05000293/LER-1999-010-02, :on 990918,reactor Startup Was in Progress. Caused by Communications Breakdown That Resulted in Operations Personnel Failing to Complete Actions in IAW Procedures.Power Ascension Was Secured.With1999-10-18018 October 1999
- on 990918,reactor Startup Was in Progress. Caused by Communications Breakdown That Resulted in Operations Personnel Failing to Complete Actions in IAW Procedures.Power Ascension Was Secured.With
05000293/LER-1999-009-02, :on 990913,manual Scram at 27 Percent Power, Occurred.Caused by Degrading Main Condenser Vacuum. Inspection of Instrument Sensing Lines to E-306B Level Transmitters Was Performed.With1999-10-13013 October 1999
- on 990913,manual Scram at 27 Percent Power, Occurred.Caused by Degrading Main Condenser Vacuum. Inspection of Instrument Sensing Lines to E-306B Level Transmitters Was Performed.With
05000293/LER-1999-008-02, :on 990805,automatic Scram Occurred While at 100% Power Due to Automatic Turbine Trip.Caused by Malfunction of Moisture Separator Drain Tank a Drain Valve Controller.Level Controllers Replaced.With1999-09-0707 September 1999
- on 990805,automatic Scram Occurred While at 100% Power Due to Automatic Turbine Trip.Caused by Malfunction of Moisture Separator Drain Tank a Drain Valve Controller.Level Controllers Replaced.With
05000293/LER-1999-007-02, :on 990716,discovered That Bus B6 Voltage Restoration Was Not Consistent with Safety Analysis Assumptions.Caused by Personnel Error During Development of Design Change.Will Evaluate Need for Mod.With1999-08-13013 August 1999
- on 990716,discovered That Bus B6 Voltage Restoration Was Not Consistent with Safety Analysis Assumptions.Caused by Personnel Error During Development of Design Change.Will Evaluate Need for Mod.With
05000293/LER-1999-006-02, :on 990705,both EDGs Were Inoperable.Caused by Ambient Air Temp Exceeding 88 Degrees Fahrenheit.Temporary Mods Tm 99-41 & Tm 99-42,implemented for EDG a Were Completed on 990706.With1999-08-0404 August 1999
- on 990705,both EDGs Were Inoperable.Caused by Ambient Air Temp Exceeding 88 Degrees Fahrenheit.Temporary Mods Tm 99-41 & Tm 99-42,implemented for EDG a Were Completed on 990706.With
05000293/LER-1999-005, :on 990608,partial Actuation of Rhr/Lpci Circuitry During Surveillance Test Was Noted.Caused by Personnel Error.Revised Procedure.With1999-07-0808 July 1999
- on 990608,partial Actuation of Rhr/Lpci Circuitry During Surveillance Test Was Noted.Caused by Personnel Error.Revised Procedure.With
05000293/LER-1999-004, :on 990529,setpoint of Target Rock Relief Valves Were Found Out of Tolerance During Testing.Caused by Setpoint Drift.Replaced Pilot Assemblies with Certified Spare Pilot Assemblies.With1999-06-28028 June 1999
- on 990529,setpoint of Target Rock Relief Valves Were Found Out of Tolerance During Testing.Caused by Setpoint Drift.Replaced Pilot Assemblies with Certified Spare Pilot Assemblies.With
05000293/LER-1999-003, :on 990516,discovered That LLRT Results Exceeded Allowable TS Leakage Rates.Cause Indeterminate. Affected Valves Were Disassembled & Inspected & Damaged or Worn Parts Were Reworked or Replaced.With1999-06-15015 June 1999
- on 990516,discovered That LLRT Results Exceeded Allowable TS Leakage Rates.Cause Indeterminate. Affected Valves Were Disassembled & Inspected & Damaged or Worn Parts Were Reworked or Replaced.With
05000293/LER-1999-002, :on 990504,HPCI & RCIC Sys Surveillance Testing Outside Design Bases,Was Identified.Caused by Incorrect Ts. Proposed License Amend to Change TS Surveillance Testing Requirements,Submitted on 990511.With1999-06-0303 June 1999
