 1 Operating Instruction, OI-ES-3, Engineered Safeguard Controls Normal Mode 1,2 & 3 Alignment Check ML20211N7521997-09-21021 September 1997 Rev 2 to Fort Calhoun Operations Dept Policy & Directive OPD-6-04, Annunciator Marking ML20211N7471997-09-12012 September 1997 Rev 2 to Fort Calhoun Operations Dept Policy & Directive OPD-6-08, Plastic Label Usage ML20211N7661997-08-25025 August 1997 Rev 4 to Fort Calhoun Station Unit 1 Annunciator Response Procedure ARP-1, APR-1 Annunciator Response Procedure ML20211N7411997-08-24024 August 1997 Rev 0 to Fort Calhoun Operations Dept Policy & Directive OPD-5-14, Test Monitor Program ML20196J0851997-07-25025 July 1997 Proposed Tech Specs Implementing Option B of 10CFR50,App J & Allowing Frequency of Conducting ILRT & Local Leak Rate Testing to Be Based on Component Performance ML20137Y1801997-04-17017 April 1997 Proposed Tech Specs Re Administrative Changes to License DPR-40 ML20137H4941997-03-26026 March 1997 Proposed Tech Specs Incorporating Addl Restrictions on Operation of MSSVs ML20138L4361997-02-20020 February 1997 Proposed Tech Specs 5.0 Re Administrative Controls ML20134J6841997-01-20020 January 1997 Rev 5,Change a to Security Training & Qualification Program LIC-96-0183, Proposed Tech Specs 5.0 Re Administrative Controls & Table of Contents1996-11-20020 November 1996 Proposed Tech Specs 5.0 Re Administrative Controls & Table of Contents ML20129E5161996-10-24024 October 1996 Proposed Tech Specs 4.3.2,regarding Reactor Core & Control to Allow Use of Either Zircaloy or ZIRLO Cladding Proposed Additional Reference to Westinghouse Topical Report, WCAP-12610-P-A, Vantage + Fuel Assembly Rept ML20129C2621996-10-22022 October 1996 Proposed Tech Specs 5.0 Re Administrative Controls & 5.9.5 Re Core Operating Limits Rept LIC-96-0125, Proposed Tech Specs Revising Paragraph 2.B(2) of License to Allow Use of Source Matl as Reactor Fuel.Ts 4.3.2 Revision Would Include Depleted U in Describing Reactor Core1996-08-23023 August 1996 Proposed Tech Specs Revising Paragraph 2.B(2) of License to Allow Use of Source Matl as Reactor Fuel.Ts 4.3.2 Revision Would Include Depleted U in Describing Reactor Core ML20115G0041996-07-15015 July 1996 Proposed Tech Specs 4.3.2 Re Reactor Core & Control ML20112D3211996-05-31031 May 1996 Proposed Tech Specs Re LCO for Trisodium Phosphate & Increasing Min Required Amount of Trisodium Phosphate Contained in Containment Sump Mesh Baskets ML20117H6981996-05-20020 May 1996 Proposed Tech Specs,Clarifying Surveillance Test Requirements Found in TS 3-1,Tables 3-1,3-2,3-3 & 3-3A ML20117H5931996-05-17017 May 1996 Proposed Tech Specs,Relocating Operability Requirements for Shock Suppressors (Snubbers) to USAR & or Plant Procedures & Incorporating Snubber Exam & Testing Requirements Into TS 3.3 ML20129C5351996-03-0101 March 1996 Rev 0 to Incore Instrumentation Operability Requirements ML20097C3081996-02-0101 February 1996 Proposed Tech Specs,Allowing Increase in Initial Nominal U-235 Enrichment Limit of Fuel Assemblies That May Be Stored in Spent Fuel Pool LIC-96-0008, Proposed Tech Specs Placing Sirw Tank Low Level Channels in Bypass Rather than Tripped Condition1996-01-22022 January 1996 Proposed Tech Specs Placing Sirw Tank Low Level Channels in Bypass Rather than Tripped Condition ML20108A7161995-12-19019 December 1995 Rev 7 to CH-ODCM-0001, ODCM, Incorporating TS Amend 171 for Section 3.1 Update/Reflect Changing Environ ML20094N8631995-11-16016 November 1995 Proposed Tech Specs,Adding LCO & Surveillance Test for Safety Related Inverters & Deleting Nonsafety Related Instrument Buses ML20092G0771995-09-0606 September 1995 Proposed Tech Spec 2.7,extending Allowed Outage Time from 7 Days Per Month to 7 Days W/ Addl Once Per Cycle 10 Day