Category:Emergency Preparedness-Emergency Plan Exercise Objectives and Scenario
MONTHYEARIR 05000272/20185012018-06-0101 June 2018 and Salem Nuclear Generating Station, Units 1 and 2: Evaluated Emergency Preparedness Exercise Inspection Report 05000354/2018501, 05000272/2018501, and 05000311/2018501 ML0824004942008-08-18018 August 2008 Final Report for the Salem Hope Creek Nuclear Generating Station Radiological Emergency Preparedness Exercise Held on May 20, 2008 2018-06-01
[Table view] Category:Inspection Report
MONTHYEARIR 05000272/20240032024-10-30030 October 2024 Integrated Inspection Report 05000272/2024003 and 05000311/2024003 IR 05000354/20240032024-10-23023 October 2024 Integrated Inspection Report 05000354/2024003 IR 05000272/20244032024-09-25025 September 2024 And Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000354/20230062024-02-28028 February 2024 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2023006) IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 IR 05000354/20230032023-11-0707 November 2023 Integrated Inspection Report 05000354/2023003 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) IR 05000354/20230052023-08-31031 August 2023 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2023005) IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 IR 05000354/20230102023-08-0303 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000354/2023010 IR 05000272/20230012023-05-0303 May 2023 Integrated Inspection Report 05000272/2023001 and 05000311/2023001 IR 05000272/20233012023-05-0101 May 2023 Initial Operator Licensing Examination Report 05000272/2023301 and 05000311/2023301 IR 05000354/20230112023-05-0101 May 2023 Commercial Grade Dedication Report 05000354/2023011 IR 05000354/20230012023-04-26026 April 2023 Integrated Inspection Report 05000354/2023001 IR 05000272/20230112023-03-0707 March 2023 Comprehensive Engineering Team Inspection Report 05000272/2023011 and 05000311/2023011 IR 05000272/20220062023-03-0101 March 2023 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022006 and 05000311/2022006) IR 05000354/20220062023-03-0101 March 2023 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2022006) IR 05000272/20220042023-01-31031 January 2023 Integrated Inspection Report 05000272/2022004 and 05000311/2022004 IR 05000354/20220042023-01-24024 January 2023 Integrated Inspection Report 05000354/2022004 IR 05000272/20220112023-01-0606 January 2023 Design Basis Assurance Inspection (Programs) Inspection Report 05000272/2022011 and 05000311/2022011 ML22335A0412022-12-0101 December 2022 Notification of Commercial Grade Dedication Inspection (05000354/2023011) and Request for Information IR 05000272/20220032022-11-0909 November 2022 Integrated Inspection Report 05000272/2022003 and 05000311/2022003 IR 05000354/20220032022-11-0303 November 2022 Integrated Inspection Report 05000354/2022003 IR 05000354/20223012022-10-24024 October 2022 Initial Operator Licensing Examination Report 05000354/2022301 IR 05000272/20224022022-10-14014 October 2022 Cyber Security Report 05000272/2022402 and 05000311/2022402 - Cover Letter Only IR 05000354/20224022022-10-14014 October 2022 Cyber Security Inspection Report 05000354/2022402 - Cover Letter Only IR 05000354/20220122022-09-0808 September 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000354/2022012 IR 05000354/20220052022-08-31031 August 2022 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2022005) IR 05000272/20220052022-08-31031 August 2022 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022005 and 05000311/2022005) 2024-09-25
[Table view] Category:Letter
MONTHYEARIR 05000272/20240032024-10-30030 October 2024 Integrated Inspection Report 05000272/2024003 and 05000311/2024003 ML24296B1932024-10-23023 October 2024 Project Manager Assignment ML24295A3742024-10-23023 October 2024 Project Manager Assignment IR 05000354/20240032024-10-23023 October 2024 Integrated Inspection Report 05000354/2024003 LR-N24-0068, Core Operating Limits Report - Cycle 282024-10-21021 October 2024 Core Operating Limits Report - Cycle 28 ML24291A0572024-10-17017 October 2024 License Amendment Request (LAR) – Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 1 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) LR-N24-0059, 2024 Annual 10 CFR 50.46 Report2024-09-30030 September 2024 2024 Annual 10 CFR 50.46 Report LR-N24-0056, Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-09-26026 September 2024 Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle IR 05000272/20244032024-09-25025 September 2024 And Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities 05000354/LER-2024-001-01, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement2024-09-0505 September 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24197A0552024-07-15015 July 2024 Requalification Program Inspection ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary 05000354/LER-2024-001, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement ML24150A1002024-05-28028 May 2024 Core Operating Limits Report, Reload 25, Cycle 26, Revision 23 LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML24142A4072024-05-20020 May 2024 License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5 IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 05000272/LER-2024-001, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram 2024-09-05
