CP-201500157, Relief Request No. 2C3-1 for the Reactor Pressure Vessel Leak-Off Flange (Third ISI Interval Start Date: August 3, 2014; Third ISI Interval End Date: August 2, 2023)

From kanterella
(Redirected from ML15065A042)
Jump to navigation Jump to search

Relief Request No. 2C3-1 for the Reactor Pressure Vessel Leak-Off Flange (Third ISI Interval Start Date: August 3, 2014; Third ISI Interval End Date: August 2, 2023)
ML15065A042
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 02/24/2015
From: Flores R, Madden F
Luminant Generation Co, Luminant Power
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CP-201500157, TAC ME9409, TAC MF2997, TXX-15022
Download: ML15065A042 (19)


Text

Rafael Flores Luminant Power Senior Vice President P 0 Box 1002

& Chief Nuclear Officer 6322 North FM 56 Rafael.Flores@Luminant.com Glen Rose, TX 76043 Luminant 2548975590 C 817 559 0403 F 254 897 6652 CP-201500157 Ref. # 10CFR50.55a(g)(6)

TXX-15022 February 24, 2015 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

SUBJECT:

COMANCHE PEAK NUCLEAR POWER PLANT DOCKET NO. 50-446 RELIEF REQUEST NO. 2C3-1 FOR THE UNIT 2 REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD ISI INTERVAL START DATE: AUGUST 3,2014; THIRD ISI INTERVAL END DATE: AUGUST 2,2023)

REFERENCES:

1. Letter logged TXX-13145 dated October 13, 2013, from Rafael Flores to the NRC submitting Relief Request No. C-3 for the Unit 2 Second 10 Year ISI Interval From 10CFR50.55a Inspection Requirements Due to Hardship (Second Interval Start Date:

August 13, 2004) (ML13312A121) as supplemented by letters dated January 23, and February 11, 2014 (ADAMS Accession Nos. ML14038A256 and ML14055A318, respectively.

2. NRC Letter dated April 4, 2014, from Michael T. Markley to Rafael Flores concerning Comanche Peak Nuclear Power Plant, Unit 2 - Approval of Relief Request No. C-3 for the Third 10-Year Inservice Inspection Interval (TAC No. MF2997) (ML14084A291)
3. Letter logged TXX-12129 dated August 23, 2012, from Rafael Flores to the NRC submitting Relief Request No. C-2 for the Unit I Third 10 Year ISI Interval From 10CFR50.55a Inspection Requirements Due to Hardship (Third Interval Start Date:

August 13, 2012)(ML12250A670) as supplemented by letter dated January 9, 2013 (ML130250339)

4. NRC Letter dated March 19, 2013, from Michael T. Markley to Rafael Flores concerning Comanche Peak Nuclear Power Plant, Unit 1 - Approval of Relief Request No. C-2 for the Third 10-Year Inservice Inspection Interval (TAC No. ME9409)

(ML13046A385)

Dear Sir or Madam:

Pursuant to 10 CFR 50.55a (h)(3)(z)(1) Luminant Generation Company LLC (Luminant Power) is submitting Relief Request 2C3-1 for Comanche Peak Nuclear Power Plant (CPNPP) Unit 2 for the third ten year inservice inspection interval. Luminant Power has determined that compliance with certain inspection requirements of ASME Section XI would result in an unnecessary hardship or unusual difficulty without a compensating increase in the level of quality and safety.

The reactor pressure vessel flange leak-off piping configuration precludes system pressure testing when the reactor vessel head is removed. The configuration also precludes pressurizing the line externally Ab ,7

U. S. Nuclear Regulatory Commission TXX-15022 Page 2 of 2 02/24/2015 when the head is installed. A visual examination of the accessible areas was performed during the second interval on the unpressurized subject piping as part of the Class 2 leakage test. No evidence of leakage has been identified for the subject component. No undue risk to the public health and safety is presented by this request.

A similar relief request was previously submitted to the NRC for Unit 2 second interval, via Reference 1, and reviewed and approved via Reference 2.