Allowed Outage Time ML20091P4011995-09-0101 September 1995 Rev 3 to Fort Calhoun Station ISI Program Plan Third Ten-Yr Interval 1993-2003 ML20087E0281995-08-0404 August 1995 Proposed Tech Specs Reducing Minimum Operable Containment Radiation High Signal Channels ML20086D5341995-06-27027 June 1995 Proposed Tech Specs Re Reformation & Clarification of TS Re Chemical & Vol Control Sys ML20091G3601995-06-26026 June 1995 Proposed Tech Specs Re Extension of Allowed Outage Time for an Inoperable Low Pressure SI Pump ML20086D3851995-06-26026 June 1995 Proposed Tech Specs Re Audit Frequencies for Plant QA Program ML20085M0081995-06-15015 June 1995 Rev 2 to ISI Program Plan for 1993-2003 Interval ML20084G7751995-05-31031 May 1995 Proposed Tech Specs,Requesting Amend to Provide Addl Restrictions on Operation of CCW Sys Heat Exchangers ML20083C0091995-05-0808 May 1995 Proposed Tech Specs,Incorporating Proposed Revs Per GL 93-05 to Specs 2.3,3.1,3.2,3.3 & 3.6 ML20087G9691995-04-0707 April 1995 Proposed Tech Specs Re Relocation of Axial Power Distribution Figure for License DPR-40 ML20082J0851995-04-0707 April 1995 Proposed Tech Specs Re Administrative Changes to License DPR-40 ML20108A7121995-03-15015 March 1995 Rev 6 to CH-ODCM-0001, ODCM, Incorporating New TS Amend 164 ML20080S0291995-03-0101 March 1995 Proposed Tech Specs Reflecting Administrative Revs to TS 5.5 & 5.8,per GL 93-07 & Revs Unrelated to GL 93-07 to TS 2.5, 2.8,2.11,3.2 & 3.10 1999-05-26
[Table view] |
Text
. .
2.0 LIMITING CONDITIONS FOR OPERATION 2.1 Reactor Coolant System (Continued) 2.1.2 Heatup and Cooldown Rate (Continued)
KIT is therefore calculated at a maximum gradient and is considered a constant = A for cooldown and zero for heatup.
Mji R is also a constant = B.
t Therefore:
KIR = AP + B P = KTR - B A
KIR is then varied as a function of temperature from Figure G-2110-1 of ASME III and the allowable pressure calculated. Hydrostatic head (48 psi) and instrumentation errors (120F an i 32 psi) are considered when plotting the 4
curves.
- 3. System Hydrostatic Test - The system hydrostatic test curve is developed in the same manner as in A above with the exception that a safety factor of 1.5 is allowed by ASME III in lieu of 2.
C. Lowest Service Temperature = 500F + 1000F + 120F = 162 0F.
As indicated previously, an RTNDT for all material with the exception of the reactor vessel belt-line was established at 500F. ASME III, Art. NB-2332(b) requires a lowest service temperature of RTNDT + 1000F for piping, pumps and valves. Below this temperature a pressure of 20 percent of
. the system hydrostatic test pressure (.20)(3125) 32 psi = 545 psia cannot be exceeded.
D. Boltup Temperature = 100F + 60 F + 120F = 820F. At pres-sure below 545 psia, a minimum vessel temperature must be maintained to comply with the manufacturer's specifications for tensioning the vessel head. This temperature is based on previous NDTT methods. This temperature corresponds to the measured 100F NDTT of the reactor vessel flange, which is not subject to radiation damage, plus 600F data scatter in NDTT measurements, plus 120F instrument error.
E. Reactor Critical Heatup and Cooldown Figures. During low physics testing, the reactor may be made critical at re-duced temperature and pressure. To provide for heatup and cooldown during testing, Appendix G requires that the RCS temperature be increased an additional 400F beyond heatup and cooldown curves for the non-critical reactor. Also, Appendix G requires that the RCS temperature must be greater than the minimum temperature, 3480F, required for the 2310 psia hydrostatic testing to 110% of the 2100 psia RCS operating pressure, in accordance with Article IWB-5000 of the ASME Boiler and Pressure Vessel Code,Section XI.
