ML17037B649
| ML17037B649 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 12/23/1976 |
| From: | Lear G Office of Nuclear Reactor Regulation |
| To: | Rhode G Niagara Mohawk Power Corp |
| References | |
| Download: ML17037B649 (16) | |
Text
Docket No.60-220 Niagara Hohauk Power Corporation ATTt<: t/r. Gerald K. Rhode Yice President - Engineerinq 300 Erie Boulevard l/est
. Syracuse, New York 13202 Gentlemen:
RE: NINE NILE, POINT NUCLEAR STATION IJl/IT NO.
1
!fe have completed our preliminary revievi of the "Hark I Containment Program Action Plan" which was submitted on behalf of the Hark I Owners Group by the General Electric Company on October 29, 1976, and
~hich you subsequently endorsed in your letter to the HRC dated November 3, 1976.
At the present time the Program Action Plan (PAP) serves as our prirlary source of infomatinn regarding the Nark I Contafnmont Long Term Program (LTP). Although the PAP provides infomation relating to the interaction and schedulinq of specific tasks in the LTP, its docwentation of the LTP task objectives and descriptions is too general and lacks sufficient detail to permit a detemination of the adequacy of the specific LTP tasks.
As they are no1~ presented, many of the task descriptions only augment the statement of task objectives rather than delineate the methods that will be utilized to acco~plish each objective.
- Consequently, Me believe that the PAP should be revised to describe, in detail, tlute objectives and associated methods to achieve each LTP task.
Additional comments, for use in preparation of a revision to the PAP, are presented in Enclosure l.
)le have also found that the schedules for those tasks relating to the definition of stean loads and to th identification of potential load mitigating devices are poorly defined in the PAP.
1fhile we realize that this situation reflects 'the onqoing efforts of the Hark I Owners Group to develop an effective program to acconplish these tasks, we believe that you should make every effort to establish a comibaient to a well-defined program in as timely a manner as is practicable.
Therefore, wo request that you be prepared to discuss the details of these tasks and their schedules for completion at. meetings beb<een the rIiaIkOwners Group and the IIPC staff during the week of Januar 24, Pjg
~(
OPPICd&
dIIRNAMdW DATd&
NRC FORM 518 (9-1'6) NRCM 0240 4 VS $. OOVdRNMdNTPRINTINO OPPICda SOTd dda<d4
0 i
Jt A
[
.Niagara Hoha>>k Power Corporation 1977.
- Horeover, we request that, you provide documentation of the details of these programs in a revision to the t'Iark I Containment Program Action Plan to be submitted to the NRC no later than January 31, 1977.
Sincerely,
Enclosures:
1.
NRC Staff Comments on Program Action Plan 2.
NRC Load Verification Require<I~ents for the Hark I Containment Long Term Program 3.
Load Ver ification Require-nents Not Adequately Addressed cc:
Arvin E. Upton, Esquire
- LeBoeuf, Lamb, Leiby 8 HacRae 1767 N Street, N. W.
Washington, D. C.
20036 Anthony Z. Roi snan, Esquir e Rois@an, t,'essler and Cashdan 1026 15th Street, W.
W.
5th Floor Vashington, D. C.
20006 George Lear, Chief Operating Reactors Branch ¹3 Division of Operating Reactors DISTRIBUTION:
Docket NRC PDR Local PDR ORB¹3 Rdg TJCarter GLear CParrish SNowicki JGuibert OELD OI8E (3)
DEisenhut TBAbernathy JRBuchanan ABRS (16)
File fir. Eugene G. Saloga, Applicant, Coordinator Nine file Point Energy Information Center P. 0.
Box Sl Lycoming, Ne:r York 13093 OREICEW SDRHAMEW DATE&
ORB JGuib:acr 12/ g~/76 ORB¹3 SNowicki 12/ Z@
7-6 ORB¹3 Lear G
12/ Z
/76.
NRC FORM 318 (9-76) NRCM 0240 4 UI 8 ODVERHMENT PRIHTINO DEFICE1 IOTO EE~SZ
I I'
l g
I' I
'q"
~ l fh<$ $ I i~a tgti W 1i S l fl<,I,
~ lI t ~ A, ll~Qi.,
I k.:~
'I t
i ilPIIW r li.=li l
l ~
-)(Ip J fy' l'
~
If)
III A
I I (,
Il I
l' 7
li
~ - ll I'I l
4 It II 4
~,
l lf
'() a'1 lli tY>i@1
3.
Drag Loads on Submerged Components A.
Consider effect of differential pressure across structure due to bubble propagation B.
Obtain 3D test data to confirm horizontal and vertical pool velocities for submerged
'tructure drag loads STP basis is based on PSTF tests considering a best fit of data for plain cylinders.
Results of future tests should include the actual vent system geometry.
This is an unresolved generic concern common to teak I, II and III containments.
STP estimate of these parameters based on 2D tests is not based on an adequate test data base
Item Basis 4.
Steam Loads (Downcomers, Submerged Structures, and Torus Boundary)
Additional two-dimensional full scale testing Confirmation of current test data used in the analysis is needed since the data is limited and is a reflection of a containment dgsiqn quite different from Mark I.
