Letter Sequence Draft RAI |
|---|
|
|
MONTHYEARML13199A0382013-07-16016 July 2013 Attachment 5 - Holtec International Report No. HI-2125245, Revision 2, Licensing Report for Quad Cities Criticality Analysis for Inserts - Non Proprietary Version Project stage: Request RS-13-148, License Amendment Request - Use of Neutron Absorbing Inserts in Units 1 and 2 Spent Fuel Pool Storage Racks2013-07-16016 July 2013 License Amendment Request - Use of Neutron Absorbing Inserts in Units 1 and 2 Spent Fuel Pool Storage Racks Project stage: Request ML13241A5102013-08-29029 August 2013 Request for Supplemental Information Project stage: Other RS-13-228, Supplemental Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks2013-09-18018 September 2013 Supplemental Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Supplement RS-14-039, Attachment 4 and 5 to RS-14-039, HI-2104790, Rev. 1, Nuclear Group Computer Code Benchmark Calculations, and HI-2125245, Rev. 4, Licensing Report for Quad Cities Criticality Analysis for Inserts-Non Proprietary Version2014-01-22022 January 2014 Attachment 4 and 5 to RS-14-039, HI-2104790, Rev. 1, Nuclear Group Computer Code Benchmark Calculations, and HI-2125245, Rev. 4, Licensing Report for Quad Cities Criticality Analysis for Inserts-Non Proprietary Version Project stage: Request ML14024A5612014-01-22022 January 2014 Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Request ML14066A1352014-02-24024 February 2014 NRR E-mail Capture - FW: Draft Request for Additional Information for Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Draft RAI ML14066A1362014-02-24024 February 2014 NRR E-mail Capture - Draft RAI from TAC Nos.: MF2489 and MF2490 Review on Neutron Absorbing Inserts Project stage: Draft RAI ML14059A1562014-02-28028 February 2014 NRR E-mail Capture - Request for Additional Information for Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: RAI ML14090A0042014-03-29029 March 2014 NRR E-mail Capture - Request for Extension -- Quad Cities Rack Inserts RAI Responses Project stage: RAI ML14203A6132014-06-23023 June 2014 NRR E-mail Capture - FW: Draft RAI from TAC Nos.: MF2489 and MF2490 Review on Neutron Absorbing Inserts Project stage: Draft RAI ML14203A6752014-07-22022 July 2014 NRR E-mail Capture - Final RAI for Quad Cities Regarding Use of Neutron Absorbing Inserts Project stage: RAI RS-14-229, Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks2014-08-12012 August 2014 Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Request ML14128A5632014-09-0404 September 2014 Request for Withholding Proprietary Information from Public Disclosure Project stage: Other ML14311A8502014-11-10010 November 2014 November 10, 2014, Discussion Topics Regarding Rack Insert Surveillance Program Project stage: Other RS-14-329, Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks2014-11-11011 November 2014 Additional Information Regarding License Amendment Request Associated with Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Request ML14353A3152014-12-24024 December 2014 Request for Withholding Proprietary Information from Public Disclosure Project stage: Other ML14346A3062014-12-31031 December 2014 Issuance of Amendments Regarding (TAC Nos. MF2489 and MF2490)(RS-13-148) Project stage: Approval ML15128A4772015-08-14014 August 2015 Summary of November 10 2014 Public Meeting with Exelon Generation Company, LLC on Netco Snap-In Rack Insert License Amendment Request Project stage: Meeting 2014-12-31
[Table View] |
Text
1 NRR-PMDAPEm Resource From:
Mozafari, Brenda Sent:
Monday, February 24, 2014 4:03 PM To:
Nicely, Ken M.:(GenCo-Nuc) (ken.nicely@exeloncorp.com)
Cc:
Purnell, Blake
Subject:
Draft RAI from TAC NOS.: MF2489 AND MF2490 review on NEUTRON ABSORBING INSERTS Follow Up Flag:
Follow up Due By:
Friday, March 07, 2014 6:00 PM Flag Status:
Flagged Tracking Tracking:
Recipient Read Nicely, Ken M.:(GenCo-Nuc)
(ken.nicely@exeloncorp.com)
Purnell, Blake Read: 2/24/2014 4:36 PM
- Ken, In case I did not send the draft RAI previously:
By letter dated July 16, 2013, (Agencywide Documents Access and Management Systems Accession Number [ADAMS] ML13199A037), Exelon Generation Company, LLC. (the licensee),
submitted a license amendment request to revise the Quad Cities Nuclear Station, Units 1 and 2 Technical Specifications to support use of neutron absorbing inserts in spent fuel pool.
REQUEST FOR ADDITIONAL INFORMATION QUAD CITIES NUCLEAR POWER STATIONS, UNITS 1 AND 2 REGARDING USE OF NEUTRON ABSORBING INSERTS IN SPENT FUEL STORAGE RACKS DOCKET NOS.: 50-254 AND 50-265 TAC NOS.: MF2489 AND MF2490
- 1. On page 23 of the July 16, 2013 submittal, it states The surveillance trees were placed within one of the QCNPS SFPS Since SFP conditions in each Unit could be different, identify in which Units SFP are the trees placed and whether the placement is considered bounding for both pools. Discuss why placement of coupons in one pool will ensure adequate material surveillance representing all panels.
- 2. On page 26 of the July 16, 2013 submittal, it states Two rack inserts from the Unit 1 SFP will be visually inspected. Discuss and justify whether inserts from Unit 2 will be visually inspected. If the inserts in Unit 1 are the only ones to be visually inspected, please discuss why a Unit 2 inspection is not necessary.
- 3. In NET-300054-01 Rev 0, the visual inspection of the coupons revealed some rust colored pitting.
- a. For coupons F15 and F16, discuss the cause of this pitting. Include whether the pitting is indicative of what the SFP inserts may be experiencing.
- b. For coupon F11, discuss whether the carbon steel tool chain was the cause of the large pit. If not, discuss the cause of the large pit.
If you require a call for clarification, let me know as soon as possible. Otherwise I will discuss a final response by March 24, 2014.
2 Thanks Brenda L. Mozafari Senior Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission Dresden 2/3 and QuadCities 1/2 301-415-2020 email: brenda.mozafari@nrc.gov
Hearing Identifier:
NRR_PMDA Email Number:
1150 Mail Envelope Properties (Brenda.Mozafari@nrc.gov20140224160200)
Subject:
Draft RAI from TAC NOS.: MF2489 AND MF2490 review on NEUTRON ABSORBING INSERTS Sent Date:
2/24/2014 4:02:48 PM Received Date:
2/24/2014 4:02:00 PM From:
Mozafari, Brenda Created By:
Brenda.Mozafari@nrc.gov Recipients:
"Purnell, Blake" <Blake.Purnell@nrc.gov>
Tracking Status:: Response: Read : 2/24/2014 4:36:00 PM "Nicely, Ken M.:(GenCo-Nuc) (ken.nicely@exeloncorp.com)" <ken.nicely@exeloncorp.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 2252 2/24/2014 4:02:00 PM Options Priority:
Standard Return Notification:
No Reply Requested:
Yes Sensitivity:
Normal Expiration Date:
Recipients Received:
Follow up By 3/7/2014 6:00:00 PM