The VT-2 system leakage tests of the reactor pressure flange leak-off piping will occur once in each of the three periods of the current third interval. Therefore, Luminant Power requests approval of this relief request by September 30, 2015, to support the upcoming CPNPP Unit 2 refueling outage.

This communication contains no new commitments regarding CPNPP Unit 2.

Should you have any questions, please contact Mr. Jack Hicks at (254) 897-6725.

Sincerely, Luminant Generation Company LLC Rafael Flores By:A 4d 2Kb%

Fred W. Madden Director, External Affairs Attachments: (1) Relief Request Number - 2C3-1 For the Reactor Pressure Vessel Leak-Off Piping (Third 10-Year ISI Interval Start Date: August 3, 2014)

(2) Reactor Pressure Vessel Seal Leak-off Details (3) Piping and Instrumentation Diagram and Piping Isometric Drawings c - Marc L. Dapas, Region IV Balwant K. Singal, NRR Resident Inspectors, Comanche Peak Jack Ballard, ANII, Comanche Peak Robert Free, TDLR

Attachment I to TXX-15022 Page 1 of 4 COMANCHE PEAK NUCLEAR POWER PLANT UNIT 2 RELIEF REQUEST NUMBER - 2C3-1 FOR THE REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD 10-YEAR ISI INTERVAL START DATE: AUGUST 3,2014)

1. ASME Code Component Affected:

ASME Code Class: Code Class 2

References:

ASME Section XI, Table IWC-2500-1 and IWC-5220 Examination Category: C-H (All Pressure Retaining Components)

Item Number: C7.10

Description:

Alternative Pressure Testing Requirements for the RPV Flange Leak-Off Piping Component: NPS 33/44"RPV Flange Seal Leak-Off Piping Material: SA376 type 304 or 316 Stainless Steel Line Numbers: RC-2-080, RC-2-081, RC-2-082 Plant Drawings: BRP-RC-2-RB-005, BRP-RC-2-RB-006, BRP-RC-2-RB-007, BRP-RC-2-RB-013, BRP-RC-2-RB-014, BRP-RC-1-RB-042, BRP-RC RB-043, M2-0250

2. Applicable Code Edition and Addenda:

The applicable ASME Boiler and Pressure Vessel Code edition and addenda is ASME Section XI, "Rules for Inservice of Nuclear Power Plant Components," 2007 Edition through 2008 Addenda.

Hereafter referred to as the "Code."

3. Applicable Code Requirement:

ASME Section XI, Subarticle IWC-2500, Table IWC-2500-1, Code Category C-H, Item Number C7.10 requires that all Class 2 pressure retaining components be subject to a system leakage test with a Visual, VT-2 examination each inspection period. The system leakage test is performed at the pressure obtained while the subject portion of the system is performing its normal operating function or during a comparable test.

4. Reason for Request: Hardship without a compensating increase in quality and safety (10 CFR 50.55a (h)(3)(z)(1)).

As discussed in Section 3, "Applicable Code Requirement," ASME Section XI, 2007 Edition through 2008 Addenda requires that Class 2 pressure boundary piping shall be pressure tested once each inspection period. The Reactor Pressure Vessel (RPV) head flange seal leak detection piping is separated from the reactor coolant pressure boundary by one passive membrane, which is an 0-ring located on the inner vessel flange as shown in Attachment 2. A second 0-ring is located on the outside of the tap in the vessel flange. Failure of the inner 0-ring is the only condition under which this line is pressurized. Therefore, the line is not expected to be pressurized during the system pressure test following a refueling outage.