- on 990504,HPCI & RCIC Sys Surveillance Testing Outside Design Bases,Was Identified.Caused by Incorrect Ts. Proposed License Amend to Change TS Surveillance Testing Requirements,Submitted on 990511.With
05000293/LER-1999-001, :on 990412,environ Enclosures of MCCs Outside Design Basis,Were Found.Caused by Failure to Translate Design Function of Pressure Relieving Devices.Removed Obstructions of Pressure Relieving Devices.With1999-05-0606 May 1999
- on 990412,environ Enclosures of MCCs Outside Design Basis,Were Found.Caused by Failure to Translate Design Function of Pressure Relieving Devices.Removed Obstructions of Pressure Relieving Devices.With
05000293/LER-1998-029, :on 981231,discovered That Intake Structure Indoor Air Temp Was Less than Winter Design Temp,Per Ufsar. Caused by Lack of Info & Administrative Controls.Will Repair Ventilation Sys & Will Revise Procedures.With1999-02-0101 February 1999
- on 981231,discovered That Intake Structure Indoor Air Temp Was Less than Winter Design Temp,Per Ufsar. Caused by Lack of Info & Administrative Controls.Will Repair Ventilation Sys & Will Revise Procedures.With
05000293/LER-1998-028, :on 981230,CR High Efficiency Air Filtration Sys Relative Humidity Switches Were Inoperable.Caused by Gradual Degradation of Nylon Filaments.Modified Sys Control Circuitry.With1999-01-28028 January 1999
- on 981230,CR High Efficiency Air Filtration Sys Relative Humidity Switches Were Inoperable.Caused by Gradual Degradation of Nylon Filaments.Modified Sys Control Circuitry.With
05000293/LER-1998-026, :on 981202,HPCI Sys Declared Inoperable.Caused by Failed Power Inverter.Failed Inverter Replaced. with1998-12-23023 December 1998
- on 981202,HPCI Sys Declared Inoperable.Caused by Failed Power Inverter.Failed Inverter Replaced. with
05000293/LER-1998-007, :on 980330,single Failure Vulnerability of RHR Sys When in Suppression Pool Cooling Mode Was Noted.Caused by Inadequate Original Design.Problem Rept Pr 98.9159 Was Written to Document Concern.With1998-12-22022 December 1998
- on 980330,single Failure Vulnerability of RHR Sys When in Suppression Pool Cooling Mode Was Noted.Caused by Inadequate Original Design.Problem Rept Pr 98.9159 Was Written to Document Concern.With
05000293/LER-1998-025, :on 981118,setpoint of Target Rock Relief Valve Was Found out-of-tolerance During Testing.Caused by Setpoint Drift.Valve Was Disassembled,Inspected & Reworked by Target Rock Corp Personnel.With1998-12-18018 December 1998
- on 981118,setpoint of Target Rock Relief Valve Was Found out-of-tolerance During Testing.Caused by Setpoint Drift.Valve Was Disassembled,Inspected & Reworked by Target Rock Corp Personnel.With
05000293/LER-1998-004, :on 980321,EDG Room Air Temp Was Below Design Basis.Caused by Significant Effect of Meteorogical Conditions.Completed Engineering Evaluation1998-12-18018 December 1998
- on 980321,EDG Room Air Temp Was Below Design Basis.Caused by Significant Effect of Meteorogical Conditions.Completed Engineering Evaluation
05000293/LER-1997-017, :on 971104,past Operation with SW Temps Were Greater than Design.Caused by Licensing Basis Ambiguity. Issued SE & License Amend Request Was Submitted.With1998-12-18018 December 1998
- on 971104,past Operation with SW Temps Were Greater than Design.Caused by Licensing Basis Ambiguity. Issued SE & License Amend Request Was Submitted.With
