CP-201500157, Relief Request No. 2C3-1 for the Reactor Pressure Vessel Leak-Off Flange (Third ISI Interval Start Date: August 3, 2014; Third ISI Interval End Date: August 2, 2023)

From kanterella
(Redirected from ML15065A042)
Jump to navigation Jump to search

Relief Request No. 2C3-1 for the Reactor Pressure Vessel Leak-Off Flange (Third ISI Interval Start Date: August 3, 2014; Third ISI Interval End Date: August 2, 2023)
ML15065A042
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 02/24/2015
From: Flores R, Madden F
Luminant Generation Co, Luminant Power
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CP-201500157, TAC ME9409, TAC MF2997, TXX-15022
Download: ML15065A042 (19)


Text

Rafael Flores Senior Vice President

& Chief Nuclear Officer Rafael.Flores@Luminant.com Luminant Power P 0 Box 1002 6322 North FM 56 Glen Rose, TX 76043 Luminant 2548975590 C 817 559 0403 F 254 897 6652 CP-201500157 TXX-15022 Ref. # 10CFR50.55a(g)(6)

February 24, 2015 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

SUBJECT:

COMANCHE PEAK NUCLEAR POWER PLANT DOCKET NO. 50-446 RELIEF REQUEST NO. 2C3-1 FOR THE UNIT 2 REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD ISI INTERVAL START DATE: AUGUST 3,2014; THIRD ISI INTERVAL END DATE: AUGUST 2,2023)

REFERENCES:

1.

Letter logged TXX-13145 dated October 13, 2013, from Rafael Flores to the NRC submitting Relief Request No. C-3 for the Unit 2 Second 10 Year ISI Interval From 10CFR50.55a Inspection Requirements Due to Hardship (Second Interval Start Date:

August 13, 2004) (ML13312A121) as supplemented by letters dated January 23, and February 11, 2014 (ADAMS Accession Nos. ML14038A256 and ML14055A318, respectively.

2. NRC Letter dated April 4, 2014, from Michael T. Markley to Rafael Flores concerning Comanche Peak Nuclear Power Plant, Unit 2 - Approval of Relief Request No. C-3 for the Third 10-Year Inservice Inspection Interval (TAC No. MF2997) (ML14084A291)
3.

Letter logged TXX-12129 dated August 23, 2012, from Rafael Flores to the NRC submitting Relief Request No. C-2 for the Unit I Third 10 Year ISI Interval From 10CFR50.55a Inspection Requirements Due to Hardship (Third Interval Start Date:

August 13, 2012)(ML12250A670) as supplemented by letter dated January 9, 2013 (ML130250339)

4.

NRC Letter dated March 19, 2013, from Michael T. Markley to Rafael Flores concerning Comanche Peak Nuclear Power Plant, Unit 1 - Approval of Relief Request No. C-2 for the Third 10-Year Inservice Inspection Interval (TAC No. ME9409)

(ML13046A385)

Dear Sir or Madam:

Pursuant to 10 CFR 50.55a (h)(3)(z)(1) Luminant Generation Company LLC (Luminant Power) is submitting Relief Request 2C3-1 for Comanche Peak Nuclear Power Plant (CPNPP) Unit 2 for the third ten year inservice inspection interval. Luminant Power has determined that compliance with certain inspection requirements of ASME Section XI would result in an unnecessary hardship or unusual difficulty without a compensating increase in the level of quality and safety.

The reactor pressure vessel flange leak-off piping configuration precludes system pressure testing when the reactor vessel head is removed. The configuration also precludes pressurizing the line externally A b

,7

U. S. Nuclear Regulatory Commission TXX-15022 Page 2 of 2 02/24/2015 when the head is installed. A visual examination of the accessible areas was performed during the second interval on the unpressurized subject piping as part of the Class 2 leakage test. No evidence of leakage has been identified for the subject component. No undue risk to the public health and safety is presented by this request.

A similar relief request was previously submitted to the NRC for Unit 2 second interval, via Reference 1, and reviewed and approved via Reference 2.