Amendment No. 22, 47 2-7 82020 10 820127 pPDR A
~
K OS000ggy l PDR - -
2.0 LIMITING CONDITIONS FOR OPERATION 2.1 Reactor Coolant System (Continued) 2.1.2 Heatup and Cooldown Rate (Continued)
F. Minimum Temperature for 1000F/hr Cooldown Rate = 1530F.
This limit provides protection against low temperature overpressurization during operation of the LPSI pumps. (6)
This temperature corresponds to a pressure of 200 psia on the 1000F/hr curve, which is the LPSI pump dead head and minimum flow pressure. For temperatures of 1530F or less, a cooldown rate of 200F/hr maximum will allow unrestricted operation of the LPSI pumps so that shutdown cooling may be utilized.
References (1) FSAR, Section 4.2.2 (2) ASME Boiler and Pressure Vessel Code,Section III (3) FSAR, Section 4.2.4 (4) FSAR, Section 3.4.6 (5) Omaha Public Power District, Fort Calhoun Station Unit No.
1, Evaluation of Irradiated Capsule W-225, Revision 1 August, 1980.
(6) Technical Specification 2.3(3)
(7) Article IWB-5000, ASME Boiler and Pressure Vessel Code,Section XI.
2-7a
RCS PRESS-TEMP LIMITS C00!.DOWN 6.1 EFPY .
Era a mmt:L REBEB RES (PSIA l m _
W 08x m
~
/
hi m IEST -
aos aos E l CILDelETE 2400
/
~
a s FSI 230
- m 5
l l1
/
in
~
/ !I aumm1E M EFMI E
/( ,
/
u,
'~
) l
>l tas E ,
/ /
./
- LOWEST SEMICE l
, - Tese imE x 162 j / [ f N < (
- N /
1
/
- 5#
/
/
BOLEP j'
- TEMPBMB Ej-NINI M 10FERATEE FOR
, 2, . . iii , .... ,,,, iP8,WY,WT.Ti ,,,, i,,, ,,,,
s2 isa 0 50 101 150 201 2iB 3 10 2il e S 500 i
l FORT CALHOUN E IltET IBF IE F1 Tc
- TECHNICAL FIGURE l SPECIFICATIONS 2-18 l
l
RCS PRESS-TEMP LIMITS HEATUP 6.1 EFPY .
a= =Tu M55ms Ess 1 PSIA 1 3 -
M -
M -
5 -
23 _
D _
- ! /
- /
in in
/
!G E /
D E
/
12 _
M _
M _
M _
0 se 0 2 101 S 200 2il N 3 al 8 500 FORT CALHOUN E M H H l s F1Tc FIGURE TECHNICAL 2-2A SPECIFICATIONS
RCS PRESS-TEMP LIMITS C00LD0'dN 6.1 EFPY is .
amama FESRE4 RES (PSIA) 3 _
M _
M _
M _
M _
M _
- /
1800 E /
i -
(
in la E /
1a E /
12 E /
8
- M _
1 M _
~
a 0
l se l 6 50 100 150 m a aos a e a 50s l
FORT CALHOUN E MH W (E F1 Tc FIGURE TECHNICAL 2-28 SPECIFICATIONS
I
=2.0 LIMITING CONDITIONS FOR OPERATION 2.3 Emergency Core Cooling System-(Continued) ;
(3) Protection Against Low Temperature Overpressurization ,
The following limiting conditions shall be applied during scheduled heatups and cooldowns. Disabling of the HPSI-pumps need not be required if the reactor vessel head,'a pressurizer safety valve, or a PORV is removed.
Whenever the reactor coolant system cold leg temperature is
- below 3370F, at least one (1) HPSI pump shall be disabled. .l Whenever the reactor coolant. system cold leg temperature is l below 3270F, at least two (2) HPSI pumps shall be disabled. l l Whenever the reactor coolant system cold leg. temperature is '
i below 2930F, all three (3) HPSI pumps shall be disabled. l Whenever the reactor coolant system cold leg temperature is. l l below 153 F, the cooldown rate of Figure 2-1B, Technical 1 ' Specification 2.1.2,~ shall be limited to a maximum rate of 200F/hr.
