MONTHYEARML24270A0652024-09-26026 September 2024 ABWR Design Certification Annual 10 CFR 50.46 Report for 2024 ML23283A0892023-10-10010 October 2023 ESBWR Design Certification Annual 10 CFR 50.46 Report for 2023 ML23277A1702023-10-0404 October 2023 GE-Hitachi Nuclear Energy Americas, LLC, ESBWR Design Certification Annual 10 CFR 50.46 Report for 2023 ML23277A1692023-10-0404 October 2023 GE-Hitachi Nuclear Energy Americas, LLC, ABWR Design Certification Annual 10 CFR 50.46 Report for 2023 ML22347A2842022-12-0808 December 2022 GE-Hitachi Nuclear Energy Americas, LLC, Accepted Version of NEDO-11209-A Revision 17, GE Hitachi Nuclear Energy Quality Assurance Program Description ML22285A0972022-12-0101 December 2022 Renewal of Certificate of Compliance 2000 Transmittal Letter ML22161A9582022-06-10010 June 2022 GEH Request for Renewal - Certificate of Compliance No. 9228 for the Model No. 2000 Package, Revision 28, Docket No. 71-9228 ML21320A1902021-11-16016 November 2021 Pre-Application Presentation Slides for Amendment to NEDO-11209-A, Rev. 16, GE Hitachi Nuclear Energy Quality Assurance Program Description ML20197A2692020-07-15015 July 2020 Pre-application Presentation Slides for Amendment to NEDO-11209-A Revision 15, GE Hitachi Nuclear Energy Quality Assurance Program Description ML20184A1582020-07-14014 July 2020 Verification of Accepted Version of NEDO-11209 Revision 15, GE Hitachi Nuclear Energy Quality Assurance Program Description ML20108F5732020-04-23023 April 2020 Certificate of Compliance No. 9228, Revision No. 28, for the Model No. 2000 Package Transmittal Letter ML20093B4532020-04-0202 April 2020 GE-Hitachi Nuclear Energy Americas, LLC - Revision of the GE Model No. 2000 (Docket No. 71-9228) to Clarify Irradiated Hardware Content and Update the Quality Assurance Program References ML20084J4102020-03-26026 March 2020 General Electric Hitachi Nuclear Energy Americas, LLC Request for Withholding Information from Public Disclosure ML20031C6992020-01-31031 January 2020 GEH - Responses to the NRC Requests for Additional Information for the GE Model No. 2000 ML19319A8522019-11-15015 November 2019 GEH Request for Additional Time to Respond to NRC Requests for Additional Information (RAI) for the GE Model No. 2000 (Docket No. 71-9228) to Reintroduce BWR Irradiated Fuel Content ML19296C2732019-10-23023 October 2019 Transmittal Letter and Enclosure - Request for Additional Information for Review of the Model No. 2000 Package ML19242D0982019-09-19019 September 2019 General Electric Hitachi Nuclear Energy Americas, LLC, Request for Withholding Information from Public Disclosure ML19242D6962019-09-19019 September 2019 Verification of NEDC-33173P Supplement 6 Revision 1, Licensing Topical Report Applicability of GE Methods to Expanded Operating Domains - Removal of the Safety Limit Minimum Critical Power Ratio (SLMCPR) Penalty ML19232A0762019-08-26026 August 2019 Letter to S. Lamb Application for the Model No. 2000 Transport Package, Revision 28 - Accepted for Review ML19199A1822019-08-0808 August 2019 Final Safety Evaluation for NEDC-33173P Supplement 6 - Applicability of GE Methods to Expanded Operating Domains - Removal of the Safety Limit Minimum Critical Power Raito (SLMCPR) Penalty ML19212A5932019-07-31031 July 2019 GEH Transmittal of Request for a Revision of the GE Model No. 2000 Certificate of Compliance (USA/9228/B(U)-96) to Reintroduce BWR Irradiated Fuel Content ML19094A0582019-04-25025 April 2019 Verification of GE Hitachi Topical Report NEDC-33173 Supplement 5p-A, Revision 1, Applicability of General Electric