ML17299A554

From kanterella
Jump to navigation Jump to search

Documents Actions to Resolve NRC Concerns Re Natural Circulation Testing Program.Testing Capability to Cool Down Plant from Hot Standby to Cold Shutdown Under Natural Circulation Will Be Demonstrated
ML17299A554
Person / Time
Site: Palo Verde 
Issue date: 08/29/1985
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Knighton G
Office of Nuclear Reactor Regulation
References
ANPP-33282-EEVB, TAC-56647, NUDOCS 8509040159
Download: ML17299A554 (6)


Text

REGULAT NFORMATION DISTRIBUTION EM (RIDS)

ACCESSION NBR; 8509000159 DOC ~ DATE: 85/08/29 NOTARIZED:

NO DOCKET FACIL:STN"50-528 Palo Yerde Nuclear Stationi Unit 1P Arizona Publi 05000528 AUTH BYNAME AUTHOR AFFILIATION YAN BRUNTiE;E ~

Arizona Nuclear Power Project (for meri y Arizona Publ ic Serv RECIP ~ NAME, RECIPIENT AFFILIATION KNIGHTONg G ~ N ~

Licensing Branch 3

SUBJECT; Documents actions to resolve NRC concerns re natural circulation testing program. Testing capability to cool down plant from hot standby to cold shutdown under natural circulation will be demonstrated, DISTRISUTION CODE:

A0580 COPIES RECEIVED:LTR QENCL SIZE:

TITLE:

OR Submittal:

Natural Circ Cooldown GL 81 21 Multiplant Action B.-66 NOTES:Standardized plant ~

OL: 12/31/84 05000528 RECIPIENT ID CODE/NAME NRR LB3 BC 01 INTERNAL: ACRS 09 ELD/HDS3 NRR/DL/ORAB NRR/DSI/RSB RGN5 COPIES LTTR ENCL 10 1

1 1

1 RECIPIENT ID CODE/NAME ADM/LFMB NRR/DL D IR RB3 REG FILE 04 COPIES LTTR ENCL EXTERNAL; 24X NRC PDR 02 LPDR NSIC 03 05 TOTAL NUMBER OF COPIES REQUIRED:

LTTR 35 ENCL 32

1 4

'i pl

&4 i

~ f

Arizona Nuclear Power Project P.o. BOX 52034

~

PHOENIX, ARIZONA85072-2034 Director of Nuclear Reactor Regulation Attention:

Mr. George W. Knighton, Chief

Licensing Branch No.

3 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D. C.

20555 August 29, 1985 ANPP-33282-EEVB/BJA

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Unit 1 Docket No.

STN 50-528, License No. NPF-41 PVNGS Unit 1 Natural Circulation Testing Program File:

85-056-026'.l.01.10

References:

(1)

Letter from E. E. Van Brunt, Jr.,

ANPP, to G.

W. Knighton, NRC, dated January 31, 1985 (ANPP=31829).

Subject:

Natural Circulation Cooldown Testing.

(2)

ANPP meeting with the NRC Staff on June 27, 1985, at Bethesda, MD.

Subject:

PVNGS Natural Circulation Cooldown Testing.

(3)

Telecon of July 10, 1985 with E. A. Licitra and C. Liang of the NRC Staff.

Subject:

PVNGS Natural Circulation Cooldown Testing.

Dear Mr. Knighton:

ANPP held a meeting with the NRC Staff on June 27,.1985 to discuss the PVNGS Unit 1 Natural Circulation Testing Program.

,The NRC Staff raised several questions during this meeting which were discussed in the telecon of Reference (3).

The purpose of this submittal is to formally document the actions that ANPP has taken to resolve the NRC concerns.

ANPP has revised the Natural Circulation Cooldown Test Procedure which has been submitted previously by Reference (1).

The following changes have been made to the procedure.

It should be noted that these changes were discussed during the telecon of Reference (3).

iv)

The procedure has been modified to assume a single failure (i.e., failure of one of the emergency diesel generators).

Only one train 'of safety related equipment will be used during the 'test.

The letdown portion of the Chemical and Volume Control System will be secured during the portion of the depressurization where the auxiliary pressurizer spray system is utilized.

The pressurizer heaters will not be utilized during the test.

However, the pressurizer heaters will be available for use during the test.

Only two of, the three charging pumps will be used during the test.

However, the third charging pump will be available for use during the test.

ANPP will demonstrate by testing the capability to cooldown the plant under natu-ral circulation conditions from hot standby conditions to cold shutdown conditions.

8509040159 850829 t

PDR ADOCK 05000528 P

PD~R

d' h

I

G.

M. Knfghton

'Natural Circulation Testing Program

  • 'NPP-33282 Page 2

The demonstration will be conducted by one of'he following two methods:

A single test that conducts a Natural Circulation Cooldown from hot standby to cold shutdown conditions.

Two separate tests:

The first test will perform a Natural Circulation Cooldown from hot standby to shutdown cooling initiation conditions.

The second test will demonstrate the capability to cooldown the plant from shutdown cooling initiation conditions to cold shutdown.

Additionally, data from the Natural Circulation Cooldown Test will be used to verify the effectiveness of the auxiliary pressurizer spray system for the Steam Generator Tube Rupture Event.

If you have any additional questions on this matter, please contact Mr. N. F. Quinn of my staff.

Very truly ou CRA'A E. E.

Van Brunt, Jr.

Executive Vice President Project Director EEVB/BJA/slh cc:

E. A. Licitra A. C. Gehr R. P.

Zimmerman C. Liang