The configuration of this piping precludes system pressure testing while the vessel head is removed because the time required by personnel for the installation and removal of a threaded plug in the flange face to act as a pressure boundary for the test would incur significant dose (estimated 20 - 40 mRem/minute), which would be an ALARA concern. This activity would also present a Foreign Material Exclusion issue for the 1/8" plug that would be required to be installed to complete a leakage test at pressure.

to TXX-15022 Page 2 of 4 COMANCHE PEAK NUCLEAR POWER PLANT UNIT 2 RELIEF REQUEST NUMBER - 2C3-1 FOR THE REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD 10-YEAR ISI INTERVAL START DATE: AUGUST 3,2014)

The configuration also precludes pressurizing the line externally with the head installed at the start of an outage. The top head of the vessel contains two grooves that hold the 0-rings. The 0-rings are held in place by a series of retainer clips that are housed in recessed cavities in the flange face. If a pressure test were to be performed with the head on, the inner 0-ring would be pressurized in a direction opposite to its design function. This test pressure would result in a net inward force on the inner O-ring that would tend to push it into the recessed cavity that houses the retainer clips. The thin O-ring material would likely be damaged by the inward force. The inner O-ring failure would prevent pressure build-up by allowing water to pass by and enter the reactor vessel. To ensure that it was in fact an O-ring failure and not a leak in the leak-off piping, the portion of piping in the reactor vessel nozzle inspection areas ("sandboxes") would have to be inspected. The conditions inside the "sandboxes" at the beginning of the outage prior to removing the head would be considered unsafe with extremely high temperatures and dose ratings ranging from 150 to 250 mRem/hr. The leak-off piping travels through three of the eight "sandboxes". It is felt that performing the examination in this manner would result in an unnecessary hardship without a sufficient compensating increase in the level of quality and safety. Therefore, the only time, other than O-ring failure, that the leak-off lines are fluid filled under any type of pressure is when the head is removed and the cavity flooded.

Attachment 3 contains the piping and instrumentation diagram (P&ID) and the piping isometric drawings showing the subject flange leak-off line.

5. Burden Caused by Compliance:

Purposely failing or not installing the inner 0-ring in order to perform a pressure test would require purchasing a new 0-ring set and the time and radiation exposure associated with removing and reinstalling the RPV head to replace the O-rings would be an undue hardship.

Therefore, compliance with the IWC-5221 system leakage test requirements results in an unnecessary hardship without a sufficient compensating increase in the level of quality and safety.

6. Proposed Alternative and Basis for Use:

In lieu of the requirements of IWC-5221, a VT-2 visual examination of the accessible areas will be performed each period on the piping subjected to the static pressure head when the reactor cavity is filled. This test will be part of the reactor coolant Class 2 leakage test.

During normal operation, the inner 0-ring isolation valve is open. Should the inner 0-ring leak, a high temperature alarm actuates at 140 degrees F in the control room, informing the operator of the leak. The operator monitors reactor vessel flange leak-off temperature in accordance the CPNPP alarm procedures (ALM-053A for Unit 1 and ALM-053B for Unit 2) and closes the valve, isolating the leak. The procedure directs shutting the manual isolation valve and opening another valve, transferring RCS pressure boundary maintenance to the outer O-ring. Opening the valve then transfers leak detection to the outer O-ring. All drainage/leakage is piped to the reactor coolant drain tank. The procedure also addresses notifying chemistry department to increase monitoring of the containment atmosphere to detect possible outer O-ring failure; perform an operations test to determine leakage rate as applicable; and initiating corrective action documents to identify the condition and correct the condition as applicable.

to TXX-15022 Page 3 of 4 COMANCHE PEAK NUCLEAR POWER PLANT UNIT 2 RELIEF REQUEST NUMBER - 2C3-1 FOR THE REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD 10-YEAR ISI INTERVAL START DATE: AUGUST 3,2014)

Additionally, the flange seal leak-off line is essentially a leakage collection/detection system and the line would only function as a Class 2 pressure boundary if the inner O-ring fails, thereby pressurizing the line. If any significant leakage does occur in the leak-off line piping itself during this time of pressurization then it would clearly exhibit boric acid accumulation and be discernable during the proposed VT-2 visual examination that will be performed unpressurized as proposed in this request. The elevation of the Reactor Vessel flange is 834' 11/22". The elevation for the water level when the cavity is flooded is 858" 6". Therefore, the minimum pressure at the opening of the flange leak-off line when the exam is performed is 24' 5 1/2 " of static pressure head or 10.6 psi.