The VT-2 system leakage tests of the reactor pressure flange leak-off piping will occur once in each of the three periods of the current third interval. Therefore, Luminant Power requests approval of this relief request by September 30, 2015, to support the upcoming CPNPP Unit 2 refueling outage.

This communication contains no new commitments regarding CPNPP Unit 2.

Should you have any questions, please contact Mr. Jack Hicks at (254) 897-6725.

Sincerely, Luminant Generation Company LLC Rafael Flores By:A 4d 2Kb%

Fred W. Madden Director, External Affairs Attachments:

(1) Relief Request Number - 2C3-1 For the Reactor Pressure Vessel Leak-Off Piping (Third 10-Year ISI Interval Start Date: August 3, 2014)

(2) Reactor Pressure Vessel Seal Leak-off Details (3) Piping and Instrumentation Diagram and Piping Isometric Drawings c -

Marc L. Dapas, Region IV Balwant K. Singal, NRR Resident Inspectors, Comanche Peak Jack Ballard, ANII, Comanche Peak Robert Free, TDLR

Attachment I to TXX-15022 Page 1 of 4 COMANCHE PEAK NUCLEAR POWER PLANT UNIT 2 RELIEF REQUEST NUMBER - 2C3-1 FOR THE REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD 10-YEAR ISI INTERVAL START DATE: AUGUST 3,2014)

1.

ASME Code Component Affected:

ASME Code Class:

Code Class 2

References:

ASME Section XI, Table IWC-2500-1 and IWC-5220 Examination Category:

C-H (All Pressure Retaining Components)

Item Number:

C7.10

==

Description:==

Alternative Pressure Testing Requirements for the RPV Flange Leak-Off Piping Component:

NPS 33/44" RPV Flange Seal Leak-Off Piping Material:

SA376 type 304 or 316 Stainless Steel Line Numbers:

RC-2-080, RC-2-081, RC-2-082 Plant Drawings:

BRP-RC-2-RB-005, BRP-RC-2-RB-006, BRP-RC-2-RB-007, BRP-RC-2-RB-013, BRP-RC-2-RB-014, BRP-RC-1-RB-042, BRP-RC RB-043, M2-0250

2.

Applicable Code Edition and Addenda

The applicable ASME Boiler and Pressure Vessel Code edition and addenda is ASME Section XI, "Rules for Inservice of Nuclear Power Plant Components," 2007 Edition through 2008 Addenda.

Hereafter referred to as the "Code."

3.

Applicable Code Requirement

ASME Section XI, Subarticle IWC-2500, Table IWC-2500-1, Code Category C-H, Item Number C7.10 requires that all Class 2 pressure retaining components be subject to a system leakage test with a Visual, VT-2 examination each inspection period. The system leakage test is performed at the pressure obtained while the subject portion of the system is performing its normal operating function or during a comparable test.

4.

Reason for Request: Hardship without a compensating increase in quality and safety (10 CFR 50.55a (h)(3)(z)(1)).

As discussed in Section 3, "Applicable Code Requirement," ASME Section XI, 2007 Edition through 2008 Addenda requires that Class 2 pressure boundary piping shall be pressure tested once each inspection period. The Reactor Pressure Vessel (RPV) head flange seal leak detection piping is separated from the reactor coolant pressure boundary by one passive membrane, which is an 0-ring located on the inner vessel flange as shown in Attachment 2. A second 0-ring is located on the outside of the tap in the vessel flange. Failure of the inner 0-ring is the only condition under which this line is pressurized. Therefore, the line is not expected to be pressurized during the system pressure test following a refueling outage.

The configuration of this piping precludes system pressure testing while the vessel head is removed because the time required by personnel for the installation and removal of a threaded plug in the flange face to act as a pressure boundary for the test would incur significant dose (estimated 20 - 40 mRem/minute), which would be an ALARA concern. This activity would also present a Foreign Material Exclusion issue for the 1/8" plug that would be required to be installed to complete a leakage test at pressure.

to TXX-15022 Page 2 of 4 COMANCHE PEAK NUCLEAR POWER PLANT UNIT 2 RELIEF REQUEST NUMBER - 2C3-1 FOR THE REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD 10-YEAR ISI INTERVAL START DATE: AUGUST 3,2014)

