MONTHYEARML24284A0042024-10-16016 October 2024 Application to Use Online Monitoring Methodology for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant Session Slides ML24228A2312024-08-15015 August 2024 TVA Meeting Slides for August 19 Public Meeting Re QAPD Supplement ML24149A1332024-05-29029 May 2024 Pre-Submittal Meeting for Proposed License Amendment Regarding Hydrologic Analysis Updates Public Portion Meeting Slides ML24113A0962024-04-22022 April 2024 RIPE Pre-Submittal Meeting Slides ML24078A2722024-04-10010 April 2024 Subsequent License Renewal Public Scoping Meeting ML24067A2832024-03-27027 March 2024 2023 Browns Ferry, Sequoyah and Watts Bar Annual Assessment Public Meeting Presentation Slides ML24032A2752024-02-0707 February 2024 Pre-Pre-Submittal Meeting for Proposed License Amendment Regarding Hydrologic Analysis Updates (Slides) ML24019A1512024-01-22022 January 2024 Slides - Modification of Browns Ferry Technical Specifications to Eliminate LCO 3.3.2.1 Actions C.2.1.1 and C.2.1.2 for Rod Worth ML23130A0912023-05-11011 May 2023 TVA Browns Ferry Nuclear Plant Safety Pre-Application Public Meeting Slides 05/11/2023 ML23130A0922023-05-11011 May 2023 NRC Browns Ferry Nuclear Plant, Units 1, 2, and 3, Subsequent License Renewal Application, Public Meeting Slides ML23128A2882023-05-0808 May 2023 TVA Nuclear Plants -2022 EOC Media Slides ML23025A0472023-01-25025 January 2023 Pre-Submittal Meeting for Proposed License Amendment Request Regarding Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves - January 25, 2023 ML22285A1902022-10-13013 October 2022 October 13, 2022 Public Meeting on 5th Interval Alternative Planned Requests - Licensee Slides ML22277A6562022-10-0606 October 2022 Subsequent License Renewal Application - SAMA Pre-Application Meeting October, 2022 (TVA Slides) ML22279A8992022-10-0606 October 2022 Subsequent License Renewal Application - SAMA Pre-Application Meeting October 6, 2022-TVA Slides ML22264A2332022-09-22022 September 2022 Slides for Pre-Submittal Meeting for Request to Use a Later Edition of the ASME OM Code for the Fifth Inservice Testing (IST) 10-Year Interval ML22080A1662022-03-21021 March 2022 TVA Nuclear Plants -2021 EOC Media Loop Slides for Automatic Play ML21281A2282021-10-13013 October 2021 Tennessee Valley Authority Fleet Pre-Submittal Meeting for License Amendment Request to Change Emergency Action Level Scheme Presentation - October 13, 2021 (EPID L-2021-LRM-0096) (Slides) ML21270A0322021-09-27027 September 2021 Presentation Slides for Browns Ferry Pre-submittal Public Meeting September 27, 2021 ML21265A0422021-09-21021 September 2021 Presentation Slides for Browns Ferry Pre-submittal Public Meeting 09/22/2021 ML21250A3012021-09-0707 September 2021 TVA Slides for September 7, 2021, Presubmittal Meeting to Discuss Planned Browns Ferry TSTF-505 License Amendment Request ML21152A1872021-06-0101 June 2021 TVA Slides for June 1, 2021, Presubmittal Meeting to Discuss Planned Control Bay Chiller Cross-Tie License Amendment Request ML24019A1322020-11-0909 November 2020 ANP-3874NP, Revision 1, Browns Ferry Atrium 11 Control Rod Drop Accident Analysis with the AURORA-B CRDA ML20175A0552020-06-23023 June 2020 TVA Slides for June 23, 2020, Emergency Plan Change Presubmittal Meeting ML20156A2812020-06-0808 June 2020 TVA Slides for June 8, 2020, ATRIUM-11 Presubmittal Meeting ML20092F5742020-04-0202 April 2020 TVA Slides for Browns Ferry 50.69 License Amendment Request Presubmittal