ML12251A122 | 7 September 2012 | Balwant Singal Plant Licensing Branch IV | Acceptance Review E-mail - Relief Request C-2 for the Reactor Pressure Vessel Leak-Off Flange, Third 10-Year Inservice Inspection Interval | Acceptance Review |
ML12345A188 | 10 December 2012 | Balwant Singal Plant Licensing Branch IV | Request for Additional Information E-mail - Relief Request C-2 for the Reactor Pressure Vessel Leak-Off Flange, Third 10-Year Inservice Inspection Interval | RAI |
ML13025A261 | 9 January 2013 | Luminant | Enclosure to TXX-13003 Drawings for Response to RAI Question 2 | Response to RAI |
CP-201300002, Response to Request for Additional Information for Unit 1 Relief Request No. C-2 | 9 January 2013 | Luminant Madden F | Response to Request for Additional Information for Unit 1 Relief Request No. C-2 | Response to RAI |
ML13046A385 | 19 March 2013 | Markley M Plant Licensing Branch IV | Relief Request C-2 for the Reactor Pressure Vessel Flange Leak-Off Piping, Third 10-Year Inservice Inspection Interval | Other |
CP-201301199, Relief Request No. C-3 for the Unit 2 Reactor Pressure Vessel leak-off Flange (Second ISI Interval Start Date: August 3, 2004; Second ISI Interval End Date: August 2, 2014 | 31 October 2013 | Luminant Flores R Thomas McCool | Relief Request No. C-3 for the Unit 2 Reactor Pressure Vessel leak-off Flange (Second ISI Interval Start Date: August 3, 2004; Second ISI Interval End Date: August 2, 2014 | Request |
ML13350A630 | 16 December 2013 | Division of Operating Reactor Licensing Joseph Sebrosky | NRR E-mail Capture - Acceptance Review for Relief Request C-3 for Comanche Peak Unit 2, - TAC No. MF2997 | Acceptance Review |
ML14007A000 | 3 January 2014 | Division of Operating Reactor Licensing Balwant Singal | NRR E-mail Capture - Request for Additional Information (RAI) - Relief Request (RR) C-3 - TAC No. MF2997 | RAI |
CP-201400070, Response to Request for Additional Information for Relief Request No. C-3 for Unit 2 Reactor Pressure Vessel Leak-off Flange (Second ISI Interval Start Date: August 3, 2004; Second ISI Interval End Date August 2, 2014) | 23 January 2014 | Luminant Thomas McCool | Response to Request for Additional Information for Relief Request No. C-3 for Unit 2 Reactor Pressure Vessel Leak-off Flange (Second ISI Interval Start Date: August 3, 2004; Second ISI Interval End Date August 2, 2014) | Response to RAI |
ML14030A466 | 30 January 2014 | Division of Operating Reactor Licensing Balwant Singal | NRR E-mail Capture - Follow-up Request for Additional Information for Relief Request C-3 - TAC MF2997 | RAI |
CP-201400144, Clarification to Response to Request for Additional Information for Relief Request No. C-3 for Unit 2 Reactor Pressure Vessel Leak-Off Flange (Second ISI Interval Start Date: August 3, 2004; Second ISI Interval End. | 11 February 2014 | Luminant Flores R Madden F | Clarification to Response to Request for Additional Information for Relief Request No. C-3 for Unit 2 Reactor Pressure Vessel Leak-Off Flange (Second ISI Interval Start Date: August 3, 2004; Second ISI Interval End. | Supplement |
ML14084A291 | 4 April 2014 | Markley M Plant Licensing Branch IV | Relief Request No. C-3 for Reactor Pressure Vessel Leak-Off Flange for the Second 10-Year Inservice Inspection Interval | Other |
CP-201500157, Relief Request No. 2C3-1 for the Reactor Pressure Vessel Leak-Off Flange (Third ISI Interval Start Date: August 3, 2014; Third ISI Interval End Date: August 2, 2023) | 24 February 2015 | Luminant Flores R Madden F | Relief Request No. 2C3-1 for the Reactor Pressure Vessel Leak-Off Flange (Third ISI Interval Start Date: August 3, 2014; Third ISI Interval End Date: August 2, 2023) | Request |