The configuration also precludes pressurizing the line externally with the head installed at the start of an outage. The top head of the vessel contains two grooves that hold the 0-rings. The 0-rings are held in place by a series of retainer clips that are housed in recessed cavities in the flange face. If a pressure test were to be performed with the head on, the inner 0-ring would be pressurized in a direction opposite to its design function. This test pressure would result in a net inward force on the inner O-ring that would tend to push it into the recessed cavity that houses the retainer clips. The thin O-ring material would likely be damaged by the inward force. The inner O-ring failure would prevent pressure build-up by allowing water to pass by and enter the reactor vessel. To ensure that it was in fact an O-ring failure and not a leak in the leak-off piping, the portion of piping in the reactor vessel nozzle inspection areas ("sandboxes") would have to be inspected. The conditions inside the "sandboxes" at the beginning of the outage prior to removing the head would be considered unsafe with extremely high temperatures and dose ratings ranging from 150 to 250 mRem/hr. The leak-off piping travels through three of the eight "sandboxes". It is felt that performing the examination in this manner would result in an unnecessary hardship without a sufficient compensating increase in the level of quality and safety. Therefore, the only time, other than O-ring failure, that the leak-off lines are fluid filled under any type of pressure is when the head is removed and the cavity flooded. contains the piping and instrumentation diagram (P&ID) and the piping isometric drawings showing the subject flange leak-off line.

5.

Burden Caused by Compliance:

Purposely failing or not installing the inner 0-ring in order to perform a pressure test would require purchasing a new 0-ring set and the time and radiation exposure associated with removing and reinstalling the RPV head to replace the O-rings would be an undue hardship.

Therefore, compliance with the IWC-5221 system leakage test requirements results in an unnecessary hardship without a sufficient compensating increase in the level of quality and safety.

6.

Proposed Alternative and Basis for Use:

In lieu of the requirements of IWC-5221, a VT-2 visual examination of the accessible areas will be performed each period on the piping subjected to the static pressure head when the reactor cavity is filled. This test will be part of the reactor coolant Class 2 leakage test.

During normal operation, the inner 0-ring isolation valve is open. Should the inner 0-ring leak, a high temperature alarm actuates at 140 degrees F in the control room, informing the operator of the leak. The operator monitors reactor vessel flange leak-off temperature in accordance the CPNPP alarm procedures (ALM-053A for Unit 1 and ALM-053B for Unit 2) and closes the valve, isolating the leak. The procedure directs shutting the manual isolation valve and opening another valve, transferring RCS pressure boundary maintenance to the outer O-ring. Opening the valve then transfers leak detection to the outer O-ring. All drainage/leakage is piped to the reactor coolant drain tank. The procedure also addresses notifying chemistry department to increase monitoring of the containment atmosphere to detect possible outer O-ring failure; perform an operations test to determine leakage rate as applicable; and initiating corrective action documents to identify the condition and correct the condition as applicable.

to TXX-15022 Page 3 of 4 COMANCHE PEAK NUCLEAR POWER PLANT UNIT 2 RELIEF REQUEST NUMBER - 2C3-1 FOR THE REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD 10-YEAR ISI INTERVAL START DATE: AUGUST 3,2014)

Additionally, the flange seal leak-off line is essentially a leakage collection/detection system and the line would only function as a Class 2 pressure boundary if the inner O-ring fails, thereby pressurizing the line. If any significant leakage does occur in the leak-off line piping itself during this time of pressurization then it would clearly exhibit boric acid accumulation and be discernable during the proposed VT-2 visual examination that will be performed unpressurized as proposed in this request. The elevation of the Reactor Vessel flange is 834' 11/22". The elevation for the water level when the cavity is flooded is 858" 6". Therefore, the minimum pressure at the opening of the flange leak-off line when the exam is performed is 24' 5 1/2 " of static pressure head or 10.6 psi.

The system leakage test will be performed in accordance with ASME Section XI Subarticle IWA-5213(a). A 10-minute hold time will be maintained after test pressure has been reached for Class 2 components that are not in use during normal operating conditions. The subject lines are also not insulated.