Meeting ML20049G1822020-02-18018 February 2020 February 20, 2020 - Pre-submittal Meeting Presentation - Transition to Westinghouse Fuel ML20022A0262020-01-22022 January 2020 NEI Presentation Status Update for Ropte Short Term Action Plan: Removed Planned Unavailability for Mitigating Systems Performance Index ML24019A1482019-01-28028 January 2019 Surveillance Procedure 2-SR-3.1.6.1, BPWS Compliance Verification, Revision 006 ML18255A0102018-09-12012 September 2018 NRC Slides for Target Rock Public Meeting ML18255A0142018-09-12012 September 2018 BWROG Presentation Slides for Public Meeting Sept 12 2018 ML18239A2522018-08-27027 August 2018 Proposed Changes to NFPA 805 License Conditions ML18158A2862018-06-0707 June 2018 May 30, 2018 Summary of Public Meeting with Browns Ferry Nuclear Plant, Docket No. 50-259, 50-260, and 50-296 ML17271A0162017-09-28028 September 2017 Meeting Slide for Tennessee Valley Authority (TVA) Hydrology Precipitation Model Topical Report Review Status ML17212A8432017-08-0101 August 2017 Meeting Slides for Pre-submittal Meeting with Tennessee Valley Authority on Unbalanced Voltage License Amendment Request for TVA Nuclear Plants ML17034A3322017-02-0303 February 2017 Presentation Slides for Public Meeting Regarding Browns Ferry Extended Power Uprate License Amendment Request Transmission System Update Supplements ML16341A7422017-01-0404 January 2017 Presentation Slides for Browns Ferry Pre-application Meeting Regarding Mellla+ ML16356A0342017-01-0404 January 2017 Pre-app Meeting Mellla+ LAR Final ML16350A2962016-12-14014 December 2016 Enclosure 3- Reactor Oversight Process Task Force FAQ Log- November 16, 2016 ML16279A2332016-10-0505 October 2016 Summary of Closed Pre-Decisional Enforcement Conference with Tennessee Valley Authority Regarding Browns Ferry Nuclear Plant ML16189A3482016-07-19019 July 2016 Presentation Slides for July 19, 2016, Public Meeting ML16200A2592016-07-19019 July 2016 July 19, 2016: NRC Public Meeting on Browns Ferry Nuclear Plant Extended Power Uprate License Amendment Request ML16028A0962016-02-0101 February 2016 Emergency Core Cooling System Preferred Pump Logic, Common Accident Signal Logic, and Unit Priority Re-Trip Logic License Amendment Request ML15308A1002015-11-10010 November 2015 Public Meeting Presentation Slides Extended Power Uprate License Amendment Request NRC Public Meeting ML15195A1252015-07-14014 July 2015 July 14, 2015 - Public Meeting Slides on Browns Ferry Seismic Risk Insights ML15293A4582015-07-14014 July 2015 Slides for July 14, 2015 Public Meeting on Browns Ferry Seismic Risk Evaluations (MF3764 Through MF3766) CNL-15-122, Presentation Slides for Closed Meeting Extended Power Uprate (EPU) License Amendment Request2015-07-0808 July 2015 Presentation Slides for Closed Meeting Extended Power Uprate (EPU) License Amendment Request ML15146A2792015-05-21021 May 2015 Bf EOC Meeting Summary 2015 ML15099A2912015-04-22022 April 2015 4/22/2015, Enclosure 2, Slides for TVA Presentation to the NRC in Support of Steam Dryer Replacement ML14147A3222014-05-27027 May 2014 Public Meeting Summary 05/21/2014 to Present Annual Assessment 2024-08-15