The system leakage test will be performed in accordance with ASME Section XI Subarticle IWA-5213(a). A 10-minute hold time will be maintained after test pressure has been reached for Class 2 components that are not in use during normal operating conditions. The subject lines are also not insulated.

There has been no known evidence of corrosion, stress corrosion cracking, or fatigue in the subject flange leak-off piping at Comanche Peak. Database searches for the subject lines in the Comanche Peak Corrective Action Program identified no historical instances of degradation.

7. Duration of Proposed Alternative:

This alternative is requested for the Third Inservice Inspection Interval, which began on August 3, 2014 and ends on August 2, 2024.

8. Precedents:

(1) Comanche Peak Nuclear Power Plant, Unit 2 Second Inspection Interval Relief Request C-3 "Alternative Pressure Testing Requirements for the RPV Flange Leak-Off Piping", as approved by the NRC on April 4, 2014 (ML14084A291).

(2) Comanche Peak Nuclear Power Plant, Unit 1 Third Inspection Interval Relief Request C-2 "Alternative Pressure Testing Requirements for the RPV Flange Leak-Off Piping", as approved by the NRC on March 19, 2013 (ML13046A385).

(3) LaSalle County Station Third Inspection Interval Relief Request 13R-08.

"Pressure Testing of the Reactor Vessel Head Flange Leak Detection System", as approved by the NRC in a letter dated January 30, 2008 (ADAMS Accession No. ML073610587)

(4) Susquehanna Steam Electric Station Third 10-Year Inservice Inspection (ISI) Interval Program Plan Request for Relief 3RR-07 "Exemption for Pressure Testing Reactor Pressure Vessel Head Flange Seal Leak Detection System", approved by the NRC in a letter dated September 24, 2004 (ADAMS Accession No. ML042680078) to TXX-15022 Page 4 of 4 COMANCHE PEAK NUCLEAR POWER PLANT UNIT 2 RELIEF REQUEST NUMBER - 2C3-1 FOR THE REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD 10-YEAR ISI INTERVAL START DATE: AUGUST 3,2014)

9.

Reference:

Code Case N-805, "Alternative to Class I Extended Boundary End of Interval or Class 2 System Leakage Testing of Reactor Vessel Head Flange O-ring Leak Detection System," was issued to the 2010 Edition of the ASME Section XI Code and is listed in Supplement 6 for Code Cases.

However, Code Case N-805 has not been approved by the NRC and is not identified in Regulatory Guide 1.147, "Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1."

Phase 2 480 VACFLEXGenerator CPX-FXDGEE-01/02 500kW, 480V, 752A 4.I6C As6060,4 8-I/C1 KCMIL 54,666,2 C66,r.6Cond 6r 3

C'-p----01 - -.---

6 ---- CPX-6PMENB-t CPX EPMEN-D2 0) 8D0A 5)UUA XB110-1 KXB10-1-4 CPX-EPDPNB-O8 CPX-EPDPNB-57 El-0024-O0E El-0024-01F (YARDnear 2ST XMFR) (U2 Train A SWGR RM810')

17 400A 21 400A 6)00A 400A 250A ') 125A M) 250A ') 125A M) ') 4.A A 6-ecah 27-/20 2-11C1 aict 3/Cat CPX-E PDSNS-*ZO s 66'c No'3 CP066MP6-6 CPXEPDlaa05,A crx-rbmo :i 3-I/C4/n 400A -/i 60a0A 4O a rI1 21 anna Iond~

3-3/12C 0' XB10-1-3 XB10-1-2 2810-1-1 5810-1-1 tin Ca,6

-EPDPNB-07 CPX-EPDPNB-06 CPZ-EPDPNB-12 CPX-EPDPNB-05 El -0024-01B E1-0024-01A E2-0024-02 El-0024-01A 0 -) 16,HP)

[ (E CPX ECB 778') (AUX852')

