Letter Sequence Other |
---|
|
Results
Other: L-2015-177, Fuel Transition Small Break LOCA Summary Report, ANP-3345NP, Revision 1, L-2015-206, ANP-3428NP, Revision 0, St. Lucie Unit 2 Fuel Transition: Response to SNPB-RAI-1, Attachment 4 to L-2015-206, L-2015-259, ANP-3440NP, Revision 1, Response to NRC Questions SRXB-RAI-1 and Snpb RAI-2 Thru Snpb RAI-20., L-2015-279, RAI Response Clarification for SRXB-RAI-1 and Snpb RAI-2 Thru RAI-20 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel, ML15197A339, ML15219A184, ML15279A226, ML15356A184, ML15356A185
|
MONTHYEARML15002A0912014-12-30030 December 2014 St. Lucie, Unit 2 - Application for Technical Specification Change and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Request L-2014-366, ANP-3352NP, Revision 0, St. Luice, Unit 2, Fuel Transition License Amendment Request, Technical Report2014-12-31031 December 2014 ANP-3352NP, Revision 0, St. Luice, Unit 2, Fuel Transition License Amendment Request, Technical Report Project stage: Request ML15084A0112015-03-23023 March 2015 St. Lucie, Unit 2 - Supplemental Information for Technical Specification Change and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Request L-2015-166, Request for Additional Information Reply for Technical Specification Changes and Exemption Request Regarding the Transitioning to Areva Fuel2015-06-0202 June 2015 Request for Additional Information Reply for Technical Specification Changes and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Request ML15181A2902015-06-18018 June 2015 St. Lucie, Unit 2 - Resubmittal of the Areva Small Break LOCA Summary Report within the Application for Technical Specification Change and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Request L-2015-177, Fuel Transition Small Break LOCA Summary Report, ANP-3345NP, Revision 12015-06-30030 June 2015 Fuel Transition Small Break LOCA Summary Report, ANP-3345NP, Revision 1 Project stage: Other ML15188A3402015-07-13013 July 2015 Summary of Closed Meeting with Florida Power and Light Company and Areva Regarding Request for Additional Information for the License Amendment and Exemption Requests Re. the Transitioning to Areva Fuel Project stage: RAI ML15219A1842015-07-30030 July 2015 RAI Response to SNPB-RAI-1 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other L-2015-206, ANP-3428NP, Revision 0, St. Lucie Unit 2 Fuel Transition: Response to SNPB-RAI-1, Attachment 4 to L-2015-2062015-07-31031 July 2015 ANP-3428NP, Revision 0, St. Lucie Unit 2 Fuel Transition: Response to SNPB-RAI-1, Attachment 4 to L-2015-206 Project stage: Other ML15197A3392015-08-31031 August 2015 Request for Withholding Proprietary Information from Public Disclosure for the License Amendment Request and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other ML15233A0362015-09-0404 September 2015 Redacted Request for Additional Information Regarding Proposed License Amendment Request and Exemption Request to Allow the Transition to Areva Fuel Project stage: RAI ML15224B3192015-09-21021 September 2015 Request for Withholding Information from Public Disclosure for the St. Lucie Plant, Unit 2 Project stage: Withholding Request Acceptance L-2015-259, ANP-3440NP, Revision 1, Response to NRC Questions SRXB-RAI-1 and Snpb RAI-2 Thru Snpb RAI-20.2015-10-0202 October 2015 ANP-3440NP, Revision 1, Response to NRC Questions SRXB-RAI-1 and Snpb RAI-2 Thru Snpb RAI-20. Project stage: Other ML15279A2262015-10-0202 October 2015 St. Lucie, Unit 2 - RAI Response to SRXB-RAI-1 and Snpb RAI-2 Thru RAI-20 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other L-2015-279, RAI Response Clarification for SRXB-RAI-1 and Snpb RAI-2 Thru RAI-20 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel2015-11-0303 November 2015 RAI Response Clarification for SRXB-RAI-1 and Snpb RAI-2 Thru RAI-20 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other L-2015-300, ANP-3352NP, Revision 1, Transition License Amendment Request, Technical Report.2015-11-30030 November 2015 ANP-3352NP, Revision 1, Transition License Amendment Request, Technical Report. Project stage: Request ML15356A1842015-12-0808 December 2015 St. Lucie, Unit 2 - RAI Response for Snpb RAI-9 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other ML15356A1852015-12-31031 December 2015 ANP-3456NP, Revision 0, Response to SLU2 NRC Snpb RAI-9, Licensing Report. Project stage: Other 2015-06-18