05000293/LER-1998-018, :on 980722,EDGs Were Declared Inoperable When Ambient Air Temp Exceeded 88 F.Caused by Inadequate EDG Cooling & Bldg Ventilation Design.Will Develop EDG Cooling & EDG Bldg Ventilation Modifications.With1998-12-18018 December 1998
- on 980722,EDGs Were Declared Inoperable When Ambient Air Temp Exceeded 88 F.Caused by Inadequate EDG Cooling & Bldg Ventilation Design.Will Develop EDG Cooling & EDG Bldg Ventilation Modifications.With
05000293/LER-1998-024, :on 981015,determined That CR High Efficiency Aire Filtration Sys (Crheafs) Found Outside Design Basis Due to Installation of Duct Tape on Trains a & B Crheafs Supply Fans.Installed Mechanical Seals on Crheafs Supply Fans1998-11-13013 November 1998
- on 981015,determined That CR High Efficiency Aire Filtration Sys (Crheafs) Found Outside Design Basis Due to Installation of Duct Tape on Trains a & B Crheafs Supply Fans.Installed Mechanical Seals on Crheafs Supply Fans
05000293/LER-1998-023, :on 981005,incorrect Wiring Mods Affected RBCCW Train B Alternate Shutdown Panel.Caused by Error Made During Preparation of Electrical Connection Drawing to Implement Plant Design.Blown Fuse Replaced.With1998-11-0404 November 1998
- on 981005,incorrect Wiring Mods Affected RBCCW Train B Alternate Shutdown Panel.Caused by Error Made During Preparation of Electrical Connection Drawing to Implement Plant Design.Blown Fuse Replaced.With
05000293/LER-1998-022, :on 981002,unplanned Actuation of a EDG Occurred During Surveillance Test of Related Logic Sys Testing.Caused by Util non-licensed I&C Technician Error. Will Review Surveillance Procedures.With1998-10-30030 October 1998
- on 981002,unplanned Actuation of a EDG Occurred During Surveillance Test of Related Logic Sys Testing.Caused by Util non-licensed I&C Technician Error. Will Review Surveillance Procedures.With
05000293/LER-1998-013, :on 980606,inconclusive Fire Barrier Test Data Was Noted.Caused by Concerns About Adequacy of Original Basis for Three Hour Rating.Declared Enclosures Inoperable & Posted Fire Watch within One Hour.With1998-09-30030 September 1998
- on 980606,inconclusive Fire Barrier Test Data Was Noted.Caused by Concerns About Adequacy of Original Basis for Three Hour Rating.Declared Enclosures Inoperable & Posted Fire Watch within One Hour.With
05000293/LER-1998-020, :on 980730,operating W/Less than Min Operating Shift Crew Composition Was Noted.Caused by off-going SCRE Not Ensuring Proper Relief of SCRE Function.Individual Was Appropriately Counseled1998-08-28028 August 1998
- on 980730,operating W/Less than Min Operating Shift Crew Composition Was Noted.Caused by off-going SCRE Not Ensuring Proper Relief of SCRE Function.Individual Was Appropriately Counseled
05000293/LER-1998-019, :on 980727,declared Standby Liquid Control Subsystem B Inoperable.Caused by Leakage Through Pipe Fitting on Pressure Gauge PI-1160B.Removed Subject Gauge, Cleaned Pipe Threads & Reinstalled Gauge1998-08-26026 August 1998
- on 980727,declared Standby Liquid Control Subsystem B Inoperable.Caused by Leakage Through Pipe Fitting on Pressure Gauge PI-1160B.Removed Subject Gauge, Cleaned Pipe Threads & Reinstalled Gauge
05000293/LER-1998-013, :on 980606,inconclusive Fire Barrier Test Data Occurred.Caused by Concerns About Adequacy of Original Basis for 3 H Rating.Encls Declared Inoperable & Fire Watch Posted1998-07-0303 July 1998
- on 980606,inconclusive Fire Barrier Test Data Occurred.Caused by Concerns About Adequacy of Original Basis for 3 H Rating.Encls Declared Inoperable & Fire Watch Posted