There has been no known evidence of corrosion, stress corrosion cracking, or fatigue in the subject flange leak-off piping at Comanche Peak. Database searches for the subject lines in the Comanche Peak Corrective Action Program identified no historical instances of degradation.

7.

Duration of Proposed Alternative:

This alternative is requested for the Third Inservice Inspection Interval, which began on August 3, 2014 and ends on August 2, 2024.

8.

Precedents:

(1) Comanche Peak Nuclear Power Plant, Unit 2 Second Inspection Interval Relief Request C-3 "Alternative Pressure Testing Requirements for the RPV Flange Leak-Off Piping", as approved by the NRC on April 4, 2014 (ML14084A291).

(2) Comanche Peak Nuclear Power Plant, Unit 1 Third Inspection Interval Relief Request C-2 "Alternative Pressure Testing Requirements for the RPV Flange Leak-Off Piping", as approved by the NRC on March 19, 2013 (ML13046A385).

(3) LaSalle County Station Third Inspection Interval Relief Request 13R-08.

"Pressure Testing of the Reactor Vessel Head Flange Leak Detection System", as approved by the NRC in a [[letter::CP-200800183, Withdrawal of License Amendment Request (LAR)06-009, Revision to Technical Specification 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators|letter dated January 30, 2008]] (ADAMS Accession No. ML073610587)

(4) Susquehanna Steam Electric Station Third 10-Year Inservice Inspection (ISI) Interval Program Plan Request for Relief 3RR-07 "Exemption for Pressure Testing Reactor Pressure Vessel Head Flange Seal Leak Detection System", approved by the NRC in a letter dated September 24, 2004 (ADAMS Accession No. ML042680078) to TXX-15022 Page 4 of 4 COMANCHE PEAK NUCLEAR POWER PLANT UNIT 2 RELIEF REQUEST NUMBER - 2C3-1 FOR THE REACTOR PRESSURE VESSEL LEAK-OFF FLANGE (THIRD 10-YEAR ISI INTERVAL START DATE: AUGUST 3,2014)

9.

Reference:

Code Case N-805, "Alternative to Class I Extended Boundary End of Interval or Class 2 System Leakage Testing of Reactor Vessel Head Flange O-ring Leak Detection System," was issued to the 2010 Edition of the ASME Section XI Code and is listed in Supplement 6 for Code Cases.

However, Code Case N-805 has not been approved by the NRC and is not identified in Regulatory Guide 1.147, "Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1."

Phase 2 480 VAC FLEX Generator CPX-FXDGEE-01/02 500kW, 480V, 752A 8-I/C 1 KCMIL C'-p----01 6 ----

CPX-6PMENB-t 4.I6C As6060,4 54,666,2 3 C66,r.6Cond 6r CPX EPMEN-D2

0) 8D0A
5) UUA XB110-1 CPX-EPDPNB-O8 El-0024-O0E (YARD near 2ST XMFR)

KXB10-1-4 CPX-EPDPNB-57 El-0024-01F (U2 Train A SWGR RM 810')

17 400A CPX-E PDSNS-*ZO 3-I/C 4/n anna Iond~

XB10-1-3

-EPDPNB-07

-0024-01B ECB 778')

[

CPX El (E

NBI

- 11B10-1-3-1 CP1-EPDPNB-28 E1-0024-01C

( U U S G 7 9 0 '

2 i 125A

) ISA k

iEe3-17S LEB3-16S 1EB3-1

-EB3.i Battery Exhaust Charger Fan 1EDi-2 1-1(A)

-6.o6

)1i0A 10t

)1iO i) 25/A L

'XBlO-1-3-1 CPX-EPDPNB-45 Ei-0024-01C (AUX 790')

125A

6) 1SA IEB4-i 1EB4-i Battery Exhaust Test Test Charger Fan Battery Battery IED2-2 1-2(8)

Charger Charger BTIXRT-01 BTXRT-o2 Note 2 Note 2 13t L

21 400A

6) 00A 400A M) 250A

') 125A M) 250A

') 125A

')