3 (U2 SG810') (AUX832'}

-6.o6 )1i0A 10t)1iO 126 6 L06 ).A2 200A 2OA 12 2.iA I" 1_ 21 13t L

NBI i) 25/A 2l0A ) 200A 2200A )OeA ) 200A

- 11B10-1-3-1 L 'XBlO-1-3-1 1B10-1-2-1 2B10-1-1-2 XB10-1-1-3 2B10-1-1-1 2B10-11-3 CP1-EPDPNB-28 CPX-EPDPNB-45 CP1-EPPN8-27 CP2-EPDPNB-25 CPX-EPDPNB-46 CP2-EPDPN8-27 CP2-EPDPNB-28 E1-0024-01C Ei-0024-01C E2-0024-03C El-0024-01C E2-0024-03C E2-0024-03D E2-0024-03C

( U SG 7 U (AUX790') {U1 SG852') (U2 SG790') (AUX790') (U2 SG810') (U2 SG852')

90 '

6 1 5 2 i125A ) ISA 125A 6) 1SA i/125A1 j 15AJi2A 2 )2aA -a 15A A 2izs A kiEe3-17S LEB3-16S lE212 EB3I8en 2EB3-575 2EB4-0li 2EB4-045 lEBISti/i Eel-3Si 1EB3-1 -EB3.i E SS1 2EB4- i 2 EB4- 1 l M 5E B2 - E W .. . . . . . . . . .

IEB4-i 1EB4-i IEB251 2 E S3SS Battery Exhaust Battery Exhaust Test Test Battery Battery Exhaust Battery Exhaust Battery Battery Charger Fan Charger Fan Battery Battery Charger Charger Fan- Charger Fan Charger Charger 6MauaT W6dl63 2Pt 1EDi-2 1-1(A) IED2-2 1-2(8) Charger Charger 1ED4-1 2EDI-2 2-1(A) 2ED2-2 2-2(B) 2ED3-1 2ED4-16 h 1a6 L~k BTIXRT-01BTXRT-o2 Note 2 Note 2 File*J,16 ra t FeableW ldlr Figure A3-23: Phase 2 480VAC FLEX Generator Connection to Plant Support Power 103 to TXX-15022 Page 1 of 3 Reactor Pressure Vessel Seal Leak-Off Details Luminant Power Comanche Peak Nuclear Power Plant to TXX-15022 Page 2 of 3 Figure 1:

REACTOR PRESSURE VESSEL HEAD FLANGE LEAK-OFF LINE CONFIGURATION to TXX-15022 Page 3 of 3 Figure 2:

Reactor Pressure Vessel Head Flange Leak-Off Line Details

Attachment 3 to TXX-15022 Piping and Instrumentation Diagram and Piping Isometric Drawings

ttachment to TXX-15022 Page 2 of 9 Ic- A I B I c I 2 4 I G H I D 4

- -~-490 --------- j~j o STEAM-GEN4ATO ~---

-0

-- ---- /

TCX-RCPCSGPC2 0-0-503-T.

2-0002E92 S 929 CO-- LOCITED -TW -T OF -T 1-sl-2-89400_fý 02 00r04 os.--0000- 55 000 ei2205.

0105 00 55 0000 000 I. - - 1. . .- 1- -11. 1. -

02055 04 20-0 000

-I T =Tl-T s,- Im -

=w ss--, s- -TOO oP.

LOOPOOP 000 7AS ~

aCV. 050 00~990 5080 REACTOR4R L=E 1:Ll

1

TO -1 r1l ETE C.=, . _M.

10 D

_S,==OW tCoo"0 T-0 M. -0590008

.:T. I IT" T1111-R REACTO 0005 0 5000 OT COOLOOP 00 5.0 LOP 10 LOOP "LT'9 T.. 1. -11. 1.

Kl- ý IE 1 ILI 004 77 2-202 7t.00 TOO To=ýIOO ýS 5-1 1~ 1TO2.

