Browns Ferry Nuclear Plant Units 1, 2, and 3 Subsequent License Renewal Application May 11, 2023 Jessica Hammock, Safety Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation
Agenda
- Introductions - NRC
- Subsequent License Renewal (SLR) Overview -
NRC
- Tentative SLR Schedule - NRC
- Discussion - NRC & TVA
- Questions - Public
- Public Comment
- If a Request for Hearing is Granted Process Overview Subsequent License Renewal Application (SLRA) Accepted Safety Review Environmental Review Hearings*
ACRS Recommendation NRC Renewal Decision 10 CFR Part 54 10 CFR Part 51 10 CFR 54.25 10 CFR Part 2 10 CFR 54.29
Safety Review Milestones Acceptance Review In-Office Technical Review Audit On-Site Audit Breakout Audit Issue Audit Report Issue Safety Evaluation March 2025 February 2024 SLRA Accepted Safety Review Environmental Review Hearings*
ACRS Recommendation NRC Renewal Decision
Activity Estimated Date Application Submission Date December 2023 Acceptance Date (Project Start Date)
February 2024 In-Office Technical Review Audit February/March 2024 On-SiteAudit March 2024 Breakout Audit April/May 2024 Safety Evaluation Report March 2025 Advisory Committee on Reactor Safeguards (ACRS) Full Committee Meeting May 2025 Licensing Decision TBD Tentative Schedule
Project Manager Contacts Safety Project Manager Jessica Hammock (Jessica.Hammock@nrc.gov)
Safety Branch Chief Lauren Gibson (Lauren.Gibson@nrc.gov)
Environmental Project Manager Jessica Umana (Jessica.Umana@nrc.gov)
Environmental Branch Chief Ted Smith (Theodore.Smith@nrc.gov)
Public Comment & Questions