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24284A0042024-10-16016 October 2024 Application to Use Online Monitoring Methodology for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant Session Slides ML24228A2312024-08-15015 August 2024 TVA Meeting Slides for August 19 Public Meeting Re QAPD Supplement ML24184B9162024-07-10010 July 2024 U.S. NRC Meeting Slides for Meeting with Tennessee Valley Authority Regarding NRC Questions Regarding Scope of Nuclear Quality Assurance Program ML24149A1332024-05-29029 May 2024 Pre-Submittal Meeting for Proposed License Amendment Regarding Hydrologic Analysis Updates Public Portion Meeting Slides ML24113A0962024-04-22022 April 2024 RIPE Pre-Submittal Meeting Slides ML24078A2722024-04-10010 April 2024 Subsequent License Renewal Public Scoping Meeting ML24067A2832024-03-27027 March 2024 2023 Browns Ferry, Sequoyah and Watts Bar Annual Assessment Public Meeting Presentation Slides ML24032A2752024-02-0707 February 2024 Pre-Pre-Submittal Meeting for Proposed License Amendment Regarding Hydrologic Analysis Updates (Slides) ML24019A1512024-01-22022 January 2024 Slides - Modification of Browns Ferry Technical Specifications to Eliminate LCO 3.3.2.1 Actions C.2.1.1 and C.2.1.2 for Rod Worth ML23130A0912023-05-11011 May 2023 TVA Browns Ferry Nuclear Plant Safety Pre-Application Public Meeting Slides 05/11/2023 ML23130A0332023-05-11011 May 2023 NRC Presentation Browns Ferry Subsequent License Renewal Pre-application Meeting, Environmental Overview ML23130A0922023-05-11011 May 2023 NRC Browns Ferry Nuclear Plant, Units 1, 2, and 3, Subsequent License Renewal Application, Public Meeting Slides ML23130A0302023-05-10010 May 2023 TVA Presentation Browns Ferry Nuclear Plant Subsequent License Renewal License Application – Environmental Report ML23128A2882023-05-0808 May 2023 TVA Nuclear Plants -2022 EOC Media Slides ML23025A0472023-01-25025 January 2023 Pre-Submittal Meeting for Proposed License Amendment Request Regarding Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves - January 25, 2023 ML22285A1902022-10-13013 October 2022 October 13, 2022 Public Meeting on 5th Interval Alternative Planned Requests - Licensee Slides ML22277A6562022-10-0606 October 2022 Subsequent License Renewal Application - SAMA Pre-Application Meeting October, 2022 (TVA Slides) ML22279A8992022-10-0606 October 2022 Subsequent License Renewal Application - SAMA Pre-Application Meeting October 6, 2022-TVA Slides ML22264A2332022-09-22022 September 2022 Slides for Pre-Submittal Meeting for Request to Use a Later Edition of the ASME OM Code for the Fifth Inservice Testing (IST) 10-Year Interval ML22080A1662022-03-21021 March 2022 TVA Nuclear Plants -2021 EOC Media Loop Slides for Automatic Play ML21281A2282021-10-13013 October 2021 Tennessee Valley Authority Fleet Pre-Submittal Meeting for License Amendment Request to Change Emergency Action Level Scheme Presentation - October 13, 2021 (EPID L-2021-LRM-0096) (Slides) ML21270A0322021-09-27027 September 2021 Presentation Slides for Browns Ferry Pre-submittal Public Meeting September 27, 2021 ML21265A0422021-09-21021 September 2021 Presentation Slides for Browns Ferry Pre-submittal Public Meeting 09/22/2021 ML21250A3012021-09-0707 September 2021 TVA Slides for September 7, 2021, Presubmittal Meeting to Discuss Planned Browns Ferry TSTF-505 License Amendment Request ML21152A1872021-06-0101 June 2021 TVA Slides for June 1, 2021, Presubmittal Meeting to Discuss Planned Control Bay Chiller Cross-Tie License Amendment Request ML21096A1002021-04-0606 April 2021 Annual Assessments ML20175A0552020-06-23023 June 2020 TVA Slides for June 23, 2020, Emergency Plan Change Presubmittal Meeting ML20156A2812020-06-0808 June 2020 TVA Slides for June 8, 2020, ATRIUM-11 Presubmittal Meeting ML20112F5302020-04-21021 