Holtec International Request for Holding Information from Public Disclosure
ML030160893
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 01/16/2003
From: Moroney B
NRC/NRR/DLPM/LPD2
To: Pellet S
Holtec
Moroney B, NRR/DLPM, 415-3974
References
TAC MB6864
Download: ML030160893 (4)


Text

January 16, 2003 Mr. Scott H. Pellet, Project Manager Holtec International 555 Lincoln Drive West Marlton, NJ 08053

SUBJECT:

HOLTEC INTERNATIONAL REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR SAINT LUCIE UNIT 1 (TAC NO. MB6864)

Dear Mr. Pellet:

By Florida Power & Light Companys letter dated November 25, 2002, and your affidavit dated November 12, 2002, you requested that Holtec Report HI-2022940, Revision 0, St. Lucie Unit 1 Spent Fuel Pool Storage Rack Boraflex Remedy, be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.790.

A nonproprietary copy of this document has been placed in the Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.

The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by Holtecs competitors without license from Holtec International constitutes a competitive economic advantage over other companies;
b. Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
c. Information which reveals aspects of past, present, or future Holtec International customer-funded development plans and programs of potential commercial value to Holtec International;
d. Information which discloses patentable subject matter for which it may be desirable to obtain patent protection.

We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.790 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the document listed above and identified as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.790(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and

S. Pellet directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, you may contact Eva Brown at 301-415-2315.

Sincerely,

/RA by Eva Brown for/

Brendan T. Moroney, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-335 cc: See next page

ML030160893 *See previous concurrence OFFICE PDII-2/PM PDII-2/PM PDII-2/LA OGC* PDII-2/SC NAME BMoroney EBrown BClayton MSiemien AHowe DATE 01/09/2003 01/09/2003 01/09/2003 01/07/2003 01/16/2003 S. Pellet ST. LUCIE PLANT Holtec International cc:

Mr. J. A. Stall Mr. Kelly J. Korth Senior Vice President, Nuclear and Licensing Manager Chief Nuclear Officer St. Lucie Nuclear Plant Florida Power and Light Company 6351 South Ocean Drive P.O. Box 14000 Jensen Beach, Florida 34957 Juno Beach, Florida 33408-0420 Mr. William Jefferson Senior Resident Inspector Vice President, Nuclear Operations Support St. Lucie Plant Florida Power & Light Company U.S. Nuclear Regulatory Commission P.O. Box 14000 P.O. Box 6090 Juno Beach, FL 33408-0420 Jensen Beach, Florida 34957 Mr. Rajiv S. Kundalkar Craig Fugate, Director Division of Vice President - Nuclear Engineering Emergency Preparedness Florida Power & Light Company Department of Community Affairs P.O. Box 14000 2740 Centerview Drive Juno Beach, FL 33408-0420 Tallahassee, Florida 32399-2100 Mr. J. Kammel M. S. Ross, Attorney Radiological Emergency Florida Power & Light Company Planning Administrator P.O. Box 14000 Department of Public Safety Juno Beach, FL 33408-0420 6000 SE. Tower Drive Stuart, Florida 34997 Mr. Douglas Anderson County Administrator St. Lucie County 2300 Virginia Avenue Fort Pierce, Florida 34982 Mr. William A. Passetti, Chief Department of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, Florida 32399-1741 Mr. Donald E. Jernigan, Site Vice President St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 Mr. R. E. Rose Plant General Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957