Methods to Expanded Operating Domains - Supplement for GNF3 Fuel ML19094A9182019-04-25025 April 2019 General Electric Hitachi Nuclear Energy Americas, LLC, Request for Withholding Information from Public Disclosure ML19108A0192019-04-18018 April 2019 Draft Safety Evaluation for NEDC-33173P Supplement 6 - Applicability of GE Methods to Expanded Operating Domains - Removal of the Safety Limit Minimum Critical Power Ratio (SLMCPR) Penalty ML19071A1012019-03-26026 March 2019 Draft Safety Evaluation for NEDC-33173p Supplement 6 - Applicability of General Electric Methods to Expanded Operating Domains - Removal of the Safety Limit Minimum Critical Power Ratio Penalty ML19074A0542019-03-21021 March 2019 Imltr Supplement 5 Final SE Non-Proprietary ML19017A0432019-03-0505 March 2019 GE Hitachi Nuclear Energy Americas, Llc, Request for Withholding Information from Public Disclosure ML19016A4072019-03-0505 March 2019 GE Hitachi Nuclear Energy Americas, LLC, Request for Withholding Information from Public Disclosure ML19002A3762019-02-0505 February 2019 Draft Safety Evaluation for NEDC-33173p Supplement 5 and Applicability of GE Methods to Expanded Operating Domains and Supplement for GNF3 Fuel ML19025A0112019-01-25025 January 2019 GE-Hitachi Nuclear Energy Americas, LLC - Presentation for February 5, 2019 GE2000 SAR Amendment Meeting ML18155A2102018-06-22022 June 2018 Verification of GE Hitachi Topical Report NEDE-33005P-A, Revision 2 Tracg Application for Emergency Core Cooling Systems/Loss-of Coolant Accident Analysis for BWR/2-6 ML18129A0242018-05-11011 May 2018 Final Safety Evaluation for Licensing Topical Report Nede 33005P-A / NEDO-33005-A, Tracg Application for Emergency Core Cooling Systems / Loss-Of-Coolant-Accident Analysis for BWR/2-6 Satisfaction of Limitation 10.7 ML18117A3112018-04-27027 April 2018 Draft Safety Evaluation for Licensing Topical Report NEDE-33005P-A / NEDO-33005-A, Tracg Application for Emergency Core Cooling Systems / Loss-of-Coolant-Accident Analysis for BWR/2-6 Satisfaction of Limitation 10.7 ML18102B4472018-04-17017 April 2018 Letter to S. Murray Certificate of Compliance No. 9228, Revision No. 27, for the Model No. 2000 Package ML18078A5872018-04-10010 April 2018 Satisfaction of TRACG-LOCA Limitation 10.7 Draft SE Cover Letter ML18046A6392018-03-0606 March 2018 Proprietary Determination Letter for TRACG-LOCA Satisfaction of Limitation 10.7 RAI Response ML18058A1112018-02-27027 February 2018 Submittal of Revision 3 of GEH Public Version Safety Analysis Report for Certificate of Compliance Renewal of the Model No. 2000 Package ML18002A4322018-01-10010 January 2018 Final SE for Amendment to NEDO-11209 Revision 13 GE QAPD ML17342A1012018-01-0909 January 2018 Proprietary Determination Letter for Nsf Annual Experience Summary Report ML17332A6012018-01-0909 January 2018 Proprietary Determination Letter for NEDC-33840P-A, Prime Model for Transient Analysis ML17347B1992018-01-0909 January 2018 GNF2 Compliance Report Proprietary Determination Letter ML18009A6912018-01-0909 January 2018 Transmittal Letter and Affidavit for Revision 2 of GEH Safety Analysis Report for Certificate of Compliance Renewal of the Model No. 2000 Package ML17332A2962018-01-0505 January 2018 Final Safety Evaluation for Global Nuclear Fuel - Americas, LLC, Proposed Amendment 44 to NEDE-24011-P-A-24 ML17341A9432018-01-0505 January 2018 Verification Letter for the Approved Version of NEDC-33840P (Prime) ML17261A0682017-09-15015 September 2017 Submittal of NEDC-33173P, Supplement 6, Applicability of GE Methods to Expanded Operating