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000335/20230102024-01-26026 January 2024 NRC Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000335/2023010 and 05000389/2023010 L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) IR 05000335/20230042024-01-24024 January 2024 Integrated Inspection Report 05000335/2023004 and 05000389/2023004 L-2024-004, Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years2024-01-18018 January 2024 Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years L-2024-002, Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2024-01-0808 January 2024 Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-179, Unusual or Important Environmental Event - Turtle Mortality2023-12-14014 December 2023 Unusual or Important Environmental Event - Turtle Mortality L-2023-168, License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 52023-12-12012 December 2023 License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 5 L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, ML23332A1772023-11-28028 November 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-162, Response to 50.69 2nd Round of Rals2023-11-21021 November 2023 Response to 50.69 2nd Round of Rals IR 05000335/20230032023-11-0606 November 2023 Integrated Inspection Report 05000335/2023003 and 05000389/2023003 ML23270B8882023-10-23023 October 2023 Regulatory Audit Summary Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structure, Systems, and Components for Nuclear Power Reactors EPID L-2022-LLA-0182 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A1102023-10-0202 October 2023 License Amendment Request Revision 2 for the Technical Specifications Conversion to NUREG-1432, Revision 5 L-2023-131, Subsequent License Renewal Application - Second Annual Update2023-09-28028 September 2023 Subsequent License Renewal Application - Second Annual Update L-2023-136, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-26026 September 2023 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-122, Corrections to the 2022 Annual Radiological Environmental Operating Report2023-09-20020 September 2023 Corrections to the 2022 Annual Radiological Environmental Operating Report IR 05000335/20233012023-09-20020 September 2023 NRC Operator License Examination Report 05000335/2023301 and 05000389/2023301 L-2023-127, Correction to the 2022 Annual Radioactive Effluent Release Report2023-09-18018 September 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-113, Correction to the 2020 Annual Radiological Environmental Operating Report2023-09-14014 September 2023 Correction to the 2020 Annual Radiological Environmental Operating Report L-2023-108, Report of 10 CFR 50.59 Plant Changes2023-09-11011 September 2023 Report of 10 CFR 50.59 Plant Changes L-2023-118, Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-11011 September 2023 Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-112, Corrections to the 2021 Annual Radioactive Effluent Release Report2023-09-0606 September 2023 Corrections to the 2021 Annual Radioactive Effluent Release Report L-2023-107, Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.42023-09-0606 September 2023 Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.4 ML23219A0042023-09-0101 September 2023 Transmittal Letter - Safety Evaluation Related to the SLRA of St. Lucie Plant, Units 1and 2, Revision 1 L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 IR 05000335/20230022023-08-0707 August 2023 Integrated Inspection Report 05000335/2023002 and 05000389/2023002 L-2023-105, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment ML23212B2652023-07-27027 July 2023 Operator Licensing Written Examination Approval 05000335/2023301 and 05000389/2023301 L-2023-099, Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2023-07-26026 July 2023 Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-102, Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches2023-07-26026 July 2023 Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches