April 18, 1988
'ocket Nos.:
50-528, 50-.529 and 50-530 Mr. E.
E.
Van Brunt, Jr.
Executive Vice President Arizona Nuclear Power Project Post Office Box 52304 Phoenix, Arizona 85072-2034 DISTRIBUTION Docket File
-NRC 8 Locel:FDRe PD5 Reading DMCrutchfield IGMHolahan
'JLee GKnighton
,EALicitra
,MJDa.v,is.
Dear Mr. Van Brunt:
SUBJECT:
EVALUATION OF THE NATURAL CIRCULATION COOLDONN CAPABILITY FOR PALO VERDE (TAC NOS.
56647 AND 56648)
EJordan JPartl ow ACRS (10)
By letter dated February 9, 1987, you provided
'a report on the Natural Circulation Cooldown Test performed at Palo 'Verde.
'Me have now completed our review of the report.
Based on that review,.we have concluded that the test results combined with the supporting analysis demonstrate that the plant meets the requirements of BTP RSB 5-1 for a Class 2 plant.
Our detailed evaluation is provided as Enclosures I and 2.
As noted in our evaluation, we recommend that you review the enclosed documents and consider the need to include in your emergency operating procedures the capability to account for rapid increases in pressurizer level if the use of the reactor head vents is a necessary method of cooldown.
If you have any questions regarding this letter, please let me know.
Sincerely, original, signed by
Enclosures:
As stated E. A. Licitra, Senior Project Manager Project Directorate V
Division of Reactor Projects - III, IV, V and Special Projects cc w/enclosure:
See next page DRSP/PDV+gP D
- PDV EALicitrF~~
'hton
// //g/88
/( /88 sea+geon~>
~saO05ae
@0418 pgR gDOCH 0 pgg P
il Ik l1 1
E I
I
" l
+
'tl
~
'l
~p,lE REG(((
(4 0+
Cy 00 Op
++*++
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 April 18, 1988 Docket Nos.:
50-528, 50-529 and 50-530 Mr. E.
E.
Van Brunt, Jr.
Executive Vice President Arizona Nuclear Power Project Post Office Box 52304 Phoenix, Arizona 85072-2034
Dear Mr. Van Brunt:
SUBJECT:
EVALUATION OF THE NATURAL CIRCULATION COOLDOWN CAPABILITY FOR PALO VERDE (TAC NOS.
56647 AND 56648)
By letter dated February 9, 1987, you provided a report on the Natural Circulation Cooldown Test performed at Palo Verde.
We have now completed our review of the report.
Based on that review, we have concluded that the test results combined with the supporting analysis demonstrate that the plant meets the requirements of BTP RSB 5-1 for a Class 2 plant.
Our detailed evaluation is provided as Enclosures 1 and 2.
As noted in our evaluation, we recommend that you review the enclosed documents and consider the need to include in your emergency operating procedures the capability to account for rapid increases in pressurizer level if the use of the reactor head vents is a necessary method of cooldown.
If you have any questions regarding this letter, please let me know.
Sincer ely,
Enclosures:
As stated E. A. Licitra, Senior Project Manager Project Directorate V
Division of Reactor Projects - III, IV, V and Special Projects cc w/enclosure:
See next page
0 0
C
Hr.
E.
E.
Van Brunt, Jr.
Arizona Nuclear Power Project Palo Verde CC:
Arthur C. Gehr, Esq.
Snell 5 Wilmer 3100 Valley 'Center Phoenix, Arizona 85073 Mr. James M. Flenner, Chief 'Counsel Arizona, Corporation Commission 1200 West Washington Phoenix, Arizona 85007 Charles R.
Kocher-,
Esq. Assistant Council James A. Boeletto, Esq.
Southern California Edison Company P. '0.
Box 800
- Rosemead, California 91770 Hr. Mark Ginsberg Energy Director Office of Economic Planning and, Development 1700 West Washington - 5th Floor Phoenix, Arizona 85007 Hr. Wayne Shirley Assistant Attorney General Bataan Memorial Building Santa Fe, New Mexico 87503 Mr. Tim,Polich U.S. Nuclear Regulatory Commission P'. 0.
Box 97 Tonopah, Arizona 85354-0097 Regional Administrator, 'Region V
U'., S. Nuclear Regulatory Commission 1'450 Maria Lane Suite 210 Walnut Creek, California 94596 Kenneth Berlin, Esq.
Winston 5 Strawn Suite 500.
2550 M.Street, NW Washington, DC 20037 Hs.
Lynne Bernabei'overnmentAccountability Project of the Institute for Pol'icy Studi'es 1901 Que Street, NW Washington, DC 20009 Mr. Ron Rayner P. 0.
Box 1509'oodyear,AZ 85338 Hr. Charles B. Brinkman, Manager Washington Nuclear Operations Combustion Engineering, Inc.
7910 Woodmont. Avenue Suite 1310 Bethesda,,
Maryland 20814
il
Chairman Arizona Corporation Commission Post Office Box 6019 Phoenix, Arizona 85003 Arizona Radiation Regulatory Agency ATTN:
Ms. Clara Palovic, Librarian 4814 South 40 Street
.Phoenix, Arizona 85040 Mr. Charles Tedford, Director Arizona Radiation Regulatory Agency 4814 South 40 Street Phoenix, Arizona 85040 Chairman Maricopa County Board of Supervisors 111 South Third Avenue Phoenix, Arizona 85003
0 Il