Domains - Removal of the Safety Limit Minimum Critical Power Ratio (SLMCPR) Penalty ML14062A0442014-03-0303 March 2014 Additional Utility Support for NEDE-33766P, GEH Simplified Stability Solution (GS3) ML1032704642010-12-28028 December 2010 Letter Transmitting Final Safety Evaluation of GE Hitachi Nuclear Energy (GEH) Topical Report NEDC-33173P, Supplement 3, Applicability of GE Methods to Expanded Operating Domains - Supplement for GNF2 Fuel ML0717106152007-07-18018 July 2007 Potential Adverse Flow Effects in Nuclear Power Plants ML0702505212007-01-19019 January 2007 Request for NRC Consent to the Transfer of Control of GE Licenses to GE-Hitachi Nuclear Energy America, LLC and for Approval of Conforming Amendments ML0610803382006-04-14014 April 2006 Withholding Letter to G Strambach, GE, GE Evaluation of OPRM Performance During Instability Events at Nine Mile Point Nuclear Station 2 and Perry Nuclear Power Plant (Mfn 06-089) 2024-09-26
[Table view] |
Text
GE Hitachi Nuclear Energy M190203 November 15, 2019 Chris Allen, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material and Safeguards U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Attention: Document Control Desk
Subject:
GEH Request for Additional Time to Respond to NRC Requests for Additional Information (RAI) for the GE Model No. 2000 (Docket No. 71-9228) to Reintroduce BWR Irradiated Fuel Content Mr. Allen, Your letter dated October 23, 2019 [Reference 1] requested additional information for the review of the amendments made to Revision 3 of the GE Model No. 2000 (GE2000) Safety Analysis Report (SAR) [Reference 2] to reintroduce GE 10x10 Boiling Water Reactor (BWR) irradiated fuel as part of the approved content (referred to as Revision 4). Reference 1 requested that GE-Hitachi Nuclear Energy Americas, LLC (GEH) provide responses to these RAIs by Friday, November 22, 2019.
GEH has evaluated several options to address these RAIs based on the teleconference between the NRC and GEH on October 21, 2019. GEH has determined the best approach is to revise and resubmit a portion of the GE2000 SAR with some of the RAI response content incorporated and provide formal responses to those RAIs that will not be included in the SAR.
Revising the applicable GE2000 SAR sections and developing the formal RAI responses will require additional time. As a result, the changes made to Revision 4 of the GE2000 SAR (Revision 5) and the RAI responses will be provided to the NRC by Friday, January 31, 2020.
Christopher Kmiec GE-Hitachi Nuclear Energy Americas, LLC Lead Nuclear Engineer Radiological and Stability Analysis 3901 Castle Hayne Road Wilmington, NC 28401 USA T 910 819-3134 christopher.kmiec@ge.com
M190203 Page 2 of 2 Please contact me if you have any questions or would like to discuss this matter further.
Sincerely, Christopher Kmiec Lead Nuclear Engineer Radiological and Stability Analysis GE-Hitachi Nuclear Energy Americas, LLC Docket No. 71-9228 References
- 1. Letter from Chris Allen, Request for Additional Information for Review of the Model No. 2000 Package, October 23, 2019. United States Nuclear Regulatory Commission ADAMS Accession Number ML19296C273.
- 2. GE Hitachi Nuclear Energy, NEDO-33866, Model 2000 Radioactive Material Transport Package Safety Analysis Report, Revision 4, July 2019. United States Nuclear Regulatory Commission ADAMS Accession Number ML19212A599.
Enclosures:
None cc:
N Otto, NRC D Doyle, NRC M Catts, GEH Wilmington, NC S Murray, GEH Wilmington, NC P McCumbee, GNF Wilmington, NC S Lamb, GNF Wilmington, NC E Kirstein, GNF Wilmington, NC