April 2020 TVA Nuclear Plants -2019 EOC Media Loop Slides for Automatic Play (Final) ML20092F5742020-04-0202 April 2020 TVA Slides for Browns Ferry 50.69 License Amendment Request Presubmittal Meeting ML20049G1822020-02-18018 February 2020 February 20, 2020 - Pre-submittal Meeting Presentation - Transition to Westinghouse Fuel ML20022A0262020-01-22022 January 2020 NEI Presentation Status Update for Ropte Short Term Action Plan: Removed Planned Unavailability for Mitigating Systems Performance Index ML19120A3692019-04-30030 April 2019 Public Meeting Summary - Browns Nuclear Plant, Docket No. 50-259, 50-260, and 50-296 ML18255A0142018-09-12012 September 2018 BWROG Presentation Slides for Public Meeting Sept 12 2018 ML18158A2862018-06-0707 June 2018 May 30, 2018 Summary of Public Meeting with Browns Ferry Nuclear Plant, Docket No. 50-259, 50-260, and 50-296 ML17271A0162017-09-28028 September 2017 Meeting Slide for Tennessee Valley Authority (TVA) Hydrology Precipitation Model Topical Report Review Status ML17212A8432017-08-0101 August 2017 Meeting Slides for Pre-submittal Meeting with Tennessee Valley Authority on Unbalanced Voltage License Amendment Request for TVA Nuclear Plants ML17034A3322017-02-0303 February 2017 Presentation Slides for Public Meeting Regarding Browns Ferry Extended Power Uprate License Amendment Request Transmission System Update Supplements ML16356A0342017-01-0404 January 2017 Pre-app Meeting Mellla+ LAR Final ML16341A7422017-01-0404 January 2017 Presentation Slides for Browns Ferry Pre-application Meeting Regarding Mellla+ ML16279A2332016-10-0505 October 2016 Summary of Closed Pre-Decisional Enforcement Conference with Tennessee Valley Authority Regarding Browns Ferry Nuclear Plant ML16189A3482016-07-19019 July 2016 Presentation Slides for July 19, 2016, Public Meeting ML16200A2592016-07-19019 July 2016 July 19, 2016: NRC Public Meeting on Browns Ferry Nuclear Plant Extended Power Uprate License Amendment Request ML16153A1982016-06-0101 June 2016 2015 EOC Meeting Summary ML16028A0962016-02-0101 February 2016 Emergency Core Cooling System Preferred Pump Logic, Common Accident Signal Logic, and Unit Priority Re-Trip Logic License Amendment Request ML16006A2882016-01-0606 January 2016 Significant Operational Experience: 7 Major Industry Events with Regulatory Implications ML15308A1002015-11-10010 November 2015 Public Meeting Presentation Slides Extended Power Uprate License Amendment Request NRC Public Meeting ML15293A4582015-07-14014 July 2015 Slides for July 14, 2015 Public Meeting on Browns Ferry Seismic Risk Evaluations (MF3764 Through MF3766) ML15195A1252015-07-14014 July 2015 July 14, 2015 - Public Meeting Slides on Browns Ferry Seismic Risk Insights CNL-15-122, Presentation Slides for Closed Meeting Extended Power Uprate (EPU) License Amendment Request2015-07-0808 July 2015 Presentation Slides for Closed Meeting Extended Power Uprate (EPU) License Amendment Request 2024-08-15
[Table view] |
Text
Browns Ferry Nuclear Plant Extended Power Uprate License Amendment Request NRC Public Meeting Gerry Doyle Director EPU July 19, 2016
BFN EPU - Agenda Introductions G Doyle Extended Power Uprate (EPU) Background D Green EPU Overview P Donahue License Amendment Request (LAR) Review D Green
- Request for Additional Information (RAI) Status
- Status of Safety Evaluation Input Questions/Comments G Doyle Browns Ferry EPU License Amendment Request l 2