5.
SRY Loads A.
Additional tests (Monticel lo tests) required SRV loads not addressed during STP (fatigue concern).
Inadequate data base for SRV loads.
B.
Consider sinole active failure in the SRV system.
6.
Seismic Slosh Loads Ho current basis for excluding pool loads due to LOCA + (1)
SRV as currently required for Mk II and III designs.
Perform tests to determine load magnitude.
Definition of this load was deferred to the LTP.
7.
Secondary Loads (Tests and/or Analyses)
A.
Vent System Thrust Confirmation of the STP calculated loads in the header is needed B.
Froth and Fallback Effects C.
Post Pool Swell Waves GE 1/12 tests are not applicable beyond breakthrough point.
Same as B
V
ENCLOSURE 3 NRC LOAD VERIFICATION REQUIREMENTS MHICH ARE NOT ADEQUATELY ADDRESSED Me have compared the NRC staff load verification requirements for the Long Term Program (LTP), as identified during our review of the Short Term Program (STP), with the commitments obtained from the Hark I Owners in the Program Action Plan and in a letter from General Electric to the NRC (L. Sobon to Y. Stello) dated August 25, 1976, both of which have been referenced on the docket by each t3ark I Owner.
From this comparison we have identified those requirements for which commitments from the tiark I Owners remain outstanding or need clarification.
These requirements, described below, should be addressed in the PAP.
l.
Durino the STP we identified a need for additional test.data to confirm the validity of the sensi tivitv parameters used to determine plant unique loads.
These additional test data are required to confirm pool swell load variation over the range of plant unique conditions.
The tiark I owners indicated in a meeting with the NRC staff on August 19th that the capability exists to obtain the required data by modification of the 1/4 scale 2D test facility tn other geometries and test conditions.
However, the )lark I Owners Group has not yet committed to provide a test data base over the range of the sensitivity parameters (i.e., plant conditions) identified in the STP.
An additional concern relates to confirmation of the validity of the selection process for the sensitivity parameters (e.g., vent area to pool area ratio) which were utilized in the STP.
The set of sensitivity parameters utilized in the STP were selected on the basis of engineering judgement; however, further consideration indicates that some of the sensitivity parameters may interrelate with the scaling laws.
Therefore, the appropriateness of the sensitivity parameters utilized in the STP must be reexamined and justified in the LTP.
Both of the above-mentioned requirements are applicable regardless of whether the plant unique loads in the LTP are determined from sensitivity parameters or from an analytical model, since the analytical code verification will probably be established using sensitivity factors.
(Refer to item 1.0 of enclosure 2) 2.
In our August 19th meeting with the Owners Group, we discussed (a) a need for a closer match between the calculated and measured drywell pressuriza-tion and enthalpy flux in the LTP test programs, (b) consideration of the effects of mass and energy inventory, downstream of the flow restrictions, on the calculated blowdown, (c) consideration of the sensitivity of the pool dynamic load to the vent system losses, and (d) the effects of the type of break (i.e., main steam or recirculation) on the pool swell loads.
Based on the material presented by the Hark I Owners Group, it is not
<<3
~ g 3 ~
clear that the interrelationships between these concerns are being considered in the proper sequence.
We believe that the Mark I Owners Group should first study the changes in the drywell pressurization and enthalpy flux rates as a function of changes in blowdown, vent system losses, and break type.
- Secondly, the revised drywell pressurization and enthalpy flux rates resulting from this study should be matched in the 1/4 2D scale and the 1/12 scale 30 test runs which are intended to improve the load data base.
This requirement does not apply to those direct comparison test runs which are intended to verify the scaling relationships.
(Refer to item 1.H of enclosure 2)
On August 19th, the Owners Group agreed to perform a sensitivity study to compare the containment response for ( 1) a main steam line break and (2) a recirculation line break.
The Program Action Plan (Task 2.5) includes a commitment to perform a single representative analysis to satisfy this requirement.
The proposed use of a single analysis must be justified in the LTP.
(Refer to item 1.H.3 of enclosure 2)
~
~
4 On August 19th, the Hark I Owners Group agreed to quantify horizontal and vertical pool velocities for submersed drag loads and also verbally referenced the Mark III pool dynamics evaluation with regard to the differential pressure loads resulting from bubble propagation.
The Mark I Owners Group should conmit to the adoption of the generic resolution of bubble propagation loads common to all GE designed BWR containments.
(Refer to item 3.A of enclosure 2)
A new requirement for the LTP concerns the vent system thrust loads.
In the STP, the vent system thrusts oads were calculated with a "nominal" vent system loss coefficient and a mass flow rate which is conservative with respect to drywell Dressurization.
As discussed in item 2 above, the drywell pressurization will be reevaluated as part of the LTP.
The Mark I Owners Group should similarly commit to reevaluate the vent system pressurization and thrust loads in the LTP considering the range of vent system losses and mass flow rates that are conservative with respect to the vent system.
(Refer to item 7.A of enclosure 2)