M 00 401-9500.TL 9--5 500805 1-2 - FOA -C

.1 - -- AOOT -1 TOO 4

,s Týl LU Of S

2 0100 RECO 100.0 _JooGO2-0O Z-1 =T=ll I V) 2ým --- - --0 B

20.04.00

-0 9 000A -

00 00 0740 5 004 CLASS I LUMINANT CPASES 6 GLEN ROSE. TEXAS FLOWDIAGRAM REACTORCOOLANT SYSTEM MS-02501 cp-18 9000am40 A M2-0250 I B I c t F FIINAL IRt IINiI 5

Attachment to TXX- 15022 Page 3 of 9 C 0 t It, F 0 1~

BILL OF MATERIAL

- !IN N h a-. 1 104 2i A

) 2 6 46 4 2 n.n.T.

I 6RC F ,-RC-2-06O-05018-2

'e-3 80286-07 83 4- ISE1)3 NOTE SE OE3 =;

rZ-r51r s.- *'-WP-2-Ot9-00AR-5 4

YTOE)RC-C--OR2--25R-

@jW--B 2w?

M.-.05 I" -

0

/s S M2-0250. M2-0264 t-2002. M-2003 250iR-2. ZSOSR-2 ROTES S

I. REFERTO MR8S (MANUMFACTURINGRECORD SKEET)FOR TIYPE OF MATERJAL USED.

2. GRADIENT fl,.65" PER FOOT IN PIECE13 WI8HVALVE 2RC-B032 1S ACCEPTABLE.
3. GRADIENT, LT.7PER FOOTIN TUB0NAT DISCHARGE OF 2R0C-B032 RTH VALVEAT HIGH ENDIS ACCEPTABLE.
4. , VAL.VE BOREDTO Y4*REFERENCE TA!92-501 BOVA.

.6 TU ELECTRIC CPSES GLEN ROSE TEXAS 00G I olýII,I,Z"- I II a

CREATE*

IRIS DRAWING ELECTROMCALLT R)6860INITIALB 0I I I, _Cj I INETS REACTOR COOLANT I~2LI L~00Ro.

L I I Iýv I I I 2llf0 .0. S *.no. UL SHRCROOOSS.IGNA a C

+ E FINAL PRINT

Attachment to TXX- 15022 Page 4 of 9 CPU A B G N

-- I .

BRP-RC-2-RB-006 H 4092 I 1ILL OF MATERIAL N

2 3

4-M1 2-0511.WI055IlO

'- -M-025 I j.4rn 29-2

1. RErER TO MRS(MANUFACTULRING RECR0DSHEETIFOR TYPEOF MATERIAl. USED.

a JREVTUE92-390.1 0 TU ELECTRIC CPSES GLEN ROSE, TEXAS 6

WELDNO/PC0401 DESIGN vI CK"L KOý ITS ELECTRO44IMAL1 CREATED DRAWING I REIýAR I--

V" 1 L

I 1 1 1 I 1 I~I f ,

IUII-10

,. 1 CIA5 I REACTOR COOLANT n

RACROOOU3.IElA I + 4 I I I I F

,,5,MS~U4., ~*l HRCRDO06F3.lCN A

4 FINALI PRINT P

Attachment to TXX- 15022 Page 5 of 9 BILL OF MATERIAL i BRP-C-2-B-OO 194I~I N 1 112!Y4'S/160 2 -L 2 ly'-s/160 3 1 i2 SA37 SRI 1 2 SA37 SRI I S/160 4'-4'A'EST L,; SA37 OR/

ST LG SA37 BR/

7HP,45_1111121 90;RNIST LG SA37 OR/

2 If.- 6COOLB SW 90'tLL SAIR2 :X SRI I 2 1Y., S/160 SA37

ý0_ z IY,- wlbu SALT _fFp_1 Ll _L 2 Y.-S/160 SA3711 BR/

lz 1 2 ye S/iso S OR/

IS I I Yll S/160 SA571 BR/

_L4 4-6000LB SW CPLG SAI&2 SRI 4f - 9499*

l- "4 =~rIxx-09*

l

~ 10459*9* r.~uNOTICE 4 TPLM- 3or8c.

M2-0250 M-2003 I

-2509*-2 m

NOTES I -REFER TOMRS (MANUFA&CTURING REMORD SKE r) F91R OF MJAT TYPE1 RALI. 151.

NEWSJUT TU ELECTRIC CPSES GLEN ROSE. TEXAS AI09095 FROM.