In the event that no charging pumps are operable, a single -;
HPSI pump may be made operable and utilized for boric acid. l injection to the core.
Basis l The normal procedure for starting the reactor is to first heat the <
reactor coolant to near operating temperature by running the i reactor coolant pumps. The reactor is then made critical by-withdrawing CEA's and diluting boron in the reactor coolant. . With-l this mode of start-up, the energy stored in the reactor coolant
! - during the approach to criticality' is substantially equal to that during power operation and therefore all engineered safety features and auxiliary cooling systems are required to be fully operable.
. During low power. physics tests at low temperatures, there is a negligible amount of stored energy in the reactor coolant; there-i fore, an accident comparable in severity to the design basis accident is not possible and the engineered safeguards systems are not required.
, The SIRW tank contains a minimum of. 283,000 gallons of usable
( . water containing at least 1700 ppm boron.(1)- This is sufficient boron concentration to provide a shutdown margin of 5%, including allowances for uncertainties, with all control rods withdrawn and a new core at a temperature of 60 F. (2) l The limits for the safety injection tank pressure and volume i j
assure the required amount of water injection during an accident-and are based on values used for the accident analyses.- The minimum 116.2 inch level corresponds to a: volume of 825 ft3 and the maximum 128.1 inch level corresponds to a volume of 895.5 ft3 Prior-to the time the reactor is brought critical, the valving of the. safety injection system must be checked for correct alignment and appropriate valved locked.. Since'the system is Amendment No. 17, 39, 43, 47 2-22 4
, - - - - - - - - m 4=---m---', + - + + e - - w
2.0 LIMITING CONDITIONS FOR OPERATION 2.3 Emergency Core Cooling System (Continued)
With respect to the core' cooling function, there is functional redundancy over most of'the range of break sizes.(3)(4)
The LOCA analysis confirms adequate core cooling for the break spectrum up to and including the 32 inch double-ended break assuming the safety injection capability which most adversely affects accident consequences and are defined as follows. The entire contents of all four safety injection tanks are assumed to
- be available for emergency core cooling, but the contents of one of the tanks is assumed to be lost through the reactor. coolant system. In addition, of the three high-pressure safety injection pumps and the two low-pressure safety injection pumps, for large break analysis it is assumed that two high pressure and one low pressure operate in the small breakwhile only(one analysis 5); and of each alsotype thatis25%
assumed of theirto com-operate bined discharge rate is lost from the reactor coolant system out.
of the break. The transient hot spot fuel clad temperatures for the break sizes considered are shown on FSAR Figures 1-19 (Amend-ment No. 34). .
Inadvertent actuation of three (3) HPSI pumps and three (3) charging pumps, coincident with the opening of one of the two
' PORV's, would result in a peak primary system pressure of 1190 psia. 1190 psia correnponds with a minimum permissible temper-
, ature of 337 F on Figure 2-1B. Thus, at least one HPSI pump is disabled at 3370F.
Inadvertent actuation of two (2) HPSI' pumps and three (3)' charging pumps, coincident with the opening of one of the two PORV's, would result in a peak primary system pressure of 1040 psia. 1040 psia corresponds with a minimum permissible temperature of 327 F on l Figure 2-1B. Thus, at least two HPSI pumps will be disabled at 327 F. l Inadvertent actuation of one (1) HPSI and three (3) charging pumps, coincident with opening of one of the two PORV's, would result in a peak primary system pressure of 685 psia. 685 psia corresponds with a minimum allowable temperature of 2930F on l Figure 2-1B. Thus, all three HPSI pumps will be disabled at 2930F. l The operation of either or both LPSI pumps, with or without three charging pumps, coincident with the opening of one of two PORV's, would result in a peak primary system pressure of 200 psia. This is the LPSI pump dead head and minimum flow pressure. 200 psia corresponds with a minimum allowable temperature of 1530F on the 1000F/hr cooldown rate curve of Figure 2-1B. (6) Since it is necessary that the LPSI pumps be available for shutdown cooling, they cannot be disabled. Thus, whenever the cold leg temperature is less than or equal to 1530F, a maximum cooldown rate of 20 F/hr shall be required.