ML23200A1232023-07-21021 July 2023 Transmittal Letter for the St. Lucie SLRA Review L-2023-097, Subsequent License Renewal Application Revision 1 - Supplement 62023-07-13013 July 2023 Subsequent License Renewal Application Revision 1 - Supplement 6 L-2023-076, In-Service Inspection Program Owner'S Activity Report (OAR-1)2023-07-11011 July 2023 In-Service Inspection Program Owner'S Activity Report (OAR-1) ML23184A0352023-06-30030 June 2023 Notification of St. Lucie Units 1 & 2 Focused Engineering Inspection (FEI) 05000335/2023010 and 05000389/2023010 and Initial Information Request L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) IR 05000335/20234032023-06-29029 June 2023 Security Inspection Report 05000335/2023403 and 05000389/2023403 IR 05000335/20234022023-06-20020 June 2023 Security Baseline Inspection Report 05000335/2023402 and 05000389/2023402 L-2023-082, Subsequent License Renewal Application Revision 1, Supplement 52023-06-14014 June 2023 Subsequent License Renewal Application Revision 1, Supplement 5 L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000335/20234012023-05-16016 May 2023 Cyber Security Inspection Report 05000335/2023401 and 05000389/2023401 (Cover Letter) IR 05000335/20230012023-05-0909 May 2023 Integrated Inspection Report 05000335/2023001 and 05000389/2023001 ML23109A1132023-04-30030 April 2023 SLRA Change Schedule Letter L-2023-059, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response2023-04-21021 April 2023 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests L-2023-055, 2022 Annual Environmental Operating Report2023-04-12012 April 2023 2022 Annual Environmental Operating Report 2024-01-08
[Table view] Category:Proprietary Information Review
MONTHYEARML21292A2252021-11-0808 November 2021 Revised Request for Withholding from Public Disclosure Regarding Subsequent License Renewal Application ML19253D1842019-09-27027 September 2019 Request for Withholding Information from Public Disclosure for St. Lucie Plant, Unit No. 1 ML16139A2002016-05-26026 May 2016 Request for Information from Public Disclosure ML16008A1692016-01-14014 January 2016 Request for Withholding Information from Public Disclosure for the St. Lucie Plant, Unit No. 2 ML15322A3612015-12-23023 December 2015 Request for Withholding Information from Public Disclosure for the St. Lucie Plant, Unit Nos. 1 and 2 ML15310A4052015-12-0202 December 2015 Request for Withholding Information from Public Disclosure for the St. Lucie Plant, Unit No. 2 ML15224B3192015-09-21021 September 2015 Request for Withholding Information from Public Disclosure for the St. Lucie Plant, Unit 2 ML15197A3392015-08-31031 August 2015 Request for Withholding Proprietary Information from Public Disclosure for the License Amendment Request and Exemption Request Regarding the Transitioning to Areva Fuel ML0933103912009-12-0404 December 2009 Request for Withholding Information from Public Disclosure ML0925302882009-09-11011 September 2009 Withholding from Public Disclosure, Florida Power & Light Company, L-2009-192, Data for NRC (Nuclear Regulatory Commission) Confirmatory EPU (Extended Power Uprate) Analyses, Attachment 2, TAC ME1883 ML0605903552006-03-0808 March 2006 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure ML0600901762006-01-13013 January 2006 Letter, Request for Withholding Information from Public Disclosure for St. Lucie Nuclear Plant, Unit 2 (Tac No. MC8757) ML0504705252005-02-15015 February 2005 Ltr, J. A. Gresham from B. Moroney, Withholding Information from Public Disclosure, Proposed License Amendment, Add Steam Generator Repair Method, Westinghouse Electric LLC, Alloy 800 Leak Limiting Sleeves ML0428706072004-10-0707 October 2004 Westinghouse Electric Co, LLC, Withholding from Public Disclosure, St. Lucie Unit 2, Proposed License Amendment, Request for Additional Information Response, WCAP-9272 Reload Methodology and Implementing 30% Steam Generator Tube Plugging Li ML0412601042004-04-28028 April 2004 Framatome Anp, Inc., Request for Withholding Information from Public Disclosure for St. Lucie Unit 1, Loss of Forced Reactor Coolant Flow Analysis ML0403000102004-01-30030 January 2004 Westinghouse Request for Withholding Information