BFN EPU - Introductions Gerry Doyle - Director, EPU Pete Donahue - EPU Engineering Manager Dan Green - EPU Licensing Manager Ed Schrull - Fleet Licensing Manager Browns Ferry EPU License Amendment Request l 3
BFN EPU - Background Browns Ferry is pursuing a power uprate Current Licensed Thermal Power: 3458 MWt Extended Power Uprate Power: 3952 MWt Constant Pressure Power Uprate 1050 psia Steam Dome Pressure Maximum Extended Load Line Limit Analyses power/flow map is retained Feedwater and Steam Flow Increased Browns Ferry EPU License Amendment Request l 4
BFN EPU - Background Previous EPU LARs withdrawn on September 18, to be replaced by new consolidated EPU LAR in September 2014 October 2015 October 2014 Fuel Safety Analysis Report Pre-application meeting on October 14 with NRC January 2015 Pre-application meeting for 10 CFR 50.46c on January 15 April 2015 Pre-application meeting for Startup Test Plan on April 7 Pre-application meeting for Replacement Steam Dryers on April 22 Pre-application meeting for Containment Accident Pressure Credit Elimination on May 12 May 2015 Pre-application meeting for PRA on May 21 June 2015 Pre-application meeting for Flow Induced Vibration Monitoring on June 9 September 2015 BFN EPU LAR submitted on September 21 January 2016 NRC acceptance letter issued on January 11 Browns Ferry EPU License Amendment Request l 5
BFN EPU - Background Browns Ferry EPU Project Team Goals
- Present NRC with high quality LAR consistent with NRC Review Standard RS-001, Review Standard for Extended Power Uprates
- Receive a minimum number of NRC RAIs
- Resolve CAP credit issues
- Install RSDs on all three Browns Ferry Units
- Facilitate smooth transition to EPU for Plant Operations Browns Ferry EPU License Amendment Request l 6
BFN EPU - Overview Browns Ferry EPU License Amendment Request l 7
BFN EPU - Overview SCHEDULE MILESTONE TARGET Submit New EPU LAR COMPLETE - 09/21/15 U3 Delivery of FW Hx #3 Shell COMPLETE - 01/06/16 Receive Acceptance Letter from NRC COMPLETE - 01/11/16 NRC Requests for Additional Information (RAIs) - (Start) COMPLETE U2 Delivery of FW Hx #3 Shell COMPLETE - 03/21/16 U3R17 Outage (FW Hx #3 Shell Replacement & Margin Modifications) COMPLETE - 03/27/16 U2 Simulator Model Upgrade COMPLETE NRC Audit - Replacement Steam Dryers Design and Analysis (04/19/16 - 04/21/16) COMPLETE NRC Audit - Containment Accident Pressure Credit Elimination (05/03/16 - 05/05/16) COMPLETE NRC Audit - Spent Fuel Pool Criticality Analysis (05/10/16 - 05/11/16) COMPLETE U3 Simulator Model Upgrade August 2016 NRC Requests for Additional Information (RAIs) - (Completion) November 2016 Receive Draft Safety Evaluation December 2016 ACRS Subcommittee (02/22/17) February 2017 U2R19 Outage (FW Hx #3 Shell Replacement) March 2017 ACRS Full Committee (04/06/17 - 04/08/17) April 2017 Receive Safety Evaluation and License Amendments July 2017 U3 RSD Delivered to BFN October 2017 U3 FW Hx #4 Tube Bundles delivered to BFN (3 Bundles) January 2018 U3R18 Outage (EPU Implementation) March 2018 U1 RSD Delivered to BFN July 2018 U1 FW Hx #4 Tube Bundles delivered to BFN (3 Bundles) August 2018 U1R12 Outage (EPU Implementation) October 2018 U2 RSD Delivered to BFN October 2018 U2 FW Hx #4 Tube Bundles delivered to BFN (3 Bundles) January 2019 U2R20 Outage (EPU Implementation) March 2019 Browns Ferry EPU License Amendment Request l 8
BFN EPU - Overview Status of modifications required to implement EPU Browns Ferry EPU License Amendment Request l 9