05000293/LER-1998-011, :on 961126,operator Discovered Two Shield Plugs Removed from Floor Directly Over Torus Compartment.Caused by Lack of Formal Program to Control sub-compartment Barriers. Developed Formal Program to Control Compartment Barriers1998-06-26026 June 1998
- on 961126,operator Discovered Two Shield Plugs Removed from Floor Directly Over Torus Compartment.Caused by Lack of Formal Program to Control sub-compartment Barriers. Developed Formal Program to Control Compartment Barriers
05000293/LER-1998-007, :on 980330,discovered Single Failure Vulnerability of RHR Sys When in SPC Mode.Caused by Inadequate Original Design.Standing Order Issued to Declare LPCI Sys Inoperable When RHR Sys Is in SPC Mode1998-04-29029 April 1998
- on 980330,discovered Single Failure Vulnerability of RHR Sys When in SPC Mode.Caused by Inadequate Original Design.Standing Order Issued to Declare LPCI Sys Inoperable When RHR Sys Is in SPC Mode
05000293/LER-1998-004, :on 980321,EDG Room Air Temp Was Below Design Basis.Cause Is Attributed to Significant Effect Meteorlogical Conditions Have on EDG Room Temp.Completed Engineering Evaluation1998-04-17017 April 1998
- on 980321,EDG Room Air Temp Was Below Design Basis.Cause Is Attributed to Significant Effect Meteorlogical Conditions Have on EDG Room Temp.Completed Engineering Evaluation
05000293/LER-1997-004, :on 970307,loss of Preferred off-site Power & Oil Spill Occurred.Caused by Degraded Winding Condition or Static Electrification of Main Transformer.Replaced Main Transformer & Updated Fire Hazards Analysis Rept1998-04-14014 April 1998
- on 970307,loss of Preferred off-site Power & Oil Spill Occurred.Caused by Degraded Winding Condition or Static Electrification of Main Transformer.Replaced Main Transformer & Updated Fire Hazards Analysis Rept
05000293/LER-1998-003, :on 980220,discovered That RBCCW & Tbccw Heat Exchanger Supports Outside Design Basis Seismic Requirements.Caused by Calculation Error.Reviewed Similar Calculations & Counseled Individuals Associated W/Errors1998-03-23023 March 1998
- on 980220,discovered That RBCCW & Tbccw Heat Exchanger Supports Outside Design Basis Seismic Requirements.Caused by Calculation Error.Reviewed Similar Calculations & Counseled Individuals Associated W/Errors
05000293/LER-1998-002, :on 980205,EDG Room Air Temperature Went Below Design Basis.Caused by Unawareness of Significant Effect Wind Direction Has on EDG Room Temp.Engineering Evaluation (Ee 97-066 R-1) Was Completed & Approved1998-03-0909 March 1998
- on 980205,EDG Room Air Temperature Went Below Design Basis.Caused by Unawareness of Significant Effect Wind Direction Has on EDG Room Temp.Engineering Evaluation (Ee 97-066 R-1) Was Completed & Approved
05000293/LER-1997-026, :on 971206,automatic Scram Was Initiated.Caused by High Reactor Water Level During Power Ascension.Pilot Valve Clip Was Repositioned Inside Bailey Positioner & Valve Was Stroked Smoothly1998-01-0505 January 1998
- on 971206,automatic Scram Was Initiated.Caused by High Reactor Water Level During Power Ascension.Pilot Valve Clip Was Repositioned Inside Bailey Positioner & Valve Was Stroked Smoothly
05000293/LER-1997-025, :on 971123,required Shutdown Was Completed. Caused by Two Inoperable Msivs.Work Was Performed on All Eight MSIVs to Improve Design Margin Based on Degradation of Actuators in MSIVs AO-203-1C & -2B1997-12-23023 December 1997