Amendment No. 39, 47 2-23a
O 2.0 LIMITING CONDITIONS FOR OPERATION 2.3- Emergency Core Cooling System (Continued)
Inadvertent actuation of three (3) charging pumps, coincident with the opening of one of two PORV's, would result in a peak primary system pressure of 160. psia. 160 psia would correspond with a minimum allowable temperature of 121 F on the 100 F/hr cooldown rate curve of . Figure 2-1B. This is less than the minimum 1530F temperature required for-use of the 100 F/hr cooldown rate curve.
Thus, the 200F/hr cooldown rate curve is-controlling and does not limit the operation of the charging pumps.
Removal of the reactor vessel head, one pressurizer safety valve, or one PORV provides sufficient expansion volume to limit any of
' the design basis pressure transients. Thus, no additional relief capacity is required.
Technical Specification 2.2(1) specifies that, when fuel. is in the reactor, at least one flow path shall be provided for boric acid
, injection to the core. Should boric acid injection become neces-sary, and no charging pumps are operable, operation of a single HPSI pump would provide the required flow path.
References (1) FSAR, Section 14.15.1 T
(2) FSAR, Section 6.2.3.1 (3) FSAR, Section 14.15.3 (4) FSAR, Appendix K (5) Omaha Public Power District's Submittal, December 1,1976 -
(6) Technical Specification 2.1.2, Figure 2-1B e
Amendment No. 47 2-23b
DISCUSSION These changes are required to allow for the safe operation of the reactor and associated primary coolant system beyond the 5.2 Equivalent Full Power Years (EFPY) of operation to which the present Technical Specifications are written. The specifications are revised to allow operation through 6.1 EFPY. This will provide operating limits through the end of fuel cycle 7. The EFPY of operation corresponds to a neutron fluence received by the reactor vessel. This fluence causes the nil-ductility transition reference temperature (RTNDT) of the reactor vessel steel to increase. The amount of RTNDT shift is predicted using procedures detailed in Regulatory Guide 1.99. The fluence value for the reactor shift vessel through belt-line 6.1 EFPY of weld materialisused operation 8.4 xforJeterm{ning 10 n/cm . The the RT NDT fluence value for 6.1 EFPY was calqulated using the end-of-life predicted fluence of 4.4 x 1019 n/cmz which was calculated and approved by the Commission for cycle 6 operation using the Fort Calhoun Station first surveillance capsule test data, as reported in the Combustion Engineer-ing document " Evaluation of Irradiated Capsule W-225", Revision 0, dated May 1979. It should be noted that the CE report, " Evaluation of Ir-calculational techniques determined the EOL fluence to be 4.2 x 10g)' radiated Capsu n/cm2 Accordingly, the E0L value and 6.1 EFPY fluence values used in the proposed calculated Technical Specifications are considgred conservative. The RTNDT total shift for 8.4 x 1018 n/cm is 2380F for the belt-line weld material. The heatup and cooldown rate pressure-temperature limit curves were then adjusted according to 10 CFR 50, Appendices G and H, to c.nsure that adequate fracture toughness is maintained through all conditions of normal operation, including anticipated operational transients and system hydrostatic tests. The beginning-of-life RTNDT value for weld materials used for developing the heatup ano cooldown limit curves was 00F in accc-dance with Branch Technical Position MTEB 5-2.
The disabling of HPSI pumps in order to ensure protection of the RCS against low temperature overpressurization is dependent upon the permissible 1000F/hr cooldown rate which is determined from the shift in RTNDT and plotted on Figure 2-18. Thus, Technical Specification 2.3(3) is modified to maintain adequate overpressurization protection. In addition, it has become apparent that the LPSI pump shutoff head will not allow operation on the 1000F/hr cooldown rate curve of Figure 2-1B at temperature at or below 1530F. It becomes necessary to limit oper-ation at that temperature and below to a cooldown rate of 200F/hr.
The present Technical Specifications, valid through 5.2 EFPY, will provide operating limits for a period of 47 days of full power operation (71,662 MW-HR) after initial criticality of fuel cycle 7. Therefore, Commission approval of the proposed Technical Specifications by no later than February 8,1982 is requested.
ATTACHMENT B
.