4.A A

A 6-ec ah 27-/ 20 2-11C1 aict 3/Cat CPX EPDlaa05,A s 'c 66 No '3 C P066 MP6-6 crx-rbmo

i 21 400A

-/i 1

60a0A a

4O 3-3/12C rI 0'

XB10-1-2 2810-1-1 5810-1-1 tin Ca,6 CPX-EPDPNB-06 CPZ-EPDPNB-12 CPX-EPDPNB-05 E1-0024-01A E2-0024-02 El-0024-01A 0

-)

16,HP)

(AUX 852')

(U2 SG 810')

(AUX832'}

126 6

L06 2

3 ).A 200A 1

2OA 2

I" 2.iA 1_

21 2l0A

) 200A 2 200A

)OeA

) 200A 1B10-1-2-1 2B10-1-1-2 XB10-1-1-3 2B10-1-1-1 2B10-11-3 CP1-EPPN8-27 CP2-EPDPNB-25 CPX-EPDPNB-46 CP2-EPDPN8-27 CP2-EPDPNB-28 El-0024-01C E2-0024-03C E2-0024-03D E2-0024-03C E2-0024-03C

{U1 SG 852')

(U2 SG 790')

(AUX 790')

(U2 SG 810')

(U2 SG 852')

i/125A1 15AJi2A 6

j 2 )2aA

-a 15A 1

2izs A

5 A

lE212 EB3I8 en 2EB3-575 2EB4-0li 2EB4-045 lEBISt i/i Eel-3Si I E B 25 1 2 E S3 S S E S S 1 2 E B 4 -

i 2 E B 4-1 l M 5E B 2 - E W...

Battery Battery Exhaust Battery Exhaust Battery Battery Charger Charger Fan-Charger Fan Charger Charger 6MauaT W6dl63 2Pt 1ED4-1 2EDI-2 2-1(A) 2ED2-2 2-2(B) 2ED3-1 2ED4-16 h

1a6 L~k File*J, 16 ra t

Feable W ldlr Figure A3-23: Phase 2 480VAC FLEX Generator Connection to Plant Support Power 103 to TXX-15022 Page 1 of 3 Reactor Pressure Vessel Seal Leak-Off Details Luminant Power Comanche Peak Nuclear Power Plant to TXX-15022 Page 2 of 3 Figure 1:

REACTOR PRESSURE VESSEL HEAD FLANGE LEAK-OFF LINE CONFIGURATION to TXX-15022 Page 3 of 3 Figure 2:

Reactor Pressure Vessel Head Flange Leak-Off Line Details to TXX-15022 Piping and Instrumentation Diagram and Piping Isometric Drawings

ttachment to TXX-15022 Page 2 of 9 Ic-A I

B I

c I

2 4

I G

H I

D 4

-~

-490 j~j o

STEAM-GEN4ATO

-0

--~


/

TCX-RCPCSGPC2 0-0-503-2-0002E92 S 929 2-89400_fý 00r04 02 os.--0000-ei2205.

55 000 0105 00 55 0000 000 02055 04 20-0 000 4R REACTOR 7

~

AS aCV.

LOOP oP. 000 OOP 050 00~990 5080 T-0 M.

-0590008 REACTO 0005 0

5000tCoo"0 COOLOOP 10 00 5.0 LOP LOOP "LT'9 77 7t.00 2-202 004 00 401-9500.TL 9--5 500805 0100 100.0 RECO

_JooGO2-0O 2ým

- --0 0.04.00 9 2 -0 000A 00 00 5 004 0740 T.

CO-- LOCITED

-TW -T OF

-T 1-sl-I. -

1..

1 -

-11.

1. -

=w

-I T =Tl-T s,- Im -

ss-s-

-TOO L=E 1:Ll

1

TO -1 r1l ETE C.=,.

_M.

_S,==OW 10 D

.:T.

I IT" T11 11 -R OT T.. 1. -11.

1.

