MONTHYEARRS-13-148, License Amendment Request - Use of Neutron Absorbing Inserts in Units 1 and 2 Spent Fuel Pool Storage Racks2013-07-16016 July 2013 License Amendment Request - Use of Neutron Absorbing Inserts in Units 1 and 2 Spent Fuel Pool Storage Racks Project stage: Request ML13241A5102013-08-29029 August 2013 Request for Supplemental Information Project stage: Other RS-14-039, Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks2014-01-22022 January 2014 Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Request ML14024A5622014-01-22022 January 2014 Attachment 4 and 5 to RS-14-039, HI-2104790, Rev. 1, Nuclear Group Computer Code Benchmark Calculations, and HI-2125245, Rev. 4, Licensing Report for Quad Cities Criticality Analysis for Inserts-Non Proprietary Version. Project stage: Request ML14066A1362014-02-24024 February 2014 NRR E-mail Capture - Draft RAI from TAC Nos.: MF2489 and MF2490 Review on Neutron Absorbing Inserts Project stage: Draft RAI ML14066A1352014-02-24024 February 2014 NRR E-mail Capture - FW: Draft Request for Additional Information for Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks (TAC Nos. MF2489 and MF2490) Project stage: Draft RAI ML14059A1562014-02-28028 February 2014 NRR E-mail Capture - Request for Additional Information for Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks (TAC Nos. MF2489 and MF2490) Project stage: RAI ML14090A0042014-03-29029 March 2014 NRR E-mail Capture - Request for Extension -- Quad Cities Rack Inserts RAI Responses Project stage: RAI ML14203A6132014-06-23023 June 2014 NRR E-mail Capture - FW: Draft RAI from TAC Nos.: MF2489 and MF2490 Review on Neutron Absorbing Inserts Project stage: Draft RAI ML14203A6752014-07-22022 July 2014 NRR E-mail Capture - Final RAI for Quad Cities Regarding Use of Neutron Absorbing Inserts (TAC Nos.: MF2489 and MF2490) Project stage: RAI RS-14-229, Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks2014-08-12012 August 2014 Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Request ML14128A5632014-09-0404 September 2014 Request for Withholding Proprietary Information from Public Disclosure Project stage: Other ML14311A8502014-11-10010 November 2014 November 10, 2014, Discussion Topics Regarding Rack Insert Surveillance Program Project stage: Other RS-14-329, Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks2014-11-11011 November 2014 Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Request ML14353A3152014-12-24024 December 2014 Request for Withholding Proprietary Information from Public Disclosure Project stage: Other ML14346A3062014-12-31031 December 2014 Issuance of Amendments Regarding (TAC Nos. MF2489 and MF2490)(RS-13-148) Project stage: Approval ML15128A4772015-08-14014 August 2015 Summary of November 10 2014 Public Meeting with Exelon Generation Company, LLC on Netco Snap-In Rack Insert License Amendment Request Project stage: Meeting 2014-02-24
[Table View] |
|
---|
Category:Letter
MONTHYEAR05000265/LER-2024-002-01, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-10-30030 October 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure SVP-24-065, Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor2024-10-29029 October 2024 Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor IR 05000254/20240102024-10-28028 October 2024 Age Related Degradation Inspection Report 05000254/2024010 and 05000265/2024010 and Notice of Violation RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-059, Correction to Registration of Use of Casks to Store Spent Fuel2024-10-0404 October 2024 Correction to Registration of Use of Casks to Store Spent Fuel ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24247A1642024-09-30030 September 2024 Alternative Request RP-01 IR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) SVP-24-054, Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds2024-09-11011 September 2024 Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) RS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024 Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval ML24183A1082024-08-0808 August 2024 – Issuance of Amendment Nos. 302 and 298 Adoption of Tstf-505, Provide Risk Informed Extended Completion Times – RITSTF Initiative 4b SVP-24-049, Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities2024-08-0707 August 2024 Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 SVP-24-048, Registration of Use of Casks to Store Spent Fuel2024-07-31031 July 2024 Registration of Use of Casks to Store Spent Fuel 05000265/LER-2024-002, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-07-22022 July 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions SVP-24-041, Regulatory Commitment Change Summary Report2024-07-0505 July 2024 Regulatory Commitment Change Summary Report SVP-24-043, Registration of Use of Casks to Store Spent Fuel2024-07-0505 July 2024 Registration of Use of Casks to Store Spent Fuel