GR9*10/

Oa REV.5 OW.BRP-RC-Z-R8-OO7 0ZIII REACTOR COOLANT RGIRZAIO MORMO0O.IflECTRI n*m ..........

6*NO*m*

Ill THSRAWING FlA 5C OC8L IlIZL I II wui2sc=, IFIn-La-505ol aRP-RC-2.RaBo? isvzp- I x I

2 NOTICE AD0W31GSTATUS OFTHIS DOILUT SýB CHECKED A II ITRGC.

8"r?- -R24-013 REV.

~ZA1IISEORlOI0.OMTU ElECTRIC ELECTR~OCALLYspw LINSORAW:CREATED nu fj

Attachment to TXX- 15 022 Page 7 of 9 1 0 7

A of 9 to TXX- 15022 r Attachment PageBRP-RC-2-RB-014SHO2 BILL OF MATERIAL I

- M2-OS13O MO2-0508.

"M--ozOC, U.-20003 2..o-2 NOTES I. REFR TO MRS(MANUFACTURINO FOR RECORDSHEET)

TYPKOF MATERI.LUSED.

Waffu.ETs wwoef(ff TU ELECTRIC CPSES GLEN ROSE. TEXAS I ICR010/T I I II I ONG.

CORA FRO.,

RPN OICRP-2-RO-014 REV.2 REACTOR COOLANT I I I I I IO~iG. ORG.TU ELECTSdC I F=ltvapIr-C ITHIS DRAWING I XWE' CR000ELECTROIIICALLV '.'.SIMTiAO I I I I I I III el f-a Rf,".If.Y-,CI D~-*,V-7:-nR.fYI h;-2 I'CP"-I OS.~RoOl4U~ A I IKRCROO14LMGN A C E I '-BRP-RC-2-RB-014

_____FINAL PRINT H

Attachment to TXX- 15022 Page 8 of 9 CPE a F a h BRP-RC-2-RB-042 sa lOPS I BILL OF MATERIAL N

-T 00OWlION  :~Iwoc ~

INNER MONITOR TUBE OF REACTOR TCX-RCPCRV-O0 IREF) I I

2 2 3 3

.4 4

40-0308. 42-0507 142-0600 M-2003 250A4-2 NOTES

1. REFERTO MRS 'MANUFACTURING RECORDSHEET)FOR TYPE OF MATERIALUSED.

ý.S RIa ISWELDED OR-CTLY TO INNER 04MT0RNOZZLE.

5 CLRS. TO aSS 2 DREAKOCCURS UPSTREAM 0F 5 NOZLL.

TUl ELECTRIC CR5 ES GLEN ROSE. TEEAS 6

IODO.CM'ZATI-1I I I I I I IIL REACTOR COOLANT DADI D- CCt'_OD..-rA' DRAWING THIDS CREATED ELECTROkiCALLY IMr_ "R'S I I"II I I I CLAI I,%=.lPb.*

IHCROO.U A 11WI21 '"'1 IHRCRO0424.16N A 1 0 C I D FINAL PRINT

Attachment to TXX- 15022 Page 9 of 9 CPE I B 0 a H

  • 1 CP A- I a BRP-RC-2-RB-043 DILL OF_MATERIAL usioF 2 N

3 3

- lg.-J-,I, ýý

'EI W4 .d 15505005 CLWY llS1-

-V 557SM 4

1",.___________

-M2-0250 45-2003 25l-

1. REFERTO MRS1 lVANL*ACTUJRNGRECORDSF5057J FRo TPEOF MAIAERIAL Uý450.

5 TU ELECTRIC CPSES GLEN ROSE.TEXAS 6

2 IDUA I IIII I I I I I I REACTOR COOLANT MIEVSE-S FWSDAIGCETDELECTRONIAL 5T75.S i I MeICiA 5(71-5515-715555 I

WT-U-r5l 15Or'~3~D9..5,A~

RP-r-l-Q-03 I,*, ,lep--*

VW25I I NRCR00433.1IN . 4, ______

1 0 FINAL PRINT