- on 971123,required Shutdown Was Completed. Caused by Two Inoperable Msivs.Work Was Performed on All Eight MSIVs to Improve Design Margin Based on Degradation of Actuators in MSIVs AO-203-1C & -2B
05000293/LER-1997-019, :on 971104,discovered That Closure of RBCCW Sys Valves Which Isolate non-essential Heat Loads Were Not Translated Into Procedure.Caused by Inadequate Design Control.Performed SE & Revised Procedures1997-12-0404 December 1997
- on 971104,discovered That Closure of RBCCW Sys Valves Which Isolate non-essential Heat Loads Were Not Translated Into Procedure.Caused by Inadequate Design Control.Performed SE & Revised Procedures
05000293/LER-1997-020, :on 971104,RHR Operating Procedure Did Not Reflect Analysis.Caused by Inadequate Translation of Analysis Parameters to Operating Procedure Parameters. Revised Procedure 2.2.19.51997-12-0404 December 1997
- on 971104,RHR Operating Procedure Did Not Reflect Analysis.Caused by Inadequate Translation of Analysis Parameters to Operating Procedure Parameters. Revised Procedure 2.2.19.5
05000293/LER-1997-021, :on 971104,EDG Ambient Air Temperature Was Noted.Caused by Ambiguity in Fsar.Conservative Operability Evaluation Has Been Completed to Show That Diesels Are Operable to 95 F1997-12-0404 December 1997
- on 971104,EDG Ambient Air Temperature Was Noted.Caused by Ambiguity in Fsar.Conservative Operability Evaluation Has Been Completed to Show That Diesels Are Operable to 95 F
05000293/LER-1997-015, :on 971104,SSW Pumps Overload Settings Were Too Low for Single SSW Pump Operation W/Degraded Voltage.Cause Is Still Under Investigation.Entered 24 H Cold Shutdown LCO (A97-355) on 971104,to Remove SSW Pumps from Svc1997-12-0303 December 1997
- on 971104,SSW Pumps Overload Settings Were Too Low for Single SSW Pump Operation W/Degraded Voltage.Cause Is Still Under Investigation.Entered 24 H Cold Shutdown LCO (A97-355) on 971104,to Remove SSW Pumps from Svc
05000293/LER-1997-023, :on 971031,discovered That Both Radwaste Bldg Trucklock Doors Were Closed.Caused by Inadequate Control of Subcompartment Barriers.Opened & Tagged Rollup Steel Door1997-12-0101 December 1997
- on 971031,discovered That Both Radwaste Bldg Trucklock Doors Were Closed.Caused by Inadequate Control of Subcompartment Barriers.Opened & Tagged Rollup Steel Door
05000293/LER-1997-014, :on 970825,determined That Transmitters Had Not Been Calibr IAW Tss.Cause Indeterminate.Calibr Transmitters W/Satisfactory as-found Results Prior to Expiration of Suveillance Interval (24 Months Plus 25% Grace Period)1997-09-24024 September 1997
- on 970825,determined That Transmitters Had Not Been Calibr IAW Tss.Cause Indeterminate.Calibr Transmitters W/Satisfactory as-found Results Prior to Expiration of Suveillance Interval (24 Months Plus 25% Grace Period)
05000293/LER-1997-012, :on 970729,failure of Relay to Energize During Surveillance Test Occurred.Caused by Relay 10A-K10B Contacts 9-10 Not Closing.Relay Replaced & LCO Terminated1997-08-29029 August 1997
- on 970729,failure of Relay to Energize During Surveillance Test Occurred.Caused by Relay 10A-K10B Contacts 9-10 Not Closing.Relay Replaced & LCO Terminated
05000293/LER-1997-003, :on 970215,manual Scram Occurred Due to Increasing Rwl During Power Reduction for Refueling Outage. FW Regulating Valves FV-642A & FV-642B & Startup FW Regulating Valve FV-643 Tested1997-07-18018 July 1997
- on 970215,manual Scram Occurred Due to Increasing Rwl During Power Reduction for Refueling Outage. FW Regulating Valves FV-642A & FV-642B & Startup FW Regulating Valve FV-643 Tested
