Appreciates Prompt Approval of Request to Purge Containment. Approval Reduced Personnel Inconvenience & man-rem Exposure. Will Pursue Review of Containment Purge Sys
ML19242D259
Person / Time
Site: Point Beach 
Issue date: 08/10/1979
From: Burstein S
WISCONSIN ELECTRIC POWER CO.
To: Schwencer A
Office of Nuclear Reactor Regulation
References
TAC-44877, TAC-44878, NUDOCS 7908140760
Download: ML19242D259 (1)


Text

O wisconsin Electnc roata coursur 231 W. MICHIGAN, P.O. BOX 2046, MILWAUKEE, WI 53201 August 10, 1979 Mr. A. Schwencer, Chief Operating Reactors Branch 1 Office of Nuclear Reactor Regulation U. S. NUCLEAR REGULATORY COMMISSION Washington, D. C.

20555

Dear Mr. Schwencer:

DOCKET N0. 50-266 POINT BEACH NUCLEAR PLANT, UN!? 1 Last Friday afternoon, we called Mr. Tranmell of your Staff con-cerning our desire to purga the Point Beach Nuclear Plant Unit 1 containment.

We explained that this purge of approximately two hours duration would not be initiated until the reactor had been shut down and the primary system cooled down to 450 F with pressure less than 1,000 psi. This purge was necessary to facilitate maintenance during the weekend outage on Unit 1 in which reinforcement was added to the auxiliary feedwater piping connection to the main feedwater line.

We appreciate your prompt response to our request. As a result of your favorable decision on this matter, we were able to significantly reduce the inconvenience to personnel and reduce the man-rem exposure necessary to complete this task. We will promptly pursue the necessary review and/or modifications to the containment purge system so that further requests of this nature will not be necessary. Thank you for your efforts in this regard.

Very truly yours, f

Sol Burstein Exec ive Vice President Copy to Mr. J. G.

Keppler, Regicn III 90

\\