[Table view] |
Text
une 1, 2018
SUBJECT:
HOPE CREEK GENERATING STATION AND SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2: EVALUATED EMERGENCY PREPAREDNESS EXERCISE - INSPECTION REPORT 05000354/2018501, 05000272/2018501, AND 05000311/2018501
Dear Mr. Sena:
On May 24, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 2. The NRC inspectors discussed the results of this inspection with Mr. Charles McFeaters, Salem Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Raymond McKinley, Chief Plant Support Branch Division of Reactor Safety Docket Nos.: 50-272, 50-311, and 50-354 License Nos.: DPR-70, DPR-75, and NPF-57
Enclosure:
Inspection Report 05000272/2018501, 05000311/2018501, and 05000354/2018501
Inspection Report
Docket Numbers: 50-272, 50-311, and 50-354 License Numbers: DPR-70, DPR-75, and NPF-57 Report Number: 05000272/2018501, 05000311/2018501, and 05000354/2018501 Enterprise Identifier: I-2018-501-0035 Licensee: PSEG Nuclear LLC Facility: Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 2 Location: Hancocks Bridge, NJ Inspection Dates: May 21 - May 24, 2018 Inspectors: J. Ambrosini, Senior Emergency Preparedness Inspector, Division of Reactor Safety (DRS)
J. DeBoer, Emergency Preparedness Inspector, DRS D. Johnson, Senior Emergency Preparedness Specialist, Office of Nuclear Security and Incident Response, Division of Preparedness and Response J. Schoppy, Senior Reactor Inspector, DRS D. Silk, Senior Operations Engineer, DRS Approved By: R. McKinley, Branch Chief Plant Support Branch Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring PSEGs performance at
Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 2 by conducting an evaluated emergency preparedness exercise inspection in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.
Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
No findings or more-than-minor violations were identified.
INSPECTION SCOPE
The inspectors conducted the inspection using the appropriate portions of the inspection procedure in effect at the beginning of the inspection unless otherwise noted. Currently approved inspection procedures with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. The inspectors determined the following samples were complete when the inspection procedure requirements were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.
REACTOR SAFETY
==71114.01 - Exercise Evaluation (1 sample)
==
The inspectors evaluated the adequacy of PSEGs conduct of the exercise and its capability to assess staff performance via a formal critique process, as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.47(b)(14).
==71114.08 - Exercise Evaluation - Scenario Review (1 sample)
==
The inspectors reviewed and evaluated the proposed scenario for biennial emergency plan
===exercise on April 20.
71151 - Performance Indicator Verification===
Main article: IP 71114.08
The inspectors verified licensee performance indicators submittals listed below for the period from January 2017 through March 2018.
- (1) Drill and Exercise Performance
- (2) Emergency Response Organization Drill Participation
- (3) Alert and Notification System
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On May 24, the inspectors presented the inspection results to with Mr. Charles McFeaters, Salem Vice President, and other members of the PSEG staff.
LIST OF
DOCUMENTS REVIEWED
Section 1EP1: Exercise Evaluation
Salem Nuclear Generating Station Emergency Preparedness Plan
Salem Nuclear Generating Station Emergency Preparedness Plan Implementing Procedures
Salem Nuclear Generating Station May 22, 2018 Graded Exercise Scenario Package
Salem Drill Reports 2016-2018
Section 1EP8: Exercise Evaluation - Scenario Review
Salem Nuclear Generating Station Emergency Preparedness Plan
Salem Nuclear Generating Station Emergency Preparedness Plan Implementing Procedures
Salem Nuclear Generating Station May 22, 2018 Graded Exercise Scenario Package
Salem Drill Reports 2016-2018
Section 4OA1: Performance Indicator (PI) Verification
DEP PI data, January 2017 - March 2018
ERO Drill Participation PI data, January 2017 - March 2018
ANS Reliability PI data, January 2017 - March 2018