Kl-

ý IE TOO To =ýIOO 1 ILI

ýS

M 5-1 1~

1 TO 2.

1-2 FOA

-C

.1 -

AOOT

-1 TOO

,s Týl Z-1 =T=ll I

LU Of S

2 V) 4 B

CLASS I LUMINANT CPASES GLEN ROSE. TEXAS FLOW DIAGRAM REACTOR COOLANT SYSTEM MS-02501 cp-18 6

9000am40 A

M2-0250 I

B I

c t

F FIINAL IRt IINi I 5

Attachment to TXX-15022 Page 3 of 9 C

0 t

It, F

0 1~

BILL OF MATERIAL N

2i 104 6

46 4

2 6RC F

,-RC-2-06O-05018-2 n.n.T.

80286-07 83 ISE NOTE 1)3 SE OE3 YTOE)RC-C--OR2--25R-2w?

@jW--B h a-.

1 - !IN A) 2

'e-I 3

4-

=;

s.- *'-WP-2-Ot9-00AR-5 0/s S r

Z-r51r M.-.

05

- I" M2-0250. M2-0264 t-2002. M-2003 250iR-2. ZSOSR-2 ROTES I. REFER TO MR8S (MANUMFACTURING RECORD SKEET) FOR TIYPE OF MATERJAL USED.

2. GRADIENT fl,.65" PER FOOT IN PIECE 13 WI8H VALVE 2RC-B032 1S ACCEPTABLE.
3. GRADIENT, LT.7 PER FOOT IN TUB0N AT DISCHARGE OF 2R0C-B032 RTH VALVE AT HIGH END IS ACCEPTABLE.
4.

, VAL.VE BORED TO Y4* REFERENCE TA!92-501 BOV A.

4 S

.6 00G TU ELECTRIC CPSES GLEN ROSE TEXAS INETS REACTOR COOLANT a

I olý,Z"-

II, I I I II IRIS DRAWING CREATE* ELECTROMCALLT 0I R)6860INITIALB

_Cj I,

I I~2LI L~00Ro.

L I

I I

I Iýv I

UL 2llf0

.0.

S

  • .no.

SHRCROOOSS.IGN A a

C

+

E FINAL PRINT

Attachment to TXX-15022 Page 4 of 9 CPU A

B G

N

-- I BRP-RC-2-RB-006 H 409 2 I 1ILL OF MATERIAL N

2 3

4-M1 2-0511. WI055IlO

-M-025 I j.4rn 29-2

1. RErER TO MRS (MANUFACTULRING RECR0D SHEETIFOR TYPE OF MATERIAl.

USED.

TU ELECTRIC CPSES GLEN ROSE, TEXAS a

TUE 92-390.1 JREV 0

6 WELD NO/PC 040 1 DESIGN CK"L KOý vI I~

L I UII-10 REACTOR COOLANT V"

1 I

1 1

1 I

1 I

f

. 1 I TS DRAWING CREATED ELECTRO44IMAL1 I REIýAR I--

CIA5 I I

4 I

I I

I

,,5,MS~U4.,

~*l RACROOOU3.IElA n

+

HRCRDO06F3.lCN A

4 F

I P

FINAL PRINT

Attachment to TXX-15022 Page 5 of 9 BRP-C-2-B-OO 194I~I BILL OF MATERIAL i

N 1 1 1 2!Y4'S/160 2 -L 2 ly'-s/160 3

1 i 2 SA37 SRI 1

2 SA37 SRI I

S/160 4'-4'A'EST L,;

SA37 OR/

ST LG SA37 BR/

7HP,45_1111121 90;RNIST LG SA37 OR/

2 If.- 6COO LB SW 90'tLL SAIR2 :X SRI I 2 1 Y., S/160 SA37

ý0_

z I Y,- wlbu SALT

_fFp_1 Ll _L 2 Y.-S/160 SA3711 BR/

lz 1

2 ye S/iso S

OR/

IS I I Yll S/160 SA 57 1 BR/

_L4 4-6000 LB SW CPLG SAI&2 SRI 4f l-9499*

"4 =~rIxx -0l 9*

~

10459*9*

r.~uNOTICE 4

TPLM-3or8c.

M2-0250 M-2003

-2509*-2 m

I NOTES I -REFER TO MRS (MANUFA&CTURING REMORD SKE r) F91R TYPE1 OF MJAT RALI. 151.