05000293/LER-1997-010, :on 970420,postulated Pipe Break Pressure Relieving Pathway Boundary Door Found Opened During Power Operation.Caused by Human Performance in That Door Was Not Closed After Maint Activity.Obtained Lock & Closed Door1997-05-20020 May 1997
- on 970420,postulated Pipe Break Pressure Relieving Pathway Boundary Door Found Opened During Power Operation.Caused by Human Performance in That Door Was Not Closed After Maint Activity.Obtained Lock & Closed Door
05000293/LER-1997-005, :on 970308,declared Turbine Bldg Effluent Monitoring Instrumentation Inoperable.Caused by Failed Power Supply to RT-1001-610.Will Perform Initial Rept Screening & Counseled Personnel on Human Error1997-05-15015 May 1997
- on 970308,declared Turbine Bldg Effluent Monitoring Instrumentation Inoperable.Caused by Failed Power Supply to RT-1001-610.Will Perform Initial Rept Screening & Counseled Personnel on Human Error
05000293/LER-1997-007, :on 970401,safeguard Buses Were de-energized Due to Severe Storm.Replacement of Microprocessor Control Units Installed in Voltage Regulating Transformers1997-05-0101 May 1997
- on 970401,safeguard Buses Were de-energized Due to Severe Storm.Replacement of Microprocessor Control Units Installed in Voltage Regulating Transformers
05000293/LER-1997-008, :on 970312,setpoint of Target Rock Relief Valve Pilot Assembly Was Out of Tolerance During Testing,Due to Setpoint Drift.Valve Was Disassembled,Inspected & Reworked by Target Rock Corp Personnel1997-04-24024 April 1997
- on 970312,setpoint of Target Rock Relief Valve Pilot Assembly Was Out of Tolerance During Testing,Due to Setpoint Drift.Valve Was Disassembled,Inspected & Reworked by Target Rock Corp Personnel
05000293/LER-1997-006, :on 970321,inadvertent Group Three Isolation Occurred While Troubleshooting 125 Volt Dc Ground on Battery a as Result of Relay Race When Circuit Breaker D4-8 Was Cycled.Electrical Print Reviewed & Verified1997-04-22022 April 1997
- on 970321,inadvertent Group Three Isolation Occurred While Troubleshooting 125 Volt Dc Ground on Battery a as Result of Relay Race When Circuit Breaker D4-8 Was Cycled.Electrical Print Reviewed & Verified
05000293/LER-1997-004, :on 970307,automatic Start of B Train EDG & Actuation of Secondary Containment Isolation Control Sys Occurred.Caused by Electrical Fault in Main Transformer. Initial Efforts for Oil Containment Initiated Immediately1997-04-0707 April 1997
- on 970307,automatic Start of B Train EDG & Actuation of Secondary Containment Isolation Control Sys Occurred.Caused by Electrical Fault in Main Transformer. Initial Efforts for Oil Containment Initiated Immediately
05000293/LER-1997-002, :on 970206,SJAE Sampling Was Not Performed in Accordance with Ts.Caused by Improper Conclusion Contained in Response to Request for Licensing Interpretation in 1990. Validation Project Is Now Complete1997-03-10010 March 1997
- on 970206,SJAE Sampling Was Not Performed in Accordance with Ts.Caused by Improper Conclusion Contained in Response to Request for Licensing Interpretation in 1990. Validation Project Is Now Complete
05000293/LER-1997-001, :on 970120,very Small Quantity of Unaccountable Special Nuclear Material Was Identifed Due to Less than Effective Methods for Control & Accounting of Devices. Procedures Revised1997-02-14014 February 1997
- on 970120,very Small Quantity of Unaccountable Special Nuclear Material Was Identifed Due to Less than Effective Methods for Control & Accounting of Devices. Procedures Revised