ML24162A0982024-07-0303 July 2024 – Issuance of Amendment Nos. 301 and 297 Adoption of 10 CFR 50.69 Risk Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors SVP-24-040, Registration of Use of Casks to Store Spent Fuel2024-06-25025 June 2024 Registration of Use of Casks to Store Spent Fuel RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations SVP-24-039, Ile Post Exam Package Letter2024-06-12012 June 2024 Ile Post Exam Package Letter RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed ML24110A0492024-05-28028 May 2024 Audit Report Related to the TSTF-505 and 10 CFR 50.59 Amendments ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24141A2102024-05-20020 May 2024 Operator Licensing Examination Approval - Quad Cities Nuclear Power Station, May 2024 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 SVP-24-034, Annual Radiological Environmental Operating Report2024-05-10010 May 2024 Annual Radiological Environmental Operating Report 05000265/LER-2024-001, Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing2024-05-10010 May 2024 Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report ML24109A0662024-05-0202 May 2024 – Relief Request I5R-26, Revision 0 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-028, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2024-04-26026 April 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report SVP-24-029, Radioactive Effluent Release Report for 20232024-04-26026 April 2024 Radioactive Effluent Release Report for 2023 ML24114A1712024-04-23023 April 2024 State of Illinois (IEMA-OHS) Comment Quad Cities HI-STORM Exemption Environmental Assessment IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion SVP-24-024, Corrected Radioactive Effluent Release Report for 20222024-04-0505 April 2024 Corrected Radioactive Effluent Release Report for 2022 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report SVP-24-023, Ile Outline Submittal Letter2024-03-29029 March 2024 Ile Outline Submittal Letter RS-24-019, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF2024-03-19019 March 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF ML23340A1552024-03-15015 March 2024 – Issuance of Amendment Nos. 299 and 295 Adoption of TSTF-564, Safety Limit MCPR RS-24-020, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS2024-03-15015 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS SVP-24-018, Ile Proposed Exam Submittal Letter2024-03-13013 March 2024 Ile Proposed Exam Submittal Letter 2024-09-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 24, 2014 Mr. Michael J. Pacilio Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Office (CNO)
Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2- REQUEST FOR WITHHOLDING PROPRIETARY INFORMATION FROM PUBLIC DISCLOSURE (TAC NOS. MF2489 AND MF2490)
Dear Mr. Pacilio:
In letters dated April 7 and August 12, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14101A213 and ML14224A445, respectively), Exelon Generation Company, LLC (licensee) submitted affidavits dated March 27 and August 4, 2014, executed by Debabrata (Debu) Mitra-Majumdar, Ph.D, on behalf of Holtec International, requesting that the information contained in the following documents be withheld from public disclosure pursuant to paragraph (a)(4) and (b)(4) of Title 10 of the Code of Federal Regulations (1 0 CFR), Part 2, Section 2.390:
- 1. Holtec International Report No. Hl-2125245, Revision 5, "Licensing Report for Quad Cities Criticality Analysis for Inserts; " and,
- 2. RRTI-2127-001 RO, "Response to Request for Additional Information", Quad Cities, RAI (proprietary information).
Non-proprietary versions of these documents are publicly available under ADAMS Accession No. ML14101A213 and ML14101A213.
The March 27, 2014, affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
- a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by Holtec's competitors without license from Holtec International constitutes a competitive economic advantage over other companies;
- b. Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, issurance of quality, or licensing of a similar product.
- e. Information which discloses patentable subject matter for which it may be desirable to obtain patent protection.
M. Pacilio We have reviewed your submittals in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the versions of the submitted information marked as proprietary in the documents identified above will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future, such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-2020.
~~~~~k---/~/
fsrenda L. Mozafari, Senior Project Manager Plant Licensing 111-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-254 and 50-265 cc: Listserv
- .. ML14353A315 OFFICE LPL3-2/PM LPL3-2/PM LPL3-2/LA LPL3-2/BC LPL3-2/PM NAME EBrown BMozafari SRohrer TTate BMozafari (BMozafari for) (MHenderson for) (JWiebe for)
DATE 12/17/14 12/18/14 12/22/14 12/22/14 12/24/14