BFN EPU - LAR Review RAI Status Total RAIs received - 205 Total RAI responses submitted - 159
- Responses submitted for 159 RAIs
- Development of responses underway for the following RAIs Forty-one NRC RAIs regarding RSDs (subject of NRC audit)
- Responses to Group 2 RAIs to be submitted by 7/29/16
- Responses to Group 3 RAIs to be submitted by 8/5/16 Spent Fuel Pool (SFP) Criticality Safety Analysis (CSA) RAIs (subject of NRC audit)
- Nine additional NRC RAIs regarding SFP CSA received 3/22/16
- Two additional NRC RAIs regarding the SFP Storage Racks Boral Monitoring Program received 3/22/16
- One additional NRC RAI regarding SFP Criticality Technical Specification requirements received 5/12/16
- Responses to all SFP CSA RAIs to be submitted by 7/29/16 Thirty-three NRC RAIs from the Containment Branch received 3/25/16 (subject of NRC audit)
- Responses to Group 2 RAIs (including CAP Credit Elimination Supplement) to be submitted by 7/25/16 One additional NRC RAI regarding Dose Consequence Analyses received 6/27/16
- Response to be submitted by 7/29/16 One additional NRC RAI regarding Probabilistic Risk Assessment received 7/1/16
- Response to be submitted by 8/12/16 Browns Ferry EPU License Amendment Request l 10
BFN EPU - LAR Review NRC Audits
- Regulatory audits allow NRC to more efficiently conduct its review or gain insights on a licensees programs or processes
- Regulatory audits are conducted for the NRC to gain understanding, to verify information, and/or to identify information that will require docketing to support the basis for the licensing or regulatory decision Audits held to facilitate NRC review of EPU LAR
- RSD Design and Analyses April 19 - 21, 2016
- CAP Credit Elimination Analyses May 3 - 5, 2016
- SFP CSA May 10 - 11, 2016 Browns Ferry EPU License Amendment Request l 11
BFN EPU - LAR Review NRC Audits
- RSD Audit Discussed/reviewed 42 RSD RAIs. Responses will be submitted in three groups related to complexity of issues NRC deleted 2.5 RAIs, added one new RAI, and modified five RAIs NRC will require revision to proposed License Condition for RSD power ascension testing and follow-on reporting Follow-up meeting with NRC held 6/23/16 regarding Safety Relief Valve loading RAIs
- CAP Credit Elimination Audit Discussed/reviewed 33 CAP RAIs. Responses will be submitted in two groups NRC modified two RAIs Clarification call with NRC reviewer regarding RHR Heat Exchanger Performance Testing uncertainty calculations held 6/16/16
- SFP CSA Discussed/reviewed 12 RAIs related to SFP CSA NRC added one new RAI associated with SFP Criticality Technical Specification requirements NRC will require License Condition for periodic testing of Boral areal density Browns Ferry EPU License Amendment Request l 12
BFN EPU - LAR Review Status of Safety Evaluation Input
- Draft input to Safety Evaluation due to NRC Project Manager by September 2016
- Draft input from two Technical Branches received by NRC Project Manager to date Browns Ferry EPU License Amendment Request l 13
BFN EPU - Acronym List
- AVSs - Acoustic Vibration Suppressors
- BFN - Browns Ferry Nuclear Plant
- CAP - Containment Accident Pressure
- CSA - Criticality Safety Analysis
- GDC - General Design Criteria
- LAR - License Amendment Request
- NRC - Nuclear Regulatory Commission
- RAI - Request for Additional Information
- RSD - Replacement Steam Dryer
- SFP - Spent Fuel Pool Browns Ferry EPU License Amendment Request l 14
BFN EPU - Questions/Comments Browns Ferry EPU License Amendment Request l 15