from Public Disclosure, Westinghouse Licensing Report 30-percent Steam Generator Tube Plugging and WCAP-9272 Reload Methodology Transition Project - Appendix C. ML0332801672003-11-21021 November 2003 Holtec International Request for Withholding Information from Public Disclosure for St. Lucie, Units 1 & 2 ML0331100932003-11-0606 November 2003 Westinghouse Electric Company, LLC, Request for Withholding Information from Public Disclosure ML0320200032003-07-21021 July 2003 Florida Power and Light Co, Withholding from Public Disclosure, WCAP -15975-P, Revision 0, NDE Inspection Strategy for the Tubesheet Region in Saint Lucie Unit 2 ML0314302142003-05-22022 May 2003 Withholding from Public Disclosure, WCAP-16038-P, Structural Integrity Evaluation of Reactor Vessel Upper Head Penetrations to Support Continued Operation: St. Lucie Unit 2. ML0312806442003-05-0808 May 2003 Westinghouse Electric Co., Llc. (Wec), Request for Withholding Information from Public Disclosure for St. Lucie, Units 1 & 2 (TAC Nos. MB3406 & MB3412), Request Granted ML0301608932003-01-16016 January 2003 Holtec International Request for Holding Information from Public Disclosure ML0301607982003-01-16016 January 2003 Withholding from Public Disclosure, WCAP-15945-P, MB5917 ML0232603672002-11-22022 November 2002 Withholding from Public Disclosure, Holtec Report HI-2022882, MB6627 & MB6628 2021-11-08
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 31, 2015 Mr. Mano Nazar President and Chief Nuclear Officer Nuclear Division NextEra Energy P.O. Box 14000 Juno Beach, FL 33408-0420
SUBJECT:
REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR THE ST. LUCIE PLANT, UNIT NO. 2 (TAC NOS. MF5494 AND MF5495)
Dear Mr. Nazar:
By letter dated December 30, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15002A091 ), Florida Power & Light Company submitted an affidavit dated December 1, 2014, executed by Alan B. Meginnis, on behalf of AREVA Inc., requesting that information contained in the following documents be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 2.390:
ANP-3352P Revision 0, "St. Lucie Unit 2 Fuel Transition License Amendment Request, Technical Report, dated December 2014 ANP-3347P Revision 0, "St. Lucie Unit 2 Fuel Transition Chapter 15 Non-LOCA
[Loss-of-Coolant Accident] Summary Report," dated December 2014 ANP-3346P Revision 0, "St. Lucie Unit 2 Fuel Transition Realistic Large Break LOCA Summary Report," dated December 2014 Non-proprietary versions of the affidavit and the reports are publicly available under ADAMS Accession Nos. ML15002A091 and ML15002A092, respectively.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
6.(b) Use of the information by a competitor would permit the competitor to significantly reduce its expenditures, in time or resources, to design, produce, or market a similar product or service.
6.(d) The information reveals certain distinguishing aspects of a process, methodology, or component, the exclusive use of which provides a competitive advantage for AREVA in product optimization or marketability.
M. Nazar 6.(e) The information is vital to a competitive advantage held by AREVA, would be helpful to competitors to AREVA, and would likely cause substantial harm to the competitive position of AREVA.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the information marked as proprietary that was included with the December 30, 2014, letter will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future, such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
M. Nazar Please direct any inquiries to Robert L. Gladney at 301-415-1022 or Robert.Gladney@nrc.gov.
Sincerely, Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-389 cc: Mr. Alan B. Meginnis Manager, Product Licensing AREVA Inc.
2101 Horn Rapids Road, RC36 Richland, WA 99354 Mr. Joseph Jensen Site Vice President Florida Power & Light Company 6501 S. Ocean Drive Jensen Beach, FL 34957 Additional Distribution via Listserv
ML15197A339 OFFICE DORL/LPL 1-2/PM DORL/LPL2-2/LA DSS/SRXB/BC DSS/SNPB/BC BClayton NAME RGladnev (LRonewicz for) CJackson JDean DATE 8/3/15 8/3/15 8/14/15 8/20/15 OFFICE DORL/LPL2-2/BC DORL/LPL2-2/PM FSaba NAME SHelton (JLamb for)
DATE 8/28/15 8/31/15