NEWSJUT TU ELECTRIC CPSES GLEN ROSE. TEXAS REACTOR COOLANT GR9*10/

AI09095 FROM.

Oa 0ZIII OW.BRP-RC-Z-R8-OO7 REV. 5 RGIRZAIO MORMO0O.I flECTRI Ill THSRAWING FlA 5C OC8L IlIZL 6*NO*m

  • n*m x

I II I

wui2sc=,

IFIn-La-505ol aRP-RC-2.RaBo?

isvzp-I

2 NOTICE AD 0W31G STATUS OF THIS DOILUT SýB CHECKED A

II ITRGC.

8"r?-

-R24-013 REV.

~ZA1IISEORlOI0.

OMTU ElECTRIC L INS ORAW: CREATED ELECTR~OCALLY spw nu fj

Attachment to TXX-15 022 Page 7 of 9 1 0 A

r Attachment to TXX-15022 Page 7 of 9 BRP-RC-2-RB-014SHO2 BILL OF MATERIAL I

Waffu.ETs wwoef(ff MO2-0508.

M2-OS13O "M--ozOC, U.-20003 2..o-2 NOTES I. REFR TO MRS (MANUFACTURINO RECORD SHEET)

FOR TYPK OF MATERI.L USED.

TU ELECTRIC CPSES GLEN ROSE. TEXAS REACTOR COOLANT Rf,".If.Y-,CI D~-*,V -7:-nR.fYI I F=ltva pIr-I I

I I CORA RPN FRO.,

ICR010/T ONG.

II OICRP-2-RO-014 REV. 2 I

I I I

I IO~iG. ORG. TU ELECTSdC ITHIS DRAWING CR000ELECTROIIICALLV I XWE'

'.'.S IMTiAO I I I I I I III el f-a

'-BRP-RC-2-RB-014 h;-2 I

'CP"- I I OS.~RoOl4U~ A C

I KRCROO14LMGN A C

E I

_____FINAL PRINT H

Attachment to TXX-15022 Page 8 of 9 CPE a

F a

h BRP-RC-2-RB-042 sa lOPS I N

BILL OF MATERIAL

-T 00OWlION

~Iwoc ~

INNER MONITOR TUBE OF REACTOR TCX-RCPCRV-O0 IREF)

I I

2 2

3

.4 3

4 40-0308. 42-0507 142-0600 M-2003 250A4-2 NOTES

1. REFER TO MRS 'MANUFACTURING RECORD SHEET)FOR TYPE OF MATERIAL USED.

ý. S RIa ISWELDED OR-CTLY TO INNER 04MT0R NOZZLE.

CLRS. TO aSS 2 DREAK OCCURS UPSTREAM 0F 5 NOZLL.

5 TUl ELECTRIC CR5 ES GLEN ROSE. TEEAS 6

IODO.CM'ZATI-1I I I I I I I IL REACTOR COOLANT THIDS DRAWING CREATED ELECTROkiCALLY I Mr_

"R'S I

I"II I

I I

CLAI DADI D-CCt'_OD..-rA' I,%=.lPb.*

I 11W 21 '"'1 IHCROO.U A

IHRCRO0424.16N A 1

0 C

I D

FINAL PRINT

Attachment to TXX-15022 Page 9 of 9 CPE I

B 0

a H

  • 1 CP A-I a

BRP-RC-2-RB-043 usioF 2 N

DILL OF _MATERIAL 3

3

- lg.-J

-,I, ýý

'EI W4

.d 15505005

-V CLWY 1-M llS 557S 4

1",.___________

-M2-0250 45-2003 25l-

1. REFER TO MRS1 lVANL*ACTUJRNG RECORD SF5057J FRo TPE OF MAIAERIAL Uý450.

TU ELECTRIC CPSES GLEN ROSE. TEXAS 5

2 6

I D U A I I II I I I I I I I REACTOR COOLANT FWSDAIGCETDELECTRONIAL MIEVSE-S 5T75.S i

I MeICiA 5(71-5515-715555 15Or'~3~D9..5,A~

I,*,,lep--*

WT-U-r5l I

RP-r-l-Q-03 VW25I I NRCR00433.1IN 4,

1 0

FINAL PRINT